CN216307601U - Temporary lighting bracket on roof truss - Google Patents

Temporary lighting bracket on roof truss Download PDF

Info

Publication number
CN216307601U
CN216307601U CN202122239493.2U CN202122239493U CN216307601U CN 216307601 U CN216307601 U CN 216307601U CN 202122239493 U CN202122239493 U CN 202122239493U CN 216307601 U CN216307601 U CN 216307601U
Authority
CN
China
Prior art keywords
screw
side props
roof truss
bracket
length
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122239493.2U
Other languages
Chinese (zh)
Inventor
董鑫
纪磊
李博
王丽丽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Shougang Construction Group Co Ltd
Original Assignee
Beijing Shougang Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Shougang Construction Group Co Ltd filed Critical Beijing Shougang Construction Group Co Ltd
Priority to CN202122239493.2U priority Critical patent/CN216307601U/en
Application granted granted Critical
Publication of CN216307601U publication Critical patent/CN216307601U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model provides a interim lighting bracket on roof truss, belongs to frame steel construction installation construction technical field. Comprises a hoop (1), a screw (2), a connecting plate (3), an inclined stay (4), a vertical plate (5) and a sleeve (6); screw (2) are twisted into clamp (1) and are fixed, two connecting plates (3) are respectively with two liang of welded fastening of four clamps (1), two to one side props (4) one end respectively with two connecting plates (3) welding, two to one side props (4) other end welding in the both sides face of riser (5), two to one side props (4) contained angle 60, sleeve pipe (6) welded fastening is in the contained angle of two to one side props (4). The advantage lies in that the equipment is simple, convenient operation, and simple and practical has avoided the use of lighting fixture and crane, has saved manpower and materials, has effectively ensured the illumination of being under construction night. The construction cost is reduced.

Description

Temporary lighting bracket on roof truss
Technical Field
The utility model belongs to the technical field of installation and construction of frame steel structures, and particularly provides a temporary lighting bracket on a roof truss.
Background
During the installation and construction of the frame steel structure, a lamp bracket lighting mode is generally adopted for night work lighting, and the mode has the disadvantages that the lamp bracket needs a large amount of steel for welding and processing, an independent foundation needs to be made for the lamp bracket, and a crane is needed for matching when the lamp bracket is installed, so that a large amount of manpower and material resources are consumed; secondly, after the construction is finished, the lamp bracket needs to be detached and cut by a crane in a matching way, most materials form waste materials, and the construction cost is increased.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a temporary lighting bracket on a roof truss, wherein a hoop of the temporary lighting bracket is fixed with a lower flange plate at the ridge top of a roof truss beam through a screw, a group of temporary lighting brackets are arranged at the ridge top of each adjacent roof truss beam, a cross rod penetrates through a sleeve on the temporary lighting bracket, and then a lighting lamp is arranged on the cross rod, so that the lighting requirement of night construction is met.
The temporary lighting bracket comprises a hoop 1, a screw 2, a connecting plate 3, a diagonal bracing 4, a vertical plate 5 and a sleeve 6 which are used in combination; screw 2 is twisted into clamp 1 and is fixed, two connecting plates 3 respectively with two liang of welded fastening of four clamps 1, two 4 one ends of diagonal brace respectively with two connecting plates 3 welding, two 4 other end welding of diagonal brace are at the both sides face of riser 5, two 4 contained angles of diagonal brace 60, and 6 welded fastening of sleeve pipe is in the contained angle of two diagonal braces 4. Wherein the hoop 1 is processed from a 14mm thick steel plate, and the size (length, width, height) is 120, 100 and 50 mm; the diameter of the screw 2 is 14mm, and the length of the screw is 40 mm; the connecting plate 3 is machined from a 12mm thick steel plate and has the size (length and width) of 200 and 120 mm; the diagonal braces 4 are processed by round pipes with the diameter of 80mm, and each is 600mm long; the vertical plate 5 is processed by a thick steel plate with the thickness of 14mm, and the size (length and width) is 150 and 150 mm; the sleeve 6 is formed by processing a circular tube with the diameter of 50mm and the length of 120mm (figures 1 and 2).
During the use, pass through screw 2 fixed with the lower flange board of hoop 1 of interim illumination bracket and 7 crest positions of roof truss roof beam, 7 crest positions of every adjacent roof truss roof beam set up a set of interim illumination bracket, then pass sleeve pipe 6 on the interim illumination bracket with horizontal pole 8, later set up illumination lamps and lanterns 9 on horizontal pole 8, satisfy the illumination demand of being under construction night. After the construction is finished, the temporary lighting bracket can be protectively removed by loosening the screw 2 and can be reused (fig. 3 and 4).
The utility model has the advantages of simple assembly, convenient operation, simplicity and practicality, avoids the use of lamp brackets and cranes, saves manpower and material resources and effectively ensures night construction illumination. The construction cost is reduced.
Drawings
Fig. 1 is a front view of a temporary lighting fixture.
Fig. 2 is a side view of a temporary lighting bracket.
Fig. 3 is a front view of the temporary lighting bracket in use.
Fig. 4 is a side view of the temporary lighting bracket in use.
In the figure, a hoop 1, a screw 2, a connecting plate 3, a diagonal brace 4, a vertical plate 5, a sleeve 6, a roof truss beam 7, a cross rod 8 and a lighting lamp 9.
Detailed Description
Fig. 1-4 illustrate an embodiment of the present invention. The utility model is further described below with reference to the accompanying drawings.
The temporary lighting bracket comprises a hoop 1, screws 2, connecting plates 3, diagonal braces 4, a vertical plate 5 and a sleeve 6, wherein the combination use is realized, the screws 2 are screwed into the hoop 1 for fixation, the two connecting plates 3 are respectively welded and fixed with the four hoops 1 in pairs, one ends of the two diagonal braces 4 are respectively welded with the two connecting plates 3, the other ends of the two diagonal braces 4 are welded on the two side surfaces of the vertical plate 5, the included angle of the two diagonal braces 4 is 60 degrees, and the sleeve 6 is welded and fixed in the included angle of the two diagonal braces 4. Wherein the hoop 1 is processed from a 14mm thick steel plate, and the size (length, width, height) is 120, 100 and 50 mm; the diameter of the screw 2 is 14mm, and the length of the screw is 40 mm; the connecting plate 3 is machined from a 12mm thick steel plate and has the size (length and width) of 200 and 120 mm; the diagonal braces 4 are processed by round pipes with the diameter of 80mm, and each is 600mm long; the vertical plate 5 is processed by a thick steel plate with the thickness of 14mm, and the size (length and width) is 150 and 150 mm; the sleeve 6 is formed by processing a circular tube with the diameter of 50mm and the length of 120 mm.
During the use, pass through screw 2 fixed with the lower flange board of hoop 1 of interim illumination bracket and 7 crest positions of roof truss roof beam, 7 crest positions of every adjacent roof truss roof beam set up a set of interim illumination bracket, then pass sleeve pipe 6 on the interim illumination bracket with horizontal pole 8, later set up illumination lamps and lanterns 9 on horizontal pole 8, satisfy the illumination demand of being under construction night. After the construction is finished, the temporary lighting bracket can be protectively removed by loosening the screw 2 and can be repeatedly used.
When being under the installation and construction of the logistics warehouse framework steel structure, the temporary lighting bracket on the roof truss is adopted for night lighting operation, and a good effect is obtained. This interim lighting bracket includes clamp, screw, connecting plate, diagonal brace, riser, sleeve pipe 6 part, and the combination is used, twists the clamp with the screw and fixes, two connecting plates respectively with two liang of welded fastening of four clamps, two diagonal braces one end respectively with two connecting plate welding, two diagonal braces other end welding are at the both sides face of riser, two diagonal braces contained angles 60, and sleeve pipe welded fastening is in the contained angle of two diagonal braces. During the use, pass through the fix with screw with the lower flange board of hoop and the roof truss roof beam crest position of interim illumination bracket, every adjacent roof truss roof beam crest position sets up a set of interim illumination bracket, then passes the sleeve pipe on the interim illumination bracket with the horizontal pole, later sets up illumination lamps and lanterns on the horizontal pole, satisfies the illumination demand of being under construction night. After the construction is finished, the temporary lighting bracket can be protectively removed by loosening the screw, and the temporary lighting bracket can be repeatedly used.

Claims (2)

1. A temporary lighting bracket on a roof truss is characterized by comprising a hoop (1), a screw (2), a connecting plate (3), a diagonal brace (4), a vertical plate (5) and a sleeve (6); screw (2) are twisted into clamp (1) and are fixed, two connecting plates (3) are respectively with two liang of welded fastening of four clamps (1), two to one side props (4) one end respectively with two connecting plates (3) welding, two to one side props (4) other end welding in the both sides face of riser (5), two to one side props (4) contained angle 60, sleeve pipe (6) welded fastening is in the contained angle of two to one side props (4).
2. A temporary lighting bracket on a roof truss according to claim 1 wherein the clip (1) is machined from 14mm thick steel plate, the dimensions length by width by height being 120 by 100 by 50 mm; the diameter of the screw (2) is 14mm, and the length of the screw is 40 mm; the connecting plate (3) is processed by a 12mm thick steel plate, and the length and the width of the connecting plate are 200 mm and 120 mm; the diagonal bracing (4) is formed by processing circular tubes with the diameter of 80mm, and each diagonal bracing is 600mm long; the vertical plate (5) is processed by a thick steel plate with the thickness of 14mm, and the length and the width of the vertical plate are 150mm and 150 mm; the sleeve (6) is formed by processing a circular tube with the diameter of 50mm and the length of 120 mm.
CN202122239493.2U 2021-09-15 2021-09-15 Temporary lighting bracket on roof truss Active CN216307601U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122239493.2U CN216307601U (en) 2021-09-15 2021-09-15 Temporary lighting bracket on roof truss

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122239493.2U CN216307601U (en) 2021-09-15 2021-09-15 Temporary lighting bracket on roof truss

Publications (1)

Publication Number Publication Date
CN216307601U true CN216307601U (en) 2022-04-15

Family

ID=81111719

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122239493.2U Active CN216307601U (en) 2021-09-15 2021-09-15 Temporary lighting bracket on roof truss

Country Status (1)

Country Link
CN (1) CN216307601U (en)

Similar Documents

Publication Publication Date Title
CN216307601U (en) Temporary lighting bracket on roof truss
CN216587872U (en) Supporting device
CN222101131U (en) An assembled building steel structure roof truss
CN217631491U (en) Support for steel structure overhanging floor bearing plate
CN216405457U (en) Foundation raft template reinforcing device
CN212317536U (en) Simply set up design and face limit safety protection support
CN113123525B (en) Corrosion-resistant concrete beam skeleton and manufacturing method
CN218668507U (en) Steel bar truss floor support plate supporting structure
CN214424017U (en) Large-size component short-edge template reinforcing device
CN211776192U (en) Steel structure factory building
CN212535053U (en) Side wall unilateral template support system combining composite fiber template and steel truss
CN210029824U (en) Novel tower crane is adhered to device
CN214790961U (en) Large-scale lamps and lanterns fixing support on riser
CN210828556U (en) Reinforcing structure of angle steel component and truss iron tower
CN221919892U (en) Prefabricated shear wall of quick installation
CN211286901U (en) A kind of angle steel tower foot reinforcement and reinforcement device
CN219175620U (en) Hanging rod for construction of conversion layer suspended ceiling
CN212893436U (en) Temporary hoisting device matched with pipe supporting beam for use
CN216276824U (en) A construction tool for on high altitude truss car roof beam
CN206753097U (en) Protection mechanism for metal roofing board installation
CN221961765U (en) Flexible support beam structure adaptable to mountain bodies with different angles
CN219711091U (en) Cantilever component supporting device
CN214328552U (en) Truss piece that connects between steel-pipe column that can freely adjust
CN219637823U (en) Expansion joint department stagnant water copper reinforcement instrument
CN220550721U (en) Wallboard connecting structure of steel structure factory building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant