CN214932257U - Novel steel pipe stacking frame - Google Patents

Novel steel pipe stacking frame Download PDF

Info

Publication number
CN214932257U
CN214932257U CN202121083376.5U CN202121083376U CN214932257U CN 214932257 U CN214932257 U CN 214932257U CN 202121083376 U CN202121083376 U CN 202121083376U CN 214932257 U CN214932257 U CN 214932257U
Authority
CN
China
Prior art keywords
steel pipe
base
horizontal pole
steel
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202121083376.5U
Other languages
Chinese (zh)
Inventor
卢新荣
蒋宇航
夏健平
陶阁
卢良
黄增林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Construction Group Co Ltd
Original Assignee
Zhongtian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongtian Construction Group Co Ltd filed Critical Zhongtian Construction Group Co Ltd
Priority to CN202121083376.5U priority Critical patent/CN214932257U/en
Application granted granted Critical
Publication of CN214932257U publication Critical patent/CN214932257U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model provides a novel steel pipe piles frame, including the base, bear the horizontal pole, connect the horizontal pole, the base is the U type to a plurality of is a set of spaced opening vertical to setting up that makes progress, a plurality of bear the horizontal pole by spaced horizontal parallel arrangement on the base, and both ends with the base both sides are perpendicular, connect the horizontal pole by the level setting, and with between a plurality of bases and interconnect. The utility model discloses simple structure, the installation is dismantled conveniently, and the turnover rate is high, and bearing stability is good, and the steel pipe layering is put things in good order, and mutual noninterference gets puts the convenience, and the steel pipe layering is put things in good order, and the fixed statistics of being convenient for of quantity piles up length and is adjustable according to steel pipe length is nimble, and the steel pipe piles up a steel pipe and accounts for the high ratio, and convenient for material collection reduces the cost and increases.

Description

Novel steel pipe stacking frame
Technical Field
The utility model belongs to the construction field, concretely relates to device is stacked to steel pipe.
Background
At present, the job site, the pile frame that the steel pipe was stacked the adoption has I shape socket joint formula steel pipe to pile up the frame, square steel welding combination type piles up the frame, multiple pile frame such as square steel earth anchor separates shelves type, these pile frame ubiquitous steel pipe pile frame bear poor stability, it is yielding, the turnover rate is low, fragile scheduling problem, secondly these pile frames still have the steel pipe wholly to stack, the pile is put the confusion, the quantity is not convenient for make up, the steel pipe is got and is needed the secondary to transport to bind, the workman gets and puts difficult inefficiency scheduling problem, therefore, it is necessary to develop or develop a novel steel pipe pile frame, solve the above-mentioned problem that exists.
SUMMERY OF THE UTILITY MODEL
In order to overcome the not enough of above-mentioned prior art, the utility model provides a novel steel pipe piles frame to solve conventional steel pipe and pile frame poor stability, yielding, the turnover inefficiency, the steel pipe is got and is put inconveniently, puts things in good order the confusion, and steel pipe quantity is difficult to the statistics scheduling problem.
The novel steel pipe stacking frame is characterized by comprising a base, bearing cross rods and connecting cross rods, wherein the base is U-shaped, a plurality of cross rods are arranged in a group of spaced openings in an upward vertical direction, the bearing cross rods are arranged on the base in a spaced horizontal parallel mode, two ends of each bearing cross rod are perpendicular to two sides of the base, and the connecting cross rods are horizontally arranged and connected with the base.
Further, the load-bearing crossbars are interconnected horizontally across their openings by providing openings in the base uprights.
Further, the base and the connecting cross rod are connected through a sleeve and fixed through bolts.
Furthermore, the base is formed by connecting a connecting steel plate, a connecting bolt and a bearing channel steel upright post.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model discloses an improve steel pipe pile frame structure, increase the bearing stability of steel pipe pile frame, reduce the spoilage that the steel pipe pile frame, improve turnover efficiency, secondly stack the design through the layering, solved workman's steel pipe and put things in good order the confusion, get the problem of putting the difficulty, improved workman work efficiency. And finally, determining the number of single-layer steel pipes of the stacking frame by calculating the spacing and the spacing size design of the fixed stacking frame, and achieving the purpose of convenience in counting the number of the steel pipes.
The utility model discloses still another purpose is through the structural optimization design who piles the frame to the steel pipe, increases the steel pipe that piles the frame structure and accounts for the ratio, and this novel steel pipe piles the base of frame, bears the horizontal pole, connects several components of horizontal pole and all takes from on-the-spot steel pipe, on-the-spot steel pipe is for waiting to stack the steel pipe, and then reaches and draws materials on the spot, reduces the purpose of cost increase.
Drawings
Fig. 1 is a schematic structural view of a three-dimensional model of the present invention;
FIG. 2 is a front view of the structure of the present invention;
FIG. 3 is a left side view of the structure of the present invention;
fig. 4 is a top view of the structure of the present invention;
fig. 5 is a partial enlarged view 19 of fig. 4.
In the figure: the steel-channel steel-based building block comprises a steel-channel steel base 1, a steel-channel steel bearing column 2, a steel-channel bearing cross rod 3, a connecting cross rod 4, a sleeve 5, a fixing bolt 6, a bearing cross rod vertical interval 7, a bearing cross rod-to-steel base interval 8, a stacking frame width 9, a stacking frame length 10, a connecting rod vertical interval 11, a connecting rod-to-column top distance 12, a steel-channel steel column length 13, a connecting rod center distance 14, a connecting rod-to-base distance 15, a steel-channel steel width 16, a connecting bolt 17, a connecting steel plate 18 and a local enlarged image 19.
Detailed Description
The present invention is further described in detail below with reference to the drawings so that those skilled in the art can implement the invention with reference to the description.
As shown in fig. 1 to 4, the steel tube stacking base of the present invention is formed by connecting channel steel 1, channel steel 2, steel plate 18 by bolts 17, channel steel 1, channel steel 2 are 100mmx48mmx10mm channel steel, channel steel 2 is perforated on the upright with a vertical distance 7 of a bearing cross rod 3, then the bearing cross rod 3 is sleeved in the hole, and then the steel tubes are stacked in layers, the vertical distance 7 is equal to 4 times of the outer diameter of the steel tube and 5 mm of the steel tube deformation allowance, the width 9 of the steel tube stacking rack is 980mm, the size of the steel tube stacking rack is fixed, 20 steel tubes are placed in the first row, and 19 steel tubes are placed in the second row; the steel pipe stacking frame structure reinforcing and stabilizing part is composed of a sleeve 5, a fixing bolt 6 and a cross rod 4, the cross rod 4 is sleeved into the sleeve 5, and the bolt 6 is screwed down to further achieve the purpose of reinforcing the steel pipe stacking frame.
When the steel pipe stacking frame is used, the frame formed by connecting the channel steel 1, the channel steel 2 and the steel plate 18 through bolts is placed in a steel pipe stacking area, then the connecting cross rods 4 are installed, the fastening bolts 6 are reinforced, finally the bearing cross rods 3 are installed in layers, and the steel pipes are stacked in layers; when the steel pipe is taken and placed, the lifting ropes are installed by utilizing the gaps between the bearing cross bars 3, and the steel pipe is taken and placed layer by layer.
The description is only for the purpose of illustrating the preferred embodiments of the present invention and is not intended to limit the scope of the present invention, but rather, any variations and modifications within the scope of the present invention as defined by the appended claims will be suggested to one of ordinary skill in the art.

Claims (4)

1. The utility model provides a novel steel pipe piles frame, its characterized in that, includes the base, bears the horizontal pole, connects the horizontal pole, the base is the U type to a plurality of is a set of vertical setting that makes progress that has the spaced opening, a plurality of bear the horizontal pole by spaced horizontal parallel arrangement be in on the base, and both ends with the base both sides are perpendicular, connect the horizontal pole by the level setting, and with between a plurality of bases and interconnect.
2. A new form of steel pipe stacking rack as claimed in claim 1 wherein said load carrying rails are interconnected horizontally across their openings by openings in said base uprights.
3. The novel steel tube stacking rack as claimed in claim 1, wherein the base and the connecting cross bar are connected through a sleeve and fixed through bolts.
4. The novel steel tube stacking rack as claimed in claim 1, wherein the base is formed by connecting steel plates, connecting bolts and bearing channel steel columns.
CN202121083376.5U 2021-05-20 2021-05-20 Novel steel pipe stacking frame Expired - Fee Related CN214932257U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121083376.5U CN214932257U (en) 2021-05-20 2021-05-20 Novel steel pipe stacking frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121083376.5U CN214932257U (en) 2021-05-20 2021-05-20 Novel steel pipe stacking frame

Publications (1)

Publication Number Publication Date
CN214932257U true CN214932257U (en) 2021-11-30

Family

ID=79061667

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121083376.5U Expired - Fee Related CN214932257U (en) 2021-05-20 2021-05-20 Novel steel pipe stacking frame

Country Status (1)

Country Link
CN (1) CN214932257U (en)

Similar Documents

Publication Publication Date Title
CN215104737U (en) A assembled support for bridge construction
CN109230155B (en) Prefabricated wallboard piling bin
CN110593547B (en) Frame body structure based on attached lifting scaffold and construction method thereof
CN110963174B (en) Assembled prefabricated staircase stacking rack and construction method
CN214932257U (en) Novel steel pipe stacking frame
CN214298886U (en) Detachable material stacking and lifting device
CN218437171U (en) Elevator foundation construction structure
CN215947849U (en) Interim steel landing stage bearing structure
CN211196946U (en) Portable plate stacking support
CN210508494U (en) Combined fairway
CN211421793U (en) Design steel operation platform
CN213731706U (en) Multifunctional storage rack for concrete segment beam reinforcing mesh
CN214394156U (en) A rack for sheet metal materials
CN214525784U (en) An assembled tower crane component stacking rack
CN215362344U (en) Convenient material stacking device
CN211867773U (en) A detachable and retractable combined storage rack
CN221277359U (en) Large-scale unsettled steel vestibule bed-jig structure
CN218714825U (en) Disc buckle type safety protection channel
CN215037381U (en) Reinforcing steel bar storage device
CN211806090U (en) Superimposed sheet storage unit and superimposed sheet storage rack
CN219138315U (en) Construction platform for hanging basket downwards
CN212897484U (en) High-altitude operation platform for constructional engineering
CN213674078U (en) Combined assembly type steel bar classifying and stacking rack
CN222290135U (en) Plate shelves
CN215945186U (en) Steel piling bin

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211130