China
Prior art keywords
lifting platform
assembly
butt joint
lifting
screw rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121722576.0U
Other languages
Chinese (zh)
Inventor
李展开
李敏
彭勇
章飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Zhongshi Metal Products Co ltd
Original Assignee
Anhui Zhongshi Metal Products Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Zhongshi Metal Products Co ltd filed Critical Anhui Zhongshi Metal Products Co ltd
Priority to CN202121722576.0U priority Critical patent/CN215846718U/en
Application granted granted Critical
Publication of CN215846718U publication Critical patent/CN215846718U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Casting Support Devices, Ladles, And Melt Control Thereby (AREA)

Abstract

The utility model discloses a nozzle assembly and butt joint assembly of a steel mill production line, which relates to the technical field of assembly and butt joint auxiliary devices and comprises a workbench, wherein a lifting assembly and a lifting platform are arranged on the workbench, the lifting assembly comprises a first lifting assembly and a second lifting assembly, the lifting platform comprises a first lifting platform and a second lifting platform, and a first horizontal moving assembly and a second horizontal moving assembly are respectively used for driving a first butt joint piece and a second butt joint piece to move in the horizontal direction. Accurate assembly and butt joint are realized.

Description

Nozzle assembly butt joint assembly for steel mill production line
Technical Field
The utility model relates to the technical field of assembly and butt joint auxiliary devices, in particular to a nozzle assembly and butt joint assembly for a steel mill production line.
Background
The nozzle is a key part in various equipment such as spraying, atomizing, oil spraying, sand blasting, spraying and the like, and plays an important role; the cooling efficiency of the nozzle is the highest and it is suitable for gases that need to be cooled rapidly. The existing nozzle assembly machine is complex in structure and is mostly produced in batches by stamping in steel mills.
Among the prior art, conventional nozzle group price carries out the assembled, needs the manual cooperation of labour cost, because reasons such as the manual centre gripping of operating personnel lead to the nozzle to appear unexpected dislocation's phenomenon easily when the assembly, lead to the yields of nozzle assembly not high, consequently, we disclose a steel mill production line nozzle assembly butt joint subassembly and satisfy the assembly demand of nozzle.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a nozzle assembly butt joint assembly for a steel mill production line, which aims to solve the problems in the background technology.
In order to achieve the purpose, the utility model provides the following technical scheme: the utility model provides a steel mill production line nozzle assembly butt joint subassembly, includes the workstation, be equipped with lifting unit and elevating platform on the workstation, lifting unit contains first lifting unit and second lifting unit, the elevating platform contains first elevating platform and second elevating platform, first lifting unit is used for the drive first elevating platform realizes going up and down, second lifting unit is used for the drive the second elevating platform realizes going up and down, first elevating platform with be equipped with first horizontal migration subassembly and second horizontal migration subassembly on the second elevating platform respectively, just first elevating platform with still be equipped with first butt joint piece and second butt joint piece in the second elevating platform, first horizontal migration subassembly and second horizontal migration subassembly are used for driving respectively first butt joint piece with second butt joint piece moves on the horizontal direction.
Preferably, first lifting unit contains first guide arm and first perpendicular screw rod, the top fixed mounting of workstation has first guide arm, just it cup joints to rotate on the workstation first perpendicular screw rod, the bottom of first perpendicular screw rod extends to outside the top side of workstation and the first perpendicular hand wheel of fixedly connected with, first elevating platform slides and cup joints on the first guide arm, just first elevating platform screw thread cup joints on the first perpendicular screw rod.
Preferably, the second lifting component comprises a second guide rod and a second vertical screw rod, the top of the workbench is fixedly provided with the second guide rod, the workbench is rotatably sleeved with the second vertical screw rod, the bottom end of the second vertical screw rod extends to the outside of the bottom side of the workbench and is fixedly connected with a second vertical hand wheel, the second lifting platform is slidably sleeved on the second guide rod, and the second lifting platform is in threaded sleeve connection with the second vertical screw rod.
Preferably, the first horizontal moving assembly comprises a first clamping block assembly and a first horizontal screw rod, a first sliding groove is formed in the first lifting platform, the first clamping block assembly is arranged in the first sliding groove, a first guide frame is fixedly connected to the first clamping block assembly, the first guide frame is slidably sleeved on the first lifting platform, the first lifting platform is rotatably sleeved with the first horizontal screw rod, and one end of the first horizontal screw rod extends to the outside of one side of the first lifting platform and is fixedly connected with a first horizontal hand wheel.
Preferably, the second horizontal moving assembly comprises a second clamping block assembly and a second horizontal screw rod, a second sliding groove is formed in the second lifting platform, the second clamping block assembly is arranged in the second sliding groove, a second guide frame is fixedly connected to the second clamping block assembly, the second guide frame is slidably sleeved on the second lifting platform, the second lifting platform is rotatably sleeved with the second horizontal screw rod, and one end of the second horizontal screw rod extends to one side of the second lifting platform and is fixedly connected with a second horizontal hand wheel.
Preferably, the first butt joint piece and the second butt joint piece are elastically sleeved on the first clamping block assembly and the second clamping block assembly respectively, and the first butt joint piece is matched with the second butt joint piece;
and the workbench is provided with a background plate matched with the first butt joint piece and the second butt joint piece.
The utility model has the technical effects and advantages that:
1. the structure of the utility model is reasonable, the first vertical screw rod is rotated to drive the first lifting platform to realize lifting under the guiding action of the first guide rod by rotating the first vertical hand wheel, the vertical height of the first butt joint piece is adjusted, the second vertical screw rod is rotated to drive the second lifting platform to realize lifting under the guiding action of the second guide rod by rotating the second vertical hand wheel, the vertical height of the second butt joint piece is adjusted, the first horizontal screw rod is rotated to drive the corresponding first clamping block component to move under the guiding action of the first lifting platform by rotating the first horizontal hand wheel, the horizontal position of the first butt joint piece is changed, the second horizontal screw rod is rotated to indirectly drive the second butt joint piece to move in the horizontal direction under the guiding action of the second lifting platform by rotating the second horizontal hand wheel, so as to adjust the horizontal position of the second butt joint piece, therefore, an operator can conveniently determine the relative position of the first butt joint piece and the second butt joint piece, and accurate assembly butt joint is realized;
2. according to the utility model, the positions of the first butt joint piece and the second butt joint piece cannot be accidentally deviated by the characteristics of the screw, so that the traditional manual clamping is replaced, the nozzle assembly is more accurate, and the yield of the nozzle on a production line is improved.
Drawings
FIG. 1 is a schematic perspective view of the present invention;
FIG. 2 is a schematic view of another perspective structure according to the present invention;
fig. 3 is a schematic perspective view of the elevating platform of the present invention.
In the figure: 1. a first guide bar; 2. a second guide bar; 3. a first vertical screw; 4. a second vertical screw; 5. a first vertical hand wheel; 6. a second vertical hand wheel; 7. a first elevating platform; 8. a second lifting table; 9. a first chute; 10. a second chute; 11. a first clamp block assembly; 12. a first guide frame; 13. a second clamp block assembly; 14. a second guide frame; 15. a first horizontal screw; 16. a second horizontal screw; 17. a first horizontal hand wheel; 18. a second horizontal hand wheel; 19. a first butt piece; 20. a second docking piece; 21. and (4) a background plate.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The utility model provides a nozzle assembly and butt joint assembly for a steel mill production line, which comprises a workbench, wherein a lifting assembly and a lifting platform are arranged on the workbench, the lifting assembly comprises a first lifting assembly and a second lifting assembly, the lifting platform comprises a first lifting platform 7 and a second lifting platform 8, the first lifting assembly is used for driving the first lifting platform 7 to lift, the second lifting assembly is used for driving the second lifting platform 8 to lift, the first lifting platform 7 and the second lifting platform 8 are respectively provided with a first horizontal moving assembly and a second horizontal moving assembly, a first butt joint piece 19 and a second butt joint piece 20 are further arranged in the first lifting platform 7 and the second lifting platform 8, and the first horizontal moving assembly and the second horizontal moving assembly are respectively used for driving the first butt joint piece 19 and the second butt joint piece 20 to move in the horizontal direction.
Further, in above-mentioned scheme, first lifting unit contains first guide arm 1 and first vertical screw 3, the top fixed mounting of workstation has first guide arm 1, and rotate on the workstation and cup joint first vertical screw 3, the bottom of first vertical screw 3 extends to outside the top side of workstation and the first perpendicular hand wheel of fixedly connected with 5, first elevating platform 7 slides and cup joints on first guide arm 1, and 7 threads of first elevating platform cup joint on first vertical screw 3, through setting up first lifting unit, drive first butt joint piece 19 and realize going up and down.
Further, in above-mentioned scheme, the second lifting unit contains second guide arm 2 and second vertical screw 4, the top fixed mounting of workstation has second guide arm 2, and rotate on the workstation and cup joint second vertical screw 4, the bottom of second vertical screw 4 extends to outside the bottom of workstation and the perpendicular hand wheel of fixedly connected with second 6, 8 sliding cup joints of second elevating platform are on second guide arm 2, and 8 screw threads of second elevating platform cup joint on second vertical screw 4, through setting up second lifting unit, be convenient for drive second butt joint piece 20 and realize going up and down.
Further, in the above scheme, the first horizontal movement assembly includes a first clamping block assembly 11 and a first horizontal screw 15, a first chute 9 is formed in the first lifting platform 7, the first clamping block assembly 11 is arranged in the first chute 9, a first guide frame 12 is fixedly connected to the first clamping block assembly 11, the first guide frame 12 is slidably sleeved on the first lifting platform 7, the first lifting platform 7 is rotatably sleeved with the first horizontal screw 15, one end of the first horizontal screw 15 extends to the outside of one side of the first lifting platform 7 and is fixedly connected with a first horizontal hand wheel 17, and the first butt joint member 19 is conveniently driven to move in the horizontal direction by the arrangement of the first horizontal movement assembly.
Further, in the above scheme, the second horizontal movement assembly includes a second clamping block assembly 13 and a second horizontal screw 16, a second chute 10 has been opened on the second lifting platform 8, the second clamping block assembly 13 is provided in the second chute 10, a second guide frame 14 is fixedly connected to the second clamping block assembly 13, the second guide frame 14 is slidably sleeved on the second lifting platform 8, the second lifting platform 8 is rotatably sleeved with the second horizontal screw 16, and one end of the second horizontal screw 16 extends to the outside of one side of the second lifting platform 8 and is fixedly connected with a second horizontal hand wheel 18, and by setting the second horizontal movement assembly, the second butt joint member 20 is conveniently driven to move in the horizontal direction. Further, in the above scheme, the first clamping block assembly 11 and the second clamping block assembly 13 are respectively elastically sleeved with a first butt joint piece 19 and a second butt joint piece 20, and the first butt joint piece 19 is matched with the second butt joint piece 20;
the workbench is provided with a background plate 21 matched with the first butt joint piece 19 and the second butt joint piece 20, and the background plate 21 is arranged to facilitate vertical observation of the distance between the first butt joint piece 19 and the second butt joint piece 20.
This practical theory of operation: by rotating the first vertical hand wheel 5, under the guiding action of the first guide rod 1, the first vertical screw 3 is rotated to drive the first lifting platform 7 to lift, the vertical height of the first butt joint piece 19 is adjusted, by rotating the second vertical hand wheel 6, under the guiding action of the second guide rod 2, the second vertical screw 4 is rotated to drive the second lifting platform 8 to lift, the vertical height of the second butt joint piece 20 is adjusted, by rotating the first horizontal hand wheel 17, under the guiding action of the first lifting platform 7, the first horizontal screw 15 is rotated to drive the corresponding first clamping block assembly 11 to move, and then the horizontal position of the first butt joint piece 19 is changed, by rotating the second horizontal hand wheel 18, under the guiding action of the second lifting platform 8, the second horizontal screw 16 is rotated to indirectly drive the second butt joint piece 20 to move in the horizontal direction, so as to adjust the horizontal position of the second butt joint piece 20, thereby be convenient for operating personnel confirm the relative position of first butt joint piece 19 and second butt joint piece 20 to through screw rod characteristic itself, make the unexpected skew can not take place for the position of first butt joint piece 19 and second butt joint piece 20, thereby replace traditional artifical manual centre gripping, make the nozzle assembly time more accurate, improved the yields of nozzle on the production line.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments or portions thereof without departing from the spirit and scope of the utility model.

Claims (6)

1. The utility model provides a steel mill production line nozzle assembly butt joint subassembly, includes the workstation, its characterized in that: the worktable is provided with a lifting component and a lifting platform, the lifting component comprises a first lifting component and a second lifting component, the lifting platform comprises a first lifting platform (7) and a second lifting platform (8), the first lifting component is used for driving the first lifting platform (7) to lift, the second lifting component is used for driving the second lifting platform (8) to lift, a first horizontal moving component and a second horizontal moving component are respectively arranged on the first lifting platform (7) and the second lifting platform (8), and a first butt joint piece (19) and a second butt joint piece (20) are also arranged in the first lifting platform (7) and the second lifting platform (8), the first horizontal moving assembly and the second horizontal moving assembly are respectively used for driving the first butt joint piece (19) and the second butt joint piece (20) to move in the horizontal direction.
2. The nozzle assembly docking assembly for a steel mill production line according to claim 1, wherein: first lifting unit contains first guide arm (1) and first perpendicular screw rod (3), the top fixed mounting of workstation has first guide arm (1), just it has cup jointed to rotate on the workstation first perpendicular screw rod (3), the bottom of first perpendicular screw rod (3) extends to outside and the first perpendicular hand wheel of fixedly connected with (5) of the top side of workstation, first elevating platform (7) slide and cup joint on first guide arm (1), just first elevating platform (7) screw thread cup joints on first perpendicular screw rod (3).
3. The nozzle assembly docking assembly for a steel mill production line according to claim 2, wherein: the second lifting component comprises a second guide rod (2) and a second vertical screw rod (4), the top of the workbench is fixedly provided with the second guide rod (2), the workbench is rotatably sleeved with the second vertical screw rod (4), the bottom end of the second vertical screw rod (4) extends to the outer side of the bottom of the workbench and a second vertical hand wheel (6) fixedly connected with the second, the second lifting platform (8) is slidably sleeved on the second guide rod (2), and the second lifting platform (8) is in threaded sleeve connection with the second vertical screw rod (4).
4. The nozzle assembly docking assembly for a steel mill production line according to claim 3, wherein: the first horizontal moving assembly comprises a first clamping block assembly (11) and a first horizontal screw rod (15), a first sliding groove (9) is formed in the first lifting platform (7), the first clamping block assembly (11) is arranged in the first sliding groove (9), a first guide frame (12) is fixedly connected to the first clamping block assembly (11), the first guide frame (12) is slidably sleeved on the first lifting platform (7), the first lifting platform (7) is rotatably sleeved with the first horizontal screw rod (15), and one end of the first horizontal screw rod (15) extends to the outer side of one side of the first lifting platform (7) and is fixedly connected with a first horizontal hand wheel (17).
5. The nozzle assembly docking assembly for a steel mill production line according to claim 4, wherein: the second horizontal moving assembly comprises a second clamping block assembly (13) and a second horizontal screw rod (16), a second sliding groove (10) is formed in the second lifting platform (8), the second clamping block assembly (13) is arranged in the second sliding groove (10), a second guide frame (14) is fixedly connected to the second clamping block assembly (13), the second guide frame (14) is slidably sleeved on the second lifting platform (8), the second lifting platform (8) is rotatably sleeved with the second horizontal screw rod (16), and one end of the second horizontal screw rod (16) extends to the outer side of one side of the second lifting platform (8) and is fixedly connected with a second horizontal hand wheel (18).
6. The nozzle assembly docking assembly for a steel mill production line according to claim 5, wherein: the first clamping block assembly (11) and the second clamping block assembly (13) are respectively elastically sleeved with the first butt joint piece (19) and the second butt joint piece (20), and the first butt joint piece (19) is matched with the second butt joint piece (20);
and a background plate (21) matched with the first butt joint piece (19) and the second butt joint piece (20) is arranged on the workbench.
CN202121722576.0U 2021-07-28 2021-07-28 Nozzle assembly butt joint assembly for steel mill production line Active CN215846718U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121722576.0U CN215846718U (en) 2021-07-28 2021-07-28 Nozzle assembly butt joint assembly for steel mill production line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121722576.0U CN215846718U (en) 2021-07-28 2021-07-28 Nozzle assembly butt joint assembly for steel mill production line

Publications (1)

Publication Number Publication Date
CN215846718U true CN215846718U (en) 2022-02-18

Family

ID=80332328

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121722576.0U Active CN215846718U (en) 2021-07-28 2021-07-28 Nozzle assembly butt joint assembly for steel mill production line

Country Status (1)

Country Link
CN (1) CN215846718U (en)

Similar Documents

Publication Publication Date Title
CN209815611U (en) Lifting platform for scaffold
CN210789777U (en) Cantilever type automatic welding device
CN117984188B (en) Numerical control side milling vertical compound grinding machine
CN215846718U (en) Nozzle assembly butt joint assembly for steel mill production line
CN213647613U (en) Intelligent mechanical arm with freely-adjusted height for machining
CN111331371A (en) Multifunctional novel deep hole drilling machine
CN213702195U (en) Laser welding machine for super capacitor
CN112265798B (en) Part conveying device for production and processing of engineering machinery
CN215789737U (en) Special jig for machining spare and accessory parts of automatic equipment
CN111633620A (en) Positioning and clamping device for mechanical workpiece production
CN107414554B (en) Double-inclined-hole drilling equipment for numerical control machining center
CN220313305U (en) Assembly platform convenient for height adjustment for manufacturing automobile accessory
CN217224917U (en) Five metals equipment of polishing convenient to angle of adjustment just is convenient for maintain
CN220224577U (en) No trace pants production is with weaving machine
CN219582180U (en) Multi-head machining center bare engine
CN212762146U (en) Gantry machining center
CN220240289U (en) Plasma flat head machine
CN219881355U (en) Processing equipment is used in water pump production
CN209319281U (en) A kind of full-automatic two stations milling attachment
CN211545366U (en) Granny rag machine with elevating system
CN215587902U (en) Liquid spraying device for multi-spindle drilling machine
CN211103975U (en) Mechanical arm support frame
CN219112947U (en) Drilling mechanism for flywheel dynamic balance
CN213438252U (en) Mounting seat for numerically controlled lathe