CN213773327U - Prestressed high-strength concrete pipe pile - Google Patents

Prestressed high-strength concrete pipe pile Download PDF

Info

Publication number
CN213773327U
CN213773327U CN202022369190.8U CN202022369190U CN213773327U CN 213773327 U CN213773327 U CN 213773327U CN 202022369190 U CN202022369190 U CN 202022369190U CN 213773327 U CN213773327 U CN 213773327U
Authority
CN
China
Prior art keywords
wall
pile
fixedly connected
tubular pile
extrusion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202022369190.8U
Other languages
Chinese (zh)
Inventor
胡宇琪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Yili Pipe Technology Co ltd
Original Assignee
Zhejiang Yili Pipe Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Yili Pipe Technology Co ltd filed Critical Zhejiang Yili Pipe Technology Co ltd
Priority to CN202022369190.8U priority Critical patent/CN213773327U/en
Application granted granted Critical
Publication of CN213773327U publication Critical patent/CN213773327U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a prestressing force high-strength concrete tubular pile, including last tubular pile and lower tubular pile, the equal fixedly connected with longitudinal reinforcement of inner wall of going up tubular pile and lower tubular pile, the outer wall of longitudinal reinforcement and the equal fixedly connected with annular anchor of mid portion that is located tubular pile and lower tubular pile, the both ends difference fixedly connected with of going up tubular pile and lower tubular pile are connected the pile head, the outer wall fixedly connected with installation piece of connecting the pile head, the first extrusion piece of outer wall fixedly connected with of installation piece. Move the second extrusion piece to the direction motion of being close to the installation piece through making extrusion ball upward movement, and then drive the fly leaf and move thereupon, make fixture block and draw-in groove joint to accomplish the fixed to the installation piece, this device has made things convenient for the connection of top tube pile and low tubular pile fastening together through the joint setting of devices such as first extrusion ball, second extrusion ball, fixture block, is favorable to the high-speed joint, and make more firm, the bearing capacity is high, bending strength is high to connect moreover, improves work efficiency.

Description

Prestressed high-strength concrete pipe pile
Technical Field
The utility model belongs to the technical field of the concrete pipe stake, concretely relates to prestressing force high-strength concrete pipe stake.
Background
The prestressed pipe pile is a common pile foundation form in China, and has the advantages of high single-pile bearing capacity, reliable quality, low unit bearing capacity manufacturing cost and convenience in detection, and can meet the requirements of high quality, environmental protection, industrial modernization and the like, so that the prestressed pipe pile is widely applied to civil engineering in recent years. The commonly used prestressed pipe pile in China is formed by a steel reinforcement cage formed by combining main steel bars and stirrups and pouring concrete outside the steel reinforcement cage. In order to facilitate the transportation and hoisting of the prestressed concrete pipe piles, the length of the prestressed concrete pipe piles is usually not too long, and if the pile foundation of the building foundation is deeper, several sections of prestressed concrete pipe piles are required to be connected.
Currently, the joint type of most prestressed pipe piles is an end plate electric welding connection method. However, the welding time is long, the welding quality mainly depends on the welding technology of workers, the welding joint part is often a weak part of the pile body of the prestressed pipe pile, the pile is continuously sunk after welding is finished, the pipe pile is difficult to inspect after being driven into the soil layer, and the joint is easy to damage due to quenching or brittle fracture when meeting water and slight bias when entering underground due to variable geological and stratum conditions, and particularly the joint is easy to damage under the action of horizontal load, so the improvement or reinforcement of the connection mode between the prestressed pipe pile units has important engineering significance for improving the horizontal bearing capacity of the pipe pile.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a prestressing force high strength concrete tubular pile to propose a prestressing force high strength concrete tubular pile that has now in solving above-mentioned background art in the use, because the joint pattern of present most prestressing force tubular pile adopts end board electric welding connection method, thereby leads to the problem that joint department takes place the destruction easily.
In order to achieve the above object, the utility model provides a following technical scheme: a prestressed high-strength concrete pipe pile comprises an upper pipe pile and a lower pipe pile, wherein longitudinal steel bars are fixedly connected to the inner walls of the upper pipe pile and the lower pipe pile, the outer walls of the longitudinal steel bars are fixedly connected with annular anchors in the middle parts of the upper pipe pile and the lower pipe pile respectively, connecting pile heads are fixedly connected to the two ends of the upper pipe pile and the lower pipe pile respectively, mounting blocks are fixedly connected to the outer walls of the connecting pile heads, first extrusion blocks are fixedly connected to the outer walls of the mounting blocks, clamping grooves are formed in the inner walls of the mounting blocks, supporting rods are fixedly connected to the inner walls of the connecting pile heads, movable rods are movably connected to the top ends of the supporting rods, fixed plates are fixedly connected to the inner walls of one sides of the connecting pile heads and located above the movable rods, second extrusion blocks are slidably connected to the inner walls of the bottom of the fixed plates, movable plates are fixedly connected to one sides of the second extrusion blocks far away from the inner walls of the connecting pile heads, and a clamping block is fixedly connected to the outer wall of one side of the movable plate, which is far away from the second extrusion block.
Preferably, the outer wall of the longitudinal steel bar is sleeved with the spiral steel bar.
Preferably, the movable rod is close to the outer wall of the top of one end of the inner wall of the connecting pile head and is fixedly connected with an extrusion ball, and the extrusion ball is arranged between the outer wall of the second extrusion block and the inner wall of the connecting pile head.
Preferably, the inner wall of the fixing plate is provided with a sliding chute, and the inner wall of the fixing plate is in sliding connection with the outer wall of the second extrusion block through the sliding chute.
Preferably, a spring is fixedly connected between the outer wall of one side of the second extrusion block and one side of the inner wall of the connecting pile head.
Preferably, the outer wall of the clamping block is clamped with the inner wall of the clamping groove.
Compared with the prior art, the beneficial effects of the utility model are that:
1. through the direction motion that will go up the tubular pile to being close to the tubular pile down, the inside motion of the tubular pile is down gone up to the installation piece of top tubular pile outer wall, the inside motion of the tubular pile is made progress to the installation piece of lower tubular pile outer wall, the first extrusion piece extrusion movable rod of installation piece outer wall, by the movable rod downstream of extruded one end, the other end upward movement, make extrusion ball upward movement with the second extrusion piece to the direction motion of being close to the installation piece, and then drive the fly leaf and move thereupon, make fixture block and draw-in groove joint, thereby accomplish the fixed to the installation piece, this device has made things convenient for the connection of top tubular pile and tubular pile fastening together through the joint setting of devices such as first extrusion ball, second extrusion ball, the fixture block, be favorable to the high-speed joint, and make the connection more firm, bear the dynamic height, bending strength is high, the cost is lower, and the work efficiency is improved, and the practicality is achieved.
2. This device sets up the spiral reinforcement through the outside at vertical reinforcing bar, and the joint setting of annular anchor has increased concrete pipe pile's prestressing force in addition, provides dual guarantee for concrete pipe pile, can reduce the emergence of the condition such as disconnected stake, has the practicality.
Drawings
Fig. 1 is a schematic perspective view of the present invention;
FIG. 2 is a schematic view of a partial three-dimensional structure of the present invention;
FIG. 3 is a schematic view of the partial cut-away structure of the present invention;
fig. 4 is an enlarged schematic structural diagram of a in fig. 3 according to the present invention.
In the figure: 1. putting a tubular pile; 2. putting a tubular pile; 3. longitudinal reinforcing steel bars; 4. spiral reinforcing steel bars; 5. annular anchoring; 6. connecting the pile heads; 7. mounting blocks; 8. a first extrusion block; 9. a card slot; 10. a support bar; 11. a movable rod; 12. extruding the ball; 13. a fixing plate; 14. a second extrusion block; 15. a spring; 16. a movable plate; 17. and (7) clamping blocks.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides a technical solution: a prestressed high-strength concrete pipe pile comprises an upper pipe pile 1 and a lower pipe pile 2, wherein the inner walls of the upper pipe pile 1 and the lower pipe pile 2 are fixedly connected with longitudinal steel bars 3, the outer walls of the longitudinal steel bars 3 are fixedly connected with annular anchors 5 at the middle parts of the upper pipe pile 1 and the lower pipe pile 2, two ends of the upper pipe pile 1 and the lower pipe pile 2 are respectively and fixedly connected with connecting pile heads 6, the outer wall of each connecting pile head 6 is fixedly connected with an installation block 7, the outer wall of the installation block 7 is fixedly connected with a first extrusion block 8, the inner wall of the installation block 7 is provided with a clamping groove 9, the inner wall of each connecting pile head 6 is fixedly connected with a support rod 10, the top end of each support rod 10 is movably connected with a movable rod 11, the inner wall of one side of each connecting pile head 6 is fixedly connected with a fixed plate 13 above the movable rod 11, the inner wall of the bottom of the fixed plate 13 is slidably connected with a second extrusion block 14, one side of the second extrusion block 14, which is far away from the inner wall of each connecting pile head 6 is fixedly connected with a movable plate 16, a clamping block 17 is fixedly connected to the outer wall of the movable plate 16 on the side away from the second pressing block 14.
In this embodiment, through longitudinal reinforcement 3, the prestressing force of concrete pipe pile has been increased in the joint setting of 4 annular anchor 5 of spiral reinforcement, through the direction motion of going up tubular pile 1 to being close to tubular pile 2 down, the inside motion of installation piece 7 downstream tubular pile 2 of going up tubular pile 1 outer wall, the inside motion of installation piece 7 upstream tubular pile 1 of tubular pile 2 outer wall down, the first extrusion piece 8 extrusion movable rod 11 of installation piece 7 outer wall, by the movable rod 11 downstream of extruded one end, the other end upward movement, make extrusion ball 12 upward movement with the second extrusion piece 14 to the direction motion of being close to installation piece 7, and then drive fly leaf 16 and move thereupon, make fixture block 17 and draw-in groove 9 joint, thereby accomplish the fixed to installation piece 7.
Specifically, the outer wall of the longitudinal steel bar 3 is sleeved with the spiral steel bar 4.
In the embodiment, the prestress of the concrete pipe pile is increased by the combined arrangement of the longitudinal steel bars 3 and the spiral steel bars 4 and the annular anchors 5.
Specifically, the outer wall of the top of one end of the movable rod 11 close to the inner wall of the connecting pile head 6 is fixedly connected with an extrusion ball 12, and the extrusion ball 12 is arranged between the outer wall of the second extrusion block 14 and the inner wall of the connecting pile head 6.
In the embodiment, when the ball 12 moves upward, since the ball 12 has a structure with a narrow top and a wide bottom, when the ball 12 moves upward, the second pressing block 14 is pressed to move to one side, and the movable plate 16 is pressed.
Specifically, the inner wall of the fixing plate 13 is provided with a sliding groove, and the inner wall of the fixing plate 13 is slidably connected with the outer wall of the second extrusion block 14 through the sliding groove.
In the present embodiment, the second pressing block 14 moves leftwards and rightwards smoothly by the arrangement of the sliding connection, and the fixing plate 13 provides support for the second pressing block 14.
Specifically, a spring 15 is fixedly connected between the outer wall of one side of the second extrusion block 14 and the inner wall of the connecting pile head 6.
In this embodiment, by the provision of the spring 15, the spring 15 assists the second pressing block 14 to return to its original position when it loses its pressing.
Specifically, the outer wall of the clamping block 17 is clamped with the inner wall of the clamping groove 9.
In this embodiment, clamping between the clamping block 17 and the clamping groove 9 is performed to fix the mounting block 7, and further fix the upper tubular pile 1 and the lower tubular pile 2.
The utility model discloses a theory of operation and use flow: during the use, through longitudinal reinforcement 3, the prestressing force of concrete pipe pile has been increased in the joint setting of 4 annular anchor 5 of spiral reinforcement, through with the direction motion of upper pipe pile 1 to being close to lower tubular pile 2, the inside motion of installation piece 7 of upper pipe pile 1 outer wall to lower tubular pile 2 outer wall, the inside motion of installation piece 7 to upper pipe pile 1 of lower tubular pile 2 outer wall, the first extrusion piece 8 extrusion movable rod 11 of installation piece 7 outer wall, by the movable rod 11 downstream of extruded one end, the other end upward movement, make extrusion ball 12 upward movement with the second extrusion piece 14 to the direction motion of being close to installation piece 7, and then drive movable plate 16 and move thereupon, make fixture block 17 and draw-in groove 9 joint, thereby accomplish the fixed to installation piece 7.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a prestressing force high strength concrete tubular pile, includes tubular pile (1) and low tubular pile (2), its characterized in that: the inner wall of the upper tubular pile (1) and the lower tubular pile (2) is fixedly connected with longitudinal steel bars (3), the outer wall of the longitudinal steel bars (3) is positioned in the middle of the upper tubular pile (1) and the lower tubular pile (2) and is fixedly connected with an annular anchor (5), two ends of the upper tubular pile (1) and the lower tubular pile (2) are respectively fixedly connected with connecting pile heads (6), the outer wall of each connecting pile head (6) is fixedly connected with an installation block (7), the outer wall of each installation block (7) is fixedly connected with a first extrusion block (8), the inner wall of each installation block (7) is provided with a clamping groove (9), the inner wall of each connecting pile head (6) is fixedly connected with a support rod (10), the top end of each support rod (10) is movably connected with a movable rod (11), one side inner wall of each connecting pile head (6) is positioned above the fixed plate (13) of the movable rod (11), the bottom inner wall sliding connection of fixed plate (13) has second extrusion piece (14), one side fixedly connected with fly leaf (16) of connecting pile head (6) inner wall is kept away from in second extrusion piece (14), one side outer wall fixedly connected with fixture block (17) of second extrusion piece (14) are kept away from in fly leaf (16).
2. The prestressed high-strength concrete pipe pile of claim 1, wherein: and spiral steel bars (4) are sleeved on the outer wall of the longitudinal steel bars (3).
3. The prestressed high-strength concrete pipe pile of claim 1, wherein: the movable rod (11) is close to one end top outer wall fixedly connected with extrusion ball (12) of connecting pile head (6) inner wall, extrusion ball (12) set up between the outer wall of second extrusion piece (14) and the inner wall of connecting pile head (6).
4. The prestressed high-strength concrete pipe pile of claim 1, wherein: the inner wall of the fixed plate (13) is provided with a sliding chute, and the inner wall of the fixed plate (13) is in sliding connection with the outer wall of the second extrusion block (14) through the sliding chute.
5. The prestressed high-strength concrete pipe pile of claim 1, wherein: and a spring (15) is fixedly connected between the outer wall of one side of the second extrusion block (14) and one side of the inner wall of the connecting pile head (6).
6. The prestressed high-strength concrete pipe pile of claim 1, wherein: the outer wall of the clamping block (17) is clamped with the inner wall of the clamping groove (9).
CN202022369190.8U 2020-10-22 2020-10-22 Prestressed high-strength concrete pipe pile Expired - Fee Related CN213773327U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022369190.8U CN213773327U (en) 2020-10-22 2020-10-22 Prestressed high-strength concrete pipe pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022369190.8U CN213773327U (en) 2020-10-22 2020-10-22 Prestressed high-strength concrete pipe pile

Publications (1)

Publication Number Publication Date
CN213773327U true CN213773327U (en) 2021-07-23

Family

ID=76910459

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022369190.8U Expired - Fee Related CN213773327U (en) 2020-10-22 2020-10-22 Prestressed high-strength concrete pipe pile

Country Status (1)

Country Link
CN (1) CN213773327U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116479870A (en) * 2023-05-15 2023-07-25 浙大城市学院 A concrete pipe pile pile head butt joint structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116479870A (en) * 2023-05-15 2023-07-25 浙大城市学院 A concrete pipe pile pile head butt joint structure

Similar Documents

Publication Publication Date Title
CN103711330B (en) A kind of prestressing force assembling precast reinforced concrete frame reinforces the method for existing structure
CN111734164A (en) Oblique steel pull rod reinforced brick masonry structure and construction method thereof
CN213509776U (en) A prefabricated platform canopy structure
CN2440893Y (en) Apparatus for unitary horizontal movement of construction
CN215290085U (en) Prestressed high-strength concrete pipe pile
CN212534125U (en) Deep foundation pit waist rail construction design template system
CN210857607U (en) Frame structure of building wall
CN219864135U (en) Reinforcing bar is installation auxiliary device in position fast
CN219260985U (en) Pile splicing structure of prefabricated prestressed concrete pipe pile
CN216740016U (en) Cold-formed thin-wall steel keel for assembled concrete beam
CN214738835U (en) Connecting joint of prefabricated reinforced concrete column
CN217537033U (en) A PHC steel-concrete composite foundation pile
CN102051929A (en) Block masonry wall configured with steel ribs and manufacture method thereof
CN213710501U (en) Concrete supporting structure
CN215926040U (en) Assembled plate type foundation adopting post-cast strip mode
CN205822448U (en) A kind of distinctiveness uses the precast frame bean column node of high performance material
CN213296411U (en) Precast pile foundation for building engineering
CN210507768U (en) Novel prefabricated balcony
CN201268918Y (en) Concealed column vertical reinforced bar with frame structure
CN221567031U (en) Concrete steel form device
CN223964215U (en) Reinforced structure of stone wall
CN211369633U (en) Prestressed carbon drill steel plate tensioning device
CN113789854A (en) A fully assembled beam-column joint based on groove-shaped UHPC splicing member and its manufacturing method
CN223781062U (en) H-shaped steel constructional column structure for autoclaved aerated block masonry structure
CN223660653U (en) Bracket support supporting mechanism of cast-in-situ box girder self-propelled movable formwork system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210723