CN214899827U - High-altitude outdoor cable terminal operation platform - Google Patents
High-altitude outdoor cable terminal operation platform Download PDFInfo
- Publication number
- CN214899827U CN214899827U CN202121457143.7U CN202121457143U CN214899827U CN 214899827 U CN214899827 U CN 214899827U CN 202121457143 U CN202121457143 U CN 202121457143U CN 214899827 U CN214899827 U CN 214899827U
- Authority
- CN
- China
- Prior art keywords
- basket
- flower basket
- main hanging
- hanging flower
- cross arm
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 229910000831 Steel Inorganic materials 0.000 claims description 9
- 239000010959 steel Substances 0.000 claims description 9
- 238000010276 construction Methods 0.000 abstract description 5
- 238000004519 manufacturing process Methods 0.000 abstract description 3
- 238000009434 installation Methods 0.000 description 4
- 238000000034 method Methods 0.000 description 3
- 239000000463 material Substances 0.000 description 2
- 230000004888 barrier function Effects 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
Images
Landscapes
- Cultivation Receptacles Or Flower-Pots, Or Pots For Seedlings (AREA)
Abstract
The utility model discloses an outdoor cable terminal operation platform in high altitude, arrange in between two adjacent cross arms about the terminal shaft tower in, including main hanging flower basket and vice hanging flower basket, hoist and the cross arm fixed connection who is located the top are passed through at main hanging flower basket top, and main hanging flower basket bottom is through anchor clamps and the cross arm fixed connection who is located the below, corresponds position department and is equipped with the uncovered that the cable terminal of being convenient for runs through in main hanging flower basket top and bottom, is equipped with on the main hanging flower basket of uncovered one side and supplies constructor to come in and go out and make things convenient for the built-in fence door in cable terminal, and vice hanging flower basket detachable connects in the main hanging flower basket bottom of uncovered side. The utility model adopts the form of upper hanging and lower locking to firmly fix the main hanging basket between the upper and lower adjacent cross arms, thus ensuring that the personnel can safely and not overturn during the cable terminal manufacturing operation; the auxiliary hanging basket is additionally arranged at the bottom of the main hanging basket, so that the construction personnel can inspect and maintain the hardware fitting used for fixing the cable terminal on the cross arm more conveniently.
Description
Technical Field
The utility model relates to a power transmission and transformation technical field especially relates to an outdoor cable termination operation platform in high altitude.
Background
In the installation engineering of high-voltage cables, the height of a terminal for connecting the high-voltage cable with an overhead line is generally 20-50 meters on a cross arm of a line terminal tower, and personnel often need to work aloft, so that the aloft work personnel manufactured by an outdoor terminal need a relatively safe work platform to complete the installation work of the terminal.
The existing work platform has two types:
firstly, a floor type steel pipe scaffold is adopted. Based on the ground, a large-volume scaffold platform is erected, a large amount of materials such as steel pipes and fasteners are needed, the erection period is long, and the working efficiency is low; and the height of the cable terminal is generally 30-50 meters, when the height of the scaffold is over 24 meters, the operation risk is raised to level 4, the operation risk is high, the danger of falling from a high place and falling from a high place is accompanied, the potential risk to personnel and equipment is high, and the expert demonstration is needed to be carried out on the scheme.
And secondly, using the cable terminal rod cross beam as an overhanging beam and erecting an overhanging type scaffold platform. The danger of the personnel is high in the setting process. Because the cable termination manufacture process has dampproofing, dustproof requirement, the platform top need set up into closed operation canopy, and the area of catching wind is great, and the platform safety stability of overhanging type is poor.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to prior art's weak point, provide an outdoor cable terminal operation platform in high altitude of installation simple, operation safety.
The utility model provides a high altitude outdoor cable terminal operation platform arranges in between two adjacent cross arms about the terminal shaft tower in, including main hanging flower basket and vice hanging flower basket, hoist and the cross arm fixed connection who is located the top are passed through at main hanging flower basket top, and main hanging flower basket bottom is through anchor clamps and the cross arm fixed connection who is located the below, corresponds position department and is equipped with the uncovered that the cable terminal of being convenient for runs through in main hanging flower basket top and bottom, is equipped with on the main hanging flower basket of uncovered one side and supplies constructor to come in and go out and make things convenient for the built-in fence door in cable terminal, and vice hanging flower basket detachable connects in the main hanging flower basket bottom of uncovered side.
The hanger comprises a door-shaped hanging seat, lifting lugs fixedly connected to two sides of the door-shaped hanging seat, a steel wire rope fixedly connected to the lifting lugs, and a lifting hook fixedly connected to the bottom of the steel wire rope, wherein hanging lugs which are hung with the lifting hook in a one-to-one manner are arranged on the periphery of the top of the main hanging basket, positioning screws are fixedly connected between the support arms on two sides of the door-shaped hanging seat, and the door-shaped hanging seat is clamped on the cross arm through the positioning screws.
The support arms on two sides of the door-shaped hanging seat are provided with vertical strip-shaped holes which are arranged face to face, and the positioning screw is connected to the door-shaped hanging seat in an adjustable manner through the vertical strip-shaped holes.
The clamp comprises an upper clamping plate arranged in the main hanging basket and a lower clamping plate arranged at the bottom of a cross arm below, adjusting screws are detachably connected to the upper clamping plates on two sides of the cross arm, and the bottoms of the adjusting screws penetrate through the bottom plate of the main hanging basket and the lower clamping plate and are in threaded connection with fastening nuts.
The two ends of the upper clamping plate are provided with strip-shaped holes transversely arranged along the cross arm, and the adjusting screw is arranged on the upper clamping plate in a left-right position adjustable mode through the strip-shaped holes.
The periphery of the main hanging basket is provided with a dustproof film.
The auxiliary hanging basket is integrally concave towards the cable terminal.
The utility model adopts the form of upper hanging and lower locking to firmly fix the main hanging basket between the upper and lower adjacent cross arms, thus ensuring that the personnel can safely and not overturn during the cable terminal manufacturing operation; the auxiliary hanging basket is additionally arranged at the bottom of the main hanging basket, so that the inspection and maintenance of hardware fittings used for fixing the cable terminal on the cross arm can be more conveniently carried out by constructors; the main hanging basket and the auxiliary hanging basket can be installed and detached through hoisting, and constructors only need to take the lift truck to cooperate, so that the field construction time is shortened, the investment of manpower and material resources is reduced, the operation risk is reduced, and the potential risk phenomenon of high-altitude falling objects on ground personnel, cables and equipment is reduced. The utility model discloses can effectively reduce the operation risk, improve work efficiency, reduce construction cost, and can reuse, the stand is sold construction cost low.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a schematic sectional view at a-a in fig. 1.
FIG. 3 is a schematic cross-sectional view at B-B in FIG. 1.
Fig. 4 is a schematic view of the structure in the direction C in fig. 1.
The labels shown in the figures and the corresponding component names are:
1. a main hanging basket; 11. opening the mouth; 12. a barrier gate; 13. hanging a lug; 14. a through hole;
2. an auxiliary hanging basket;
3. a spreader; 31. a gantry crane base; 32. lifting lugs; 33. a wire rope; 34. a hook; 35. positioning a screw rod; 311. a vertical strip-shaped hole;
4. a clamp; 41. an upper clamping plate; 42. a lower clamping plate; 43. adjusting the screw rod; 44. fastening a nut; 411. a strip hole;
5. a dust-proof film;
6. a terminal tower;
7. a cross arm;
8. and (4) cable termination.
Detailed Description
As can be seen from figures 1 to 4, the aerial outdoor cable terminal operation platform of the utility model is arranged between two adjacent cross arms 7 on the upper and lower sides of a terminal tower 6, comprises a main hanging basket 1, an auxiliary hanging basket 2, a lifting appliance 3 and a clamp 4,
an opening 11 convenient for the cable terminal 8 to penetrate through is arranged at the corresponding position of the top and the bottom of the main hanging basket 1, a fence door 12 for constructors to go in and out and convenient for the cable terminal 8 to be embedded is arranged on the main hanging basket 1 at one side of the opening 11, one side of the fence door 12 is hinged with the main hanging basket 1 through a pin shaft, and the other side of the fence door is detachably connected with the main hanging basket 1 through a bolt;
the auxiliary hanging basket 2 is detachably connected to the bottom of the main hanging basket 1 on the side of the opening 11 through a threaded fastener, and the whole auxiliary hanging basket 2 is concave and arranged facing the cable terminal 8;
the main hanging basket 1 is arranged on a cross arm 7 located below, the top of the main hanging basket 1 is fixedly connected with the cross arm 7 located above through a lifting appliance 3, and the bottom of the main hanging basket 1 is fixedly connected with the cross arm 7 located below through a clamp 4.
As can be seen from fig. 1 to 4, the lifting appliance 3 of the present invention includes a door-shaped hanging seat 31, two lifting lugs 32, four steel wire ropes 33, four lifting hooks 34 and a positioning screw 35, the opening of the door-shaped hanging seat 31 is clamped on the cross arm 7 located above, the two lifting lugs 32 are symmetrically welded on the support arms of each side of the door-shaped hanging seat 31, the two steel wire ropes 33 are fixedly connected to the lifting lugs 32 of each side in a group, the lifting hooks 34 are fixedly connected to the bottom of each steel wire rope 33 in a one-to-one manner, the hanging lugs 13 hooked with the lifting hooks 34 in a one-to-one manner are arranged at the four corner positions at the top of the main hanging basket 1, and the main hanging basket 1 is hung at the bottom of the door-shaped hanging seat 31 by the matching of the hanging lugs 13 and the lifting hooks 34; the support arms on two sides of the door-shaped hanging seat 31 are provided with vertical strip-shaped holes 311 which are arranged face to face, the positioning screw 35 passes through the vertical strip-shaped holes 311 at the bottom of the cross arm 7 below and is connected with the two support arms of the door-shaped hanging seat 31, the positioning screw 35 adjusts the vertical position at the bottom of the cross arm 7 through the vertical strip-shaped holes 311, and the door-shaped hanging seat 31 is clamped on the cross arm 7 below through the positioning screw 35.
As can be seen from fig. 1 to 4, the utility model provides a clamp 4 includes grip block 41, lower grip block 42 and two adjusting screw 43, it arranges in on the bottom plate of main hanging flower basket 1 inboard and along cross arm 7 transverse arrangement to go up grip block 41, be equipped with symmetrical arrangement through-hole 14 on the bottom plate of the main hanging flower basket 1 of cross arm 7 both sides, be equipped with on the last grip block 41 that corresponds with through-hole 14 along cross arm 7 transverse arrangement's bar hole 411, lower grip block 42 is arranged in the bottom of below cross arm 7 and is arranged with last grip block 41 parallel, adjusting screw 43's screw rod portion passes bar hole 411, through-hole 14 and lower grip block 42 and fastening nut 44 threaded connection, adjusting screw 43 carries out the regulation of left and right positions in the cross arm both sides through bar hole 411, the bottom plate of main hanging flower basket 1 is fixed in on the cross arm 7 that is located the below through last grip block 41 locking.
The utility model discloses during the installation, utilize earlier 6 upper cross arms 7 of terminal shaft tower hoist 3 of fixed, hoist 3 draws forth four wire rope 33 of taking lifting hook 34 from this, correspond and hold four hangers 13 on 1 upper portion of main hanging flower basket, recycle positioning screw 35, adjust the position of door type hanging seat 31 on cross arm 7, make wire rope 33 atress, make main hanging flower basket 1 keep the level and make 1 bottom of main hanging flower basket sit on this layer cross arm 7, utilize anchor clamps 4 to be fixed in this layer cross arm 7 with 1 bottom of main hanging flower basket at last.
As can be seen from figures 1, 2 and 4, when the utility model is used for high-speed work, the periphery of the main hanging basket 1 can be wrapped with the dustproof film 5.
The utility model can be processed and manufactured in factories, and is installed and disassembled by adopting lifting on the construction site, thereby reducing the operation risk, improving the working efficiency, saving resources, better protecting personnel and equipment from being damaged,
the utility model discloses having succeeded many times in the engineering and using, the technique is mature, has better popularization and application and worth.
Claims (7)
1. The utility model provides an outdoor cable terminal operation platform in high altitude arranges in between two adjacent cross arms about the terminal shaft tower, its characterized in that: including main hanging flower basket (1) and vice hanging flower basket (2), hoist (3) and the cross arm fixed connection who is located the top are passed through to main hanging flower basket top, main hanging flower basket bottom through anchor clamps (4) and the cross arm fixed connection who is located the below, correspond position department and be equipped with uncovered (11) that the cable terminal of being convenient for runs through in main hanging flower basket top and bottom, be equipped with on the main hanging flower basket of uncovered one side and supply constructor to come in and go out and make things convenient for built-in fence door (12) in cable terminal, vice hanging flower basket detachable connects in the main hanging flower basket bottom of uncovered side.
2. The aerial outdoor cable termination work platform of claim 1, wherein: the lifting appliance comprises a door-shaped lifting seat (31), lifting lugs (32) fixedly connected to two sides of the door-shaped lifting seat, a steel wire rope (33) fixedly connected to the lifting lugs, and lifting hooks (34) fixedly connected to the bottom of the steel wire rope, wherein the lifting lugs (13) are arranged on the periphery of the top of the main lifting basket and are connected with the lifting hooks in a one-to-one mode, positioning screws (35) are fixedly connected between support arms on two sides of the door-shaped lifting seat, and the door-shaped lifting seat is clamped on the cross arm through the positioning screws.
3. The aerial outdoor cable termination work platform of claim 2, wherein: the support arms on two sides of the door-shaped hanging seat are provided with vertical strip-shaped holes (311) which are arranged face to face, and the positioning screw is connected to the door-shaped hanging seat in an adjustable manner through the vertical strip-shaped holes.
4. The aerial outdoor cable termination work platform of claim 1, wherein: the clamp comprises an upper clamping plate (41) arranged in the main hanging basket and a lower clamping plate (42) arranged at the bottom of a cross arm below, adjusting screws (43) are detachably connected to the upper clamping plates on two sides of the cross arm, and the bottoms of the adjusting screws penetrate through a bottom plate (14) of the main hanging basket and the lower clamping plate and are in threaded connection with fastening nuts (44).
5. The aerial outdoor cable termination work platform of claim 4, wherein: be equipped with along the bar hole (411) of cross arm transverse arrangement at last grip block both ends, adjusting screw passes through this bar hole and controls the position adjustable and install on last grip block.
6. The aerial outdoor cable termination work platform of claim 1, wherein: the periphery of the main hanging basket is provided with a dustproof film (5).
7. The aerial outdoor cable termination work platform of claim 1, wherein: the auxiliary hanging basket is integrally concave towards the cable terminal.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121457143.7U CN214899827U (en) | 2021-06-29 | 2021-06-29 | High-altitude outdoor cable terminal operation platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121457143.7U CN214899827U (en) | 2021-06-29 | 2021-06-29 | High-altitude outdoor cable terminal operation platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN214899827U true CN214899827U (en) | 2021-11-26 |
Family
ID=78929139
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202121457143.7U Active CN214899827U (en) | 2021-06-29 | 2021-06-29 | High-altitude outdoor cable terminal operation platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN214899827U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117977439A (en) * | 2024-03-29 | 2024-05-03 | 中国水利水电第七工程局有限公司 | Aerial working platform structure |
-
2021
- 2021-06-29 CN CN202121457143.7U patent/CN214899827U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117977439A (en) * | 2024-03-29 | 2024-05-03 | 中国水利水电第七工程局有限公司 | Aerial working platform structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101177959A (en) | Curtain wall unit hanging equipment and construction method thereof | |
CN112431399A (en) | Hanging basket for building outer wall and mounting method thereof | |
CN112681714A (en) | Construction method of steel wire rope lengthened rear support type hanging basket | |
CN214899827U (en) | High-altitude outdoor cable terminal operation platform | |
CN104153586B (en) | A kind of suspension cable hangs the construction method of mounting purlines | |
CN208166361U (en) | A kind of overlength light-weight metal roof boarding lifting attachment device | |
CN203867274U (en) | Installing equipment for double cross arms | |
CN213596814U (en) | Movable three-dimensional crossing type multipurpose suspension bridge construction platform | |
CN204850516U (en) | A horizontal lifeline system for steel construction factory building | |
CN108341331B (en) | Hoisting connection device for ultra-long light metal roof panel and vertical transportation method thereof | |
CN110552495A (en) | assembled building combined tool type outer protective frame system and construction method thereof | |
CN217921154U (en) | Portable hoisting tool | |
CN110040632A (en) | A kind of segmental hoisting construction method of large span section steel beam | |
CN210393401U (en) | Hoisting and positioning device for stand column | |
CN115492404A (en) | Rapid paving method for roof purlines of factory building | |
CN212295594U (en) | Lower hoisting point truss structure of climbing frame | |
CN212174337U (en) | A safe hanging flower basket for construction of industrial factory building steel construction | |
CN204826704U (en) | A horizontal lifeline system for steel construction factory building | |
CN209685129U (en) | A kind of stator of steam turbine generator hanging apparatus | |
CN114109014A (en) | Ultrahigh small-diameter cylindrical curtain wall annular hanging basket and construction method thereof | |
CN114221260A (en) | Insulator maintenance frame of electric power pylon | |
CN203345999U (en) | Special multifunctional lifting frame for busbar bridge | |
CN217418025U (en) | Winch installation device and hoisting system for telegraph pole | |
CN111764623A (en) | Lower hanging construction platform module of high-altitude large-cantilever steel roof truss and construction method | |
CN205151577U (en) | Fix small -size hoisting machine on steel support of groove |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |