CN214679727U - Construction site well control fire control integrated device - Google Patents

Construction site well control fire control integrated device Download PDF

Info

Publication number
CN214679727U
CN214679727U CN202120904830.2U CN202120904830U CN214679727U CN 214679727 U CN214679727 U CN 214679727U CN 202120904830 U CN202120904830 U CN 202120904830U CN 214679727 U CN214679727 U CN 214679727U
Authority
CN
China
Prior art keywords
gear
fire
box
integrated
conveying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120904830.2U
Other languages
Chinese (zh)
Inventor
张�雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Detai Construction Engineering Co ltd
Original Assignee
Shenzhen Detai Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Detai Construction Engineering Co ltd filed Critical Shenzhen Detai Construction Engineering Co ltd
Priority to CN202120904830.2U priority Critical patent/CN214679727U/en
Application granted granted Critical
Publication of CN214679727U publication Critical patent/CN214679727U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model belongs to the technical field of the technique of fire control collection moulding piece and specifically relates to a job site well control fire integrated device, it includes fire control collection moulding piece, conveying mechanism and storing mechanism, conveying mechanism rotates to be connected on the inside wall of fire control collection moulding piece, and conveying mechanism includes driving motor, first transport assembly and second transport assembly, is connected with sleeve pipe, elastic component and the electro-magnet that slides between driving motor and the first transport assembly, and second transport assembly is connected with the hand pole, storing mechanism rotates with conveying mechanism to be connected. This application is when the power supply is normal, and driving motor provides the power source for conveying mechanism, and when the power supply was unusual, the hand pole provides the power source for conveying mechanism, and drive conveying mechanism transportation storing mechanism, this application are deposited the individual layer of fire control cabinet and are improved into the multilayer and deposit, have improved space utilization to by conveying mechanism transportation storing mechanism, be convenient for get and put the fire-fighting equipment, promote the working effect.

Description

Construction site well control fire control integrated device
Technical Field
The application relates to the technical field of fire control integrated devices, in particular to a construction site well control fire control integrated device.
Background
Well control, i.e. kick control or pressure control. The method is required to control the formation pressure by a certain method, basically keeps the pressure balance in the well and ensures the smooth operation and construction. When an accident occurs, the accident position needs to be repaired, and the accident is prevented from further worsening. At present, the well control technology is developed from simple blowout prevention into important guarantee for protecting oil and gas reservoirs, preventing resources from being damaged and preventing environmental pollution.
Current well control fire integrated device generally includes the cabinet body, and the cabinet body is internal through settling a plurality of crosspieces and erecting the shelves, puts the region into the cabinet body and divides into different equipment.
To the correlation technique among the above-mentioned, the inventor finds that in order to increase the cabinet body and hold the quantity of equipment, the height of the cabinet body is usually than higher, and length is than longer, through the volume that enlarges well control fire control integrated cabinet, divides the equipment more and puts the regional quantity that holds that is used for increasing the equipment, but the equipment is taken comparatively inconveniently.
SUMMERY OF THE UTILITY MODEL
In order to improve the well control fire control integrated cabinet space utilization of certain volume, get more conveniently and put the fire-fighting equipment, this application provides a job site well control fire control integrated device.
The application provides a job site well control fire control integrated device adopts following technical scheme:
the utility model provides a job site well control fire control integrated device, includes fire control integrated cabinet, conveying mechanism and storing mechanism, the cabinet gate has been seted up on the fire control integrated cabinet, conveying mechanism rotates to be connected on the inside wall of fire control integrated cabinet, storing mechanism rotates with conveying mechanism and is connected.
Through adopting above-mentioned technical scheme, the integrated cabinet of fire control is used for settling conveying mechanism and storing mechanism, plays main support fixed action, and the exit of equipment of taking is regarded as to the cabinet door opening, does not set up the cabinet door, has practiced thrift the time of cubical switchboard door under emergency. The storage mechanism is used for storing fire-fighting equipment and temporarily storing data information, and the conveying mechanism is used for rotating the storage mechanism so as to conveniently take and place the fire-fighting equipment in the storage mechanism.
Preferably, conveying mechanism includes driving motor, first conveying component and second conveying component all include chain and a plurality of gear, and the gear revolve connects on the integrated cabinet of fire control, chain and gear interlock, first conveying component and second conveying component symmetric distribution on the integrated cabinet inside wall of fire control, the gear that is close to the cabinet gate below first conveying component is first gear, driving motor and first gear fixed connection. The gear that is close to the cabinet mouth below the second conveying assembly is the second gear, be connected with the transmission shaft between second gear and the first gear, second gear fixedly connected with hand rocker.
Through adopting above-mentioned technical scheme, driving motor provides the power source for whole conveying mechanism, and the first gear of driving motor drive rotates to drive first conveyor components's rotation transmission, the second gear among the second conveyor components passes through the transmission shaft with first gear and is connected, makes first gear and the coaxial rotation of second gear, keeps first conveyor components and second conveyor components's synchronous rotation then, realizes the rotation to storing mechanism. When circuit failure results in that driving motor can't normally work, can provide power for conveying mechanism through rotating the hand rocker, guarantee conveying mechanism's normal operating.
Preferably, a sliding pipe sleeve is connected between the driving motor and the gear, a convex transverse bar is arranged on the inner side wall of the sliding pipe sleeve, a first clamping groove is formed in an output shaft of the driving motor, and a second clamping groove is formed in a central shaft of the first gear. Be provided with the electro-magnet on the integrated cabinet inside wall of fire control, the electro-magnet is worn to establish on the center pin of first gear, is provided with elastic component between electro-magnet and the pipe box that slides. The elastic component comprises a thrust bearing and a spring, the thrust bearing is arranged on a central shaft of the first gear in a penetrating mode and is located between the electromagnet and the sliding pipe sleeve, one end of the spring is fixedly connected to the thrust bearing, and the other end of the spring is fixedly connected to the sliding pipe sleeve.
By adopting the technical scheme, after the electromagnet is powered on, the sliding pipe sleeve is attracted, slides from the first clamping groove on the output shaft of the driving motor to the second clamping groove on the central shaft of the first gear, then completes the connection of the output shaft of the driving motor and the central shaft of the first gear, and realizes the coaxial rotation of the output shaft and the central shaft. The gliding in-process of pipe sleeve by first draw-in groove to the second draw-in groove that slides, the spring is compressed gradually, and after the electro-magnet outage, the electro-magnet no longer provides the appeal to the pipe sleeve that slides, and under the effect of spring elasticity, the pipe sleeve that slides is kick-backed to first draw-in groove in, is convenient for drive conveying mechanism through rotating the hand lever and moves.
Preferably, the storage mechanism comprises a first fire-fighting box and a second fire-fighting box, a bearing rod is connected between a chain of the first conveying assembly and a chain of the second conveying assembly, and a position fixing rod is connected between the first fire-fighting box or the second fire-fighting box and the bearing rod; the gear that is close to the cabinet gate above the first conveyor assembly is the third gear, and the interval of bottom surface to the carrier bar under the storing mechanism is less than the interval of third gear topmost to first gear bottommost to the interval of retaining lever to the storing mechanism side in the junction of storing mechanism upper surface is less than the radius of gear. There is a cavity in the inside of first fire hose, the inside of second fire hose is provided with the baffle, and the baffle separates the second fire hose and forms two cavities.
Through adopting above-mentioned technical scheme, the maintenance pole couples together storing mechanism and carrier bar to when the carrier bar moves the corner of gear along with the chain, the relative rotation takes place for maintenance pole and carrier bar, realizes that storing mechanism keeps vertical downwards always. Through setting up the interval that the bottom surface was less than the third gear to the carrier bar under the storing mechanism the interval of top to the first gear bottommost, when realizing that the second fire hose moves near the third gear, first fire hose can normal operating near first gear, and in the same way, when the position of first fire hose and second fire hose exchanged, both still normal operating. The distance from the joint of the upper surface of the storage mechanism to the side edge of the storage mechanism is smaller than the radius of the gear through the arrangement of the retaining rod. When the storage mechanism runs on the chain between the third gear and the first gear, the storage mechanism does not collide with the transmission shaft. The first fire box has larger internal volume, and is convenient for storing large-scale fire-fighting equipment. Inside two cavities of formation of separating by the baffle of second fire hose, be convenient for deposit well control annex and the data material of keeping in to first fire hose is generally deposited in the lower extreme of fire control integrated cabinet, and the second fire hose is deposited in the upper end of fire control integrated cabinet, and the constructor of being convenient for in time takes article.
Preferably, first fire hose and second fire hose all are provided with the chamber door, are provided with observation window, door handle and bolt on the chamber door.
Through adopting above-mentioned technical scheme, the inside equipment of depositing of first fire hose or second fire hose is convenient for look over to the observation window, reduces and blindly opens the probability that discovery instrument is wrong behind first fire hose or the second fire hose to save time. The door handle is convenient for open or close first fire hose and second fire hose, and the bolt is convenient for close the chamber door encapsulation of the chamber door of first fire hose or second fire hose tightly, prevents that the chamber door of first fire hose or the chamber door of second fire hose from transporting the in-process and opening the back unusually, and fire-fighting equipment drops and leads to other problems.
In summary, the present application includes at least one of the following beneficial technical effects:
1. the integrated cabinet of fire control of this application has expanded the degree of depth of the internal portion of cabinet, makes and to place more storing mechanisms on same horizontal plane, has reduced the area that occupies in vertical direction, and other higher machine equipment are settled to the job site of being convenient for, and conveying mechanism makes the circulation transportation of storing mechanism, and the staff of being convenient for gets and puts fire-fighting equipment and well control annex after the classification.
2. The utility model provides a pipe box, elastic component and the electro-magnet that slides that set up between driving motor and the first gear of job site well control fire integrated device, when the circuit normally supplies power, the electro-magnet attracts the pipe box that slides to slide by first draw-in groove to the second draw-in groove slides to driving motor and first gear are connected to the pipe box that slides, realize driving motor drive conveying mechanism and move. When the circuit power supply is unusual, the appeal of electro-magnet weakens, and under the effect of spring in the elastic component, the pipe box that slides to first draw-in groove in, breaks off being connected of driving motor and first gear, rotates the hand lever, realizes conveying mechanism's operation.
3. Be provided with the observation window on this application storing mechanism, the inside fire-fighting equipment or the well control subassembly of depositing of storing mechanism is directly seen to the outside of being convenient for, efficiency when improving the instrument of seeking.
Drawings
Fig. 1 is a schematic structural diagram of a construction site well control fire protection integrated device according to an embodiment of the application.
Fig. 2 is a partially cut-away schematic view of a construction site well control fire protection integrated device according to an embodiment of the application.
Fig. 3 is an enlarged schematic view at a in fig. 2.
FIG. 4 is a schematic view illustrating a state that a sliding pipe sleeve is connected with an output shaft and a central shaft in a well control fire protection integrated device on a construction site according to an embodiment of the application.
FIG. 5 is a schematic view of a state that a sliding pipe sleeve in the integrated device for well control and fire protection in a construction site is located on one side of an output shaft according to an embodiment of the application.
Description of reference numerals: 1. a fire-fighting integrated cabinet; 11. a cabinet door opening; 2. a conveying mechanism; 21. a drive motor; 22. a first conveying assembly; 23. a second transport assembly; 24. a support frame; 25. a protective shell; 3. a storage mechanism; 31. a first fire box; 32. a second fire box; 321. a partition plate; 33. a retention rod; 34. a box door; 341. an observation window; 342. a door handle; 343. a bolt; 35. a carrier bar; 41. a chain; 42. a gear; 421. a first gear; 422. a second gear; 423. a central shaft; 424. an output shaft; 425. a drive shaft; 426. a third gear; 5. sliding the pipe sleeve; 51. a protruding cross bar; 52. a first card slot; 53. a second card slot; 6. an electromagnet; 7. an elastic component; 71. a spring; 72. a thrust bearing; 8. a hand lever.
Detailed Description
The present application is described in further detail below with reference to figures 1-4.
The embodiment of the application discloses job site well control fire control integrated device. Referring to fig. 1 and 2, the integrated device for well control and fire protection in a construction site comprises an integrated cabinet for fire protection 1, a conveying mechanism 2 and a storage mechanism 3. Conveying mechanism 2 sets up on the inside wall of integrated cabinet of fire control 1, and conveying mechanism 2 transmission is connected with storing mechanism 3, and integrated cabinet of fire control 1 is used for settling conveying mechanism 2 and storing mechanism 3, plays main support fixed action. Storing mechanism 3 is used for depositing fire-fighting equipment, well control annex and the data material of keeping in, and conveying mechanism 2 is used for transporting storing mechanism 3.
Referring to fig. 1 and 2, the integrated fire protection cabinet 1 is a cuboid with an opening on one side and a closed other side, wherein the side of the opening is a cabinet door 11. The conveying mechanism 2 includes a drive motor 21, a first conveying member 22, and a second conveying member 23. The first conveying assembly 22 and the second conveying assembly 23 both include a chain 41 and a plurality of gears 42, in this embodiment, the first conveying assembly 22 and the second conveying assembly 23 both include a chain 41 and four gears 42, the gears 42 are rotatably connected to the inner side wall of the integrated fire protection cabinet 1, and the chain 41 is engaged with the four gears 42. The chain 41 and the gear 42 of the first conveying assembly 22 and the chain 41 and the gear 42 of the second conveying assembly 23 are symmetrically distributed on the inner side wall of the fire protection integrated cabinet 1. The gear 42 of the first conveying assembly 22 located at the lower end of the integrated fire protection cabinet 1 and close to the cabinet door 11 is a first gear 421, the gear 42 of the first conveying assembly 22 located at the upper end of the integrated fire protection cabinet 1 and close to the cabinet door 11 is a third gear 426, and the gear 42 of the second conveying assembly 23 located at the lower end of the integrated fire protection cabinet 1 and close to the cabinet door 11 is a second gear 422. Fixedly connected with transmission shaft 425 between first gear 421 and the second gear 422, the one end and the first gear 421 welding of transmission shaft 425, the other end and the second gear 422 welding of transmission shaft 425, transmission shaft 425 is used for realizing the synchronous rotation of first gear 421 and second gear 422, one side fixedly connected with hand rocking bar 8 that second gear 422 deviates from transmission shaft 425.
Referring to fig. 2 and 3, driving motor 21 installs on the lateral wall that integrated cabinet of fire control 1 is close to first conveyor components 22, and the parcel in the driving motor 21 outside has protective housing 25, and fixedly connected with support frame 24 on the integrated cabinet of fire control 1 lateral wall that is close to driving motor 21, support frame 24 and integrated cabinet of fire control 1 be integrated into one piece, and bolted connection has protective housing 25 on the support frame 24 to realize that support frame 24 fixes protective housing 25.
Referring to fig. 4 and 5, the output shaft 424 of the driving motor 21 is provided with two first engaging grooves 52, and the two first engaging grooves 52 are symmetrically distributed on the output shaft 424 along the circumferential direction. The output shaft 424 is sleeved with one end of the sliding pipe sleeve 5, two protruding cross bars 51 which are symmetrically distributed are arranged on the inner side wall of the sliding pipe sleeve 5, and the size and the specification of the protruding cross bars 51 are matched with the first clamping groove 52. The other end of the sliding pipe sleeve 5 is sleeved with a central shaft 423 of the first gear 421, a gap is left between the central shaft 423 and an output shaft 424 of the driving motor 21, second clamping grooves 53 which are symmetrically distributed are formed in the central shaft 423, and the size and the specification of the second clamping grooves 53 are the same as those of the first clamping grooves 52. The central shaft 423 is sleeved with the electromagnet 6 at a position close to the outer side wall of the integrated fire protection cabinet 1, and the electromagnet 6 attracts the sliding pipe sleeve 5 to slide from the first clamping groove 52 to the second clamping groove 53 after being electrified. An elastic component 7 is arranged between the electromagnet 6 and the sliding pipe sleeve 5, the elastic component 7 comprises a spring 71 and a thrust bearing 72, the thrust bearing 72 is sleeved on the central shaft 423 and is positioned between the sliding pipe sleeve 5 and the electromagnet 6, the spring 71 is sleeved on the output shaft 424 and the central shaft 423, one end of the spring 71 is abutted against the sliding pipe sleeve 5, and the other end of the spring 71 is welded with the thrust bearing 72.
Referring back to fig. 1 and 2, the storage facility 3 includes a first fire box 31 and a second fire box 32. The first fire box 31 and the second fire box 32 have the same external dimensions and different internal structures. The entire chamber inside the first fire box 31 is used for storing larger fire-fighting equipment. Inside baffle 321 that is provided with of second fire hose 32, baffle 321 separates second fire hose 32 inside and forms two cavities, is used for depositing well control annex and temporary storage data material respectively. The upper surface welding of first fire hose 31 and second fire hose 32 has two retaining rods 33, and retaining rod 33 rotates and is connected with carrier bar 35, and carrier bar 35 one end and the chain 41 fixed connection of first conveyor components 22, the other end of carrier bar 35 and the chain 41 fixed connection of second conveyor components 23, the chain 41 symmetric distribution that carrier bar 35 both ends are connected. In this embodiment, the distance from the bottom surface of the storage mechanism 3 to the carrying rod 35 is smaller than the distance from the uppermost end of the third gear 426 to the lowermost end of the first gear 421, so that the first fire box 31 can normally operate near the first gear 421 when the second fire box 32 is operated near the third gear 426, and similarly, when the positions of the first fire box and the second fire box are interchanged, the first fire box and the second fire box can still normally operate. And the distance between the connecting position of the upper surface of the storage mechanism 3 and the side edge of the storage mechanism 3 is smaller than the radius of the gear 42, so that the storage mechanism 3 does not collide with the transmission shaft 425 when running on the chain 41 between the third gear 426 and the first gear 421. The door 34 of the first fire box 31 and the door 34 of the second fire box 32 are provided with a viewing window 341, a door handle 342 and a latch 343.
The implementation principle of the construction site well control fire protection integrated device is as follows: when the equipment that needs to be taken is located the first fire hose 31 or the second fire hose 32 that the integrated cabinet 1 of fire control is inside to be close to backplate one side, give electro-magnet 6 circular telegram earlier, electro-magnet 6 produces the appeal, slide pipe box 5 by first draw-in groove 52 to the second draw-in groove 53 slip, spring 71 is compressed simultaneously, the elasticity that slide pipe box 5 received afterwards and magnetic force balance stop sliding, slide pipe box 5 one end this moment cup joints on driving motor 21's output shaft 424, the other end cup joints on the center pin 423 of first gear 421. Then, the power is supplied to the driving motor 21, the output shaft 424 of the driving motor 21 starts to rotate, the central shaft 423 sleeved with the sliding pipe sleeve 5 starts to rotate, the first gear 421 starts to rotate, the second gear 422 connected through the transmission shaft 425 synchronously rotates, and the conveying mechanism 2 starts to operate. When a circuit fault occurs, the magnetic force generated by the electromagnet 6 is gradually reduced, the sliding pipe sleeve 5 slides to the first clamping groove 52 under the action of elastic force, then stops in the first clamping groove 52, the connection with the central shaft 423 is disconnected, the hand lever 8 is rotated at the moment, the second gear 422 is driven to rotate, the first gear 421 connected with the second gear 422 through the transmission shaft 425 synchronously rotates, and the conveying mechanism 2 starts to operate. After the first fire box 31 or the second fire box 32 reaches a predetermined position, the conveying mechanism 2 is closed, the bolt 343 is opened, and the equipment in the first fire box 31 or the second fire box 32 is taken for preemptive maintenance and the like.
The above examples are only used to illustrate the technical solutions of the present application, and do not limit the scope of the present application. It is to be understood that the embodiments described are only some of the embodiments of the present application and not all of them. Although the present application has been described in detail with reference to the above embodiments, those skilled in the art may still make various combinations, additions, deletions or other modifications of the features of the embodiments of the present application without conflict, and thus, different technical solutions that do not substantially depart from the spirit of the present application may be obtained.

Claims (9)

1. The utility model provides a job site well control fire control integrated device which characterized in that: including integrated cabinet of fire control (1), conveying mechanism (2) and storing mechanism (3), cabinet door opening (11) have been seted up on integrated cabinet of fire control (1), conveying mechanism (2) rotate to be connected on the inside wall of integrated cabinet of fire control (1), storing mechanism (3) rotate with conveying mechanism (2) and are connected.
2. The integrated well control fire protection device for the construction site according to claim 1, wherein: conveying mechanism (2) are including driving motor (21), first conveying subassembly (22) and second conveying subassembly (23) all include chain (41) and a plurality of gear (42), and gear (42) rotate to be connected on integrated cabinet of fire control (1), and chain (41) and gear (42) meshing, first conveying subassembly (22) and second conveying subassembly (23) symmetric distribution on integrated cabinet of fire control (1) inside wall, gear (42) that first conveying subassembly (22) below is close to cabinet gate (11) are first gear (421), driving motor (21) and first gear (421) fixed connection.
3. The integrated well control fire protection device for the construction site according to claim 2, wherein: gear (42) that second conveying component (23) below is close to cabinet gate (11) is second gear (422), be connected with between second gear (422) and first gear (421) transmission shaft (425), one side fixedly connected with hand rocking bar (8) that second gear (422) deviate from transmission shaft (425).
4. The integrated well control fire protection device for the construction site according to claim 3, wherein: be connected with between driving motor (21) and gear (42) and slide pipe box (5), be provided with protrusion horizontal bar (51) on slide pipe box (5) inside wall, first draw-in groove (52) have been seted up in output shaft (424) of driving motor (21), and second draw-in groove (53) have been seted up in center pin (423) of first gear (421).
5. The integrated well control fire protection device for the construction site according to claim 4, wherein: be provided with electro-magnet (6) on the integrated cabinet of fire control (1) inside wall, on central shaft (423) of first gear (421) are worn to establish by electro-magnet (6), be provided with elastic component (7) between electro-magnet (6) and sliding pipe box (5).
6. The integrated well control fire protection device for the construction site according to claim 5, wherein: the elastic component (7) comprises a thrust bearing (72) and a spring (71), the thrust bearing (72) is arranged on a central shaft (423) of the first gear (421) in a penetrating mode and is located between the electromagnet (6) and the sliding pipe sleeve (5), one end of the spring (71) is fixedly connected to the thrust bearing (72), and the other end of the spring (71) is fixedly connected to the sliding pipe sleeve (5).
7. The integrated well control fire protection device for the construction site according to claim 2, wherein: the storage mechanism (3) comprises a first fire-fighting box (31) and a second fire-fighting box (32), a bearing rod (35) is connected between a chain (41) of the first conveying assembly (22) and a chain (41) of the second conveying assembly (23), and a retaining rod (33) is connected between the first fire-fighting box (31) or the second fire-fighting box (32) and the bearing rod (35); the gear (42) above the first conveying assembly (22) close to the cabinet door opening (11) is a third gear (426), the distance from the lower bottom surface of the storage mechanism (3) to the bearing rod (35) is smaller than the distance from the uppermost end of the third gear (426) to the lowermost end of the first gear (421), and the distance from the connecting position of the upper surface of the storage mechanism (3) of the retaining rod (33) to the side edge of the storage mechanism (3) is smaller than the radius of the gear (42).
8. The integrated well-control fire protection device for the construction site as claimed in claim 7, wherein: a chamber is arranged in the first fire box (31), a partition plate (321) is arranged in the second fire box (32), and the second fire box (32) is separated by the partition plate (321) to form two chambers.
9. The integrated well control fire protection device for the construction site according to claim 8, wherein: the first fire box (31) and the second fire box (32) are both provided with a box door (34), and the box door (34) is provided with an observation window (341), a door handle (342) and a bolt (343).
CN202120904830.2U 2021-04-28 2021-04-28 Construction site well control fire control integrated device Active CN214679727U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120904830.2U CN214679727U (en) 2021-04-28 2021-04-28 Construction site well control fire control integrated device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120904830.2U CN214679727U (en) 2021-04-28 2021-04-28 Construction site well control fire control integrated device

Publications (1)

Publication Number Publication Date
CN214679727U true CN214679727U (en) 2021-11-12

Family

ID=78534748

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120904830.2U Active CN214679727U (en) 2021-04-28 2021-04-28 Construction site well control fire control integrated device

Country Status (1)

Country Link
CN (1) CN214679727U (en)

Similar Documents

Publication Publication Date Title
CN107224177B (en) A kind of letter box arrangement
CN101927901A (en) Transaction system work station, working method and method for placing goods in or taking goods out of work station
CN214679727U (en) Construction site well control fire control integrated device
CN109809093A (en) A kind of warehouse logistics information management system
CN205327987U (en) Express delivery cabinet with chain transmission structure
CN104029958A (en) Solar electric high-grade dustbin
CN214752355U (en) Training platform for internet enterprise training education
CN111559643B (en) Automatic gasket sequencing machine
CN214586055U (en) Portal frame security check machine capable of being assembled quickly
CN214086062U (en) Dumping device and cleaning robot
CN208979236U (en) A kind of case unpacker
CN210818056U (en) Spot welding equipment suitable for lithium battery welding
CN110295345A (en) A kind of vacuum coating equipment
CN202379337U (en) Solar electric high-grade garbage box
CN110979909A (en) Interim strorage device of article for commodity circulation
CN216944310U (en) Carton with lock lid function
CN111977123A (en) Embedded door-opening type logistics turnover box and using method thereof
CN216644657U (en) Horizontal refrigerator-freezer with processing platform
CN216231779U (en) Heavy truck that magnetic force hoisted trades battery box
CN215456875U (en) Tool to lock presentation device
CN110921233B (en) Clothing production water line based on thing networking
CN220319313U (en) Cabinet lock device of door cabinet
CN210942852U (en) Trademark drop storage device capable of being positioned in two dimensions
CN220032579U (en) Triangle-shaped signboard packing box
CN215904804U (en) Automatic screw taking and placing device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant