CN213390295U CN202020748138.0U CN202020748138U CN213390295U CN 213390295 U CN213390295 U CN 213390295U CN 202020748138 U CN202020748138 U CN 202020748138U CN 213390295 U CN213390295 U CN 213390295U
Authority
CN
China
Prior art keywords
carriage
vertical board
straight cylinder
foundation
guide rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020748138.0U
Other languages
Chinese (zh)
Inventor
黄礼瑶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Wanyi Construction Engineering Co ltd
Original Assignee
Sichuan Wanyi Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Wanyi Construction Engineering Co ltd filed Critical Sichuan Wanyi Construction Engineering Co ltd
Priority to CN202020748138.0U priority Critical patent/CN213390295U/en
Application granted granted Critical
Publication of CN213390295U publication Critical patent/CN213390295U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model belongs to the technical field of basic building, especially, be a building equipment for basic building, including the frid guide rail, install the carriage on the frid guide rail, one side of carriage is provided with the drum, drum and carriage welded fastening, the inboard of drum is provided with straight cylinder, the bottom of straight cylinder is provided with vertical board, vertical board and straight cylinder welded fastening, the top of frid guide rail is provided with the controller, the top of controller is provided with the keypad, one side of keypad is provided with electric telescopic handle, electric telescopic handle's free end and carriage welded fastening; use is convenient for through the vertical board and the electric telescopic handle who sets up, and electric telescopic handle's promotion through setting up makes vertical board can remove, can excavate the foundation groove along with the removal of vertical board, can carry out the shaping to the foundation groove along with the removal of vertical board, guarantees fashioned effect when labour saving and time saving.

Description

Building equipment for foundation building
Technical Field
The utility model belongs to the technical field of basic building, concretely relates to a building equipment for basic building.
Background
The foundation refers to a soil body or a rock body for supporting a foundation under a building, the soil layer serving as the building foundation is divided into rock, gravel soil, sand soil, silt, cohesive soil and artificial filling soil, the foundation comprises a natural foundation and an artificial foundation (composite foundation), the natural foundation is a natural soil layer which does not need to be reinforced by people, the artificial foundation needs to be reinforced by people, a stone chip cushion layer, a sand cushion layer and mixed lime soil are commonly backfilled and then tamped, and the like, so that a foundation pit is not easy to be conveniently excavated in the foundation excavation process.
The prior art has the following problems:
1. in the using process, the foundation groove is uneven, the foundation groove is not easy to push flat during excavation, the forming effect is not good, and manual excavation is time-consuming and labor-consuming;
2. the in-process of using is difficult for adjusting, simultaneously, can not separate the grit among the excavation process.
In order to solve the above problems, a construction equipment for foundation construction is proposed in the present application.
SUMMERY OF THE UTILITY MODEL
To solve the problems set forth in the background art described above. The utility model provides a building equipment for basic building has that the shaping is effectual, labour saving and time saving, the characteristics of the adjustment of being convenient for.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a construction equipment for basic building, includes the frid guide rail, install the carriage on the frid guide rail, one side of carriage is provided with the drum, drum and carriage welded fastening, the inboard of drum is provided with straight cylinder, straight cylindrical bottom is provided with vertical board, vertical board and straight cylinder welded fastening, the top of frid guide rail is provided with the controller, the top of controller is provided with the keypad, one side of keypad is provided with electric telescopic handle, electric telescopic handle's free end and carriage welded fastening.
As the utility model relates to a construction equipment is preferred for basic building, one side of vertical board is provided with the arc line board, the perforation has been seted up on the arc line board, the perforation is provided with a plurality of altogether.
As the utility model relates to a construction equipment is preferred for basic building, be provided with the scale mark on the straight cylinder, the originated scale of scale mark is located the below.
As the utility model relates to a construction equipment is preferred for basic building, the frid guide rail is provided with two altogether, and all is provided with the carriage on two frid guide rails.
As the utility model relates to a construction equipment is preferred for basic building, install the set screw on the arc line board, the arc line board passes through set screw and vertical board fixed connection.
As the utility model relates to a construction equipment is preferred for basic building, install fixing bolt on the drum, straight cylinder passes through fixing bolt and drum fixed connection.
Compared with the prior art, the beneficial effects of the utility model are that:
1. use is convenient for through the vertical board and the electric telescopic handle who sets up, and electric telescopic handle's promotion through setting up makes vertical board can remove, can excavate the foundation groove along with the removal of vertical board, can carry out the shaping to the foundation groove along with the removal of vertical board, guarantees fashioned effect when labour saving and time saving.
2. Through the straight cylinder and the arc line board that set up convenient to use, through the straight cylindrical height adjustment who sets up, be applicable to the foundation ditch excavation of the different degree of depth, simultaneously, can also separate the grit when promoting through the arc line board that sets up for great stone and fine sand separation are convenient for utilize the grit of excavation.
Drawings
The accompanying drawings are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description serve to explain the invention and not to limit the invention. In the drawings:
fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a side view of the channel plate guide of the present invention;
fig. 3 is a schematic structural view of the arc wire plate of the present invention;
fig. 4 is a front view of the arc wire plate of the present invention;
in the figure: 1. a vertical plate; 2. a channel plate guide rail; 3. a carriage; 4. a cylinder; 5. a straight cylinder; 6. fixing the bolt; 7. scale lines; 8. an electric telescopic rod; 9. a key sheet; 10. a controller; 11. an arc plate; 12. perforating; 13. and fixing the screw.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Example 1
As shown in fig. 1, 2, 3 and 4;
fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a side view of the channel plate guide of the present invention;
fig. 3 is a schematic structural view of the arc wire plate of the present invention;
figure 4 is the front view of the arc line board of the utility model.
The utility model provides a construction equipment for basic building, including frid guide rail 2, install carriage 3 on the frid guide rail 2, one side of carriage 3 is provided with drum 4, drum 4 and carriage 3 welded fastening, the inboard of drum 4 is provided with straight cylinder 5, the bottom of straight cylinder 5 is provided with vertical board 1, vertical board 1 and straight cylinder 5 welded fastening, the top of frid guide rail 2 is provided with controller 10, the top of controller 10 is provided with keypad 9, one side of keypad 9 is provided with electric telescopic handle 8, electric telescopic handle 8's free end and carriage 3 welded fastening.
As shown in fig. 3;
fig. 3 is a schematic structural view of the arc wire plate of the present invention;
in an optional embodiment, an arc line plate 11 is arranged on one side of the vertical plate 1, a through hole 12 is formed in the arc line plate 11, and a plurality of through holes 12 are arranged.
In this embodiment: soil in the foundation pit can be pushed through the arranged arc line plates 11.
As shown in fig. 1;
fig. 1 is a schematic structural view of the present invention;
in an alternative embodiment, the straight cylinder 5 is provided with graduation marks 7, the starting graduation of the graduation marks 7 being located below.
In this embodiment: the fixed position of the straight cylinder 5 is convenient to know through the scale marks 7 arranged, and the vertical plate 1 at the bottom end of the straight cylinder 5 is convenient to guarantee to be in a horizontal state.
As shown in fig. 1;
fig. 1 is a schematic structural view of the present invention;
in an alternative embodiment, a total of two slat guides 2 are provided, and a carriage 3 is provided on each of the two slat guides 2.
In this embodiment: the stability of removal is convenient for guarantee.
As shown in fig. 4;
figure 4 is the front view of the arc line board of the utility model.
In an alternative embodiment, the arc wire plate 11 is provided with a fixing screw 13, and the arc wire plate 11 is fixedly connected with the vertical plate 1 through the fixing screw 13.
In this embodiment: the arc line board 11 through setting up is convenient for promote soil, is convenient for fix arc line board 11 through set screw 13.
As shown in fig. 1;
fig. 1 is a schematic structural view of the present invention;
in an alternative embodiment, a fixing bolt 6 is mounted on the cylinder 4, and the straight cylinder 5 is fixedly connected with the cylinder 4 through the fixing bolt 6.
In this embodiment: the position of the straight cylinder 5 is convenient to adjust through the arranged fixing bolt 6.
The utility model discloses a theory of operation and use flow: when using, fix through placing the both sides in the foundation hole with frid guide rail 2, input the instruction through keypad 9 on frid guide rail 2, through the flexible of controller 10 according to the instruction control electric telescopic handle 8 of input, can promote carriage 3 through electric telescopic handle 8 and remove, make straight cylinder 5 remove through the removal of carriage 3, make vertical board 1 remove through the removal of straight cylinder 5, thereby it promotes to the soil in the foundation hole to drive arc line board 11 through vertical board 1, thereby be convenient for excavate the foundation hole.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described in the foregoing embodiments, or equivalents may be substituted for elements thereof. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (6)

1. Construction equipment for foundation construction, comprising a channel plate guide rail (2), characterized in that: install carriage (3) on frid guide rail (2), one side of carriage (3) is provided with drum (4), drum (4) and carriage (3) welded fastening, the inboard of drum (4) is provided with straight cylinder (5), the bottom of straight cylinder (5) is provided with vertical board (1), vertical board (1) and straight cylinder (5) welded fastening, the top of frid guide rail (2) is provided with controller (10), the top of controller (10) is provided with keypad (9), one side of keypad (9) is provided with electric telescopic handle (8), the free end and carriage (3) welded fastening of electric telescopic handle (8).
2. Construction equipment for foundation construction according to claim 1, characterized in that: one side of vertical board (1) is provided with arc line board (11), seted up perforation (12) on arc line board (11), perforation (12) are provided with a plurality of altogether.
3. Construction equipment for foundation construction according to claim 1, characterized in that: the straight cylinder (5) is provided with scale marks (7), and the starting scale of the scale marks (7) is positioned below.
4. Construction equipment for foundation construction according to claim 1, characterized in that: the two groove plate guide rails (2) are arranged, and sliding frames (3) are arranged on the two groove plate guide rails (2).
5. Construction equipment for foundation construction according to claim 2, characterized in that: the arc line board (11) is provided with a fixing screw (13), and the arc line board (11) is fixedly connected with the vertical board (1) through the fixing screw (13).
6. Construction equipment for foundation construction according to claim 1, characterized in that: and the cylinder (4) is provided with a fixing bolt (6), and the straight cylinder (5) is fixedly connected with the cylinder (4) through the fixing bolt (6).
CN202020748138.0U 2020-05-07 2020-05-07 Building equipment for foundation building Expired - Fee Related CN213390295U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020748138.0U CN213390295U (en) 2020-05-07 2020-05-07 Building equipment for foundation building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020748138.0U CN213390295U (en) 2020-05-07 2020-05-07 Building equipment for foundation building

Publications (1)

Publication Number Publication Date
CN213390295U true CN213390295U (en) 2021-06-08

Family

ID=76177353

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020748138.0U Expired - Fee Related CN213390295U (en) 2020-05-07 2020-05-07 Building equipment for foundation building

Country Status (1)

Country Link
CN (1) CN213390295U (en)

Similar Documents

Publication Publication Date Title
CN102797252B (en) Construction method of underground continuous walls
CN106049193B (en) One kind being used for roadbed section ballastless track of high-speed railway center line method for correcting error
CN111350259B (en) Construction method of assembled slip-form cast-in-situ drainage ditch
CN101906768B (en) Panel construction method of concrete faced rock-fill dam
CN108193608A (en) The cast-in-place road gully of mobile moldbase and construction method
CN109454746B (en) Concrete pouring device for building construction and construction method thereof
CN103410524A (en) Soft rock tunnel construction method
CN208152052U (en) Steel sheet pile underground structure of controllable deformation
CN111395344A (en) Reusable secant pile positioning device and construction method
CN113969795A (en) Excavation supporting structure and construction method of tunnel
CN213390295U (en) Building equipment for foundation building
CN107299640A (en) A kind of variable cross-section well shaft type ground continuous wall base and its construction method
CN110820756A (en) Shield well and vertical shaft deep foundation pit excavation safety construction method
CN103866787B (en) A kind of spacious reverse masonry method concrete cut that digs builds construction technology
CN205276272U (en) A tub machine is beaten in static pressure pneumatics
CN216429507U (en) Excavator transformation drilling machine
CN211472615U (en) Foundation reinforcing device
CN209907168U (en) Road and bridge curb ramming device
CN208121753U (en) A kind of auxiliary device for steel sheet pile construction
CN214219618U (en) Railway roadbed reinforcing construction device
CN206352299U (en) A kind of cage car device constructed for water seepage mechanism
CN216075298U (en) Building equipment for foundation building
CN215057352U (en) Rotary excavating and sliding formwork device for large-mouth well
CN112323788B (en) Anti-seismic cement mixing pile and construction method
CN213329881U (en) Tile plastering tool

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210608

CF01 Termination of patent right due to non-payment of annual fee