CN214737427U - Rope clip suspender installation device of cable bridge - Google Patents

Rope clip suspender installation device of cable bridge Download PDF

Info

Publication number
CN214737427U
CN214737427U CN202120536090.1U CN202120536090U CN214737427U CN 214737427 U CN214737427 U CN 214737427U CN 202120536090 U CN202120536090 U CN 202120536090U CN 214737427 U CN214737427 U CN 214737427U
Authority
CN
China
Prior art keywords
cable
main
operation frame
annular groove
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120536090.1U
Other languages
Chinese (zh)
Inventor
薛敏
杨海
朱伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN202120536090.1U priority Critical patent/CN214737427U/en
Application granted granted Critical
Publication of CN214737427U publication Critical patent/CN214737427U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a cable clamp jib installation device of cable bridge, including the main tower, set up main push-towing rope on the main tower and slide the operation frame that sets up on the main push-towing rope, main push-towing rope top roll connection have two gyro wheels, the operation frame is connected in the gyro wheel below, is provided with the locking device who is connected with the main push-towing rope on the operation frame, the main tower on be provided with the hand block of being connected through hand block pull wire with the operation frame. The utility model has the advantages that: this scheme can slide on installing main rope after good to drive the staff and remove the high altitude and carry out the operation, make the installation of cable clamp and jib more convenient, and this scheme is convenient to be prepared fast on the scene, is detachable with main rope and is connected, convenient recovery recycle.

Description

Rope clip suspender installation device of cable bridge
Technical Field
The utility model relates to a cable bridge construction technical field, specific theory is a cable clamp jib installation device of cable bridge.
Background
At present, the conventional method for constructing the cable bridge adopts a catwalk technology to install a main cable, a cable clamp and a suspender, wherein the accurate positioning of the cable clamp is the key point for ensuring the follow-up work, and the installation of the cable clamp and the suspender belongs to high-altitude operation and has high safety risk. For a small-sized cable bridge, the measure cost of a catwalk system is high, and accounts for about 50% -60% of the measure cost of the whole cable bridge, the repeated utilization rate of the catwalk system is low, particularly, a bearing cable, a protection cable and the like of the catwalk system can be utilized only once, the construction cost is invisibly increased, the construction period of the catwalk system is long, and more potential safety hazards exist in catwalk construction.
SUMMERY OF THE UTILITY MODEL
For overcoming the deficiencies of the prior art, an object of the utility model is to provide a cable clamp jib installation device of cable bridge for improve the installation effectiveness of cable clamp and jib, improve construction equipment's cyclic utilization ratio.
The utility model discloses a following technical scheme realizes: the utility model provides a cable clamp jib installation device of cable bridge, includes the main tower, sets up the main push-towing rope on the main tower and slides the operation frame that sets up on the main push-towing rope, main push-towing rope top roll connection have two gyro wheels, the operation frame is connected in the gyro wheel below, be provided with the locking device who is connected with the main push-towing rope on the operation frame, the main tower on be provided with the hand calabash of being connected through hand calabash pull wire with the operation frame.
Further, for better realization the utility model discloses, the face of cylinder of gyro wheel on be provided with the annular groove of indent, annular groove and main push-towing rope cooperation installation.
Further, for better realization the utility model discloses, the annular groove in be provided with a plurality of teeth along the circumferencial direction of annular groove.
Further, for better realization the utility model discloses, the cross section of annular groove be V type or convex.
Further, for better realization the utility model discloses, locking device include two splint and the screw of connection between two splint of setting in the main push-towing rope both sides.
Further, in order to better realize the utility model, the height of the operation frame is 1.5 m.
Further, for better realization the utility model discloses, the operation frame on be provided with the connection structure who is connected with the main tower.
The beneficial effect that this scheme obtained is: this scheme can slide on installing main rope after good to drive the staff and remove the high altitude and carry out the operation, make the installation of cable clamp and jib more convenient, and this scheme is convenient to be prepared fast on the scene, is detachable with main rope and is connected, convenient recovery recycle.
Drawings
FIG. 1 is a schematic structural diagram of the present embodiment;
FIG. 2 is a top view of the operation block;
the device comprises a main tower, a main cable, an operation frame, rollers, a locking device, a hand hoist traction line, a hand hoist and roller supporting plates, wherein the main tower is 1, the main cable is 2, the operation frame is 3, the rollers are 4, the locking device is 5, the hand hoist traction line is 6, and the hand hoist is 7, and the roller supporting plates are 8.
Detailed Description
The present invention will be described in further detail with reference to examples, but the present invention is not limited thereto.
Example 1:
as shown in fig. 1, in this embodiment, a cable clamp boom installation device for a cable bridge includes a main tower, a main cable disposed on the main tower, and an operation frame slidably disposed on the main cable, wherein two rollers are connected to the upper side of the main cable in a rolling manner, the operation frame is connected to the lower side of the rollers, a locking device connected to the main cable is disposed on the operation frame, and a chain block connected to the operation frame through a chain block pull line is disposed on the main tower.
After the main cable is installed, the idler wheel is installed above the main cable, the operation frame is connected with the idler wheel and installed below the main cable, and the hand block on the main tower can be used for pulling the operation frame at the lower part to the position near the top of the main tower through the hand block pulling rope, so that the working personnel in the operation frame can construct the cable clamp and the hanging rod. And after the construction is finished, moving the operation frame to a low position. This structure can utilize the main push-towing rope structure of adorning, need not set up extra catwalk, is favorable to reducing construction cost, reduces the material waste. And this scheme simple structure conveniently prepares at the job site fast, and after finishing using, the dismantlement that can not have the destruction avoids the structure or the device itself of having been under construction impaired to can used repeatedly. The both sides of gyro wheel are provided with the gyro wheel backup pad, are provided with the gyro wheel pivot between the gyro wheel backup pad, and the gyro wheel rotates and sets up in the gyro wheel pivot. The roller supporting plate is detachably connected with the operation frame. Therefore, the operation frame is convenient to disassemble and assemble, and the influence on the constructed main cable when the operation frame is disassembled and assembled is avoided.
The main cable is limited between the two roller supporting plates, so that the safety performance can be improved, and the operation frame is prevented from being completely separated from the main cable.
Example 2:
on the basis of the above embodiment, in this embodiment, the cylindrical surface of the roller is provided with an inward concave annular groove, and the annular groove is installed in cooperation with the main cable. Utilize annular groove can restrict the side direction relative movement of gyro wheel and main push-towing rope, improve the joint strength of gyro wheel and main push-towing rope to be favorable to improving the stability and the security of operation frame.
Example 3:
on the basis of the above embodiment, in this embodiment, a plurality of teeth are arranged in the annular groove along the circumferential direction of the annular groove. Through set up a plurality of teeth in the annular groove, can strengthen the frictional force of gyro wheel and main push-towing rope, avoid appearing the phenomenon of skidding and lead to the main push-towing rope wearing and tearing aggravation.
In this embodiment, the inner surface of the annular groove can be provided with anti-slip patterns to avoid slipping.
Example 4:
on the basis of the above embodiment, in this embodiment, the cross section of the annular groove is V-shaped or circular arc-shaped. The contact area of the roller and the main cable can be increased, so that the dynamic friction force of the roller and the main cable is increased, the connection strength of the roller and the main cable is improved, and the stability of the operation frame is improved.
Example 5:
on the basis of the above embodiment, in this embodiment, the locking device includes two clamping plates disposed on both sides of the main cable and a screw connected between the two clamping plates. When the operation frame needs to be fixed, the clamping plates are clamped on two sides of the main cable, and the two clamping plates are locked by screws, so that the operation frame is fixed. One side of the clamping plate close to the main cable can be provided with anti-skidding patterns, so that the phenomena of skidding and loosening are avoided.
Also can be provided with V type or arc recess and main cable cooperation installation on the splint to this area of contact who increases splint and main cable, thereby improves the joint strength of splint and main cable.
Example 6:
on the basis of the above embodiment, in the present embodiment, the height of the operation frame is 1.5 m. Thereby being convenient for the unrestricted construction of the upper half of staff.
Example 7:
on the basis of the above embodiment, in this embodiment, the operation frame is provided with a connection structure connected with the main tower. Therefore, the operation frame is conveniently connected with the main tower, and the stability of the operation frame is improved. The connecting structure can be connected by adopting a hook or a bracket.
In this embodiment, other undescribed contents are the same as those in the above embodiment, and thus are not described again.
The above is only the preferred embodiment of the present invention, not to the limitation of the present invention in any form, all the technical matters of the present invention all fall into the protection scope of the present invention to any simple modification and equivalent change of the above embodiments.

Claims (7)

1. The utility model provides a cable clip jib installation device of cable bridge which characterized in that: including main tower, setting main cable and the operation frame of sliding setting on the main cable on the main tower, main cable top roll connection have two gyro wheels, the operation frame is connected in the gyro wheel below, be provided with the locking device who is connected with the main cable on the operation frame, the main tower on be provided with and operate the chain block that the frame passes through chain block pull wire and is connected.
2. A cable clamp boom attachment system for a cable bridge as defined in claim 1, wherein: the cylindrical surface of the roller is provided with an inwards concave annular groove, and the annular groove is matched with the main cable for installation.
3. A cable clamp boom attachment system for a cable bridge as defined in claim 2, wherein: a plurality of teeth are arranged in the annular groove along the circumferential direction of the annular groove.
4. A cable clamp boom attachment system for a cable bridge as defined in claim 2, wherein: the cross section of the annular groove is V-shaped or circular arc-shaped.
5. A cable clamp boom attachment system for a cable bridge as defined in claim 1, wherein: the locking device comprises two clamping plates arranged on two sides of the main cable and a screw connected between the two clamping plates.
6. A cable clamp boom attachment system for a cable bridge as defined in claim 1, wherein: the height of the operation frame is 1.5 m.
7. A cable clamp boom attachment system for a cable bridge as defined in claim 1, wherein: and the operation frame is provided with a connecting structure connected with the main tower.
CN202120536090.1U 2021-03-15 2021-03-15 Rope clip suspender installation device of cable bridge Active CN214737427U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120536090.1U CN214737427U (en) 2021-03-15 2021-03-15 Rope clip suspender installation device of cable bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120536090.1U CN214737427U (en) 2021-03-15 2021-03-15 Rope clip suspender installation device of cable bridge

Publications (1)

Publication Number Publication Date
CN214737427U true CN214737427U (en) 2021-11-16

Family

ID=78594682

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120536090.1U Active CN214737427U (en) 2021-03-15 2021-03-15 Rope clip suspender installation device of cable bridge

Country Status (1)

Country Link
CN (1) CN214737427U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114960427A (en) * 2022-04-22 2022-08-30 中国铁建大桥工程局集团有限公司 Suspension bridge superstructure construction draw gear

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114960427A (en) * 2022-04-22 2022-08-30 中国铁建大桥工程局集团有限公司 Suspension bridge superstructure construction draw gear

Similar Documents

Publication Publication Date Title
CN214737427U (en) Rope clip suspender installation device of cable bridge
CN203583910U (en) Fixing bracket system for safety rope for high-altitude operations with steel structure
CN205000255U (en) Fluid pressure type suspension bridge construction girder steel cable carries loop wheel machine
CN207812980U (en) A kind of attachment type raise scaffold hydraulic lifting system
CN210366784U (en) Civil engineering is with dismantled and assembled small-size machinery hoisting accessory
CN112878206A (en) Cable clamp suspender installation device and method for cable bridge
CN208858177U (en) Steel Structure Installation lifeline sets up device
CN204474191U (en) The jib body dumping mechanism of tower crane
CN203347324U (en) Holding pole wall attached matched hoop
CN213477714U (en) Face limit operation safety belt and open linkage
CN112279041B (en) Tower crane manned lifting device
CN210134355U (en) Conversion adjusting device for anchor main cable traction system of super-large and large inclination angle tunnel
CN108298432A (en) A kind of improved cable crane
CN209805246U (en) Lifting system based on insulator string
CN203614664U (en) Locking steel-wire rope pulling buckle
CN218809915U (en) Tool for preventing steel wire rope of grab bucket pulley block from disengaging from groove
CN211368426U (en) Stay cable beam end anchor pressing traction operation platform
CN108302251B (en) Pipeline support that municipal construction used based on lever drive
CN218261737U (en) Winch for geophysical logging
CN207312923U (en) A kind of heavy-duty steel component hanging apparatus
CN221029618U (en) Cast-in-situ box girder prestress tensioning jack adjusting device
CN221500409U (en) Small-size portable gantry crane
CN210302106U (en) Movable safety belt hanging device
CN205532362U (en) Long stroke righting device for pylon can shirk
CN214693010U (en) Tower crane gap bridge device

Legal Events

Date Code Title Description
GR01 Patent grant