CN212805995U - Intelligent control system for air volume of industrial factory building ventilation pipeline - Google Patents

Intelligent control system for air volume of industrial factory building ventilation pipeline Download PDF

Info

Publication number
CN212805995U
CN212805995U CN202021300916.6U CN202021300916U CN212805995U CN 212805995 U CN212805995 U CN 212805995U CN 202021300916 U CN202021300916 U CN 202021300916U CN 212805995 U CN212805995 U CN 212805995U
Authority
CN
China
Prior art keywords
factory building
control system
air volume
intelligent control
plc terminal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021300916.6U
Other languages
Chinese (zh)
Inventor
蒲兴平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaoguan Bairui Environmental Protection Technology Co ltd
Original Assignee
Shaoguan Bairui Environmental Protection Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaoguan Bairui Environmental Protection Technology Co ltd filed Critical Shaoguan Bairui Environmental Protection Technology Co ltd
Priority to CN202021300916.6U priority Critical patent/CN212805995U/en
Application granted granted Critical
Publication of CN212805995U publication Critical patent/CN212805995U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Ventilation (AREA)

Abstract

The utility model relates to the technical field of industrial factory building ventilation, and discloses an intelligent control system for the air volume of an industrial factory building ventilation pipeline, which comprises an air valve actuator, a dust concentration sensor, a PLC terminal and a dust collection module, wherein the air valve actuator and the dust concentration sensor are in signal connection with the dust collection module, and the dust collection module is in signal connection with the PLC terminal; the intelligent work condition and air volume adjusting of the scene reality can be realized, the ventilation efficiency of a factory building can be improved, the working environment is improved, meanwhile, the manual operation is reduced, and the humanized control is realized.

Description

Intelligent control system for air volume of industrial factory building ventilation pipeline
Technical Field
The utility model relates to an industry factory building ventilation technical field specifically is an industry factory building air pipe amount of wind intelligent control system.
Background
Among the general factory building ventilation system, the control of regional air volume all is by wind channel valve control, and the control mode of valve divide into manual and electronic two kinds, explains with regard to the drawback of these two kinds of modes now: manual control is basically achieved once, particularly, a pipeline is erected on a roof, if air volume needs to be changed, manpower is wasted, and reasonable parameter matching is difficult to obtain; electric control mainly is to the regulation of individual valve, can realize that the amount of wind size is controlled through the switch size, but need improve the collection dirt effect of whole factory building, overall air volume matching still need the manual calculation, also does not accord with the actual conditions of mill's work.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
Aiming at the defects of the prior art, the utility model provides an intelligent control system for the air flow of an air conduit of an industrial factory building, which solves the problem that a manual control valve is arranged on the roof of the pipeline, if the air flow needs to be changed, not only the manpower is wasted, but also reasonable parameter matching is difficult to obtain; the electric control valve mainly aims at adjusting individual valves, can realize that the air volume is controlled by the switch, but needs to improve the dust collecting effect of the whole factory building, needs manual calculation for overall air volume matching and does not accord with the actual situation problem of factory work.
(II) technical scheme
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides an industry factory building air pipe amount of wind intelligent control system, includes blast gate executor, dust concentration sensor, PLC terminal and collection dirt module, the blast gate executor with dust concentration sensor all with collection dirt module signal connection, collection dirt module with PLC terminal signal connection.
Preferably, the number of the dust concentration sensors 10 and the number of the damper actuators are 16.
Preferably, the system further comprises a touch screen, and the touch screen is electrically connected with the PLC terminal.
(III) advantageous effects
The utility model provides an industry factory building air pipe amount of wind intelligent control system possesses following beneficial effect:
(1) the utility model discloses the working condition of scene reality and air regulation's intellectuality can be realized.
(2) The utility model discloses can promote factory building ventilation efficiency, improve operational environment.
(3) The utility model discloses can reduce manual operation, realize humanized control.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
In the figure: 1. an air valve actuator; 2. a dust concentration sensor; 3. a touch screen; 4. a PLC terminal; 5. and a dust collection module.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
As shown in fig. 1, the utility model provides a technical solution: the utility model provides an industrial factory building air pipe amount of wind intelligent control system, including blast gate executor 1, dust concentration sensor 2, PLC terminal 4 and collection dirt module 5, blast gate executor 1 and dust concentration sensor 2 all with collection dirt module 5 signal connection, collection dirt module 5 and PLC terminal 4 signal connection, in the in-process of using, blast gate executor 1 on-off angle feedback signal and dust concentration sensor 2's feedback signal, transmit to collection dirt module 5, then collection dirt module 5 transmits feedback signal to PLC terminal 4 again, can realize the intelligent regulation of the regional air volume of factory building through the calculation of PLC terminal 4, the ventilation efficiency of factory building has been improved, when improving operational environment, the manual operation has been reduced, realize humanized control, PLC terminal 4's calculation mode has following several key elements to constitute: the minimum standard of the total air quantity of the pipeline, the dust concentration of the space, the ventilation times, the sectional area of the air valve and the number of the air valves.
Furthermore, the quantity of the dust concentration sensors 2 is 10 and the quantity of the air valve actuators 1 is 16, and the PLC terminal 4 can be calculated more accurately through the feedback signals of the dust concentration sensors 2 and the air valve actuators 1, so that the ventilation efficiency of the plant can be better improved, and the working environment of the plant can be better improved.
Further, the system further comprises a touch screen 3, the touch screen 3 is electrically connected with the PLC terminal 4, and an operator can control the system through the touch screen 3.
To sum up, the utility model discloses a work flow: in the process of using, the feedback signal of 1 switch angle feedback signal of blast gate executor and dust concentration sensor 2 transmits to collection dirt module 5, then collection dirt module 5 is with feedback signal transmission to PLC terminal 4 again, can realize the intelligent regulation of the regional air volume of factory building through the calculation of PLC terminal 4, has improved the ventilation efficiency of factory building, when improving operational environment, has reduced manual operation, realizes humanized control.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (3)

