CN215277907U - Sorting and recycling device for construction waste - Google Patents

Sorting and recycling device for construction waste Download PDF

Info

Publication number
CN215277907U
CN215277907U CN202022906184.1U CN202022906184U CN215277907U CN 215277907 U CN215277907 U CN 215277907U CN 202022906184 U CN202022906184 U CN 202022906184U CN 215277907 U CN215277907 U CN 215277907U
Authority
CN
China
Prior art keywords
furling
sorting
conveyer belt
screening
letter sorting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022906184.1U
Other languages
Chinese (zh)
Inventor
孙振杰
姚泽明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Town World Environmental Protection Technology Engineering Co ltd
Original Assignee
Shenzhen Town World Environmental Protection Technology Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Town World Environmental Protection Technology Engineering Co ltd filed Critical Shenzhen Town World Environmental Protection Technology Engineering Co ltd
Priority to CN202022906184.1U priority Critical patent/CN215277907U/en
Application granted granted Critical
Publication of CN215277907U publication Critical patent/CN215277907U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Processing Of Solid Wastes (AREA)

Abstract

The utility model discloses a sorting recovery unit of construction waste, including retrieving the letter sorting automobile body, screening partial shipment subassembly, drawing in the subassembly, drawing in conveyer belt and fixed stay, screening partial shipment subassembly is located in retrieving the letter sorting automobile body, fixed stay locates on retrieving the letter sorting automobile body, draw in the conveyer belt and locate on the fixed stay, draw in the subassembly and locate on retrieving the letter sorting automobile body and be located the both sides of drawing in the conveyer belt, draw in the subassembly including draw in the board, draw in the chain, driving shaft, driven shaft, draw in motor and regulation hydraulic stem in; the utility model belongs to the technical field of the building rubbish handles, specifically be an adjustable setting through drawing in the subassembly, improved the application scope of device letter sorting, increased letter sorting efficiency to through the setting of screening partial shipment subassembly, can sieve metal material and other rubbish, improved building rubbish's letter sorting recovery unit of building rubbish utilization ratio.

Description

Sorting and recycling device for construction waste
Technical Field
The utility model belongs to the technical field of building rubbish handles, specifically indicate a building rubbish's letter sorting recovery unit.
Background
With the rapid development of national economy, the national infrastructure is also under continuous renewal construction, especially the construction of railways and highways, and the reconstruction of urban buildings. The development of cities enables old buildings to be dismantled successively in the continuous construction of various house projects. During the house dismantling process, a large amount of solid waste, namely construction waste, can be generated. At present, the quantity of the construction waste in China accounts for 30 to 40 percent of the total quantity of the urban waste. Reckoning by the standard of 500-600 tons/ten thousand square meters, as far as 2020, the newly increased building area of China is about 300 hundred million square meters, and the newly generated building garbage is a shocking number. However, most of the construction wastes are not treated, and are transported to the suburbs or villages by construction units, and are piled or buried in the open air, so that a large amount of construction expenses such as land acquisition expenses and garbage clearing and transporting expenses are consumed, and meanwhile, the problems of scattering, dust, sand flying and the like in the clearing and piling processes cause serious environmental pollution.
Because building site construction ground is comparatively unevenness, present construction waste recovery unit does not have regulatory function, and then can not be effective convenient all receive everywhere rubbish and choose, mixes more metal material in the construction waste simultaneously, and this part metal can be retrieved and recycled, and present construction waste recovery unit can not filter the metal material, has caused the waste of resource.
SUMMERY OF THE UTILITY MODEL
To the above situation, for overcoming prior art's defect, the utility model provides a through the adjustable setting of drawing in the subassembly, improved the application scope of device letter sorting, increased letter sorting efficiency to through the setting of screening partial shipment subassembly, can sieve metal material and other rubbish, improved the building rubbish's of building rubbish utilization ratio letter sorting recovery unit.
The utility model adopts the following technical scheme: the utility model relates to a sorting recovery unit of construction waste, including retrieving the letter sorting automobile body, screening partial shipment subassembly, drawing in the conveyer belt and fixed stay, screening partial shipment subassembly is located in retrieving the letter sorting automobile body, fixed stay locates on retrieving the letter sorting automobile body, draw in the conveyer belt and locate on fixed stay, draw in the subassembly and locate on retrieving the letter sorting automobile body and be located the both sides of drawing in the conveyer belt, draw in the subassembly including draw in the board, draw in the chain, driving shaft, driven shaft, draw in motor and regulation hydraulic stem in, draw in the board and articulate on retrieving the letter sorting automobile body, driving shaft and driven shaft rotatable locate on drawing in the board in, draw in the chain rotatable locate on drawing in the board in and with driving shaft and driven shaft connection, be equipped with drawing in the tooth on drawing in the chain, draw in the motor and locate on drawing in the board in, draw in motor output and locate on the driving shaft, the adjusting hydraulic rod is arranged on the fixed supporting frame and hinged with the furling plate.
Further, screening partial shipment subassembly is including screening conveyer belt, glove compartment and metal box, it is internal that the recovery letter sorting car is located to the screening conveyer belt, the screening conveyer belt with draw in the conveyer belt and connect, the glove compartment is located and is retrieved in the letter sorting car, the glove compartment is located the terminal below of screening conveyer belt, it is internal that the recovery letter sorting car is located to the metal box, the metal box is located the screening conveyer belt below, be equipped with magnetism on the screening conveyer belt and inhale the strip, be equipped with the scraper blade on the metal box, scraper blade and the laminating of screening conveyer belt bottom.
Furthermore, the furling components are symmetrical and arranged on two sides of the furling conveying belt.
Further, the furling motors of the furling components on two sides of the furling conveying belt rotate in opposite directions.
Furthermore, a pushing handle is arranged on the recycling sorting vehicle body.
Adopt above-mentioned structure the utility model discloses the beneficial effect who gains as follows: this scheme building rubbish's letter sorting recovery unit through the adjustable setting that draws in the subassembly in, has improved the application scope of device letter sorting, has increased letter sorting efficiency to through the setting of screening partial shipment subassembly, can sieve metal material and other rubbish, improved the building rubbish utilization ratio.
Drawings
Fig. 1 is a schematic view of the overall structure of a sorting and recycling device for construction waste according to the present invention;
fig. 2 is the utility model relates to a building rubbish's letter sorting recovery unit's top view.
The sorting machine comprises a recycling sorting vehicle body 1, a screening and subpackaging component 2, a collecting component 3, a collecting conveyor belt 4, a fixing support frame 5, a collecting plate 6, a collecting chain 7, a collecting chain 8, a driving shaft 9, a driven shaft 10, a collecting motor 11, a regulating hydraulic rod 12, collecting teeth 13, a screening conveyor belt 14, a sundry box 15, a metal box 16, a magnetic suction strip 17, a pushing handle 18 and a scraper.
The accompanying drawings are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description serve to explain the invention and not to limit the invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments; based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
As shown in fig. 1-2, the utility model relates to a sorting and recycling device for construction waste, which comprises a recycling sorting vehicle body 1, a screening and subpackaging assembly 2, a furling assembly 3, a furling conveyor belt 4 and a fixed support frame 5, wherein the screening and subpackaging assembly 2 is arranged in the recycling sorting vehicle body 1, the fixed support frame 5 is arranged on the recycling sorting vehicle body 1, the furling conveyor belt 4 is arranged on the fixed support frame 5, the furling assembly 3 is arranged on the recycling sorting vehicle body 1 and is positioned at two sides of the furling conveyor belt 4, the furling assembly 3 comprises a furling plate 6, a furling chain 7, a driving shaft 8, a driven shaft 9, a furling motor 10 and an adjusting hydraulic rod 11, the furling plate 6 is hinged on the recycling sorting vehicle body 1, the driving shaft 8 and the driven shaft 9 are rotatably arranged on the furling plate 6, the furling chain 7 is rotatably arranged on the furling plate 6 and is connected with the driving shaft 8 and the driven shaft 9, the folding chain 7 is provided with folding teeth 12, the folding motor 10 is arranged on the folding plate 6, the output end of the folding motor 10 is arranged on the driving shaft 8, the adjusting hydraulic rod 11 is arranged on the fixed supporting frame 5, and the adjusting hydraulic rod 11 is hinged with the folding plate.
Wherein, screening partial shipment subassembly 2 is including screening conveyer belt 13, glove compartment 14 and metal box 15, screening conveyer belt 13 is located and is retrieved in the letter sorting automobile body 1, screening conveyer belt 13 is connected with drawing in conveyer belt 4, glove compartment 14 is located and is retrieved in the letter sorting automobile body 1, glove compartment 14 is located the terminal below of screening conveyer belt 13, metal box 15 is located and is retrieved in the letter sorting automobile body 1, metal box 15 is located screening conveyer belt 13 below, it inhales strip 16 to be equipped with magnetism on the screening conveyer belt 13, be equipped with scraper blade 18 on the metal box 15, the laminating of scraper blade 18 and screening conveyer belt 13 bottom.
The furling assembly 3 is symmetrical and arranged at two sides of the furling conveying belt 4.
The furling motors 10 of the furling components 3 on both sides of the furling conveyor belt 4 rotate in opposite directions.
The recycling and sorting trolley body 1 is provided with a pushing handle 17.
During the specific use, the staff promotes and promotes handle 17 to job site, then start regulation hydraulic stem 11, adjust the angle of drawing in board 6, then start the motor 10 relative rotation that draws in of drawing in 4 both sides of conveyer belt that draws in, and then drive and draw in chain 7 and draw in building rubbish to drawing in on conveyer belt 4 through drawing in tooth 12 in, start to draw in conveyer belt 4 and convey rubbish to screening conveyer belt 13, the metal material is inhaled strip 16 by magnetism simultaneously and is adsorbed, start screening conveyer belt 13, building rubbish is carried to in debris box 14, then the metal material is adsorbed on inhaling strip 16 by magnetism, when transporting to metal box 15 department, strike off by scraper blade 18 and fall into in metal box 15.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
The present invention and the embodiments thereof have been described above, but the description is not limited thereto, and the embodiment shown in the drawings is only one of the embodiments of the present invention, and the actual structure is not limited thereto. In summary, those skilled in the art should understand that they should not be limited to the embodiments described above, and that they can design the similar structure and embodiments without departing from the spirit of the invention.

Claims (5)

1. The utility model provides a building rubbish's letter sorting recovery unit which characterized in that: the sorting machine comprises a recovery sorting vehicle body, a screening and subpackaging assembly, a furling conveyor belt and a fixed support frame, wherein the screening and subpackaging assembly is arranged in the recovery sorting vehicle body, the fixed support frame is arranged on the recovery sorting vehicle body, the furling conveyor belt is arranged on the fixed support frame, the furling assembly is arranged on the recovery sorting vehicle body and positioned on two sides of the furling conveyor belt, the furling assembly comprises a furling plate, a furling chain, a driving shaft, a driven shaft, a furling motor and an adjusting hydraulic rod, the furling plate is hinged on the recovery sorting vehicle body, the driving shaft and the driven shaft are rotatably arranged on the furling plate, the furling chain is rotatably arranged on the furling plate and connected with the driving shaft and the driven shaft, furling teeth are arranged on the furling chain, the furling motor is arranged on the furling motor, the output end of the furling motor is arranged on the driving shaft, and the adjusting hydraulic rod is arranged on the fixed support frame, the adjusting hydraulic rod is hinged with the furling plate.
2. The sorting and recycling device for construction waste as claimed in claim 1, wherein: screening partial shipment subassembly is including screening conveyer belt, glove compartment and metal box, it is internal that the recovery letter sorting car is located to the screening conveyer belt, the screening conveyer belt with draw in the conveyer belt and connect, the glove compartment is located and retrieves in the letter sorting car internally, the glove compartment is located the terminal below of screening conveyer belt, it is internal that the recovery letter sorting car is located to the metal box, the metal box is located screening conveyer belt below, it inhales the strip to be equipped with magnetism on the screening conveyer belt, be equipped with the scraper blade on the metal box, the laminating of scraper blade and screening conveyer belt bottom.
3. The sorting and recycling device for construction waste as claimed in claim 1, wherein: the furling components are symmetrical and arranged on two sides of the furling conveying belt.
4. The sorting and recycling device for construction waste as claimed in claim 3, wherein: the furling motors of the furling components on two sides of the furling conveying belt rotate in opposite directions.
5. The sorting and recycling device for construction waste as claimed in claim 1, wherein: the recycling and sorting trolley body is provided with a pushing handle.
CN202022906184.1U 2020-12-05 2020-12-05 Sorting and recycling device for construction waste Active CN215277907U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022906184.1U CN215277907U (en) 2020-12-05 2020-12-05 Sorting and recycling device for construction waste

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022906184.1U CN215277907U (en) 2020-12-05 2020-12-05 Sorting and recycling device for construction waste

Publications (1)

Publication Number Publication Date
CN215277907U true CN215277907U (en) 2021-12-24

Family

ID=79513141

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022906184.1U Active CN215277907U (en) 2020-12-05 2020-12-05 Sorting and recycling device for construction waste

Country Status (1)

Country Link
CN (1) CN215277907U (en)

Similar Documents

Publication Publication Date Title
CN206980843U (en) A kind of recycle device for building waste
CN206304869U (en) A kind of building waste crushing and screening retracting device
CN110560235A (en) Building rubbish reducing mechanism with dustproof and metal recycle
CN107754989A (en) A kind of building rubbish treatment device
CN208727584U (en) A kind of building waste recyclable device
CN108086217A (en) A kind of clearing apparatus and garbage truck
CN102974531B (en) Soil purification separator
CN117772384A (en) Mineralized refuse exploitation crushing and sorting conveyor
CN202779143U (en) Crawler traveling type construction waste treatment equipment
CN215277907U (en) Sorting and recycling device for construction waste
CN204418074U (en) Handcart for sweeping
CN107268514B (en) Self-travel type railroad track removes sand vehicle
CN205475022U (en) Subway tunnel rubbish cleaning device
CN105862633A (en) Intelligent garbage sweeping and classification collecting device
CN206486855U (en) Refuse collection vehicle
CN212017943U (en) Crushing and screening machine for construction waste
CN205776014U (en) A kind of intelligent garbage cleans classified collection device
CN110102363B (en) Categorised recovery plant of cubic building rubbish
CN2608552Y (en) Environimental protection cleaning vehicle
CN111701980A (en) Construction waste grading treatment device capable of recycling metal
CN205868796U (en) Portable building rubbish sorting machine
CN217419481U (en) Sandy beach rubbish cleaning device
CN210658176U (en) Gardens fallen leaves recovery unit
CN212069152U (en) Building rubbish feeding and conveying belt for brickmaking
CN210315352U (en) Sanitation cleaning device for municipal road

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant