CN212960201U - Pipeline fixing structure for coal mine vertical shaft construction - Google Patents
Pipeline fixing structure for coal mine vertical shaft construction Download PDFInfo
- Publication number
- CN212960201U CN212960201U CN202021411364.6U CN202021411364U CN212960201U CN 212960201 U CN212960201 U CN 212960201U CN 202021411364 U CN202021411364 U CN 202021411364U CN 212960201 U CN212960201 U CN 212960201U
- Authority
- CN
- China
- Prior art keywords
- pipe
- fixed
- screw
- threaded holes
- pipeline
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Clamps And Clips (AREA)
Abstract
The utility model discloses a pipeline fixed knot constructs for colliery vertical construction, including the pipe cassette, be equipped with two relative first screw holes on the pipe cassette, two all establish first fastening screw in the first screw hole, and the pipe cassette is fixed in on the platelike device of concrete well wall through two first fastening screw, be equipped with the location on the pipe cassette and link the piece, be equipped with two relative third screw holes on the pipe cassette, and fix a position and link to be equipped with the second screw hole that corresponds with the third screw hole on the piece, corresponding second screw hole and third threaded hole are equipped with same second fastening screw, the location links the piece and is fixed in on the pipe cassette through two second fastening screw. The utility model discloses establish the card pipe box of cover on the pipeline, be fixed in the pipe cassette on the wall of a well, even piece will block the pipe box and install on the pipe cassette through the location, do benefit to installer alone, quick convenient installation, this device does benefit to orderly installation operation, practices thrift installation time, guarantees progress, time limit for a project and benefit of engineering.
Description
Technical Field
The utility model relates to a colliery vertical construction pipeline fixed field specifically is a colliery is pipeline fixed knot structure for vertical construction, is particularly useful for the fixed of the pipeline that the transport medium is compressed air.
Background
In the construction process of a coal mine vertical shaft, pipelines are required to be arranged for ventilation and drainage, the pipelines are basically fixed through suspension and wall hanging at the present stage, in the construction of the vertical shaft with a smaller well diameter, the pipeline is fixed through a wall hanging mode, so that an operation workshop is more favorably expanded, but the operation process of the wall hanging fixed pipelines needs to be performed in a multi-user cooperation mode, operation disorder is easily caused, the installation time is prolonged, the progress, the construction period and the benefit of engineering are finally influenced, and in view of the above, the pipeline fixing structure for the construction of the coal mine vertical shaft is provided for solving the problems.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a pipeline fixed knot constructs for colliery vertical construction to solve the problem that proposes among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: a pipeline fixing structure for coal mine vertical shaft construction comprises a pipe clamping seat, wherein two opposite first threaded holes are formed in the pipe clamping seat, first fastening screws are arranged in the two first threaded holes, the pipe clamping seat is fixed on a plate-shaped device of a concrete well wall through the two first fastening screws, a positioning connecting piece is arranged on the pipe clamping seat, two opposite third threaded holes are formed in the pipe clamping seat, a second threaded hole corresponding to the third threaded hole is formed in the positioning connecting piece, the same second fastening screw is arranged in the corresponding second threaded hole and the corresponding third threaded hole, the positioning connecting piece is fixed on the pipe clamping seat through the two second fastening screws, a clamping opening is formed in the pipe clamping seat, a pipeline is clamped in the clamping opening, a clamping pipe sleeve is sleeved on the pipeline, the clamping pipe sleeve is composed of paired clamping pipe half sleeves, and fifth threaded holes are formed in two adjacent ends of the two clamping pipe half sleeves, and fourth threaded holes corresponding to the paired fifth threaded holes at the two ends of the pipe clamping sleeve are formed in the positioning connecting piece, the same third fastening screw is arranged in the corresponding fourth threaded hole and the paired fifth threaded hole, and the pipe clamping sleeve is fixed on the positioning connecting piece through the third fastening screw.
Compared with the prior art, the beneficial effects of the utility model are that:
the utility model discloses establish the card pipe box of cover on the pipeline, be fixed in the pipe cassette on the wall of a well, even piece will block the pipe box and install on the pipe cassette through the location, do benefit to installer alone, quick convenient installation, this device does benefit to orderly installation operation, practices thrift installation time, guarantees progress, time limit for a project and benefit of engineering.
Drawings
FIG. 1 is a schematic top view of the present invention;
fig. 2 is a schematic view of the present invention viewed from the bottom.
In the figure: 1 pipeline, 2 location even piece, 3 pipe clamp covers, 4 first screw holes, 5 pipe cassette, 6 second screw holes, 7 third screw holes, 8 fourth screw holes, 9 fifth screw holes.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-2, the present invention provides a technical solution: a pipeline fixing structure for coal mine vertical shaft construction comprises a pipe clamping seat 5, wherein two opposite first threaded holes 4 are formed in the pipe clamping seat 5, first fastening screws are arranged in the two first threaded holes 4, the pipe clamping seat 5 is fixed on a plate-shaped device of a concrete well wall through the two first fastening screws, a positioning connecting piece 2 is arranged on the pipe clamping seat 5, two opposite third threaded holes 7 are formed in the pipe clamping seat 5, second threaded holes 6 corresponding to the third threaded holes are formed in the positioning connecting piece 2, the same second fastening screws are arranged in the corresponding second threaded holes 6 and the corresponding third threaded holes 7, the positioning connecting piece 2 is fixed on the pipe clamping seat 5 through the two second fastening screws, a clamping opening is formed in the pipe clamping seat 5, a pipeline 1 is clamped in the clamping opening, a clamping pipe sleeve 3 is sleeved on the pipeline 1, the clamping pipe sleeve 3 is formed by paired clamping pipe half sleeves, and two adjacent ends of the two clamping pipe half sleeves are provided with fifth threaded holes 9, the positioning connecting piece 2 is provided with a fourth threaded hole 8 corresponding to the paired fifth threaded holes 9 at the two ends of the clamping sleeve 3, the corresponding fourth threaded hole 8 and the paired fifth threaded holes are internally provided with the same third fastening screw, and the clamping sleeve 3 is fixed on the positioning connecting piece 2 through the third fastening screw.
The working principle is as follows: during the installation, even piece 2 is fixed in the pipe cassette 5 in the location through second fastening screw, earlier be fixed in the riser wall through first fastening screw with pipe cassette 5 again on, block pipeline 1 in corresponding bayonet in advance, block corresponding card pipe box 3 on pipeline 1 in advance, rethread third fastening screw is fixed mutually with card pipe box 3 and location even piece 2, can be fast convenient the realization pipeline 1 fixed.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (1)
1. The utility model provides a pipeline fixed knot constructs for colliery vertical construction, includes pipe cassette (5), its characterized in that: the pipe clamping seat (5) is provided with two opposite first threaded holes (4), first fastening screws are arranged in the two first threaded holes (4), the pipe clamping seat (5) is fixed on a plate-shaped device of a concrete well wall through the two first fastening screws, the pipe clamping seat (5) is provided with a positioning connecting piece (2), the pipe clamping seat (5) is provided with two opposite third threaded holes (7), the positioning connecting piece (2) is provided with second threaded holes (6) corresponding to the third threaded holes, the corresponding second threaded holes (6) and the third threaded holes (7) are internally provided with the same second fastening screws, the positioning connecting piece (2) is fixed on the pipe clamping seat (5) through the two second fastening screws, a clamping opening is arranged on the pipe clamping seat (5), a pipeline (1) is clamped in the clamping opening, and a pipe clamping sleeve (3) is arranged on the pipeline (1), card pipe box (3) comprises mated card pipe half cover, and all is equipped with fifth screw hole (9) on two adjacent ends of two card pipe half covers, be equipped with on the even piece of location (2) with card pipe box (3) both ends respectively mated fifth screw hole (9) corresponding fourth screw hole (8), be equipped with same third fastening screw in corresponding fourth screw hole (8) and mated fifth screw, and card pipe box (3) are fixed in the location through third fastening screw and are linked on piece (2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021411364.6U CN212960201U (en) | 2020-07-17 | 2020-07-17 | Pipeline fixing structure for coal mine vertical shaft construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021411364.6U CN212960201U (en) | 2020-07-17 | 2020-07-17 | Pipeline fixing structure for coal mine vertical shaft construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212960201U true CN212960201U (en) | 2021-04-13 |
Family
ID=75393398
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202021411364.6U Expired - Fee Related CN212960201U (en) | 2020-07-17 | 2020-07-17 | Pipeline fixing structure for coal mine vertical shaft construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212960201U (en) |
-
2020
- 2020-07-17 CN CN202021411364.6U patent/CN212960201U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204611104U (en) | A kind of fixture being applicable to I-shape beam | |
CN212960201U (en) | Pipeline fixing structure for coal mine vertical shaft construction | |
CN204284665U (en) | A kind of diagonal-bracing type suspension and support of rationally arranging for line classification | |
CN208268548U (en) | A kind of urban Underground pipeline pipe gallery piping lane suspension and support | |
CN103075576A (en) | Pipeline fixing device | |
CN203445556U (en) | Cable suspension device | |
CN216112496U (en) | Pipe support frame of quick installation | |
CN214479530U (en) | Stainless steel kudzuvine root head easy to assemble | |
CN201034214Y (en) | Pipe fitting shelf | |
CN211574409U (en) | Multidirectional antidetonation support of piping lane | |
CN217927563U (en) | Oil pipe arranging and fixing device | |
CN202884306U (en) | Pipeline fastener | |
CN215110973U (en) | Fastening type is adjusted conveniently and is managed jib | |
CN203427015U (en) | Petroleum pipeline elastic force mark belt | |
CN203614918U (en) | Pipe clamp suitable for engineering machine | |
CN219954460U (en) | Prefabricated assembled pipe jacking | |
CN204728702U (en) | A kind of pipeline hangs mould mould | |
CN204005194U (en) | A kind of locking device and the profile structure that adopts this locking device to connect | |
CN204960939U (en) | A pipeline fixing base for mine shaft | |
CN220957158U (en) | Portable installation fixed knot of building pipeline upper wall constructs | |
CN204843600U (en) | Copper pipe bit hole positioning fixture | |
CN211398808U (en) | Pipeline installation fixing device in underground mine tunnel | |
CN216131532U (en) | Quick clamp of petroleum pipeline | |
CN212616753U (en) | Pipe clamp for plastic-coated steel pipe | |
CN214500299U (en) | Combined adjustable pipe clamp device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20210413 Termination date: 20210717 |