Foundation trench construction dust device
Technical Field
The utility model relates to a dust device especially relates to a foundation trench construction dust device.
Background
The foundation trench construction is a common open cut construction process in civil engineering operation, and comprises construction foundation construction, underground diaphragm wall construction, subway construction, underground pipeline laying, canal construction and other various civil engineering operations, which all involve foundation trench construction, and the construction process is usually shallow earthwork excavation, support system building, deep earthwork excavation, and lining pouring, and the earthwork amount to be excavated is very large.
A typical foundation trench earth excavation process is as follows: excavating shallow earthwork by a large excavator positioned on the ground; then digging deep earthwork by a small excavator positioned in the foundation trench, and lifting the earthwork out by a crane; and (5) leveling the earthwork with the thickness of 0.3 m at the bottom layer by adopting manual excavation. There are, of course, also relatively shallow foundation trenches that can be excavated all the time using an excavator located above ground, but in any case the bottom of the foundation trench needs to be manually leveled.
Excavation of foundation trench earthwork is an open-air work with high labor intensity and serious dust emission, and workers are easy to get heatstroke.
When an excavator positioned on the ground is used for excavating, the labor intensity is relatively low, the heatstroke prevention is easy, and water can be directly sprayed to the excavating tunnel face for dust prevention; however, when earth excavation is performed on the deep layer of the foundation trench, labor intensity is high, and dust prevention is not easy to perform. In addition, the construction of the foundation pit supporting system and the process of pouring the lining also have great labor intensity.
SUMMERY OF THE UTILITY MODEL
The utility model provides a foundation trench construction dust device.
The technical problem to be solved is that: the deep earthwork excavation work of the foundation trench, the construction of a foundation trench supporting system and the dust raising in the pouring and lining process are not easy to control.
In order to solve the technical problem, the utility model adopts the following technical scheme:
a foundation trench construction dust-settling device comprises two slide rails which are respectively arranged on two sides of a foundation trench along the length direction of the foundation trench, and a sunshade which is arranged on the two slide rails in a sliding manner;
the sunshade comprises an upright post arranged on the sliding rail in a sliding way, an arched beam erected on the upright post and tarpaulin covered on the arched beam, wherein spray fans with outlets facing the base groove are respectively arranged below the arched beam and on the inner side of the upright post, and the spray fans are communicated with a water supply network through pipelines;
the sunshade and the working surface of the base groove are arranged above the working surface in a one-to-one correspondence manner.
Furthermore, the arched girders are truss girders and are arranged at intervals along the length direction of the slide rails, and two ends of each truss girder are erected on the two slide rails through upright posts respectively; the slide rail is a channel steel with an upward opening, and the lower end of the upright post is arranged in the channel steel opening in a sliding manner; the upper ends of the stand columns positioned on the same side of the base groove are respectively and fixedly connected with a through long connecting rod parallel to the slide rail.
Furthermore, the spraying fans are arranged at intervals along the length directions of the upright posts and the arched beams, and the distance between every two adjacent spraying fans is not more than two meters.
Furthermore, a cross brace is arranged between the adjacent stand columns positioned on the same side of the base groove, and the cross brace is fixedly connected with the two adjacent stand columns respectively.
Furthermore, the lower end of the upright post is anchored with a spherical end, and the inner surface of the slide rail is coated with a Teflon coating.
Further, the lower end of the upright post is provided with a wheel, and the wheel is rotatably connected with the upright post through a sealing bearing.
Further, the slide rail is fixedly connected with a supporting structure of the foundation trench.
The utility model relates to a foundation trench construction dust device compares with prior art, has following beneficial effect:
in the utility model, the slide rails are arranged on the two sides of the base groove, and then the sunshade is arranged on the slide rails, the sunshade slides along the working surface of the base groove, so that workers who construct on the working surface can be prevented from being directly irradiated by sunlight; the sunshade is also provided with a spray fan facing the base groove, the spray fan can suppress dust generated in the construction process so as not to diffuse outwards, and meanwhile, the spray fan blows fog-containing air with the temperature lower than the ambient temperature to workers, so that the effect of heatstroke prevention and cooling is achieved.
Drawings
Fig. 1 is a schematic structural view of a foundation trench construction dust-settling device of the utility model;
the device comprises a sliding rail 1, an arched beam 21, an upright column 22, a spherical end 221, a through long connecting rod 23, a shear support 24, a tarpaulin 25 and a spray fan 3.
Detailed Description
As shown in fig. 1, a foundation trench construction dust-settling device comprises two slide rails 1 which are respectively arranged at two sides of a foundation trench along the length direction of the foundation trench, and a sunshade which is slidably arranged on the two slide rails 1;
the sunshade comprises an upright post 22 arranged on the sliding rail 1 in a sliding way, an arch beam 21 erected on the upright post 22 and tarpaulin 25 covered on the arch beam 21, wherein spray fans 3 with outlets facing to the base groove are respectively arranged below the arch beam 21 and on the inner side of the upright post 22, and the spray fans 3 are communicated with a water supply network through pipelines; the atomizing fan 3 is a common outdoor labor protection cooling article, fine water mist is sprayed out through an atomizing nozzle, then the fan blows the water mist to workers in the labor, the air containing fine mist drops is kept at the wet bulb temperature which is lower than the air temperature, and therefore the heatstroke prevention cooling effect is achieved. Meanwhile, air containing fog drops can be adhered with dust, and the effect of dust fall is achieved.
The sunshade and the working surface of the base groove are arranged above the working surface in a one-to-one correspondence manner. Because the foundation ditch is interior for the construction progress, probably need two-way or even multidirectional construction, have a plurality of working faces, for heatstroke prevention cooling and dust fall, all should set up the sunshade on every working face.
The arched beams 21 are truss beams and are arranged at intervals along the length direction of the slide rails 1, and two ends of each truss beam are respectively erected on the two slide rails 1 through upright posts 22; the slide rail 1 is a channel steel with an upward opening, and the lower end of the upright post 22 is arranged in the channel steel opening in a sliding manner; the upper ends of the upright posts 22 positioned at the same side of the base groove are respectively and fixedly connected with a through long connecting rod 23 parallel to the slide rail 1. The truss girder is a light steel truss girder, has higher strength than a ceiling of a conventional awning, and can meet the requirements of hoisting the spray fan 3 and the water pipe. The wind end plates can be arranged at the two ends of the channel steel to prevent the awning from being separated from the two ends of the slide rail 1.
The spraying fans 3 are arranged at intervals along the length direction of the upright posts 22 and the arched beams 21, and the distance between two adjacent spraying fans 3 is not more than two meters. If the distance is too large, dust may overflow from the gap.
And a cross brace 24 is arranged between the adjacent upright posts 22 positioned on the same side of the base groove, and the cross brace 24 is fixedly connected with the two adjacent upright posts 22 respectively so as to enhance the rigidity of the whole sunshade and prevent the sunshade from deforming.
The spherical end 221 is anchored at the lower end of the upright post 22, the teflon coating is coated on the inner surface of the slide rail 1, and the wheel is not arranged at the lower end of the upright post 22, so that various impurities can enter the slide rail 1 to influence the movement of the wheel in the construction process of a construction site, and if the wheel is adopted, the wheel with a larger diameter is used, the wheel shaft of the wheel is higher than the slide rail 1, and the bearing on the wheel shaft is a sealed bearing.
The slide rail 1 is fixedly connected with the supporting structure of the foundation trench to strengthen the supporting structure of the foundation trench and prevent the slide rail 1 from moving randomly.
The utility model relates to a foundation trench construction dust device, its use includes following step:
the method comprises the following steps: after earth excavation of a shallow layer of the foundation trench and construction of a supporting system are finished, installing sliding rails 1 on two sides of the foundation trench and connecting the sliding rails with the supporting system of the foundation trench;
step two: building a sunshade, and connecting each spray fan 3 with a water supply pipe network;
step three: the spraying fan 3 is powered on, a switch of the water supply pipe network is opened, and the sunshade is pushed to move along with the working surface in the foundation pit.
The above-mentioned embodiments are only for describing the preferred embodiments of the present invention, and are not intended to limit the scope of the present invention, and various modifications and improvements made by those skilled in the art without departing from the design spirit of the present invention should fall into the protection scope defined by the claims of the present invention.