CN214220083U - Prefabricated shear wall of assembled - Google Patents

Prefabricated shear wall of assembled Download PDF

Info

Publication number
CN214220083U
CN214220083U CN202023028558.0U CN202023028558U CN214220083U CN 214220083 U CN214220083 U CN 214220083U CN 202023028558 U CN202023028558 U CN 202023028558U CN 214220083 U CN214220083 U CN 214220083U
Authority
CN
China
Prior art keywords
wall body
wall
assembled
prefabricated shear
horizontal pole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202023028558.0U
Other languages
Chinese (zh)
Inventor
陈阳
李文军
陈晓
张闯
孙利
孔令楠
孙传勇
杨宪伟
付强
程海波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liaoning Dingyu Environmental Protection Building Materials Co ltd
Original Assignee
Liaoning Dingyu Environmental Protection Building Materials Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Liaoning Dingyu Environmental Protection Building Materials Co ltd filed Critical Liaoning Dingyu Environmental Protection Building Materials Co ltd
Priority to CN202023028558.0U priority Critical patent/CN214220083U/en
Application granted granted Critical
Publication of CN214220083U publication Critical patent/CN214220083U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses an assembled precast shear wall body, including first wall body, the side of first wall body is equipped with the second wall body, the inside of first wall body and second wall body all is embedded to have the montant, the outer wall clearance fit of montant has the standpipe. The utility model relates to a building technical field, this prefabricated shear force wall body of assembled, through first wall body, the second wall body, the montant, the standpipe, cooperation between horizontal pole and the down tube, the bulk strength of this prefabricated shear force wall body of assembled has been improved, and after filling the concrete, first wall body and second wall body are very stable, be difficult to the atress inflation, guarantee the whole thickness of this prefabricated shear force wall body of assembled, be convenient for assemble and installation, through the acoustic celotex board, the threaded rod, cooperation between third wall body and the nut, not only further improved the intensity of this prefabricated shear force wall body of assembled, and make the syllable-dividing effect of this prefabricated shear force wall body of assembled improve greatly.

Description

Prefabricated shear wall of assembled
Technical Field
The utility model relates to a building technical field specifically is an assembled precast shear wall body.
Background
The shear wall is also called as wind-resistant wall, earthquake-resistant wall or structural wall, a wall body mainly bearing horizontal load and vertical load caused by wind load or earthquake action in a house or a structure and preventing structural shear damage, and is also called as earthquake-resistant wall, generally made of reinforced concrete, and is divided into a plane shear wall and a barrel shear wall, wherein the plane shear wall is used in a reinforced concrete frame structure, a lifting plate structure and a flat slab system, in order to increase the rigidity, the strength and the collapse resistance of the structure, the reinforced concrete shear wall can be cast or prefabricated at certain positions, the cast-in-place shear wall, peripheral beams and columns are simultaneously cast, the integrity is good, the barrel shear wall is used in a high-rise structure and a suspension structure and is surrounded by partition walls of an elevator room, a staircase room, equipment and an auxiliary room, the barrel walls are cast-in-place reinforced concrete walls, the rigidity and the strength of the barrel shear wall are higher than those of the plane shear wall, with the rise of fabricated buildings, fabricated prefabricated shear walls have also been used in a large number of applications.
But assembled precast shear wall body among the prior art, at the in-process that uses, the bulk strength needs rely on the use of concrete and reinforcing bar to guarantee to after filling the concrete, easy atress inflation leads to thickness to improve, influences the use, and gives sound insulation effect relatively poor, during the fitment, need additionally install the acoustic celotex board, the increase operation degree of difficulty, so prior art can't satisfy people's use needs.
SUMMERY OF THE UTILITY MODEL
The utility model provides a not enough to prior art, the utility model provides an assembled precast shear wall body has solved the assembled precast shear wall body among the prior art, and at the in-process that uses, the bulk strength needs rely on the use of concrete and reinforcing bar to guarantee, and after filling the concrete, easy atress inflation leads to thickness to improve, influences the problem of using.
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: the utility model provides an assembled precast shear wall, includes first wall body, the side of first wall body is equipped with the second wall body, the inside of first wall body and second wall body all is embedded to have the montant, the outer wall clearance fit of montant has the standpipe, the equidistance is equipped with the horizontal pole between first wall body and the second wall body, the both ends of horizontal pole link to each other with the standpipe of the left and right sides is fixed respectively, the through-hole has all been seted up to the top left and right sides and the bottom left and right sides of horizontal pole, two adjacent be equipped with the down tube between the horizontal pole, the end of down tube passes through the through-hole and links to each other with the horizontal pole is fixed, two the down tube is the cross.
Preferably, the first wall body and the second wall body have the same specification.
Preferably, one side that first wall body was kept away from to the second wall body is equipped with the third wall body, the clamp has the acoustic celotex board between third wall body and the second wall body, the inside embedded baffle that has in one side that the second wall body is close to the acoustic celotex board, one side fixedly connected with threaded rod that the baffle is close to the third wall body, the outer wall left side threaded connection of threaded rod has the nut.
Preferably, the left end of the threaded rod is located inside the third wall.
Preferably, the outer wall of the sound insulation board is flush with the outer wall of the third wall.
Advantageous effects
The utility model provides an assembled precast shear wall body. The method has the following beneficial effects: according to the assembly type prefabricated shear wall, the first wall body, the second wall body, the vertical rods, the vertical pipes, the transverse rods and the inclined rods are matched, so that the overall strength of the assembly type prefabricated shear wall is improved, the first wall body and the second wall body are quite stable after concrete is filled, the first wall body and the second wall body are not prone to stress expansion, the overall thickness of the assembly type prefabricated shear wall is guaranteed, and assembly and installation are facilitated;
through the cooperation between acoustic celotex board, threaded rod, third wall body and the nut, not only further improved this prefabricated shear force wall body of assembled's intensity to make this prefabricated shear force wall body of assembled's syllable-dividing effect improve greatly, under the general condition, do not need additionally to install the acoustic celotex board, reduce operation personnel's the installation degree of difficulty.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the connection structure of the vertical tube, the cross bar and the diagonal bar in FIG. 1;
fig. 3 is a schematic view of the connection relationship between the second wall, the threaded rod and the nut in fig. 2.
In the figure: 1. the sound insulation wall comprises a first wall body, 2, a second wall body, 3, a vertical rod, 4, a vertical pipe, 5, a cross rod, 6, a through hole, 7, an inclined rod, 8, a sound insulation board, 9, a third wall body, 10, a nut, 11, a baffle, 12 and a threaded rod.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
The following working principles, detailed connecting means thereof, and the following main descriptions of the working principles and processes are well known in the art, and will be referred to by those skilled in the art for the specific connection and operation sequence of the components in this application.
The utility model provides a technical scheme:
as shown in fig. 1-3, the prefabricated shear wall in this case includes a first wall 1, a second wall 2 is disposed on a side surface of the first wall 1, the first wall 1 and the second wall 2 are both made of reinforced concrete, and for the prior art, details of the first wall 1 and the second wall 2 are not repeated herein, a vertical rod 3 is embedded inside each of the first wall 1 and the second wall 2, the vertical rod 3, a vertical pipe 4 and a cross rod 5 are matched to fix and connect the first wall 1 and the second wall 2, when the prefabricated shear wall is installed, concrete needs to be poured between the first wall 1 and the second wall 2, the vertical pipe 4 is in clearance fit with an outer wall of the vertical rod 3, the cross rod 5 is equidistantly disposed between the first wall 1 and the second wall 2, two ends of the cross rod 5 are respectively fixedly connected with the vertical pipes 4 on the left and right sides, through holes 6 are disposed on the left sides of the top and the right sides of the bottom and the left sides of the cross rod 5, an inclined rod 7 is arranged between two adjacent cross rods 5, the inclined rod 7 plays a role in reinforcing the two adjacent cross rods 5, the tail ends of the inclined rods 7 are fixedly connected with the cross rods 5 through holes 6, the two inclined rods 7 are crossed, and the specifications of the first wall body 1 and the second wall body 2 are the same;
in the specific implementation process, worth pointing out very much, first wall body 1 and second wall body 2 are reinforced concrete structure, for prior art, do not do here and describe any more, through montant 3, standpipe 4 and the cooperation of horizontal pole 5, play fixed and the effect of connecting to first wall body 1 and second wall body 2, when installing this prefabricated shear force wall body of assembled, need pour into the concrete between first wall body 1 and second wall body 2, the down tube 7 plays reinforced effect to two adjacent horizontal poles 5.
A third wall body 9 is arranged on one side of the second wall body 2 far away from the first wall body 1, a sound insulation board 8 is clamped between the third wall body 9 and the second wall body 2, the sound insulation board 8 is made of sound insulation cotton, the third wall body 9, a threaded rod 12 and a nut 10 are matched to realize fixation with the second wall body 2, a baffle plate 11 is embedded in one side of the second wall body 2 close to the sound insulation board 8, a threaded rod 12 is fixedly connected to one side of the baffle plate 11 close to the third wall body 9, the nut 10 is in threaded connection with the left side of the outer wall of the threaded rod 12, the left end of the threaded rod 12 is positioned in the third wall body 9, the outer wall of the sound insulation board 8 is level with the outer wall of the third wall body 9,
in the specific implementation process, it is worth pointing out that the sound insulation board 8 is made of sound insulation cotton, and is fixed with the second wall 2 through the cooperation of the third wall 9, the threaded rod 12 and the nut 10, so that the sound insulation effect of the prefabricated shear wall is improved.
Can know through the aforesaid, when installing this prefabricated shear force wall body of assembled, need pour into the concrete between first wall body 1 and second wall body 2, down tube 7 plays reinforced (rfd) effect to two adjacent horizontal poles 5, and then forms complete wall body, according to the user demand, at the side-mounting acoustic celotex board 8 and the third wall body 9 of second wall body 2, through the cooperation of nut 10 and threaded rod 12, fix acoustic celotex board 8 and third wall body 9, improve this prefabricated shear force wall body of assembled's syllable-dividing effect.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation. The use of the phrase "comprising one of the elements does not exclude the presence of other like elements in the process, method, article, or apparatus that comprises the element.
In the present invention, unless otherwise expressly stated or limited, the terms "mounted," "disposed," "connected," "fixed," "screwed" and the like are to be construed broadly, e.g., as meaning fixedly connected, detachably connected, or integrally formed; can be mechanically or electrically connected; they may be directly connected or indirectly connected through an intermediate medium, and may be connected through the inside of two elements or in an interaction relationship between two elements, unless otherwise specifically defined, and the specific meaning of the above terms in the present invention will be understood by those skilled in the art according to specific situations.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. The utility model provides an assembled precast shear wall body, includes first wall body (1), its characterized in that: the side of first wall body (1) is equipped with second wall body (2), the inside of first wall body (1) and second wall body (2) all is embedded to have montant (3), the outer wall clearance fit of montant (3) has standpipe (4), the equidistance is equipped with horizontal pole (5) between first wall body (1) and the second wall body (2), the both ends of horizontal pole (5) are fixed continuous with standpipe (4) of the left and right sides respectively, through-hole (6) have all been seted up to the top left and right sides and the bottom left and right sides of horizontal pole (5), and two are adjacent be equipped with down tube (7) between horizontal pole (5), the end of down tube (7) is fixed continuous with horizontal pole (5) through-hole (6), two down tube (7) are the cross.
2. The fabricated precast shear wall of claim 1, wherein: the first wall body (1) and the second wall body (2) are identical in specification.
3. The fabricated precast shear wall of claim 1, wherein: one side that first wall body (1) was kept away from in second wall body (2) is equipped with third wall body (9), clamping has acoustic celotex board (8) between third wall body (9) and second wall body (2), one side that second wall body (2) are close to acoustic celotex board (8) is inside to be embedded to have baffle (11), one side fixedly connected with threaded rod (12) that baffle (11) are close to third wall body (9), the outer wall left side threaded connection of threaded rod (12) has nut (10).
4. The fabricated precast shear wall of claim 3, wherein: the left end of the threaded rod (12) is positioned inside the third wall body (9).
5. The fabricated precast shear wall of claim 3, wherein: the outer wall of the sound insulation board (8) is level with the outer wall of the third wall body (9).
CN202023028558.0U 2020-12-15 2020-12-15 Prefabricated shear wall of assembled Active CN214220083U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202023028558.0U CN214220083U (en) 2020-12-15 2020-12-15 Prefabricated shear wall of assembled

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202023028558.0U CN214220083U (en) 2020-12-15 2020-12-15 Prefabricated shear wall of assembled

Publications (1)

Publication Number Publication Date
CN214220083U true CN214220083U (en) 2021-09-17

Family

ID=77702824

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202023028558.0U Active CN214220083U (en) 2020-12-15 2020-12-15 Prefabricated shear wall of assembled

Country Status (1)

Country Link
CN (1) CN214220083U (en)

Similar Documents

Publication Publication Date Title
CN109083308B (en) Anti-seismic prefabricated assembly type wall and construction method thereof
CN207017483U (en) The full precast shear wall structural system of regenerative steel skeleton
CN102943572A (en) Single-floor masonry residential building steel-frame canopy guard structure and construction method thereof
CN214220083U (en) Prefabricated shear wall of assembled
CN206015882U (en) The steel structure of housing system that a kind of lateral resisting and antigravity separate
CN213296679U (en) Shear wall for enhancing shear resistance
CN212715350U (en) Section steel concrete beam column structure
CN113216388A (en) Support-free assembled concrete beam column connecting structure and assembling method
CN106088398A (en) A kind of combined wall board
CN206607706U (en) A kind of drawing shore for shear wall construction
CN218292482U (en) Double-deck steel sheet concrete shear wall structure
CN215907392U (en) Combined post-cast strip independent support system
CN211007241U (en) Steel construction building assembled floor fixed knot constructs
CN216588003U (en) Novel assembled enclosure module
CN213329660U (en) Anti-seismic prefabricated slab for building
CN213174217U (en) Precast concrete frame and steel shotcrete assembly connection structure
CN216920999U (en) Building spandrel girder structure is built in room
CN111705954B (en) High-strength underground shear wall and construction method thereof
CN215483820U (en) Assembled shear force wall body for building
CN210177740U (en) Super-thick shear wall with anti-seismic effect
CN211690999U (en) Profiled steel sheet concrete floor
CN211200741U (en) Close-packed steel tube concrete column-steel plate beam wall type frame
CN211229117U (en) Assembled composite floor and node structure
CN218466788U (en) Light batten internal partition wall structure for prefabricated building
CN210946843U (en) Arch ring support piece for grouted arch slope protection

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant