CN215978628U - Support whole bathroom that two layers were built - Google Patents

Support whole bathroom that two layers were built Download PDF

Info

Publication number
CN215978628U
CN215978628U CN202121582077.6U CN202121582077U CN215978628U CN 215978628 U CN215978628 U CN 215978628U CN 202121582077 U CN202121582077 U CN 202121582077U CN 215978628 U CN215978628 U CN 215978628U
Authority
CN
China
Prior art keywords
frame
ceiling
supporting
wall body
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121582077.6U
Other languages
Chinese (zh)
Inventor
高若凡
刘嘉淇
程才淑
许广提
冉开林
梁泽彬
彭展钊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Linghe Composite Materials Co ltd
Original Assignee
Guangdong Linghe Composite Materials Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Linghe Composite Materials Co ltd filed Critical Guangdong Linghe Composite Materials Co ltd
Priority to CN202121582077.6U priority Critical patent/CN215978628U/en
Application granted granted Critical
Publication of CN215978628U publication Critical patent/CN215978628U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Residential Or Office Buildings (AREA)

Abstract

The utility model provides a whole bathroom built by supporting two layers, which comprises a ceiling, a bottom plate and a wall body, wherein the ceiling and the wall body and the bottom plate and the wall body are spliced to form an integral structure, the wall body is a composite steel pipe wall plate, the bottom of the bottom plate is provided with a bottom frame for strengthening stability, the ceiling is fixed with the wall body through a keel, and a top frame assembly for supporting two layers of space is arranged above the ceiling. The utility model provides a support two layers and build including ceiling, bottom plate and wall body, assemble into overall structure through the concatenation between ceiling and the wall body, between bottom plate and the wall body, the wall body is compound steel pipe wallboard, the bottom of bottom plate is equipped with the chassis of strengthening the steadiness, the ceiling passes through fossil fragments and wall body fastening, the ceiling top is equipped with the roof-rack subassembly that supports two layers of spaces.

Description

Support whole bathroom that two layers were built
Technical Field
The utility model relates to the technical field of integrated bathrooms, in particular to an integrated bathroom capable of supporting two layers of buildings.
Background
The bearing structure of most houses in China is formed by casting cast-in-place concrete, the bearing structure of a part of the houses is a multi-layer building adopting prefabricated plates, the plate body structure of a sanitary room part of the houses is also formed by casting cast-in-place concrete, and the sanitary room part of the houses is generally formed by casting cast-in-place caisson structures. Certainly, few parts also adopt whole bathroom, and compared with traditional bathroom, whole bathroom has advantages such as simple to operate, space utilization is high, the material is good, watertight. With the popularity of LOFT house types, the LOFT house types are usually small house types and high lifting frames, the area is 30-50 square meters, and the layer height is about 3.6-5.2 meters. The LOFT house type generally builds a second-layer space above a bathroom, the existing integral bathroom can not support the building work of the second-layer space, the Chinese patent publication No. CN204510914U, the disclosure date is 2015 07-29, the patent provides the integral bathroom comprising a top plate, a bottom plate and a wall body, the top plate and the wall body and the bottom plate and the wall body are connected through a connected framework to form an integral structure, the framework is a steel-concrete structure, but the integral bathroom mentioned in the patent can not directly support the second-layer structure, if the two-layer structure needs to be built at the top of the integral bathroom, an independent separation steel structure needs to be supported, the independent separation steel structure needs to be fixed by a support vertical pipe, or the building wall body is fixed through hole opening and pulling explosion, the support vertical pipe occupies the indoor space, the hole opening or pulling explosion construction consumes long time and has large noise.
SUMMERY OF THE UTILITY MODEL
The utility model aims to overcome the defects that the existing integral bathroom can not directly support a two-layer structure and needs to be matched with an independent separation steel structure to complete two-layer construction, and provides the integral bathroom for supporting the two-layer construction. The structure of the integral bathroom is improved, the strength of the integral bathroom is enhanced, a two-layer space can be directly built on the integral bathroom, and a steel structure for supporting does not need to be additionally arranged.
In order to solve the technical problems, the utility model adopts the technical scheme that: the utility model provides a support two layers and build including ceiling, bottom plate and wall body, assemble into overall structure through the concatenation between ceiling and the wall body, between bottom plate and the wall body, the wall body is compound steel pipe wallboard, the bottom of bottom plate is equipped with the chassis of strengthening the steadiness, the ceiling passes through fossil fragments and wall body fastening, the ceiling top is equipped with the roof-rack subassembly that supports two layers of spaces.
In the technical scheme, the integral bathroom adopts the composite steel pipe wall plate which can powerfully support the roof assembly and the two-layer space at the top of the roof assembly. Meanwhile, the bottom of the whole bathroom is provided with a bottom frame, and the bottom frame is used for supporting the whole bathroom and the two-layer space at the top of the whole bathroom, so that the stability of the whole bathroom and the two-layer space at the top of the whole bathroom is enhanced. According to the technical scheme, an additional independent separation steel structure is not required, and the building process of the two-layer space is simplified; other main parts in roof-rack subassembly, chassis and bathroom can be at the mill preparation, then directly at the job site installation, have shortened the fitment engineering time of setting up two layers of space house types greatly, avoid trompil or beat to draw to explode the production construction noise simultaneously.
Furthermore, the underframe comprises a bearing frame and a supporting seat, the supporting seat is fixed at the bottom of the bearing frame through a nut, and the nut adjusts the connecting height of the supporting seat on the bearing frame. The nut can adjust the supporting height of the supporting seat on the bearing frame besides fixing the supporting seat on the bearing frame, and the underframe can be quickly leveled.
Furthermore, the bearing frame is formed by welding a plurality of galvanized steel pipes.
Furthermore, the top frame assembly is fixedly connected with the keel through a connecting piece.
Further, the connecting piece passes through welded fastening in the bottom of roof-rack subassembly, the connecting piece include with the recess of fossil fragments cooperation joint. In this technical scheme, the roof-rack subassembly passes through the recess lock of connecting piece to be fixed on fossil fragments.
Furthermore, the top frame assembly comprises a first frame fixed to the top of the ceiling through a connecting piece and a second frame extending out of the ceiling, and a support frame is arranged at one end, far away from the integrated bathroom, of the second frame. In the technical scheme, the planning area of the second layer space is larger than the occupied area of the whole bathroom, so that the part of the top frame assembly extending out of the ceiling is the second frame, and the support frame is matched with the whole bathroom to support the second frame.
Furthermore, the support frame is fixedly connected with the second frame through a self drilling screw.
Furthermore, a bottom plate of a two-layer space is formed by laying plates on the top frame assembly.
Furthermore, compound steel pipe wallboard includes rectangular frame and steel pipe strengthening rib, the steel pipe strengthening rib is in place to incline in the rectangular frame, the both ends of steel pipe strengthening rib with the rectangular frame is fixed, inside compound foaming material through the rectangular frame forms smooth wallboard.
Furthermore, two steel pipe reinforcing ribs which are arranged obliquely relative to each other are arranged in the rectangular frame.
Compared with the prior art, the utility model has the beneficial effects that:
according to the utility model, the composite steel pipe wall plate is adopted to enhance the bearing capacity of the integral bathroom, the bottom frame is arranged at the bottom, the bottom frame is used for bearing the integral bathroom and the two-layer space built at the top of the integral bathroom, the stability of the integral bathroom and the two-layer space built at the top of the integral bathroom is enhanced, constructors can directly build the two-layer space at the top of a ceiling without additionally arranging a separation steel structure for supporting, the space is saved, and the building process of the two-layer space is simplified; the top frame assembly, the bottom frame and other main body parts in the bathroom can be manufactured in a factory and then directly installed on a construction site, so that the decoration construction time is shortened.
Drawings
FIG. 1 is an exploded schematic view of the present invention;
FIG. 2 is a schematic view of the overall structure of the present invention;
FIG. 3 is a schematic view of the top frame assembly of the present invention mated with a composite steel pipe wall;
FIG. 4 is a schematic view of the present invention in cooperation with a plate.
The graphic symbols are illustrated as follows:
1. a ceiling; 2. a composite steel pipe wall plate; 3. a base plate; 4. a chassis; 401. a receiving frame; 402. a supporting seat; 5. a top frame assembly; 501. a first frame; 502. a second frame; 6. a connecting member; 7. a keel; 8. a plate material; 9. a support frame.
Detailed Description
The present invention will be further described with reference to the following embodiments. Wherein the showings are for the purpose of illustration only and are shown by way of illustration only and not in actual form, and are not to be construed as limiting the present patent; to better illustrate the embodiments of the present invention, some parts of the drawings may be omitted, enlarged or reduced, and do not represent the size of an actual product; it will be understood by those skilled in the art that certain well-known structures in the drawings and descriptions thereof may be omitted.
The same or similar reference numerals in the drawings of the embodiments of the present invention correspond to the same or similar components; in the description of the present invention, it should be understood that if there is an orientation or positional relationship indicated by the terms "upper", "lower", "left", "right", etc. based on the orientation or positional relationship shown in the drawings, it is only for convenience of describing the present invention and simplifying the description, but it is not intended to indicate or imply that the referred device or element must have a specific orientation, be constructed in a specific orientation, and be operated, and therefore, the terms describing the positional relationship in the drawings are only used for illustrative purposes and are not to be construed as limiting the present patent, and the specific meaning of the terms may be understood by those skilled in the art according to specific circumstances.
Examples
Fig. 1 to 4 show an embodiment of the integrated bathroom of the present invention supporting two floors. A support two-layer built integral bathroom comprises a ceiling 1, a bottom plate 3 and a wall body. The ceiling 1 and the wall body, and the bottom plate 3 and the wall body are assembled into an integral structure through splicing, and the wall body is a composite steel pipe wall plate 2. The bottom of bottom plate 3 is equipped with the chassis 4 of strengthening the steadiness, and ceiling 1 is fixed with compound steel pipe wallboard 2 through fossil fragments 7, and ceiling 1 top is equipped with the roof-rack subassembly 5 of building the double space. The composite steel pipe wall plate 2 enables the whole bathroom to have bearing capacity for supporting two layers of space. The underframe 4 is used for bearing the whole bathroom and the two-layer space supported by the top of the whole bathroom. The stability of the whole bathroom and the two-layer space at the top of the bathroom is enhanced; meanwhile, the underframe 4 leaves a space for the bottom of the whole bathroom, and the space needs to be provided with a drainage system of the whole bathroom.
In one embodiment, the base frame 4 comprises a receiving frame 401 and a support base 402, the support base 402 being fixed to the bottom of the receiving frame 401 by nuts. The nut can fix the support base 402 on the receiving frame 401, and can adjust the support height of the support base 402 on the receiving frame 401, so as to quickly level the underframe. The receiving frame 401 is formed by welding a plurality of galvanized steel pipes.
In one embodiment, the top frame assembly 5 is clamped with the keel 7 through the connecting piece 6, as shown in fig. 2, the top frame assembly 5 is divided into a first frame 501 positioned at the top of the ceiling 1 and a second frame 502 extending out of the ceiling 1. A plurality of connecting members 6 are welded to the periphery of the first frame 501. As shown in fig. 3, the connecting member 6 is provided with a groove for engaging with the keel 7. The first frame 501 can completely attach to the ceiling 1 of the entire bathroom. One end of the second frame 502, which is far away from the integrated bathroom, is further provided with a support frame 9, and the support frame 9 is fixedly connected with the second frame 502 through a self drilling screw. Because the plan area of the two-layer space is larger than the floor area of the whole bathroom, the part of the top frame assembly 5 extending out of the ceiling 1 is the second frame 502, and the support frame 9 supports the top frame assembly 5 by matching with the whole bathroom to jointly bear the two-layer space.
In one embodiment, the composite steel pipe wall plate 2 comprises a rectangular frame and steel pipe reinforcing ribs, wherein the steel pipe reinforcing ribs are obliquely arranged in the rectangular frame, two ends of each steel pipe reinforcing rib are fixed with the rectangular frame, the rectangular frame is internally provided with a flat wall plate through composite foaming materials, and two steel pipe reinforcing ribs which are obliquely arranged relatively are arranged in the rectangular frame. The bearing capacity of the composite steel pipe wall plate 2 is far stronger than that of a common wall plate, and the secondary space can be supported.
In one embodiment, as shown in fig. 4, the top frame assembly 5 is provided with the plate 8 as the bottom plate 3 of the two-layer space, and a separate steel structure is not required, so that the space is saved. The top frame assembly 5, the bottom frame 4, the wall body and the main body parts inside the wall body of the integral bathroom can be manufactured in a factory and then directly installed on a construction site, so that the decoration construction time for building a two-layer space house type is greatly shortened, and meanwhile, holes are prevented from being formed in the wall or the construction noise caused by pulling explosion is avoided.
It should be understood that the above-described embodiments of the present invention are merely examples for clearly illustrating the present invention, and are not intended to limit the embodiments of the present invention. Other variations and modifications will be apparent to persons skilled in the art in light of the above description. And are neither required nor exhaustive of all embodiments. Any modification, equivalent replacement, and improvement made within the spirit and principle of the present invention should be included in the protection scope of the claims of the present invention.

Claims (10)

1. The utility model provides a support integral bathroom that two layers were built, includes ceiling (1), bottom plate (3) and wall body, between ceiling (1) and the wall body, assemble into overall structure through the concatenation between bottom plate (3) and the wall body, the wall body is compound steel pipe wallboard (2), its characterized in that: the bottom of bottom plate (3) is equipped with chassis (4) of strengthening the steadiness, ceiling (1) is fixed with the wall body through fossil fragments (7), ceiling (1) top is equipped with roof-rack subassembly (5) that support two layers of space.
2. The bathroom unit for supporting two-layer construction according to claim 1, wherein: the underframe (4) comprises a bearing frame (401) and a supporting seat (402), the supporting seat (402) is fixed at the bottom of the bearing frame (401) through a nut, and the nut adjusts the connecting height of the supporting seat (402) on the bearing frame (401).
3. The bathroom unit for supporting two-layer construction according to claim 2, wherein: the bearing frame (401) is formed by welding a plurality of galvanized steel pipes.
4. The bathroom unit for supporting two-layer construction according to claim 2, wherein: the top frame assembly (5) is fixedly connected with the keel (7) through a connecting piece (6).
5. The bathroom unit for supporting two-layer construction according to claim 4, wherein: connecting piece (6) pass through welded fastening in the bottom of roof-rack subassembly (5), connecting piece (6) include with the recess of fossil fragments (7) cooperation joint.
6. The bathroom unit for supporting two-layer construction according to claim 1, wherein: the top frame assembly (5) comprises a first frame (501) fixed to the top of the ceiling (1) through a connecting piece (6) and a second frame (502) extending out of the ceiling (1), and a supporting frame (9) is arranged at one end, far away from the whole bathroom, of the second frame (502).
7. The bathroom unit for supporting two-layer construction according to claim 6, wherein: the support frame is fixedly connected with the second frame (502) through a self drilling screw.
8. The bathroom unit for supporting two-layer construction according to claim 1, wherein: and plates (8) are laid on the top frame assembly (5) to form a bottom plate (3) with a two-layer space.
9. The bathroom unit for supporting two-layer construction according to claim 1, wherein: the composite steel pipe wall plate (2) comprises a rectangular frame and steel pipe reinforcing ribs, wherein the steel pipe reinforcing ribs are obliquely arranged in the rectangular frame, two ends of each steel pipe reinforcing rib are fixed with the rectangular frame, and the rectangular frame is internally provided with a smooth wall plate through composite foaming materials.
10. The bathroom unit for supporting two-layer construction according to claim 9, wherein: two steel pipe reinforcing ribs which are obliquely arranged relatively are arranged in the rectangular frame.
CN202121582077.6U 2021-07-12 2021-07-12 Support whole bathroom that two layers were built Active CN215978628U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121582077.6U CN215978628U (en) 2021-07-12 2021-07-12 Support whole bathroom that two layers were built

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121582077.6U CN215978628U (en) 2021-07-12 2021-07-12 Support whole bathroom that two layers were built

Publications (1)

Publication Number Publication Date
CN215978628U true CN215978628U (en) 2022-03-08

Family

ID=80516113

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121582077.6U Active CN215978628U (en) 2021-07-12 2021-07-12 Support whole bathroom that two layers were built

Country Status (1)

Country Link
CN (1) CN215978628U (en)

Similar Documents

Publication Publication Date Title
JP5643205B2 (en) Unit building system
CN101654930B (en) Beam frame structure of combined type house and assembly method thereof
CN105178629A (en) Jointed wood structure house
US20110219712A1 (en) Method and system for twisting building structure
CN111088859A (en) Assembled outer wall structure and mounting method thereof
CN215978628U (en) Support whole bathroom that two layers were built
CN213868258U (en) Assembled steel construction building system
CN110725412A (en) Integrated house system with embedded steel structure
CN214423572U (en) Steel frame and concrete wallboard mixed full-assembly type multilayer steel structure system
CN206299015U (en) Assembled composite floor
KR101086060B1 (en) Prefebrication module
JP6732073B2 (en) Building structure
TW202225530A (en) Pre-manufactured floor-ceiling panel for a multi-story building having load bearing walls
CN211172365U (en) Assembled low-rise residential structure system
CN209799469U (en) Box-type room maintenance ground and box-type room
CN203066239U (en) Multi-storey moving combined building
CN218715464U (en) Prefabricated house unit of assembled composite building with terrace
CN201276758Y (en) Beam frame structure of combined house
CN216142251U (en) Assembled floor with steel beam and floor arranged in equal height range
JP4031452B2 (en) Unit type building and construction method of the unit type building
CN212534634U (en) Installation adjusting device for assembling shear wall
CN116427531A (en) Novel laminated beam concrete MiC structure system
CN219364911U (en) Concealed frame assembled house system adopting concrete outer wall
CN219909466U (en) Prefabricated external wall panel connection structure
CN110965635B (en) Supporting structure and layering industrialization building of building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant