CN216240111U - Safety barrier for construction - Google Patents

Safety barrier for construction Download PDF

Info

Publication number
CN216240111U
CN216240111U CN202121960498.8U CN202121960498U CN216240111U CN 216240111 U CN216240111 U CN 216240111U CN 202121960498 U CN202121960498 U CN 202121960498U CN 216240111 U CN216240111 U CN 216240111U
Authority
CN
China
Prior art keywords
blocking
construction
clamping
fixing
baffle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121960498.8U
Other languages
Chinese (zh)
Inventor
马洋洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chizhou Senhai Construction Engineering Co ltd
Original Assignee
Chizhou Senhai Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chizhou Senhai Construction Engineering Co ltd filed Critical Chizhou Senhai Construction Engineering Co ltd
Priority to CN202121960498.8U priority Critical patent/CN216240111U/en
Application granted granted Critical
Publication of CN216240111U publication Critical patent/CN216240111U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a safety guardrail for building construction, which comprises a blocking mechanism, wherein the blocking mechanism comprises a baffle and clamping hooks, two clamping hooks are respectively arranged on two sides of the baffle, each clamping hook is connected with a clamping seat, and the two clamping seats on two sides are respectively arranged on a vertical pipe; the device also comprises a fixing mechanism which is arranged below the blocking mechanism and is used for fixing and supporting the blocking mechanism. Compared with the traditional fixed guard rail, the fixed guard rail is required to be disassembled after the project is finished, so that the waste of materials is caused, the construction time and the construction difficulty are also increased, the guard rail is of a detachable structure, the installation can be conveniently and rapidly carried out, the repeated utilization is convenient, and the practicability is high.

Description

Safety barrier for construction
Technical Field
The utility model relates to the technical field of buildings, in particular to a safety guardrail for building construction.
Background
Guardrail-here refers to industrial "protective fence", and guardrail is mainly used in the protection and protection of people's personal safety and equipment and facilities in occasions such as house, highway, commercial district, public place, and the like, and guardrail is seen everywhere in our life. The price per meter length of the guardrail can also be different according to the height. Guard rails are commonly made of steel, such as: stainless steel, round steel pipe, square steel pipe or profiled steel sheet, iron wire, surface treatment process: full-automatic electrostatic powder spraying (namely plastic spraying) or paint spraying, and the aluminum alloy material is more popular in recent years for splicing and assembling type guardrails. The stand of guardrail passes through expansion bolts and fixes with ground, installs usually in if commodity circulation passageway both sides, production facility periphery, building corner, the both sides of door and goods platform border etc. bring the damage of equipment, facility that unexpected striking caused when effectively reducing and exempting from haulage equipment to shuttle back and forth, the guardrail material has: aluminum alloy, malleable steel, carbon steel, stainless steel, plastic steel, zinc steel, PVC and other metal guardrails and the like.
However, the existing safety guardrail for building construction is not convenient to assemble and disassemble due to the simple structure and single function, so that the construction time and difficulty are increased, and the practicability is not strong.
SUMMERY OF THE UTILITY MODEL
The present invention has been made to solve the above problems, and an object of the present invention is to provide a safety fence for building construction.
The utility model realizes the purpose through the following technical scheme:
a safety guardrail for building construction comprises a blocking mechanism, wherein the blocking mechanism comprises a baffle and clamping hooks, two clamping hooks are respectively arranged on two sides of the baffle, each clamping hook is connected with a clamping seat, and the two clamping seats on two sides are respectively arranged on a vertical pipe;
the device also comprises a fixing mechanism which is arranged below the blocking mechanism and is used for fixing and supporting the blocking mechanism.
Preferably: the fixing mechanism comprises a bottom plate, sleeves and locking pieces, the upper end of the bottom plate is installed at a position corresponding to the two vertical pipes, and the sleeves are connected with the corresponding vertical pipes through the locking pieces.
With the arrangement, the vertical pipe is inserted into the corresponding sleeve and is fixed by the locking piece, and the blocking mechanism is fixed.
Preferably: the fixing mechanism comprises an adjusting frame, two adjusting frames are arranged on two sides of the sleeve, a connecting piece and a connecting rod are arranged on each adjusting frame, the connecting rods are arranged at the rear portions of the connecting pieces, the connecting rods are arranged at the upper ends of the bottom plates, and the bottom plates are connected with the connecting rods in a welding mode.
According to the arrangement, the corresponding vertical pipe is inserted into the sleeve, the position of the connecting piece is adjusted to be corresponding to the corresponding connecting rod, then the connecting rod and the connecting piece are fixed through screws, and then the locking piece is inserted into the sleeve, so that the blocking mechanism is installed and fixed.
Preferably: the clamping hook is connected with the baffle in a welding mode, and the vertical pipe is connected with the clamping seat in a welding mode.
So set up, through welded connection guaranteed certain joint strength between interconnect's the two.
Preferably: the sleeve is connected with the bottom plate in a welding mode.
So configured, the sleeve is used to mount the standpipe.
Preferably: the connecting piece with the connecting rod passes through screw fastening connection, the adjusting frame with the sleeve pipe passes through welded connection.
So set up, the adjusting frame is used for the installation the connecting piece is fixed between the two of convenient connection through screw fastening connection.
Compared with the prior art, the utility model has the following beneficial effects:
compare traditional fixed rail guard, wait after the engineering, still need dismantle, caused the waste of material, also increaseed the time and the degree of difficulty of construction, this guardrail is detachable construction, installation that can convenient and fast to reuse repeatedly many times, the practicality is stronger.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
FIG. 1 is a schematic structural view of a first embodiment of a safety barrier for building construction according to the present invention;
FIG. 2 is a front view of a first embodiment of a safety barrier for construction according to the present invention;
FIG. 3 is a schematic structural view of a second embodiment of the safety barrier for building construction according to the present invention;
fig. 4 is a front view of a second embodiment of the safety barrier for building construction according to the present invention.
The reference numerals are explained below:
1. a blocking mechanism; 11. a baffle plate; 12. a hook; 13. a vertical tube; 14. a card holder; 2. a fixing mechanism; 21. a base plate; 22. a connecting rod; 23. an adjusting frame; 24. a sleeve; 25. a connecting member; 26. a locking member.
Detailed Description
In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", and the like, indicate orientations or positional relationships based on those shown in the drawings, and are used only for convenience in describing the present invention and for simplicity in description, and do not indicate or imply that the referenced devices or elements must have a particular orientation, be constructed and operated in a particular orientation, and thus, are not to be construed as limiting the present invention. Furthermore, the terms "first", "second", etc. are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first," "second," etc. may explicitly or implicitly include one or more of that feature. In the description of the present invention, "a plurality" means two or more unless otherwise specified.
In the description of the present invention, it should be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning either a fixed connection, a removable connection, or an integral connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood by those of ordinary skill in the art through specific situations.
The utility model will be further described with reference to the accompanying drawings in which:
example 1
As shown in fig. 1-2, a safety barrier for building construction comprises a blocking mechanism 1, wherein the blocking mechanism 1 comprises a baffle 11 and hooks 12, two hooks 12 are respectively installed on two sides of the baffle 11, each hook 12 is connected with a clamping seat 14, and the two clamping seats 14 on two sides are respectively installed on a vertical pipe 13;
the device also comprises a fixing mechanism 2 which is arranged below the blocking mechanism 1 and is used for fixing and supporting the blocking mechanism.
Preferably: the fixing mechanism 2 comprises a bottom plate 21, sleeves 24 and locking pieces 26, the sleeves 24 are mounted at the upper end of the bottom plate 21 and at positions corresponding to the two vertical pipes 13, the sleeves 24 are connected with the corresponding vertical pipes 13 through the locking pieces 26, the vertical pipes 13 are inserted into the corresponding sleeves 24 and are fixed through the locking pieces 26, and then the blocking mechanism 1 is fixed; the clamping hook 12 is connected with the baffle 11 through welding, the vertical pipe 13 is connected with the clamping seat 14 through welding, and certain connecting strength between the two parts which are connected with each other is ensured through welding; the sleeve 24 is connected with the bottom plate 21 in a welding mode, and the sleeve 24 is used for installing the vertical pipe 13.
Example 2
As shown in fig. 3-4, a safety barrier for building construction comprises a blocking mechanism 1, wherein the blocking mechanism 1 comprises a baffle plate 11 and hooks 12, two hooks 12 are respectively installed on two sides of the baffle plate 11, each hook 12 is connected with a clamping seat 14, and the two clamping seats 14 on two sides are respectively installed on a vertical pipe 13;
the device also comprises a fixing mechanism 2 which is arranged below the blocking mechanism 1 and is used for fixing and supporting the blocking mechanism.
Preferably: the fixing mechanism 2 comprises adjusting frames 23, the adjusting frames 23 are mounted on two sides of two sleeves 24, a connecting piece 25 is mounted on each adjusting frame 23, a connecting rod 22 is mounted at the rear part of each connecting piece 25, the connecting rod 22 is mounted at the upper end of the bottom plate 21, the bottom plate 21 is connected with the connecting rod 22 in a welding mode, the corresponding vertical pipe 13 is inserted into the sleeve 24, the position of each connecting piece 25 is adjusted to enable the connecting pieces to correspond to the corresponding connecting rod 22, then the connecting rods 22 and the connecting pieces 25 are fixed through screws, and then the locking pieces 26 are inserted into the sleeves 24 to achieve mounting and fixing of the blocking mechanism 1; the clamping hook 12 is connected with the baffle 11 through welding, the vertical pipe 13 is connected with the clamping seat 14 through welding, and certain connecting strength between the two parts which are connected with each other is ensured through welding; the connecting piece 25 is fastened and connected with the connecting rod 22 through screws, the adjusting frame 23 is connected with the sleeve 24 through welding, the adjusting frame 23 is used for installing the connecting piece 25, and the connecting piece 25 and the sleeve are conveniently connected and fixed through fastening and connecting of the screws.
The working principle and the using method of the utility model are as follows: when the vertical pipe fixing device is used, the corresponding vertical pipe 13 is inserted into the sleeve pipe 24, then the locking piece 26 is used for fixing and locking, or the vertical pipe 13 is inserted into the sleeve pipe 24, the position of the connecting piece 25 is moved to enable the vertical pipe 13 to correspond to the connecting rod 22, the fastening screw on the connecting piece is tightened, the vertical pipe 13 and the sleeve pipe 24 are fixed through the locking piece 26, and finally the clamping hooks 12 on two sides of the baffle plate 11 are connected with the corresponding clamping seats 14.
The foregoing illustrates and describes the principles, general features, and advantages of the present invention. It will be understood by those skilled in the art that the present invention is not limited to the embodiments described above, which are described in the specification and illustrated only to illustrate the principle of the present invention, but that various changes and modifications may be made therein without departing from the spirit and scope of the present invention, which fall within the scope of the utility model as claimed.

Claims (6)

1. The utility model provides a safety barrier for construction which characterized in that: the device comprises a blocking mechanism (1), wherein the blocking mechanism (1) comprises a baffle (11) and clamping hooks (12), two clamping hooks (12) are respectively installed on two sides of the baffle (11), each clamping hook (12) is connected with a clamping seat (14), and the two clamping seats (14) on two sides are respectively installed on a vertical pipe (13);
the device also comprises a fixing mechanism (2) which is arranged below the blocking mechanism (1) and is used for fixing and supporting the blocking mechanism.
2. The safety fence for construction according to claim 1, characterized in that: the fixing mechanism (2) comprises a bottom plate (21), sleeves (24) and locking pieces (26), the sleeves (24) are installed at the positions, corresponding to the vertical pipes (13), of the upper end of the bottom plate (21), and the sleeves (24) are connected with the corresponding vertical pipes (13) through the locking pieces (26).
3. The safety fence for construction according to claim 2, wherein: fixed establishment (2) are including adjusting frame (23), two the both sides of sleeve pipe (24) are all installed adjust frame (23), every all install connecting piece (25), every on adjusting frame (23) connecting rod (22) are all installed to the rear portion of connecting piece (25), install connecting rod (22) the upper end of bottom plate (21), bottom plate (21) with connecting rod (22) are through welded connection.
4. The safety fence for construction according to claim 1, characterized in that: the clamping hook (12) is connected with the baffle (11) through welding, and the vertical pipe (13) is connected with the clamping seat (14) through welding.
5. The safety fence for construction according to claim 2, wherein: the sleeve (24) is connected with the bottom plate (21) in a welding mode.
6. The safety fence for construction according to claim 3, wherein: the connecting piece (25) is fixedly connected with the connecting rod (22) through screws, and the adjusting frame (23) is connected with the sleeve (24) through welding.
CN202121960498.8U 2021-08-20 2021-08-20 Safety barrier for construction Active CN216240111U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121960498.8U CN216240111U (en) 2021-08-20 2021-08-20 Safety barrier for construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121960498.8U CN216240111U (en) 2021-08-20 2021-08-20 Safety barrier for construction

Publications (1)

Publication Number Publication Date
CN216240111U true CN216240111U (en) 2022-04-08

Family

ID=80983961

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121960498.8U Active CN216240111U (en) 2021-08-20 2021-08-20 Safety barrier for construction

Country Status (1)

Country Link
CN (1) CN216240111U (en)

Similar Documents

Publication Publication Date Title
CN216240111U (en) Safety barrier for construction
CN210508494U (en) Combined fairway
CN211923806U (en) Assembled temporary enclosure for construction of constructional engineering
CN216428972U (en) Scaffold for building electromechanical installation engineering
CN212154363U (en) Assembled guardrail rod for constructional engineering
CN213328818U (en) Steel guardrail
CN210067635U (en) Novel protective support structure for highway
CN216108995U (en) Frame connecting piece of steel construction joint department
CN213205212U (en) Green belt enclosure device
CN216304918U (en) Steel construction of factory building
CN216076241U (en) External protector of scaffold
CN216109254U (en) Pre-buried structure of structure floor prestressing force pipeline
CN213805024U (en) Building engineering warns protector
CN213015731U (en) Dust suppression device for building construction
CN215482374U (en) Continuous beam quick assembly disassembly faces limit protector
CN215631489U (en) Building templates operation platform
CN213015760U (en) Guardrail for building construction
CN210483117U (en) Edge protection device for color steel tile roof cornice
CN216239690U (en) Scaffold pedal unit with guardrail and scaffold working platform
CN210767916U (en) Elevartor shaft rail guard on building site
CN216110056U (en) Anti-theft guardrail net
CN216476264U (en) Fixing assembly for side-mounted electric hanging basket front support on flower stand beam
CN214883094U (en) Portable sound barrier support for quickly installing narrow section
CN206477596U (en) A kind of reusable concrete pump pipe mounting system
CN211201378U (en) Safety barrier for building easy to assemble

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant