CN216195528U - Assembled building element that can hoist fast - Google Patents

Assembled building element that can hoist fast Download PDF

Info

Publication number
CN216195528U
CN216195528U CN202122241057.9U CN202122241057U CN216195528U CN 216195528 U CN216195528 U CN 216195528U CN 202122241057 U CN202122241057 U CN 202122241057U CN 216195528 U CN216195528 U CN 216195528U
Authority
CN
China
Prior art keywords
wallboard
nut
plate
fixing plate
hoist
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122241057.9U
Other languages
Chinese (zh)
Inventor
万平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group International Engineering Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202122241057.9U priority Critical patent/CN216195528U/en
Application granted granted Critical
Publication of CN216195528U publication Critical patent/CN216195528U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model belongs to the technical field of assembly type building components, and discloses an assembly type building component capable of being quickly hoisted, which comprises a top plate and a wall plate, wherein a base is arranged above the top plate, a supporting plate is arranged at the bottom of the wall plate, a baffle is welded in the middle of the supporting plate, a first nut is arranged above the baffle, a screw rod is arranged at the bottom of the first nut, and a second nut is arranged in the middle of the screw rod; the wall plate and the top plate are connected through the screw rod, the structural strength is high, an auxiliary supporting component is not required to be installed, labor is saved, and the construction period is shortened.

Description

Assembled building element that can hoist fast
Technical Field
The utility model belongs to the technical field of fabricated building structures, and particularly relates to a fabricated building member capable of being quickly hoisted.
Background
Assembled building element mainly used prefabricated construction, according to the construction drawing, calculate suitable size, make required component (like the floor in advance at the mill, the wallboard, the stair, the balcony etc.), transport to the job site through the transport vechicle, through lifting by crane equipment, hoist building element hoist to the assembly position, current assembled building element when the installation, need install a large amount of auxiliary stay equipment, the artifical demand is great, the installation cost time is longer, influence the construction progress, special construction site, secondly, when making the wallboard, the deviation appears easily in grout sleeve position, influence later stage wallboard and the butt joint of the butt joint reinforcing bar of reserving.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide an assembly type building component capable of being hoisted quickly, and aims to solve the problems that a large amount of auxiliary supporting equipment is required to be installed when the existing assembly type building component is installed, the construction period is long, the position of a sleeve is deviated, and the existing assembly type building component cannot be butted with a butted steel bar.
In order to achieve the purpose, the utility model provides the following technical scheme: the utility model provides an assembled building element that can hoist fast, includes roof and wallboard, the top of roof is provided with base and butt joint reinforcing bar, the top of base sets up threaded hole, the bottom of wallboard is provided with the backup pad, the middle welding of backup pad has the baffle, the top of baffle is provided with first nut, the bottom of first nut is provided with the screw rod, the centre of screw rod is provided with the second nut.
Preferably, the bottom of wallboard is provided with the fixed plate, the inside of fixed plate is provided with the grout pipe, the outside of fixed plate has the grout mouth.
Preferably, a through hole is formed above the fixing plate, and a grouting layer is arranged inside the grouting pipe.
Preferably, the inside of wallboard is provided with longitudinal reinforcement, the outside of longitudinal reinforcement is provided with the horizontal stirrup.
Preferably, a mounting hole is formed above the fixing plate, threads are formed in the inner surface of the mounting hole, and the longitudinal steel bar is fixedly connected with the fixing plate through the mounting hole.
Preferably, the top of the wallboard is provided with a hanging hole, and a hanging nail is arranged in the hanging hole.
Compared with the prior art, the utility model has the following beneficial effects:
(1) the wall plate supporting structure is provided with the supporting plate, the base, the first nut, the second nut and the screw rod, the through hole is formed in the baffle in the middle of the supporting plate, one end of the screw rod is fixedly welded with the first nut and penetrates through the baffle, the second nut is sleeved below the baffle, the supporting plate and the base are respectively embedded in the wall plate and the top plate, four groups of supporting structures are arranged at the corners of the wall plate, the wall plate is hoisted to a proper position, the screw rod is screwed into the threaded hole of the base through the first nut, the angle and the height of the wall plate are adjusted through the second thread, the wall plate and the top plate are connected through the screw rod, the structural strength is high, an auxiliary supporting component does not need to be additionally installed, the labor is saved, the construction period is shortened, and the building efficiency is effectively improved.
(2) According to the fixing plate, the grouting pipeline is arranged in the fixing plate, the mounting hole is formed in the top of the fixing plate, the longitudinal steel bar is inserted into the mounting hole for fixing when the wall plate is prefabricated, the transverse stirrups are bound, the wood plate is fixed around the longitudinal steel bar, concrete is poured into the wood plate to form the prefabricated wall plate, the traditional single grouting pipe is replaced, the fixing plate is of an integral structure, fixing and mounting are convenient, meanwhile, the size is predetermined, deviation is not prone to occurring, and later-stage wall body and top plate assembly is not prone to being influenced.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a front view of the present invention;
FIG. 3 is a left side view of the present invention;
FIG. 4 is an enlarged view of the utility model at A;
FIG. 5 is a front view of a fixation plate of the present invention;
FIG. 6 is a cross-sectional view of a fixation plate of the present invention;
in the figure: 1. a top plate; 2. a base; 3. a transverse stirrup; 4. a wallboard; 5. hanging holes; 6. hanging nails; 7. longitudinal reinforcing steel bars; 8. a support plate; 9. a fixing plate; 10. butt-jointing reinforcing steel bars; 11. grouting layer; 12. a screw; 13. a baffle plate; 14. a first nut; 15. a second nut; 16. a threaded hole; 17. grouting ports; 18. mounting holes; 19. a through hole; 20. and (7) grouting pipes.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-6, the present invention provides the following technical solutions: the utility model provides an assembled building element that can hoist fast, including roof 1 and wallboard 4, the top of roof 1 is provided with base 2 and butt joint reinforcing bar 10, screw hole 16 is seted up to the top of base 2, the bottom of wallboard 4 is provided with backup pad 8, the centre welding of backup pad 8 has baffle 13, the top of baffle 13 is provided with first nut 14, the bottom of first nut 14 is provided with screw rod 12, the centre of screw rod 12 is provided with second nut 15, screw rod 12 passes baffle 13 and first nut 14 welding, and twist second nut 15 in the below, it is pre-buried at wallboard 4 turning together with backup pad 8, this bearing structure is provided with four groups altogether, it is fixed with roof 1 with wallboard 4 through screw rod 12 and base 2, and through adjusting the angle and the height of four second nuts 15 regulation wallboards.
Further, the bottom of the wall plate 4 is provided with a fixing plate 9, a grouting pipe 20 is arranged inside the fixing plate 9, a grouting opening 17 is formed in the outer portion of the fixing plate 9, the size of the fixing plate 9 is determined according to requirements, the grouting pipe 20 is communicated with the grouting opening 17, and the top and the bottom of each grouting pipe 20 are respectively provided with one grouting opening 17.
Furthermore, a through hole 19 is formed above the fixing plate 9, a grouting layer 11 is arranged inside the grouting pipe 20, the fixing plate 9 is hollow and provided with a plurality of through holes 19, and concrete flows into the fixing plate 9 through the through holes 19 to enable the fixing plate 9 to be tightly connected with the wall plate 4.
Specifically, wallboard 4's inside is provided with longitudinal reinforcement 7, and longitudinal reinforcement 7's outside is provided with horizontal stirrup 3, and longitudinal reinforcement 7 ties up through the steel wire with horizontal stirrup 3, effectively improves wallboard 4's structural strength.
It should be noted that a mounting hole 18 is formed above the fixing plate 9, a thread is formed on an inner surface of the mounting hole 18, and the longitudinal steel bar 7 is fixedly connected with the fixing plate 9 through the mounting hole 18.
Further, hanging hole 5 has been seted up at the top of wallboard 4, and the internally mounted of hanging hole 5 has peg 6, and when wallboard 4 pour, will form the mould of hanging hole 5 and peg 6 pre-buried inside wallboard 4, demolish the mould after pouring, form hanging hole 5, and peg 6 uses with supporting couple together.
The working principle and the using process of the utility model are as follows: when the utility model is used, the wall plate 4 template is built according to the size, the fixing plate 9 is placed at the bottom of the template, the longitudinal steel bar 7 is inserted into the mounting hole 18, in the stranded transverse stirrup 3, a support plate 8, a hanging hole die and a hanging nail 6 are fixed at proper positions, concrete is poured, a template and the hanging hole die are removed to form a wall plate and a hanging hole 5, a hook hooks the hanging nail 6 in the hanging hole 5, the wall plate 4 is hoisted to an installation position, a base 2 and a butt-joint reinforcing steel bar 10 are pre-embedded in a top plate 1, aligning the position, dropping the wall plate 4, inserting the butt-joint reinforcing steel bar 10 into the grouting pipe 20, screwing the screw 12 into the threaded hole 16 of the base 2, the installation height and the angle of the wall plate 4 are adjusted through the second nut 15, after the installation is finished, grouting material is poured from a lower grouting opening 17 through grouting equipment, when other grouting openings 17 flow out grouting materials, the grouting materials are sequentially blocked until the grouting layer 11 is completely formed.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a can hoist assembled building element fast, includes roof (1) and wallboard (4), its characterized in that: the top of roof (1) is provided with base (2) and butt joint reinforcing bar (10), screw hole (16) are seted up to the top of base (2), the bottom of wallboard (4) is provided with backup pad (8), the centre welding of backup pad (8) has baffle (13), the top of baffle (13) is provided with first nut (14), the bottom of first nut (14) is provided with screw rod (12), the centre of screw rod (12) is provided with second nut (15).
2. The assembled building component capable of being hoisted quickly according to claim 1, wherein: the bottom of wallboard (4) is provided with fixed plate (9), the inside of fixed plate (9) is provided with grout pipe (20), there is grout mouth (17) outside of fixed plate (9).
3. A rapid-to-hoist fabricated building component according to claim 2, characterized in that: a through hole (19) is formed above the fixing plate (9), and a grouting layer (11) is arranged inside the grouting pipe (20).
4. A rapid-to-hoist fabricated building component according to claim 2, characterized in that: the inside of wallboard (4) is provided with longitudinal reinforcement (7), the outside of longitudinal reinforcement (7) is provided with horizontal stirrup (3).
5. A rapid-to-hoist fabricated building component according to claim 4, characterized in that: the fixing plate is characterized in that a mounting hole (18) is formed in the upper portion of the fixing plate (9), threads are formed in the inner surface of the mounting hole (18), and the longitudinal steel bar (7) is fixedly connected with the fixing plate (9) through the mounting hole (18).
6. The assembled building component capable of being hoisted quickly according to claim 1, wherein: hanging holes (5) are formed in the top of the wallboard (4), and hanging nails (6) are installed inside the hanging holes (5).
CN202122241057.9U 2021-09-16 2021-09-16 Assembled building element that can hoist fast Active CN216195528U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122241057.9U CN216195528U (en) 2021-09-16 2021-09-16 Assembled building element that can hoist fast

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122241057.9U CN216195528U (en) 2021-09-16 2021-09-16 Assembled building element that can hoist fast

Publications (1)

Publication Number Publication Date
CN216195528U true CN216195528U (en) 2022-04-05

Family

ID=80919250

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122241057.9U Active CN216195528U (en) 2021-09-16 2021-09-16 Assembled building element that can hoist fast

Country Status (1)

Country Link
CN (1) CN216195528U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115012671A (en) * 2022-06-24 2022-09-06 中建八局装饰工程有限公司 Assembly type building structure and construction method thereof
CN120311866A (en) * 2025-06-19 2025-07-15 中国建筑西北设计研究院有限公司 Steel tube truss prestressed concrete composite slab

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115012671A (en) * 2022-06-24 2022-09-06 中建八局装饰工程有限公司 Assembly type building structure and construction method thereof
CN120311866A (en) * 2025-06-19 2025-07-15 中国建筑西北设计研究院有限公司 Steel tube truss prestressed concrete composite slab

Similar Documents

Publication Publication Date Title
CN215254604U (en) Template support system encorbelments
CN203188121U (en) Cast-in-place bridge floor suspending mold of half-through or through arch bridge
CN101787733A (en) Prefabricated vertical member
CN113605771B (en) Prestress assembly type frame structure system
CN109457814B (en) Construction method for top cover of high-rise and large-diameter building based on Bailey truss structure
CN108005387A (en) A kind of assembled wallboard and the cast-in-place main body method for synchronously constructing of shear wall with short piers
CN216195528U (en) Assembled building element that can hoist fast
CN109732773B (en) Installation node and installation method of support hinged concrete prefabricated member
CN218668474U (en) Basket type overhanging bearing frame
CN217711698U (en) Steel bar truss combined template free of supporting detachable bottom die
CN115075613A (en) Fabricated building supporting system and construction method thereof
CN109629447B (en) Variable cross-section cast-in-situ box girder construction and concrete pouring method
CN203034799U (en) Tower hoist standard knot bearing overhead support formwork steel platform structure
CN114922360A (en) Device for combining prefabrication and cast-in-place of roof cornice structure and construction method thereof
CN119083734A (en) A method for installing and constructing an assembled building structure
CN216664766U (en) Assembled parapet that cornices
CN108019040B (en) A construction method for the Bailey frame platform of the transfer floor of a high-rise building
CN214832930U (en) Prefabricated non-dismantling post-pouring strip template
CN213204438U (en) Semi-prefabricated and semi-cast-in-place building component
CN209244243U (en) A kind of fixed device of fashioned iron sizing tripod for builder's jack
CN212358786U (en) Assembly type prefabricated steel bar truss disassembly-free template system
CN103290980A (en) Multilayer load bearing heat-insulated cantilever plate butted with frame structure and preparation and construction method
CN211948857U (en) Independent node assembled frame construction
CN112523591A (en) Steel pipe column installation method
CN113482328A (en) Integral hoisting installation construction method for steel pipe template of outer shear wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20220630

Address after: 300000 1,2-201, building 6, Huiying Industrial Park, No. 86, Zhonghuan West Road, Tianjin pilot free trade zone (Airport Economic Zone), Binhai New Area, Tianjin

Patentee after: INTERNATIONAL ENGINEERING Co.,Ltd. OF CRCC 12

Address before: 750021 Yixiang community, 97 Shuofang Road, Xixia District, Yinchuan City, Ningxia Hui Autonomous Region

Patentee before: Wan Ping

TR01 Transfer of patent right