CN216380245U - Building support steel beam structure - Google Patents

Building support steel beam structure Download PDF

Info

Publication number
CN216380245U
CN216380245U CN202121813013.2U CN202121813013U CN216380245U CN 216380245 U CN216380245 U CN 216380245U CN 202121813013 U CN202121813013 U CN 202121813013U CN 216380245 U CN216380245 U CN 216380245U
Authority
CN
China
Prior art keywords
chute
secondary beam
fixed
main
building support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202121813013.2U
Other languages
Chinese (zh)
Inventor
吕达文
陈永明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Aoji Architectural Design Co ltd
Original Assignee
Shenzhen Aoji Architectural Design Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Aoji Architectural Design Co ltd filed Critical Shenzhen Aoji Architectural Design Co ltd
Priority to CN202121813013.2U priority Critical patent/CN216380245U/en
Application granted granted Critical
Publication of CN216380245U publication Critical patent/CN216380245U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses a building supporting steel beam structure, which comprises: the main beams are symmetrically arranged on two sides of the floor; the first secondary beam and the second secondary beam are symmetrically arranged at the top of the main beam; the fixed secondary beams are fixed at one ends of the two main beams; the adjusting mechanism is connected between the first secondary beam and the second secondary beam in a sliding mode, the fixing secondary beam is fixed on the main beam through a bolt, the first secondary beam and the second secondary beam are driven to move through rotation of the first secondary beam and the threaded rod, the first secondary beam is fixed through the bolt after the first secondary beam moves to the overlapping position of the bolt hole and the second bolt hole, the second secondary beam is moved along the direction of the threaded rod, the second secondary beam is driven to move to the overlapping position of the bolt hole and the second bolt hole and then is fixed through the bolt, installation of the device is achieved, connection and fixation among the fixing secondary beam, the first secondary beam, the second secondary beam and the main beam are improved, and stability of the device is improved.

Description

一种建筑支撑钢梁结构A building supporting steel beam structure

技术领域technical field

本实用新型涉及建筑技术领域,具体为一种建筑支撑钢梁结构。The utility model relates to the technical field of construction, in particular to a building supporting steel beam structure.

背景技术Background technique

建筑支撑组合结构,在建筑施工中普遍采用木杆、钢管、木方、扣件、U托、步步紧等连接作为混凝土成形过程的主要支撑体系,而且是经验化的、拼凑的、安装繁琐的,现有设计中的建筑支撑钢梁结构一般是将主梁和次梁进行安装,在安装过程中,两个次梁之间的连接是通过一种伸缩杆相似的结构进行连接,两个次梁之间的连接稳定性不高。The building support composite structure is generally used in the construction of wooden poles, steel pipes, wooden squares, fasteners, U brackets, step by step and other connections as the main support system in the concrete forming process, and it is experienced, patchwork, and complicated to install. In the existing design, the building support steel beam structure generally installs the main beam and the secondary beam. During the installation process, the connection between the two secondary beams is connected through a structure similar to a telescopic rod. The connection stability between the secondary beams is not high.

为此,我们提出一种建筑支撑钢梁结构。To this end, we propose a building-supporting steel beam structure.

实用新型内容Utility model content

本实用新型的目的在于提供一种建筑支撑钢梁结构,以解决上述背景技术中提出的问题。The purpose of the present invention is to provide a building supporting steel beam structure to solve the problems raised in the above background technology.

为实现上述目的,本实用新型提供如下技术方案:一种建筑支撑钢梁结构,包括:To achieve the above purpose, the present utility model provides the following technical solutions: a building support steel beam structure, comprising:

主梁,对称设置在楼面两侧;The main beam is symmetrically arranged on both sides of the floor;

第一次梁和第二次梁,对称设置在主梁的顶部;The first beam and the second beam are symmetrically arranged on the top of the main beam;

固定次梁,固定在两个所述主梁的一端;fixing the secondary beams, which are fixed at one end of the two main beams;

调节机构,滑动连接在第一次梁和第二次梁之间;Adjustment mechanism, slidingly connected between the first beam and the second beam;

所述调节机构包括:The adjustment mechanism includes:

第一滑槽,对称设置在固定次梁的两端;The first chute is symmetrically arranged at both ends of the fixed secondary beam;

第二滑槽,对称设置在所述第一次梁和所述第二次梁的两端;The second chute is symmetrically arranged at both ends of the first beam and the second beam;

连接杆,对称滑动连接在第一滑槽和第二滑槽之间,所述连接杆的两端的对称固定有限位柱,且限位柱与所述第一滑槽、或与所述第二滑槽滑动连接;A connecting rod is symmetrically slidably connected between the first chute and the second chute, limit posts are symmetrically fixed at both ends of the connecting rod, and the limit posts are connected to the first chute or the second chute. Chute sliding connection;

第一入口槽,设置在所述第一滑槽的一端,且所述第一入口槽与第一滑槽连通设置,用于所述连接杆连入所述第一滑槽内;a first inlet slot, arranged at one end of the first chute, and the first inlet slot is communicated with the first chute and is used for connecting the connecting rod into the first chute;

第二入口槽,设置在所述第二滑槽的一端,且所述第二入口槽与第二滑槽连通设置,用于所述连接杆连入所述第一滑槽内;A second inlet slot is arranged at one end of the second chute, and the second inlet slot is communicated with the second chute and is used for connecting the connecting rod into the first chute;

螺纹杆,通过轴承转动连接在固定次梁的中部,所述第一次梁的中部开设有螺纹孔,所述第一次梁通过螺纹孔与螺纹杆螺纹连接。The threaded rod is rotatably connected to the middle of the fixed secondary beam through the bearing, the middle of the primary beam is provided with a threaded hole, and the primary beam is threadedly connected to the threaded rod through the threaded hole.

优选的,所述第一次梁、第二次梁和所述固定次梁的两端设置有用于滑动包裹所述主梁的配对槽,所述第一次梁、第二次梁和所述固定次梁组成次梁总成。Preferably, two ends of the first secondary beam, the second secondary beam and the fixed secondary beam are provided with matching grooves for slidingly wrapping the main beam, the first secondary beam, the second secondary beam and the The fixed secondary beam forms the secondary beam assembly.

优选的,所述主梁的一侧等距开设有螺栓孔,所述固定次梁、所述第一次梁和所述第二次梁两端开设有安装通孔,所述螺栓孔和所述安装通孔之间通过螺栓固定连接。Preferably, one side of the main beam is equidistantly provided with bolt holes, the two ends of the fixed secondary beam, the first secondary beam and the second secondary beam are provided with mounting through holes, and the bolt holes and the The mounting through holes are fixedly connected by bolts.

优选的,所述固定次梁、所述第一次梁和所述第二次梁的两端均设置平行设置有两块弹性板,两块所述弹性板上均设置有所述安装通孔,且两个所述安装通孔对位。Preferably, both ends of the fixed secondary beam, the first primary beam and the second secondary beam are provided with two elastic plates arranged in parallel, and the two elastic plates are provided with the installation through holes , and the two mounting through holes are aligned.

优选的,所述第二次梁的中部开设有通孔,所述螺纹杆穿过通孔设置。Preferably, a through hole is opened in the middle of the second beam, and the threaded rod is arranged through the through hole.

优选的,所述螺纹杆靠近固定次梁的一端固定有转块。Preferably, a rotating block is fixed at one end of the threaded rod close to the fixed secondary beam.

优选的,所述连接杆的长度小于第一次梁和第二次梁之间的距离。Preferably, the length of the connecting rod is less than the distance between the first beam and the second beam.

优选的,所述主梁的两侧对称开设有固定槽。Preferably, two sides of the main beam are symmetrically provided with fixing grooves.

与现有技术相比,本实用新型的有益效果是:Compared with the prior art, the beneficial effects of the present utility model are:

本实用新型使用时,通过吊机将吊线卡在安装通孔处,将第一次梁、第二次梁和固定次梁通过吊机移动至主梁的顶部,通过螺栓将固定次梁进行固定,通过第一次梁与螺纹杆的转动将带动第一次梁和第二次梁的同步移动,在第一次梁移动至螺栓孔和第二螺栓孔的重叠位置后通过螺栓对第一次梁进行固定,后顺着螺纹杆的方向移动第二次梁,带动第二次梁移动至螺栓孔和第二螺栓孔的重叠位置后通过螺栓对第二次梁进行固定,各个螺栓孔和安装通孔一一自动对位,操作便捷,省时省力的实现对装置的安装,提高了固定次梁、第一次梁、第二次梁和主梁之间的连接固定,提高装置的稳定性。When the utility model is used, the hanging wire is clamped at the installation through hole by the crane, the first beam, the second beam and the fixed secondary beam are moved to the top of the main beam by the crane, and the fixed secondary beam is fixed by bolts. , the rotation of the first beam and the threaded rod will drive the synchronous movement of the first beam and the second beam. After the first beam moves to the overlapping position of the bolt hole and the second bolt hole The beam is fixed, and then the second beam is moved in the direction of the threaded rod, and the second beam is moved to the overlapping position of the bolt hole and the second bolt hole, and the second beam is fixed by bolts. The through holes are automatically aligned one by one, which is convenient to operate, saves time and effort to install the device, improves the connection and fixation between the fixed secondary beam, the first beam, the second beam and the main beam, and improves the stability of the device .

附图说明Description of drawings

图1为本实用新型的整体结构示意图;Fig. 1 is the overall structure schematic diagram of the present utility model;

图2为本实用新型的调节机构的结构示意图。FIG. 2 is a schematic structural diagram of the adjusting mechanism of the present invention.

图中:1、主梁;2、第一次梁;3、第二次梁;4、固定次梁;5、调节机构;6、第一滑槽;7、第二滑槽;8、第一入口槽;9、第二入口槽;10、限位柱;11、螺纹杆;12、螺栓孔;13、安装通孔;14、通孔;15、转块;16、弹性板;17、连接杆;18、固定槽。In the figure: 1. Main beam; 2. First beam; 3. Second beam; 4. Fixed secondary beam; 5. Adjustment mechanism; 6. First chute; 7. Second chute; 8, No. an inlet slot; 9, the second inlet slot; 10, the limit post; 11, the threaded rod; 12, the bolt hole; 13, the installation through hole; 14, the through hole; 15, the turning block; 16, the elastic plate; 17, Connecting rod; 18. Fixing slot.

具体实施方式Detailed ways

下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions in the embodiments of the present utility model will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present utility model. Obviously, the described embodiments are only a part of the embodiments of the present utility model, rather than all the implementations. example. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative work fall within the protection scope of the present invention.

请参阅图1和图2,图示中的一种建筑支撑钢梁结构,包括主梁1、固定次梁4、第一次梁2、第二次梁3、以及调节机构5。Please refer to FIG. 1 and FIG. 2 , a building supporting steel beam structure in the illustration includes a main beam 1 , a fixed secondary beam 4 , a first secondary beam 2 , a second secondary beam 3 , and an adjustment mechanism 5 .

主梁1对称设置在楼面两侧,主梁1的两侧对称开设有固定槽18,用于进行固定安装。The main beam 1 is symmetrically arranged on both sides of the floor, and the two sides of the main beam 1 are symmetrically provided with fixing grooves 18 for fixed installation.

第一次梁2和第二次梁3对称设置在主梁1的顶部;The first beam 2 and the second beam 3 are symmetrically arranged on the top of the main beam 1;

固定次梁4固定在两个主梁1的一端,第一次梁2、第二次梁3和固定次梁4组成次梁总成,固定次梁4、第一次梁2和第二次梁3的两端对称开设有安装通孔13;The fixed secondary beam 4 is fixed at one end of the two main beams 1. The first primary beam 2, the second secondary beam 3 and the fixed secondary beam 4 form a secondary beam assembly, and the fixed secondary beam 4, the first primary beam 2 and the second secondary beam Two ends of the beam 3 are symmetrically provided with installation through holes 13;

调节机构5滑动连接在第一次梁2和第二次梁3之间。The adjustment mechanism 5 is slidably connected between the first beam 2 and the second beam 3 .

请参阅图1和图2,调节机构5包括:第一滑槽6、第二滑槽7、连接杆17、第一入口槽8、第二入口槽9以及螺纹杆11。Please refer to FIG. 1 and FIG. 2 , the adjustment mechanism 5 includes: a first chute 6 , a second chute 7 , a connecting rod 17 , a first inlet slot 8 , a second inlet slot 9 and a threaded rod 11 .

第一滑槽6对称设置在固定次梁4的两端;The first chute 6 is symmetrically arranged at both ends of the fixed secondary beam 4;

第二滑槽7对称设置在所述第一次梁2和所述第二次梁3的两端;The second chute 7 is symmetrically arranged at both ends of the first beam 2 and the second beam 3;

连接杆17对称滑动连接在第一滑槽6和第二滑槽7之间,所述连接杆17的两端的对称固定有限位柱10,且限位柱10与所述第一滑槽6、或与所述第二滑槽7滑动连接;The connecting rod 17 is symmetrically slidably connected between the first chute 6 and the second chute 7, the limit posts 10 are fixed symmetrically at both ends of the connecting rod 17, and the limit posts 10 are connected to the first chute 6, Or slidingly connected with the second chute 7;

第一入口槽8设置在所述第一滑槽6的一端,且所述第一入口槽3与第一滑槽6连通设置,用于所述连接杆17连入所述第一滑槽6内;The first inlet slot 8 is provided at one end of the first chute 6 , and the first inlet slot 3 is communicated with the first chute 6 for connecting the connecting rod 17 to the first chute 6 Inside;

第二入口槽9设置在所述第二滑槽8的一端,且所述第二入口槽9与第二滑槽8连通设置,用于所述连接杆17连入所述第一滑槽6内;The second inlet slot 9 is provided at one end of the second chute 8 , and the second inlet slot 9 is communicated with the second chute 8 for connecting the connecting rod 17 to the first chute 6 Inside;

螺纹杆11通过轴承转动连接在固定次梁4的中部,所述第一次梁2的中部开设有螺纹孔,所述第一次梁2通过螺纹孔与螺纹杆11螺纹连接。The threaded rod 11 is rotatably connected to the middle of the fixed secondary beam 4 through a bearing, the middle of the primary beam 2 is provided with a threaded hole, and the primary beam 2 is threadedly connected to the threaded rod 11 through the threaded hole.

第二次梁3的中部开设有通孔14,螺纹杆11穿过通孔14设置,螺纹杆11靠近固定次梁4的一端固定有转块15。A through hole 14 is opened in the middle of the secondary beam 3 , a threaded rod 11 is disposed through the through hole 14 , and a turning block 15 is fixed at one end of the threaded rod 11 close to the fixed secondary beam 4 .

限位柱10靠近第一次梁2靠近螺纹杆11的距离小于限位柱10靠近第二次梁3靠近螺纹杆11的距离,方便对第二次梁3的拉动。The distance between the limiting column 10 and the first beam 2 and the threaded rod 11 is smaller than the distance between the limiting column 10 and the second beam 3 and the threaded rod 11 , which is convenient for pulling the second beam 3 .

主梁1的一侧等距开设有螺栓孔12,固定次梁4、第一次梁2和第二次梁3两端对称开设有安装通孔13,螺栓孔12和安装通孔13之间通过螺栓固定连接。One side of the main beam 1 is equidistantly provided with bolt holes 12 , and the two ends of the fixed secondary beam 4 , the first beam 2 and the second beam 3 are symmetrically provided with installation through holes 13 , and the bolt holes 12 and the installation through holes 13 are provided between the two ends. The connection is secured by bolts.

另外,所述固定次梁4、所述第一次梁2和所述第二次梁3的两端均设置平行设置有两块弹性板16,两块所述弹性板16上均设置有所述安装通孔13,且两个所述安装通孔13对位,弹性板16能对螺栓形成弹性挤压使得连接更稳固,防松。In addition, two elastic plates 16 are arranged in parallel at both ends of the fixed secondary beam 4 , the first primary beam 2 and the second secondary beam 3 , and two elastic plates 16 are provided with The installation through holes 13 are formed, and the two installation through holes 13 are aligned, and the elastic plate 16 can elastically squeeze the bolts to make the connection more stable and prevent loosening.

工作原理:装置使用时,人们通过吊机将主梁1掉至安装处,对主梁1进行固定后,通过吊机将吊线卡在安装通孔13处,将第一次梁2、第二次梁3和固定次梁4通过吊机移动至主梁1的顶部,通过螺栓将固定次梁4进行固定,通过转动转块15进而将带动螺纹杆11转动,通过第一次梁2与螺纹杆11的转动将带动第一次梁2和第二次梁3的同步移动,在第一次梁2移动至螺栓孔12和第二螺栓孔13的重叠位置后通过螺栓对第一次梁2进行固定,后顺着螺纹杆11的方向移动第二次梁3,带动第二次梁3移动至螺栓孔12和第二螺栓孔13的重叠位置后,通过螺栓对第二次梁3进行固定,再次过程中,连接杆17将顺着第一入口槽8的方向移动,各个螺栓孔和安装通孔一一自动对位,操作便捷,省时省力的实现对装置的安装,提高了固定次梁4、第一次梁2、第二次梁3和主梁1之间的连接固定,提高装置的稳定性。Working principle: When the device is in use, people drop the main beam 1 to the installation place through the crane. After fixing the main beam 1, the hanging wire is clamped at the installation through hole 13 by the crane, and the first beam 2, the second beam The secondary beam 3 and the fixed secondary beam 4 are moved to the top of the main beam 1 by the crane, the fixed secondary beam 4 is fixed by bolts, and the threaded rod 11 is driven to rotate by rotating the swivel block 15. The rotation of the rod 11 will drive the synchronous movement of the first beam 2 and the second beam 3. After the first beam 2 moves to the overlapping position of the bolt hole 12 and the second bolt hole 13, the first beam 2 is connected to the first beam 2 by bolts. After fixing, move the second beam 3 in the direction of the threaded rod 11, drive the second beam 3 to move to the overlapping position of the bolt hole 12 and the second bolt hole 13, and then fix the second beam 3 with bolts , In the process again, the connecting rod 17 will move in the direction of the first inlet slot 8, and each bolt hole and the installation through hole will be automatically aligned one by one, which is convenient to operate, saves time and effort to install the device, and improves the fixing time. The connection between the beam 4, the first beam 2, the second beam 3 and the main beam 1 is fixed, which improves the stability of the device.

需要说明的是,在本文中,诸如第一和第二等之类的关系术语仅仅用来将一个实体或者操作与另一个实体或操作区分开来,而不一定要求或者暗示这些实体或操作之间存在任何这种实际的关系或者顺序。而且,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。It should be noted that, in this document, relational terms such as first and second are used only to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any relationship between these entities or operations. any such actual relationship or sequence exists. Moreover, the terms "comprising", "comprising" or any other variation thereof are intended to encompass a non-exclusive inclusion such that a process, method, article or device comprising a list of elements includes not only those elements, but also includes not explicitly listed or other elements inherent to such a process, method, article or apparatus.

尽管已经示出和描述了本实用新型的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本实用新型的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本实用新型的范围由所附权利要求及其等同物限定。Although the embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes and modifications can be made to these embodiments without departing from the principles and spirit of the present invention , alternatives and modifications, the scope of the present invention is defined by the appended claims and their equivalents.

Claims (8)

1.一种建筑支撑钢梁结构,其特征在于,包括:1. a building support steel beam structure, is characterized in that, comprises: 主梁(1),对称设置在楼面两侧;The main beam (1) is symmetrically arranged on both sides of the floor; 第一次梁(2)和第二次梁(3),对称设置在主梁(1)的顶部;The first beam (2) and the second beam (3) are symmetrically arranged on the top of the main beam (1); 固定次梁(4),固定在两个所述主梁(1)的一端;The secondary beams (4) are fixed on one end of the two main beams (1); 调节机构(5),滑动连接在第一次梁(2)和第二次梁(3)之间;an adjustment mechanism (5), slidably connected between the first beam (2) and the second beam (3); 所述调节机构(5)包括:The adjusting mechanism (5) includes: 第一滑槽(6),对称设置在固定次梁(4)的两端;The first chute (6) is symmetrically arranged at both ends of the fixed secondary beam (4); 第二滑槽(7),对称设置在所述第一次梁(2)和所述第二次梁(3)的两端;The second chute (7) is symmetrically arranged at both ends of the first secondary beam (2) and the second secondary beam (3); 连接杆(17),对称滑动连接在第一滑槽(6)和第二滑槽(7)之间,所述连接杆(17)的两端的对称固定有限位柱(10),且限位柱(10)与所述第一滑槽(6)、或与所述第二滑槽(7)滑动连接;A connecting rod (17) is symmetrically slidably connected between the first chute (6) and the second chute (7), and limit posts (10) are symmetrically fixed at both ends of the connecting rod (17), and are limited The column (10) is slidably connected with the first chute (6) or with the second chute (7); 第一入口槽(8),设置在所述第一滑槽(6)的一端,且所述第一入口槽(3)与第一滑槽(6)连通设置,用于所述连接杆(17)连入所述第一滑槽(6)内;A first inlet slot (8) is provided at one end of the first chute (6), and the first inlet slot (3) is communicated with the first chute (6) and is used for the connecting rod ( 17) Connected into the first chute (6); 第二入口槽(9),设置在所述第二滑槽(8)的一端,且所述第二入口槽(9)与第二滑槽(8)连通设置,用于所述连接杆(17)连入所述第一滑槽(6)内;A second inlet slot (9) is provided at one end of the second chute (8), and the second inlet slot (9) is communicated with the second chute (8) and is used for the connecting rod ( 17) Connected into the first chute (6); 螺纹杆(11),通过轴承转动连接在固定次梁(4)的中部,所述第一次梁(2)的中部开设有螺纹孔,所述第一次梁(2)通过螺纹孔与螺纹杆(11)螺纹连接。The threaded rod (11) is rotatably connected to the middle of the fixed secondary beam (4) through a bearing, the middle of the primary beam (2) is provided with a threaded hole, and the primary beam (2) is connected to the thread through the threaded hole (2). The rod (11) is threaded. 2.根据权利要求1所述的一种建筑支撑钢梁结构,其特征在于:所述第一次梁(2)、第二次梁(3)和所述固定次梁(4)的两端设置有用于滑动包裹所述主梁(1)的配对槽,所述第一次梁(2)、第二次梁(3)和所述固定次梁(4)组成次梁总成。2. A steel beam structure for building support according to claim 1, characterized in that: both ends of the first primary beam (2), the second secondary beam (3) and the fixed secondary beam (4) A paired groove is provided for slidingly wrapping the main beam (1), and the first secondary beam (2), the second secondary beam (3) and the fixed secondary beam (4) form a secondary beam assembly. 3.根据权利要求1所述的一种建筑支撑钢梁结构,其特征在于:所述主梁(1)的一侧等距开设有螺栓孔(12),所述固定次梁(4)、所述第一次梁(2)和所述第二次梁(3)两端开设有安装通孔(13),所述螺栓孔(12)和所述安装通孔(13)之间通过螺栓固定连接。3. A building support steel beam structure according to claim 1, characterized in that: one side of the main beam (1) is provided with bolt holes (12) at equal distances, and the fixed secondary beams (4), Installation through holes (13) are provided at both ends of the first primary beam (2) and the second secondary beam (3), and bolts pass between the bolt holes (12) and the installation through holes (13). Fixed connection. 4.根据权利要求3所述的一种建筑支撑钢梁结构,其特征在于:所述固定次梁(4)、所述第一次梁(2)和所述第二次梁(3)的两端均设置平行设置有两块弹性板(16),两块所述弹性板(16)上均设置有所述安装通孔(13),且两个所述安装通孔(13)对位。4. A building support steel beam structure according to claim 3, characterized in that: the fixed secondary beam (4), the first secondary beam (2) and the second secondary beam (3) Two elastic plates (16) are arranged in parallel on both ends, the two elastic plates (16) are provided with the installation through holes (13), and the two installation through holes (13) are aligned in position . 5.根据权利要求4所述的一种建筑支撑钢梁结构,其特征在于:所述第二次梁(3)的中部开设有通孔(14),所述螺纹杆(11)穿过通孔(14)设置。5. A steel beam structure for building support according to claim 4, characterized in that: a through hole (14) is opened in the middle of the second beam (3), and the threaded rod (11) passes through the through hole (14). A hole (14) is provided. 6.根据权利要求1所述的一种建筑支撑钢梁结构,其特征在于:所述螺纹杆(11)靠近固定次梁(4)的一端固定有转块(15)。6 . The steel beam structure for building support according to claim 1 , wherein a turning block ( 15 ) is fixed at one end of the threaded rod ( 11 ) close to the fixed secondary beam ( 4 ). 7 . 7.根据权利要求1所述的一种建筑支撑钢梁结构,其特征在于:所述连接杆(17)的长度小于第一次梁(2)和第二次梁(3)之间的距离。7. A building support steel beam structure according to claim 1, characterized in that: the length of the connecting rod (17) is less than the distance between the first beam (2) and the second beam (3) . 8.根据权利要求1所述的一种建筑支撑钢梁结构,其特征在于:所述主梁(1)的两侧对称开设有固定槽(18)。8 . The steel beam structure for building support according to claim 1 , wherein fixing grooves ( 18 ) are symmetrically opened on both sides of the main beam ( 1 ). 9 .
CN202121813013.2U 2021-08-04 2021-08-04 Building support steel beam structure Expired - Fee Related CN216380245U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121813013.2U CN216380245U (en) 2021-08-04 2021-08-04 Building support steel beam structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121813013.2U CN216380245U (en) 2021-08-04 2021-08-04 Building support steel beam structure

Publications (1)

Publication Number Publication Date
CN216380245U true CN216380245U (en) 2022-04-26

Family

ID=81238988

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121813013.2U Expired - Fee Related CN216380245U (en) 2021-08-04 2021-08-04 Building support steel beam structure

Country Status (1)

Country Link
CN (1) CN216380245U (en)

Similar Documents

Publication Publication Date Title
CN207794609U (en) One kind accurately adjusting compound jacking
CN216380245U (en) Building support steel beam structure
CN207144474U (en) A kind of reinforcement tools for oblique circular cylinder formwork reinforcement
CN217759861U (en) Adjustable platform for pipeline construction under platform beam
CN211547392U (en) Positioning device for mounting arch rib of tied arch bridge
CN214384043U (en) Scaffold frame of encorbelmenting of building engineering construction usefulness
CN210878249U (en) Steel pipe welding assembly platform
CN112072581A (en) Pipeline erecting device for assembled wall
CN210002877U (en) Back ridge external corner active diagonal pulling device in aluminum alloy template system
CN201620592U (en) Scaffold double steel pipe welding base
CN219554515U (en) Bridge structure
CN209339327U (en) A prefabricated node for building structure
CN114232965A (en) Combined supporting device for overhanging scaffold and using method
CN223661064U (en) A building support connector
CN209384648U (en) A kind of construction assembled supporting construction
CN206073995U (en) Detection tool for verticality of aluminum alloy template
CN220848969U (en) Adjustable steel diagonal column supporting device
CN223706870U (en) A steel structure support column that is easy to connect
CN220580621U (en) Reinforcing and connecting device for building structure
CN206000167U (en) Adjustable Alminum Project slab form support meanss
CN223088888U (en) Anti-overturning triangular bracket
CN219471206U (en) a building support
CN224031499U (en) Bridge temporary structure falsework system with retractable cross bracing
CN223410480U (en) Angle-adjustable scaffolding support structure
CN222594880U (en) Movable safety protection device on supporting beam

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20220426

CF01 Termination of patent right due to non-payment of annual fee