High-altitude construction feeding machine
Technical Field
The utility model relates to wall construction, in particular to a high-altitude construction feeding machine which is high in efficiency and capable of saving labor cost.
Background
In public building projects, wall bodies are mostly built in a brick-laying mode, and therefore the requirement of people for space division is met. Adopt the mode of setting up operation construction platform when building high wall construction, when traditional scaffold frame operation platform set up, not only need consider the restraint of platform operation face, still need consider the difficulty of brick, the operation of plastering concurrently and the operation personnel and the safety of brick when same operation face, the difficult degree of material loading when considering the support body to set up too high relies on the manual work, brings very big inconvenience for the construction. According to production experience, the building blocks are generally transported by manpower in many ways, the problems of the transportation of the building blocks and the feeding of mortar are more obvious when the construction of the building engineering meets high-rise building, serious hidden quality troubles and serious labor waste exist, and meanwhile, the improvement of the construction efficiency is also restricted.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve the problems, and provides the high-altitude construction feeding machine which is high in efficiency and saves labor cost.
The utility model solves the problems and adopts the technical scheme that:
a high-place construction feeder comprises a motor, a steel wire rope, a frame body, a transportation platform, pulleys and a base, wherein the motor and the frame body are arranged on the base, the frame body comprises two vertical columns which are symmetrically arranged, a cross beam is arranged on each vertical column, the transportation platform is connected onto the frame body in a sliding mode, the pulleys are arranged at the top end of the frame body, the steel wire rope is wound on the pulleys, and two ends of the steel wire rope are respectively connected with the motor and the transportation platform.
Compared with the prior art, the utility model adopting the technical scheme has the outstanding characteristics that:
the material conveying device has the advantages that the steel wire rope is driven to rotate forwards and backwards through the remote control motor, the conveying platform is driven to ascend and descend, the ascending and descending speed is high, materials on the conveying platform can be easily and rapidly conveyed to a high place, construction is convenient and fast, the materials can be circulated and repeatedly utilized for an unlimited time, the problem that ultrahigh wall constructors move bricks, plaster and operate repeatedly from top to bottom is avoided, working efficiency is greatly improved, and the construction period is shortened.
The device is simple to operate, only one person is needed to provide service for multi-person masonry operation, labor cost is saved, and construction operation space is enlarged.
The device commonality is strong, and overall structure is small and exquisite, can get into various narrow and small places, and the construction in various size spaces of large tracts of land within range of being convenient for can guarantee to build by laying bricks or stones, the whole quality of plastering.
The device has simple structure, convenient processing and low cost, and meets the requirements of modern production.
The whole mechanical structure, it is simple to maintain.
Preferably, the further technical scheme of the utility model is as follows:
wheels which are symmetrically arranged are arranged below the base; convenient free mobile device to the construction position, two people just can remove, satisfy various operation spaces, convenient operation, labour saving and time saving can accelerate the construction progress.
Drawings
FIG. 1 is a schematic front view of an embodiment of the present invention;
FIG. 2 is a schematic side view of an embodiment of the present invention.
In the figure: a copper core motor 1; a wire rope 2; a frame body 3; a transport platform 4; a base 5; a universal wheel 6; a pulley 7; and (7) feeding the material 8.
The specific implementation mode is as follows:
the utility model will be further illustrated by the following examples, which are intended only for a better understanding of the present invention and therefore do not limit the scope of the utility model.
Referring to fig. 1 and 2, a high-place construction feeding machine, including copper core motor 1, wire rope 2, support body 3, transportation platform 4, pulley 7 and base 5, install universal wheel 6 that is the symmetrical form and arranges below base 5, make things convenient for free mobile device to the construction position, two people just can remove, satisfy various operating spaces, convenient operation, time saving and labor saving, can accelerate the construction progress, copper core motor 1 and support body 3 are all installed on base 5, support body 3 includes two stands that are the symmetrical form, the welding has the crossbeam on the stand, the crossbeam that stands the top is the square frame shape, transportation platform 4 passes through guide rail sliding connection on support body 3, transportation platform 4 and support body 3 smooth contact, pulley 7 sets up on the crossbeam on the top of support body 3, the axis of pulley 7 is parallel with the axis of copper core motor 1, wire rope 2 winds on two pulleys 7 and both ends respectively with copper core motor 1, the both ends of pulley 7, 4 connections of transport platform, the device is drawn materials locally, with on-the-spot frame pipe welding, construction simple to operate uses manpower sparingly, and the safety of operation and the life-span of using are ensured to the high strength and the wearability of device material, wholly adopt the cordwood system design, can look at the separate combination of vision, and is very convenient.
During the use, select suitable support body 3 according to building by laying bricks or stones highly, mobile device to 8 stacking departments of material, locking universal wheel 6, preventing device removes, place transport platform 4 with material 8 on, unblock universal wheel 6, mobile device to the construction scope, the angle has been adjusted, locking universal wheel 6, through starting copper core motor 1 with material 8 stable promote rapidly to treating the construction position, lift material 8 off, transport platform 4 drops, unblock universal wheel 6 carries out the transport next time.
The utility model drives the steel wire rope 2 by the positive and negative rotation of the remote control copper core motor 1 to further drive the transportation platform 4 to ascend and descend, has high ascending and descending speed, can easily and rapidly transport the materials 8 on the transportation platform 4 to a high place, is convenient and rapid to construct, can be circulated and recycled for unlimited times, avoids the problems of up-and-down brick carrying, plastering and repeated operation of ultrahigh wall constructors, greatly improves the working efficiency, shortens the construction period, has simple operation, can provide service for multi-person masonry operation by only one person, saves the labor cost, increases the construction operation space, has strong universality and small overall structure, can enter various narrow places, is convenient for construction in various large-area spaces, can ensure the overall quality of masonry and plastering, has simple structure, convenient processing and low cost, and meets the requirements of modern production, the full mechanical structure, it is simple to maintain.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the scope of the present invention, which is defined in the appended claims.