CN214780489U - High-rise building outer wall decoration construction device - Google Patents

High-rise building outer wall decoration construction device Download PDF

Info

Publication number
CN214780489U
CN214780489U CN202121334002.6U CN202121334002U CN214780489U CN 214780489 U CN214780489 U CN 214780489U CN 202121334002 U CN202121334002 U CN 202121334002U CN 214780489 U CN214780489 U CN 214780489U
Authority
CN
China
Prior art keywords
construction
lifting
fixed
rise building
sets
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202121334002.6U
Other languages
Chinese (zh)
Inventor
刘敏
余小玉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hefei Hairui Decoration Engineering Co ltd
Original Assignee
Hefei Hairui Decoration Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hefei Hairui Decoration Engineering Co ltd filed Critical Hefei Hairui Decoration Engineering Co ltd
Priority to CN202121334002.6U priority Critical patent/CN214780489U/en
Application granted granted Critical
Publication of CN214780489U publication Critical patent/CN214780489U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to a high-rise building outer wall decoration construction device, which comprises a construction base, wherein the outer side walls at the two ends of the construction base are provided with a movable supporting mechanism, the two sides of the top of the construction base are symmetrically fixed with construction supporting plates, the top of the two groups of construction supporting plates are fixed with an adjusting housing, the level of the inner cavity of the adjusting housing is provided with a rope winding rotating rod, the side wall of the construction supporting plate at the left side is provided with a servo motor, the output end of the servo motor is sleeved with a synchronous driving wheel, the rope winding rotating rod rotates to penetrate through the side wall at the left end of the adjusting housing and is sleeved with a synchronous driven wheel, the synchronous driving wheel is mutually sleeved with the synchronous driving wheel through a connecting rotating belt, the outer side walls at the two ends of the rope winding rotating rod are wound and connected with a first lifting sling and a second lifting sling, the bottoms of the first lifting sling and the second lifting sling are positioned below the adjusting housing and are fixed with a lifting sling, the device can ensure the stability of the lifting sling in the ascending or descending process of the lifting sling, the lifting platform is prevented from shaking left and right in the lifting process.

Description

High-rise building outer wall decoration construction device
Technical Field
The utility model relates to a building construction field, concretely relates to high-rise building outer wall decoration construction equipment.
Background
The building construction refers to production activities in the engineering construction implementation stage, is the construction process of various buildings, and also can be a process of changing various lines on a design drawing into a real object at a specified place. The method comprises foundation engineering construction, main structure construction, roofing engineering construction, decoration engineering construction and the like. The place of construction work is called "construction site" or "construction site".
When the building construction outer wall is decorated, a hoisting device is often used, the existing high-rise building outer wall decoration construction device has the defects that the stability of the lifting hanging platform in the ascending or descending process during transportation is insufficient, and the lifting hanging platform shakes left and right in the ascending and descending process.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to overcome the above-mentioned problem that exists among the prior art, provide a high-rise building outer wall decoration construction equipment.
In order to realize the technical purpose, the technical effect is achieved, the utility model discloses a realize through following technical scheme:
the utility model provides a high-rise building outer wall decoration construction equipment, includes the construction base, the removal supporting mechanism is installed to construction base both ends lateral wall, construction base top bilateral symmetry is fixed with the construction fagging, and is two sets of construction fagging top is fixed with the regulation housing, it is provided with the wiring bull stick, left side to adjust housing inner chamber level servo motor is installed to construction fagging lateral wall, servo motor output has cup jointed synchronous action wheel, the wiring bull stick rotates to run through and adjusts housing left end lateral wall and has cup jointed synchronous from the driving wheel, synchronous action wheel cup joints each other through connecting the commentaries on classics area and synchronous action wheel, wiring bull stick both ends lateral wall winding is connected with first lift lifting rope, second lift lifting rope, first lift lifting rope, second lift lifting rope bottom are located and adjust the housing below and are fixed with the lift platform.
Preferably, the movable supporting mechanism comprises two groups of supporting sleeve seats, the supporting sleeve seats are fixedly connected with the side walls of the two ends of the construction base respectively, the top of each supporting sleeve seat is connected with a lifting screw rod in a penetrating and screwed mode, the bottom of each lifting screw rod is fixed with a roller mounting seat, and the bottom of each roller mounting seat is provided with a movable universal wheel.
Preferably, the top of the two groups of lifting screws is fixed with a rotating handle above the supporting sleeve seat.
Preferably, the side walls of the opposite ends of the two groups of construction supporting plates are provided with fixed sliding grooves, and the outer side walls of the two ends of the lifting platform are fixed with lifting sliding blocks which are connected with the fixed sliding grooves in a sliding manner.
Preferably, the outer wall of the rope winding rotating rod is positioned between the first lifting sling and the second lifting sling and is sleeved with a limit stop.
Preferably, the construction supporting plate on the right side is fixed with a connecting push handle.
Preferably, the right side of the rope winding rotating rod is rotatably connected with the right end side wall of the inner cavity of the adjusting cover shell through a rotating shaft.
Has the advantages that:
1. at first, the construction tool that will hoist is put into on the lift platform, start servo motor drive synchronous action wheel afterwards and rotate, because synchronous action wheel cup joints each other through connecting the commentaries on classics area and synchronous follow driving wheel, rotate the wiring bull stick through synchronous driven wheel, through first lift lifting rope, the second lift lifting rope hoists the lift platform, the first lift lifting rope that sets up, second lift lifting rope and lift platform both ends lateral wall are fixed with fixed spout sliding connection's lift slider, can guarantee to lift the in-process of platform transportation rising or decline and guarantee its stability, prevent to rock about the in-process lift platform that goes up and down.
2. When carrying out construction hoist and mount, rotatory handle that rotates drives the lifting screw and rotates, because lifting screw and support cover seat top looks spiro union, and then drive the removal universal wheel rebound of bottom, until make and remove the universal wheel and break away from ground, support cover seat bottom and ground looks butt, prevent effectively that the in-process to building tool hoist and mount, the construction base is not steady.
Of course, it is not necessary for any product to achieve all of the above advantages simultaneously in practicing the invention.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings used in the description of the embodiments will be briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art that other drawings can be obtained according to these drawings without creative efforts.
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the connection of the lifting platform of the present invention;
FIG. 3 is a schematic view of the structure of the mobile support mechanism of the present invention;
the reference numbers in the drawings are as follows:
1-construction base, 2-moving support mechanism, 201-support sleeve seat, 202-lifting screw, 203-roller mounting seat, 204-moving universal wheel, 3-construction support plate, 4-adjusting housing, 5-rope-winding rotating rod, 6-servo motor, 7-synchronous driving wheel, 8-synchronous driven wheel, 9-connecting rotating belt, 10-first lifting sling, 11-second lifting sling, 12-lifting platform, 13-rotating handle, 14-fixed sliding chute, 15-limit stop, 16-connecting pushing handle, 17-rotating shaft and 18-lifting slide block.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by a person of ordinary skill in the art without creative efforts belong to the protection scope of the present invention.
Example 1:
as shown in figures 1-3, the utility model relates to a high-rise building outer wall decoration construction device, which comprises a construction base 1, the outer side walls of the two ends of the construction base 1 are provided with a movable supporting mechanism 2, the two sides of the top of the construction base 1 are symmetrically fixed with construction supporting plates 3, the tops of two groups of construction supporting plates 3 are fixed with an adjusting housing 4, the inner cavity of the adjusting housing 4 is horizontally provided with a rope winding rotating rod 5, the side wall of the left construction supporting plate 3 is provided with a servo motor 6, the output end of the servo motor 6 is sleeved with a synchronous driving wheel 7, the rope winding rotating rod 5 rotates to penetrate through the left side wall of the adjusting housing 4 and is sleeved with a synchronous driven wheel 8, the synchronous driving wheel 7 is sleeved with the synchronous driving wheel 7 through a connecting rotating belt 9, the outer side walls of the two ends of the rope winding rotating rod 5 are connected with a first lifting rope 10, a second lifting rope 11 and a first lifting rope 10, a lifting platform 12 is fixed at the bottom of the second lifting sling 11 below the adjusting cover 4.
One specific application of this embodiment is: the utility model provides a high-rise building outer wall decoration construction equipment, at first put into lift platform 12 with the construction tool who needs hoist and mount on, start servo motor 6 afterwards and drive synchronous action wheel 7 and rotate, because synchronous action wheel 7 cup joints each other with synchronous follow driving wheel 8 through connecting the commentaries on classics area 9, rotate around rope bull stick 5 through synchronous follow driving wheel 8, through first lift lifting rope 10, second lift lifting rope 11 lifts lift platform 12, the first lift lifting rope 10 that sets up, second lift lifting rope 11 and lift platform 12 both ends lateral wall are fixed with the lifting slide of fixed spout 14 sliding connection, can guarantee to lift platform 12 transportation ascending or the in-process of descending and guarantee its stability, prevent to rock about the in-process lift platform 12 that goes up and down.
Example 2:
wherein, remove supporting mechanism 2 and include two sets of support sleeve seats 201, two sets of support sleeve seats 201 respectively with 1 both ends lateral wall fixed connection of construction base, two sets of support sleeve seats 201 top is run through the spiro union and is had lifting screw 202, two sets of lifting screw 202 bottoms are fixed with gyro wheel mount pad 203, two sets of gyro wheel mount pads 203 bottoms are installed and are removed universal wheel 204, two sets of lifting screw 202 tops are located support sleeve seat 201 top and are fixed with rotation handle 13, two sets of construction fagging 3 looks remote site lateral walls have seted up fixed spout 14, lifting platform 12 both ends lateral wall is fixed with fixed spout 14 sliding connection's elevator slide block 18, 5 outer walls of wiring bull stick are located and have cup jointed limit stop 15 between first lift lifting rope 10 and the second lift rope 11, right side construction fagging 3 is fixed with and connects pushing handle 16, wiring bull stick 5 right side is passed through axis of rotation 17 and is adjusted the 4 inner chamber lateral walls of housing and is rotated and is connected.
The specific application of this embodiment is: when carrying out construction hoist and mount, rotatory handle 13 that rotates drives lifting screw 202 and rotates, because lifting screw 202 and support sleeve seat 201 top looks spiro union, and then drive the removal universal wheel 204 rebound of bottom, until making remove universal wheel 204 and break away from ground, support sleeve seat 201 bottom and ground looks butt effectively prevent at the in-process to building tool hoist and mount, construction base 1 is not steady.
In the description herein, references to the description of the terms "one embodiment," "an example," "a specific example," etc., mean that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the invention. In this specification, the schematic representations of the terms used above do not necessarily refer to the same embodiment or example. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.
The preferred embodiments of the present invention disclosed above are intended only to help illustrate the present invention. The preferred embodiments are not intended to be exhaustive or to limit the invention to the precise embodiments disclosed, and obviously many modifications and variations are possible in light of the above teaching. The embodiments were chosen and described in order to best explain the principles of the invention and its practical applications, to thereby enable others skilled in the art to best understand the invention for and utilize the invention. The present invention is limited only by the claims and their full scope and equivalents.

Claims (7)

1. The utility model provides a construction equipment is decorated to high-rise building outer wall which characterized in that: including construction base (1), removal supporting mechanism (2) are installed to construction base (1) both ends lateral wall, construction base (1) top bilateral symmetry is fixed with construction fagging (3), and is two sets of construction fagging (3) top is fixed with adjusts housing (4), it is provided with wiring bull stick (5) to adjust housing (4) inner chamber level, the left side servo motor (6) are installed to construction fagging (3) lateral wall, servo motor (6) output has cup jointed synchronous action wheel (7), wiring bull stick (5) are rotated and are run through regulation housing (4) left end lateral wall and have cup jointed synchronous follow driving wheel (8), synchronous action wheel (7) are cup jointed each other through connecting change area (9) and synchronous action wheel (7), wiring bull stick (5) both ends lateral wall winding is connected with first lift lifting rope (10), And the bottoms of the first lifting rope (10) and the second lifting rope (11) are positioned below the adjusting housing (4) and are fixedly provided with a lifting platform (12).
2. The high-rise building exterior wall decoration construction device according to claim 1, characterized in that: remove supporting mechanism (2) including two sets of support cover seats (201), it is two sets of support cover seat (201) respectively with construction base (1) both ends lateral wall fixed connection, it is two sets of support cover seat (201) top is run through the spiro union and is had lifting screw (202), and is two sets of lifting screw (202) bottom is fixed with gyro wheel mount pad (203), and is two sets of remove universal wheel (204) are installed to gyro wheel mount pad (203) bottom.
3. The high-rise building exterior wall decoration construction device according to claim 2, characterized in that: and the top parts of the two groups of lifting screw rods (202) are positioned above the supporting sleeve seat (201) and are fixedly provided with rotating handles (13).
4. The high-rise building exterior wall decoration construction device according to claim 1, characterized in that: the side walls of the opposite ends of the two groups of construction supporting plates (3) are provided with fixed sliding grooves (14), and the outer side walls of the two ends of the lifting hanging platform (12) are fixed with lifting sliding blocks (18) which are connected with the fixed sliding grooves (14) in a sliding manner.
5. The high-rise building exterior wall decoration construction device according to claim 1, characterized in that: and the outer wall of the rope winding rotating rod (5) is positioned between the first lifting rope (10) and the second lifting rope (11) and is sleeved with a limit stop (15).
6. The high-rise building exterior wall decoration construction device according to claim 1, characterized in that: and a connecting push handle (16) is fixed on the construction supporting plate (3) on the right side.
7. The high-rise building exterior wall decoration construction device according to claim 1, characterized in that: the right side of the rope winding rotating rod (5) is rotatably connected with the side wall of the right end of the inner cavity of the adjusting cover shell (4) through a rotating shaft (17).
CN202121334002.6U 2021-06-16 2021-06-16 High-rise building outer wall decoration construction device Expired - Fee Related CN214780489U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121334002.6U CN214780489U (en) 2021-06-16 2021-06-16 High-rise building outer wall decoration construction device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121334002.6U CN214780489U (en) 2021-06-16 2021-06-16 High-rise building outer wall decoration construction device

Publications (1)

Publication Number Publication Date
CN214780489U true CN214780489U (en) 2021-11-19

Family

ID=78712819

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121334002.6U Expired - Fee Related CN214780489U (en) 2021-06-16 2021-06-16 High-rise building outer wall decoration construction device

Country Status (1)

Country Link
CN (1) CN214780489U (en)

Similar Documents

Publication Publication Date Title
CN208137422U (en) Integral lifting hoistway formwork support system
CN212174317U (en) Steel sheet overhead hoist for construction
CN108590172A (en) A kind of integral lifting hoistway formwork supporting mechanism
WO2022252633A1 (en) Method for arranging upside-down hoisting power device in attached lifting scaffold
CN212425137U (en) Concrete block hoist device
CN107651564B (en) Crane hoisting posture adjusting device
CN214780489U (en) High-rise building outer wall decoration construction device
CN206624573U (en) A kind of Architectural Equipment for being used to lift weight
CN216340801U (en) Building decoration outer wall transformation platform lifting device
CN206972169U (en) Drilling equipment
CN212105028U (en) Safe type scaffold frame for construction
CN212687416U (en) Heavy object hoisting apparatus for construction
CN218205824U (en) Super large specification stone material masonry device
CN217708636U (en) Building wallboard hoisting device
CN217578145U (en) Construction material lifting machine
JPH06263369A (en) Elevator
CN213141338U (en) Electric construction elevating gear
CN112661026B (en) High building construction of security uses hoisting device
CN211169564U (en) Special crane for stacking autoclaved aerated concrete products
CN212426800U (en) A suspension bridge maintenance workbench
CN211871183U (en) A hoisting device for construction
CN210710521U (en) Elevating gear for construction
CN211813309U (en) Multi-functional lifting device of architectural equipment
CN210239082U (en) Temporary hydropower integrated bracket for construction site
CN221459708U (en) Movable type slab wall hoisting and installing vehicle

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee