CN214743814U CN202120888538.6U CN202120888538U CN214743814U CN 214743814 U CN214743814 U CN 214743814U CN 202120888538 U CN202120888538 U CN 202120888538U CN 214743814 U CN214743814 U CN 214743814U
Authority
CN
China
Prior art keywords
channel
channel steel
steel
hanger
finished
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120888538.6U
Other languages
Chinese (zh)
Inventor
郭志轩
弓志强
姚文龙
史瑞峰
王晓宏
苏建平
张立波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongdi Yingang Construction Group Co Ltd
Original Assignee
Zhongdi Yingang Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongdi Yingang Construction Group Co Ltd filed Critical Zhongdi Yingang Construction Group Co Ltd
Priority to CN202120888538.6U priority Critical patent/CN214743814U/en
Application granted granted Critical
Publication of CN214743814U publication Critical patent/CN214743814U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a finished C-shaped steel support hanger tool, which comprises a channel steel, hangers, a toothed plate, a gear, a rotating shaft and a locking assembly, wherein two hangers are detachably connected at two ends of the channel steel through the locking assembly, the hangers and the channel steel jointly form a C-shaped steel structure, and more than 1 support frame is detachably connected at the upper end of the channel steel; this application avoids directly adopting the inconvenient adjustment of one-piece type structure and the drawback of tearing open and changing among the prior art, increases the flexibility, stops to damage the extravagant phenomenon that just need change whole gallows of one of them part.

Description

Finished C-shaped steel support hanger tool
Technical Field
The utility model relates to a bearing structure technical field, concretely relates to off-the-shelf C shaped steel gallows frock.
Background
At present, in both factories and residential buildings, in consideration of factors such as space limitation and the like, a large number of finished products need to be installed at high positions of the buildings through hangers, most typically, pipelines are installed, and a large number of pipelines are used in the factory production process or the residential life gas utilization process; secondly, if a large amount of pipe laying when subaerial, very easily by the mechanical scratch who removes and damage, if the pipeline buries underground in ground, still need dig out the pipeline when the pipeline appears damaged or reveals, thereby take time hard, thereby also need set up the pipeline in the eminence of building and avoid above problem. Based on this, need in the pipeline erection process through a gallows with pipeline hang and establish the eminence in the building.
However, most of the existing support hangers are of an integrated structure, so that subsequent disassembly, modification and adjustment are not convenient, once one part (mainly comprising channel steel, hangers and 3 support frames) in the support hanger breaks down, the whole support hanger needs to be replaced, and unnecessary waste is caused; meanwhile, the positions of the hanger and the support frame on the channel steel cannot be flexibly adjusted by the conventional support hanger, the position of the support frame on the channel steel cannot be randomly adjusted according to the position change of the pipeline, and the function is single; the support frame of traditional gallows can not adapt to the pipeline of different pipe diameters.
Disclosure of Invention
In view of this, the utility model aims at providing a finished C shaped steel gallows frock through setting up channel-section steel, gallows, support frame into dismantled and assembled triplex, has solved the problem that a prior art gallows installation is fixed, the function is single, can't adapt to different pipe diameter pipelines.
The utility model discloses a finished C-shaped steel support hanger tool, which comprises a channel steel, a hanger, a toothed plate, a gear, a rotating shaft and a locking assembly, wherein two hangers are arranged at two ends of the channel steel through the locking assembly; c shaped steel structure is constituteed jointly to gallows and channel-section steel, and is concrete, in order to be convenient for remove two gallows on the channel-section steel, the back of channel-section steel is equipped with the pinion rack, and the gallows bottom has the gear through the pivot switching, and gear and the mutual meshing of pinion rack, and the upper end of channel-section steel is equipped with a plurality of support frames. This application guarantees that the gallows can be dismantled or the position of quick adjustment gallows on the channel-section steel from the channel-section steel fast, avoid directly adopting the inconvenient adjustment of one-piece type structure and the drawback of tearing open and changing among the prior art, possible need not welding and drilling through this application, alright realize tearing open and change the adjustment, and channel-section steel and gallows after the decomposition, no matter which part goes wrong, only need to appear the part of damage and retrieve and be used for other uses, and the part that does not go wrong then can continue used repeatedly, stop the waste of material.
One embodiment of a locking assembly is: the locking assembly comprises a locking column and a buffer spring, a bearing plate is welded on one side of the bottom end of the hanger, and a through hole for the locking column to pass through is formed in the bearing plate; the locking column arranged above the bearing plate is sleeved with a buffer spring, and two ends of the buffer spring are respectively connected with the top end of the bearing plate and the top end of the locking column; a plurality of limiting circular grooves used for limiting the tail ends of the locking columns are formed in the grooves of the channel steel at equal intervals. Through inserting the spacing circular slot of difference into adjusting the locking post to realize the regulation of crane different positions on the channel-section steel, buffer spring provides power for the locking post spacing circular slot of impressing and locking.
Another embodiment of the locking assembly is: the locking assembly is a screw rod, a threaded hole matched with the screw rod is formed in the bearing plate at the bottom end of the hanging bracket, and the tail end of the screw rod is matched with a plurality of limiting circular grooves in the channel steel. Through rotatory screw rod, the screw rod is unscrewed from the lower extreme of screw hole, offsets with spacing circular slot inside up to the end of screw rod, accomplishes the locking of gallows and channel-section steel.
In both embodiments of the locking assembly described above, the top end of the locking post or screw is fitted with a knob to facilitate lifting of the locking post or rotation of the screw.
When specifically setting up the positional relationship of above-mentioned channel-section steel and gallows, two grooves of channel-section steel are along the buckle slip joint with gallows bottom both sides, avoid the gallows to move the in-process on the channel-section steel and take place the skew, effectively play limiting displacement to the gallows through the cooperation of buckle and channel-section steel, guarantee that the gallows realizes removing at the predetermined track of installation on the channel-section steel.
In order to improve the sliding fluency of the hanger on the channel steel, a sliding groove is arranged on the groove edge of the channel steel, and a roller wheel used for sliding in the sliding groove is arranged on the pinch plate on the near side.
When the support frame is arranged specifically, the support frame comprises a left clamp, a right clamp, a rubber pad, a placing plate, an installation frame, a double-threaded rod and a sliding block, the installation frame is connected to the top end of channel steel through bolts, the placing plate is welded to the top end of the channel steel, the left clamp and the right clamp are arranged on two sides of the top end of the placing plate respectively, the left clamp and the right clamp are opposite in groove parts, and the rubber pads are arranged on the groove parts of the left clamp and the right clamp respectively in order to ensure that pipelines with different pipe diameters can be realized through a frame-shaped structure formed by the left clamp and the right clamp; the bottom ends of the left clamp and the right clamp are respectively provided with a sliding block, and the top end of the placing plate is provided with a limiting groove for limiting the sliding blocks; the two sliding blocks are respectively matched with the threads at the two ends of the double-thread rod through threaded holes formed in the upper ends of the two sliding blocks, and the thread directions of the two ends of the double-thread rod are opposite. The support frame of this application can carry out the centre gripping with the pipeline of different pipe diameters, increases the practicality and the variety of this application.
The beneficial effects of the utility model reside in that following several:
first, this application sets up to dismantled and assembled through gallows, channel-section steel, support frame triplex, can make gallows, support frame install the optional position at the channel-section steel, guarantees that gallows, support frame carry out quick dismantlement and adjustment on the channel-section steel, avoids among the prior art directly adopting the inconvenient adjustment of one-piece type structure and tearing the drawback of changing, increases the flexibility, stops to damage the extravagant phenomenon that one of them part just need change whole gallows.
Second, this application can carry out the centre gripping with the pipeline of different pipe diameters through combining the support frame, increases the practicality and the variety of this application.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention.
Fig. 2 is a schematic structural view of the toothed plate, the gear and the rotating shaft.
FIG. 3 is a schematic view of the structure of the pinch plate, the sliding groove and the roller.
FIG. 4 is a schematic structural diagram of one embodiment of a locking assembly.
FIG. 5 is a schematic structural view of another embodiment of a locking assembly.
Fig. 6 is a schematic structural diagram of the support frame.
In the figure, channel steel 1, gallows 2, pinion rack 3, gear 4, pivot 5, locking Assembly 6, locking post 6.1, buffer spring 6.2, screw rod 6.3, support frame 7, left clamp 7.1, right clamp 7.2, rubber pad 7.3, place board 7.4, mounting bracket 7.5, two screw 7.6, sliding block 7.7, spacing circular slot 8, buckle 9, sliding tray 10, gyro wheel 11.
Detailed Description
In order to make the objects, technical solutions and advantages of the present application more clear, the present application will be further described in detail with reference to the accompanying drawings.
For convenience in understanding the finished C-shaped steel support hanger tool provided in the embodiment of the present application, an application scenario thereof is first described below.
At present, a large number of pipelines are used in the production process of a factory or the domestic gas use process of residents, and firstly, when a high-rise building needs gas, the pipelines are often required to be erected at a high place; secondly, if a large amount of pipe laying when subaerial, very easily by the mechanical scratch who removes and damage, if the pipeline buries underground in ground, still need dig out the pipeline when the pipeline appears damaged or reveals, thereby take time hard, thereby also need set up the pipeline in the eminence of building and avoid above problem. Based on this, the pipeline needs to be hung at the high position of the building through a supporting and hanging frame in the pipeline erecting process, however, most of the existing supporting and hanging frames are of an integrated structure, the supporting and hanging frame cannot be adjusted according to actual use requirements, once the supporting and hanging frame breaks down, the whole supporting and hanging frame needs to be replaced, and unnecessary waste is caused; and this application is through dividing into accessory and the dismantled and assembled two parts of channel-section steel 1 with a gallows, and the adjustment is changed to follow-up tearing open a gallows of being convenient for, and avoids welding and drilling for the time limit for a project.
For clear understanding of the technical solution of the present application, a detailed description will be given below of a finished C-shaped steel support and hanger tool provided in the present application with reference to specific embodiments and accompanying drawings.
The terminology used in the following examples is for the purpose of describing particular embodiments only and is not intended to be limiting of the application. As used in the specification of the present application and the appended claims, the singular forms "a", "an", "the" and "the" are intended to include the plural forms as well, such as "one or more", unless the context clearly indicates otherwise. It should also be understood that in the following embodiments of the present application, "at least one", "one or more" means one, two or more.
Reference throughout this specification to "one embodiment" or "some embodiments," or the like, means that a particular feature, structure, or characteristic described in connection with the embodiment is included in one or more embodiments of the present application. Thus, appearances of the phrases "one embodiment," "in some embodiments," "in other embodiments," or the like, in various places throughout this specification are not necessarily all referring to the same embodiment, but rather "one or more but not all embodiments" unless specifically stated otherwise. The terms "comprising," "including," "having," and variations thereof mean "including, but not limited to," unless expressly specified otherwise.
Fig. 1 to 3 show structural schematic diagrams of a finished C-shaped steel support hanger tool in the present application, which include a channel steel 1, a hanger 2, a toothed plate 3, a gear 4, a rotating shaft 5 and a locking assembly 6, wherein two ends of the channel steel 1 are respectively movably sleeved with the two hangers 2, the hanger 2 and the channel steel 1 jointly form a C-shaped steel structure, specifically, in order to move the two hangers 2 on the channel steel 1, the toothed plate 3 is disposed at the back of the channel steel 1, the gear 4 is rotatably connected to the bottom end of the hanger 2 through the rotating shaft 5, the gear 4 is mutually engaged with the toothed plate 3, a knob is disposed at one end of the rotating shaft 5, when the tool is used, the rotating shaft 5 is driven to rotate by rotating the knob, correspondingly, the rotating shaft 5 drives the gear 4 to rotate, and simultaneously under the engagement effect, the gear 4 drives the hanger 2 to move on the channel steel 1, so that the hanger 2 can move to any position of the channel steel 1, and further, the hanger 2 can realize any adjustment on the channel steel 1, the hanging bracket 2 can be quickly detached from the channel steel 1 or the position of the hanging bracket 2 on the channel steel 1 can be quickly adjusted, the defect that an integral structure is inconvenient to adjust and detach and change in the prior art is overcome, welding and drilling are not needed through the method, the detaching, changing and adjusting can be realized, and the channel steel 1 and the hanging bracket 2 after being disassembled can be recycled for other use only by recycling the damaged part no matter which part has a problem, and the part without the problem can be continuously reused, so that the waste of materials is avoided; a locking assembly 6 capable of positioning the hanger 2 on the channel steel 1 is installed on one side of the hanger 2, when a worker adjusts the hanger 2 to a certain position of the channel steel 1 according to actual requirements, the hanger 2 and the channel steel 1 are effectively locked through the locking assembly 6, the installation positions of the channel steel 1 and the hanger 2 are flexibly adjusted, subsequent dismantling, modifying and adjusting are facilitated, and working efficiency is improved; there are 3 support frames 7 in channel-section steel 1's upper end through bolted connection, support frame 7 is as the name suggests exactly to improve the platform that bears and support for the pipeline, according to the actual design demand on scene, the quantity of support frame 7 is not restricted to 3, can be any quantity more than 1, be convenient for follow channel-section steel 1 with support frame 7 through bolted connection's benefit dismouting, subsequent change and the maintenance of being convenient for, except bolted connection, can also adopt other connected modes of the dismouting of being convenient for.
As shown in fig. 4, when the above-mentioned locking assembly 6 is specifically provided, one embodiment of the locking assembly 6 is: the locking assembly 6 comprises a locking column 6.1 and a buffer spring 6.2, one side of the bottom end of the hanger 2 is welded with a bearing plate, and the bearing plate is provided with a through hole for the locking column 6.1 to pass through; a buffer spring 6.2 is sleeved on the locking column 6.1 arranged above the bearing plate, and two ends of the buffer spring 6.2 are respectively connected with the top end of the bearing plate and the top end of the locking column 6.1; a plurality of limiting circular grooves 8 used for limiting the tail ends of the locking columns 6.1 are formed in the grooves of the channel steel 1 at equal intervals. According to the actual use requirement, a worker firstly lifts the locking column 6.1, meanwhile, the buffer spring 6.2 is compressed in the process of lifting the locking column 6.1 until the tail end of the locking column 6.1 slides out of the limiting circular groove 8, the worker pushes the hanger 2 to move to a selected position on the channel steel 1, the tail end of the locking column 6.1 is aligned with the limiting circular groove 8 corresponding to the lower end, the locking column 6.1 is loosened, the locking column 6.1 presses the locking column 6.1 into the corresponding limiting circular groove 8 under the action of deformation force of the buffer spring 6.2, the locking column 6.1 is adjusted to be inserted into different limiting circular grooves 8, adjustment of the hanger 2 on different positions of the channel steel 1 is facilitated, and the buffer spring 6.2 provides power for the locking column 6.1 to be pressed into the limiting circular groove 8 and locked.
As shown in fig. 5, another embodiment of the locking assembly 6 is: locking subassembly 6 is screw rod 6.3, installs on the loading board of gallows 2 bottoms be equipped with screw rod 6.3 assorted screw hole, the equal adaptation of a plurality of spacing circular slots 8 on terminal and the channel-section steel 1 of screw rod 6.3. Through rotatory screw rod 6.3, screw rod 6.3 is unscrewed from the lower extreme of screw hole, and the locking of gallows 2 and channel-section steel 1 is accomplished to the terminal of screw rod 6.3 and the inside counterbalance of spacing circular slot 8.
Wherein, in both embodiments of the locking assembly 6 described above, the top end of the locking post 6.1 or the screw 6.3 is provided with a knob to facilitate lifting of the locking post 6.1 or rotation of the screw 6.3.
When specifically setting up the position relation of above-mentioned channel-section steel 1 and gallows 2, the two grooves of channel-section steel 1 are along the buckle 9 slip joint with 2 bottom both sides of gallows, avoid gallows 2 to move the in-process on channel-section steel 1 and take place the skew, effectively play limiting displacement to gallows 2 through buckle 9 and 1 cooperation of channel-section steel, guarantee that gallows 2 installs predetermined track on channel-section steel 1 and realize removing.
Wherein, in order to improve the gliding smoothness nature of gallows 2 on channel-section steel 1, be provided with sliding tray 10 on the groove edge of channel-section steel 1, and install gyro wheel 11 on the buckle 9 of close side, realize the motion in sliding tray 10 through gyro wheel 11, make sliding friction change into rolling friction, reduced the gliding resistance of gallows 2 on channel-section steel 1.
As shown in fig. 6, when the support frame 7 is specifically provided, the support frame 7 specifically includes a left clamp 7.1, a right clamp 7.2, a rubber pad 7.3, a placing plate 7.4, an installation frame 7.5, a double-threaded rod 7.6, and a sliding block 7.7, the installation frame 7.5 is connected to the top end of the channel steel 1 through a bolt, the placing plate 7.4 is welded to the top end of the channel steel 1, the left clamp 7.1 and the right clamp 7.2 are respectively arranged on two sides of the top end of the placing plate 7.4, and the left clamp 7.1 and the right clamp 7.2 are opposite in groove portion, in order to ensure that the frame-shaped structure formed by the left clamp 7.1 and the right clamp 7.2 can realize pipelines with different pipe diameters, the rubber pads 7.3 are respectively arranged on the groove portions of the left clamp 7.1 and the right clamp 7.2, the elastic deformation of the rubber pads 7.3 is adapted to pipelines with different sizes, and in addition, not only the rubber pads 7.3, but also other elastic materials similar to the rubber pads 7.3 can be selected; the bottom ends of the left clamp 7.1 and the right clamp 7.2 are both provided with a sliding block 7.7, and the top end of the placing plate 7.4 is provided with a limiting groove for limiting the sliding block 7.7; the two sliding blocks 7.7 are respectively matched with the threads at the two ends of the double-thread rod 7.6 through the threaded holes formed in the upper ends of the two sliding blocks, and the thread directions of the two ends of the double-thread rod 7.6 are opposite. Through rotating double-threaded rod 7.6 to make left clamp 7.1 at threaded rod both ends, right clamp 7.2 realize being close to each other or keeping away from each other, the cooperation has rubber pad 7.3 to carry out the centre gripping with the pipeline of different pipe diameters, increases the practicality and the variety of this application.
The use principle of the device is as follows: when the device is used, firstly, the channel steel 1 and the two hangers 2 are assembled, meanwhile, the positions of the two hangers 2 on the channel steel 1 are adjusted according to actual requirements, and the hangers 2 and the channel steel 1 are locked through the locking assembly 6; then, 3 support frames 7 are installed at the upper end of the channel steel 1 through bolts, and the assembled application is hoisted to the top of a high-rise building; and finally, the pipelines to be distributed are sequentially installed with the supporting frame 7.

Claims (6)

1. The utility model provides a finished C shaped steel gallows frock, includes channel-section steel (1), gallows (2), pinion rack (3), gear (4), pivot (5), locking Assembly (6), its characterized in that: two ends of the channel steel (1) are detachably connected with two hangers (2) through locking components (6), the hangers (2) and the channel steel (1) jointly form a C-shaped steel structure, and the upper end of the channel steel (1) is detachably connected with more than 1 supporting frame (7);
the back of channel-section steel (1) is equipped with pinion rack (3), and gallows (2) bottom has gear (4) through pivot (5) switching, and gear (4) and pinion rack (3) intermeshing.
2. The finished C-shaped steel support and hanger tool of claim 1, which is characterized in that: the locking assembly (6) comprises a locking column (6.1) and a buffer spring (6.2), and a through hole for the locking column (6.1) to pass through is formed in one side of the bottom end of the hanger (2); a buffer spring (6.2) is sleeved on the locking column (6.1) arranged above the through hole; a plurality of limiting circular grooves (8) used for limiting the tail ends of the locking columns (6.1) are arranged in the grooves of the channel steel (1).
3. The finished C-shaped steel support and hanger tool of claim 1, which is characterized in that: the locking assembly (6) is a screw rod (6.3), the bottom end of the hanger (2) is provided with a threaded hole matched with the screw rod (6.3), and the tail end of the screw rod (6.3) is matched with a plurality of limiting circular grooves (8) in the channel steel (1) in an equal mode.
4. The finished C-shaped steel support and hanger tool of claim 1, which is characterized in that: the two groove edges of the channel steel (1) are in sliding clamping connection with the pinch plates (9) on the two sides of the bottom end of the hanger (2).
5. The finished C-shaped steel support and hanger tool of claim 1, which is characterized in that: a sliding groove (10) is arranged on the groove edge of the channel steel (1), and a roller (11) which is used for sliding in the sliding groove (10) is arranged on the pinch plate (9) at the near side.
6. The finished C-shaped steel support and hanger tool of claim 1, which is characterized in that: the supporting frame (7) comprises a left clamp (7.1), a right clamp (7.2), rubber pads (7.3), a placing plate (7.4), an installing frame (7.5), a double-threaded rod (7.6) and a sliding block (7.7), wherein the installing frame (7.5) is connected to the top end of the channel steel (1), the placing plate (7.4) is arranged at the top end of the channel steel (1), the left clamp (7.1) and the right clamp (7.2) are respectively arranged on two sides of the top end of the placing plate (7.4), the groove portions of the left clamp (7.1) and the right clamp (7.2) are opposite, and the rubber pads (7.3) are respectively arranged on the groove portions of the left clamp (7.1) and the right clamp (7.2); the bottom ends of the left clamp (7.1) and the right clamp (7.2) are respectively provided with a sliding block (7.7), and the top end of the placing plate (7.4) is provided with a limiting groove for limiting the sliding block (7.7); the two sliding blocks (7.7) are respectively matched with the threads at the two ends of the double-thread rod (7.6) through the threaded holes formed in the upper ends of the two sliding blocks, and the thread directions of the two ends of the double-thread rod (7.6) are opposite.
CN202120888538.6U 2021-04-28 2021-04-28 Finished C-shaped steel support hanger tool Active CN214743814U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120888538.6U CN214743814U (en) 2021-04-28 2021-04-28 Finished C-shaped steel support hanger tool

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120888538.6U CN214743814U (en) 2021-04-28 2021-04-28 Finished C-shaped steel support hanger tool

Publications (1)

Publication Number Publication Date
CN214743814U true CN214743814U (en) 2021-11-16

Family

ID=78614361

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120888538.6U Active CN214743814U (en) 2021-04-28 2021-04-28 Finished C-shaped steel support hanger tool

Country Status (1)

Country Link
CN (1) CN214743814U (en)

Similar Documents

Publication Publication Date Title
CN101972930B (en) Carrier roller exchanging device of belt conveyor
CN210918166U (en) Scaffold for elevator shaft
CN109138444B (en) Light steel structure
CN111379901A (en) Pipeline butt-joint machine
CN214743814U (en) Finished C-shaped steel support hanger tool
CN209509282U (en) A kind of assembled sheet-pile steel structure system
CN102748535A (en) Fixed support device and operating method thereof
CN216263822U (en) Water supply pipe cutting device
CN114923034A (en) Pipeline installing support for hydraulic engineering convenient to installation and regulation
CN211646867U (en) House building rapid construction wall
CN112713558B (en) Adjustable pipeline fixing device for building construction and pipeline arrangement method for construction
CN220434027U (en) Hotel interior decoration panel connecting piece
CN111022773A (en) Auxiliary mounting device for building drain pipe
CN216616981U (en) Make things convenient for adjustable formwork mounting structure of dismouting
CN206000167U (en) Adjustable Alminum Project slab form support meanss
CN218518576U (en) Device for mounting air pipe bolt
CN218844372U (en) Reinforcement frame for subway pipeline maintenance
CN217972234U (en) Hanging bracket for mounting drain pipe
CN220757865U (en) Fixed fire gun convenient to installation
CN218323599U (en) Heat preservation decorative wall mounting structure
CN214643558U (en) Civil engineering pipeline that is difficult for droing puts frame
CN216551608U (en) Box girder template for municipal administration road bridge construction
CN216471812U (en) Roof portal frame
CN108000139B (en) Large-scale concrete pipe pile assembly device and control method thereof
CN210033490U (en) Anchor rod fixing device for engineering building connection