1. The utility model provides an industry factory building air pipe amount of wind intelligent control system, includes blast gate executor (1), dust concentration sensor (2), PLC terminal (4) and collection dirt module (5), its characterized in that: the air valve actuator (1) and the dust concentration sensor (2) are in signal connection with the dust collection module (5), and the dust collection module (5) is in signal connection with the PLC terminal (4).
2. The intelligent control system for the air volume of the ventilation duct of the industrial factory building according to claim 1, characterized in that: the number of the dust concentration sensors (2) is 10, and the number of the air valve actuators (1) is 16.
3. The intelligent control system for the air volume of the ventilation duct of the industrial factory building according to any one of claims 1 to 2, characterized in that: the system further comprises a touch screen (3), and the touch screen (3) is electrically connected with the PLC terminal (4).
CN202021300916.6U 2020-07-06 2020-07-06 Intelligent control system for air volume of industrial factory building ventilation pipeline Active CN212805995U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021300916.6U CN212805995U (en) 2020-07-06 2020-07-06 Intelligent control system for air volume of industrial factory building ventilation pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021300916.6U CN212805995U (en) 2020-07-06 2020-07-06 Intelligent control system for air volume of industrial factory building ventilation pipeline

Publications (1)

Publication Number Publication Date
CN212805995U true CN212805995U (en) 2021-03-26

Family

ID=75101169

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021300916.6U Active CN212805995U (en) 2020-07-06 2020-07-06 Intelligent control system for air volume of industrial factory building ventilation pipeline

Country Status (1)

Country Link
CN (1) CN212805995U (en)

Similar Documents

Publication Publication Date Title
CN1687852A (en) Digitalized control energy-saving method for central air conditioner
CN203478522U (en) Intelligent variable-frequency variable-air-rate closed-loop control system for lab
CN101936301A (en) Automatic operation control device of tunnel ventilator
CN212805995U (en) Intelligent control system for air volume of industrial factory building ventilation pipeline
CN210801468U (en) Intelligent temperature and humidity adjusting device for data center machine room
CN205600161U (en) A exhaust system for welding process
CN101684962B (en) Air conditioning ventilation automatic control system and method for single-brand air conditioner of transformer substation
CN110081578B (en) Intelligent control heat exchanger with bypass pipeline and control method
CN201688865U (en) Environment monitoring system in gymnasium
CN117404730A (en) Full-decoupling type purifying air conditioning system with fan air valve combined control and control method thereof
CN201562160U (en) Automatic control system for ventilation and rain prevention of plastic canopy population
CN203274132U (en) Real-time monitoring device for evaporative cooling air conditioning unit
CN102081396A (en) Multi-sensor concentrated control method for full-automatic blast furnace dedusting fan control system
CN205540205U (en) Dust exhausting fan economizer system
CN218033605U (en) Intelligent control system for energy conservation of central air conditioner
CN201014676Y (en) Air conditioner cooling volume self-adaptive energy-saving controller
CN203950188U (en) A kind of Flour production line traffic control system
CN108386377A (en) A kind of remodeling method of dedusting fan end control system and dust pelletizing system
CN102538089A (en) Reuse method of exhausted steam of steam condensate water
CN211189559U (en) Full-automatic full-coverage spraying device
CN204757215U (en) New air conditioning system
CN204752781U (en) Converter secondary dust collector
CN209569824U (en) A kind of central heating control system
CN204313393U (en) The built-in machine room of a kind of air-conditioning
CN211716792U (en) High ventilation building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant