Live working distribution network overhauls with laborsaving kit
Technical Field
The utility model belongs to the field of electric power overhaul, relates to live-line work overhaul technology, and particularly relates to a labor-saving complete tool for live-line work distribution network overhaul.
Background
Along with the rapid development of social economy, the urban power load is rapidly increased, the dependence of vast users on electric power is increasingly greater, the requirement on the power supply reliability is also increasingly higher, and in order to guarantee reliable power supply, live-line operation (uninterrupted operation) becomes the mainstream trend of distribution network maintenance.
The upper lead of the insulated rod electrified drop-out fuse is common work in distribution network uninterrupted operation, but the work consumes long time and has low efficiency at present. The reason is that at present, hot-line workers mostly transfer tools up and down in a mode of tying insulating ropes, only one tool can be transferred at a time, and the time and the labor are very serious because the insulating rods, the shielding covers and the like required in the work are more than 20, so that the time and the labor are very serious.
SUMMERY OF THE UTILITY MODEL
The utility model aims to overcome the defects of the prior art, and provides the labor-saving complete tool for overhauling the live working distribution network, which is convenient and quick to assemble, can transfer a plurality of tools at one time, does not generate the phenomenon that the tools collide with an electric pole, and greatly improves the working efficiency and safety of live working.
The technical problem to be solved by the utility model is realized by adopting the following technical scheme:
the utility model provides a net is joined in marriage in live working and is overhauld with laborsaving complete sets, includes assembly pulley, insulating rope and tube-shape toolbox, the assembly pulley include two pulleys, first pulley setting is on the pole cross arm, the second pulley setting is subaerial at the level of pole cross arm below, insulating rope both ends pass first pulley and second pulley and pass the rings of setting on the tube-shape toolbox for the tube-shape toolbox slides and hoists on the insulating rope between two pulleys.
First pulley hangs on first rope fastening 1 through the couple, first rope fastening suit on the pole cross arm, the second pulley hangs on the second rope fastening through the couple, second rope fastening suit on the weight that pole cross arm below level ground placed.
The insulation rope is provided with a limiting buckle in a sliding manner, the lower end of the limiting buckle is provided with a limiting hook, the limiting hook is hung on a hanging ring of the cylindrical tool box to achieve the function of sliding limiting, and the buckle is a clamping structure with two sides capable of being opened and buckled.
The utility model has the advantages and positive effects that:
the tool box has scientific and reasonable design, realizes labor-saving transmission of the tool box through the pulley structure, is very convenient and quick to mount and dismount, can transmit a plurality of tools at one time, and improves the working efficiency by times; the required materials are cheap, and large investment is not needed; the safety coefficient of the transfer tool room is high, and the phenomenon that tools fall off or collide with an electric pole cannot occur; the applicability is strong, and the device can be widely popularized and used in the electric power distribution operation range after conversion, so that the working efficiency is effectively improved.
Drawings
Fig. 1 is a schematic structural diagram of a use state of the present invention.
Detailed Description
The present invention will be described in further detail with reference to the following embodiments, which are illustrative only and not limiting, and the scope of the present invention is not limited thereby.
The utility model provides a net distribution of live working overhauls with laborsaving complete sets, as shown in figure 1, includes assembly pulley, insulating rope 9 and tube-shape toolbox 5, the assembly pulley include two pulleys, first pulley 4 sets up on pole cross arm 2, second pulley 6 sets up on the level of pole cross arm below subaerial, insulating rope both ends pass first pulley and second pulley and pass the rings that set up on the tube-shape toolbox for the tube-shape toolbox slides and hoists on the insulating rope between two pulleys.
First pulley hang on first rope fastening 1 through couple 3, first rope fastening suit on the pole cross arm.
The second pulley hang on second rope fastening 7 through the couple, second rope fastening suit on the weight 8 that pole cross arm below level ground placed.
The insulation rope is provided with a limit buckle 10 in a sliding mode, the lower end of the limit buckle is provided with a limit hook 11, the limit hook is hung on a hanging ring of the cylindrical tool box and has a sliding limit function, and the buckle is of a clamping structure, two sides of the clamping structure can be opened and buckled.
In the actual use process, the tubular toolbox is mostly in a tubular box structure, if the weight is reduced, the toolbox can also be in a tool bag form, and if the tool bag form is adopted, a rolled PVC plastic plate needs to be inserted into the tool bag to play a supporting role.
In the specific embodiment, the length of the insulating rope is 15-18 meters, the weight of the weight is more than 30kg, and the insulating rope is placed 8-10 meters away from the electric pole to ensure that the insulating rope does not collide with the electric pole in the process of lifting the tool box. During operation, the ground electrician can complete the transmission of the tools required by one-phase operation to the tool position on the rod, and can use the limiting buckle to manually limit the clamping stop of the tool box, so that the ground electrician can prepare the materials required by the second-phase operation.
Although the embodiments of the present invention and the accompanying drawings are disclosed for illustrative purposes, those skilled in the art will appreciate that: various substitutions, changes and modifications are possible without departing from the spirit and scope of the utility model and the appended claims, and therefore the scope of the utility model is not limited to the disclosure of the embodiments and the accompanying drawings.