CN212671160U - Combined building scaffold - Google Patents
Combined building scaffold Download PDFInfo
- Publication number
- CN212671160U CN212671160U CN202020569428.9U CN202020569428U CN212671160U CN 212671160 U CN212671160 U CN 212671160U CN 202020569428 U CN202020569428 U CN 202020569428U CN 212671160 U CN212671160 U CN 212671160U
- Authority
- CN
- China
- Prior art keywords
- fixed
- installed part
- fixed block
- block
- bolt mounting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 230000008878 coupling Effects 0.000 claims abstract description 19
- 238000010168 coupling process Methods 0.000 claims abstract description 19
- 238000005859 coupling reaction Methods 0.000 claims abstract description 19
- 238000010276 construction Methods 0.000 claims abstract description 13
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 11
- 239000010959 steel Substances 0.000 claims abstract description 11
- 238000003466 welding Methods 0.000 claims abstract description 5
- 238000009434 installation Methods 0.000 abstract description 20
- 230000000694 effects Effects 0.000 description 4
- 238000000034 method Methods 0.000 description 4
- 239000002184 metal Substances 0.000 description 2
- 235000017166 Bambusa arundinacea Nutrition 0.000 description 1
- 235000017491 Bambusa tulda Nutrition 0.000 description 1
- 241001330002 Bambuseae Species 0.000 description 1
- 235000015334 Phyllostachys viridis Nutrition 0.000 description 1
- 239000011425 bamboo Substances 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000009194 climbing Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
- 239000002023 wood Substances 0.000 description 1
Images
Landscapes
- Mutual Connection Of Rods And Tubes (AREA)
Abstract
The utility model discloses a modular construction scaffold, including vertical support bar, the outside cover of vertical support bar is equipped with the fixed cover of installed part, and the section of the fixed cover of installed part is the rectangle to the fixed cover outer wall of installed part is equipped with the fixed block installed part of a plurality of "U" shape, the welding of the inboard central point of fixed block installed part has the connecting piece fixed block of rectangle, and the inboard block of fixed block installed part has the fixed union coupling piece of "U" shape to first bolt mounting hole has all been seted up to the below of fixed block installed part, the fixed block mounting groove has been seted up to fixed union coupling piece one side, and the welding of fixed union coupling piece opposite side has horizontal fixed pipe, and the second bolt mounting hole has all been. This combination formula building scaffold is provided with the block structure, can directly block the both ends of steel pipe, makes things convenient for the installation work of steel pipe.
Description
Technical Field
The utility model relates to a scaffold technical field specifically is a modular construction scaffold.
Background
The scaffold is a working platform which is erected for ensuring that each construction process is smoothly carried out. The scaffold is divided into an outer scaffold and an inner scaffold according to the erected positions; the scaffold can be divided into a wood scaffold, a bamboo scaffold and a steel pipe scaffold according to different materials; the scaffold is divided into a vertical rod type scaffold, a bridge type scaffold, a door type scaffold, a suspension type scaffold, a hanging type scaffold, a lifting type scaffold and a climbing type scaffold according to the structural form.
The connection of steel pipe is carried out through the retainer plate to current scaffold frame in the in-process that uses, and crooked condition appears easily at the in-process of installation to the metal retainer plate, can reduce the efficiency of installation like this, can reduce the installation effect of steel pipe moreover.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a modular construction scaffold to the crooked condition appears easily at the in-process of installation in the metal retainer plate on the scaffold that proposes in the solution background art, can reduce the efficiency of installation like this, can reduce the problem of the installation effect of steel pipe moreover.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a modular construction scaffold, includes vertical support rod, the outside cover of vertical support rod is equipped with the fixed cover of installed part, and the section of the fixed cover of installed part is the rectangle to the fixed cover outer wall of installed part is equipped with the fixed block installed part of a plurality of "U" shape, the inboard central point of fixed block installed part welds the connecting piece fixed block of rectangle, and the inboard block of fixed block installed part has the fixed union coupling spare of "U" shape to first bolt mounting hole has all been seted up to the below of fixed block installed part, the fixed block mounting groove has been seted up to fixed union coupling spare one side, and the welding of fixed union coupling spare opposite side has horizontal fixed pipe, and the second bolt mounting hole has.
Preferably, the fixed block installed part is equipped with four altogether, and fixed block installed part evenly distributed is around the fixed cover of installed part.
Preferably, the outer wall of the connecting piece fixing block is provided with a through hole, and the position of the through hole on the connecting piece fixing block corresponds to the positions of the first bolt mounting hole and the second bolt mounting hole.
Preferably, the transverse fixing pipe is a circular steel pipe and is positioned on the transverse central line of the fixing pipe connecting piece.
Preferably, fixing bolts are arranged in the first bolt mounting hole and the second bolt mounting hole.
Preferably, the inner shape of the fixing block mounting groove is matched with the outer shape of the connecting piece fixing block.
Compared with the prior art, the beneficial effects of the utility model are that: this combination formula building scaffold is provided with the block structure, can directly block the both ends of steel pipe, makes things convenient for the installation work of steel pipe. The fixed block installed part of the device can block fixed union coupling spare, and the inboard fixed block mounting groove of fixed union coupling spare can block on the connecting piece fixed block simultaneously, and fixing bolt can pass first bolt mounting hole and second bolt mounting hole, makes fixed block installed part, fixed union coupling spare and connecting piece fixed block can be fixed together, avoids fixed union coupling spare to break away from in the fixed block installed part.
Drawings
FIG. 1 is a schematic structural view of a combined scaffold for building of the present invention;
FIG. 2 is a top view of the vertical support rod of the combined scaffold for building of the present invention;
FIG. 3 is a schematic structural view of a mounting member for fixing blocks of a combined scaffold for construction according to the present invention;
fig. 4 is the utility model relates to a modular construction scaffolding fixes pipe connector structure sketch.
In the figure: 1. vertical bracing piece, 2, fixed block installed part, 3, fixed union coupling, 4, connecting piece fixed block, 5, horizontal fixed pipe, 6, fixing bolt, 7, the fixed cover of installed part, 8, first bolt mounting hole, 9, second bolt mounting hole, 10, fixed block mounting groove.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides a technical solution: a combined type building scaffold comprises a vertical supporting rod 1, wherein an installation part fixing sleeve 7 is sleeved outside the vertical supporting rod 1, the section of the installation part fixing sleeve 7 is rectangular, a plurality of U-shaped fixing block installation parts 2 are arranged on the outer wall of the installation part fixing sleeve 7, rectangular connecting part fixing blocks 4 are welded at the center positions of the inner sides of the fixing block installation parts 2, U-shaped fixing pipe connecting parts 3 are clamped at the inner sides of the fixing block installation parts 2, first bolt installation holes 8 are formed in the upper side and the lower side of each fixing block installation part 2, the four fixing block installation parts 2 are arranged, the fixing block installation parts 2 are uniformly distributed around the installation part fixing sleeve 7, the fixing pipe connecting parts 3 can be clamped by the fixing block installation parts 2 of the structure, the fixing pipe connecting parts 3 are uniformly distributed around the vertical supporting rod 1, and through holes, and the through hole position on the fixed block 4 of the connecting piece corresponds to the position of the first bolt mounting hole 8 and the second bolt mounting hole 9, the through hole on the fixed block 4 of the connecting piece of the structure plays a role of accommodating the fixing bolt 6, so that the fixing bolt 6 can pass through the first bolt mounting hole 8 to be fixed in the second bolt mounting hole 9, so that the fixing bolt 6 can fix the fixed block mounting piece 2, the fixed pipe connecting piece 3 and the fixed block 4 of the connecting piece together, the fixing bolt 6 is arranged in the first bolt mounting hole 8 and the second bolt mounting hole 9, the first bolt mounting hole 8 and the second bolt mounting hole 9 of the structure play a role of accommodating the fixing bolt 6, so that the fixing bolt 6 can fix the fixed block mounting piece 2 and the fixed pipe connecting piece 3 together, one side of the fixed pipe connecting piece 3 is provided with the fixed block mounting groove 10, and the other side of the fixed pipe connecting piece 3 is welded, and second bolt mounting hole 9 has all been seted up to fixed union coupling spare 3's upper and lower side, horizontal fixed pipe 5 adopts circular steel pipe, and horizontal fixed pipe 5 is located the horizontal central line of fixed union coupling spare 3, the horizontal fixed pipe 5 of this structure is more firm with fixed union coupling spare 3 connection, be difficult to the cracked condition that appears, the inside shape of fixed block mounting groove 10 is identical with the outside shape of connecting piece fixed block 4, the fixed block mounting groove 10 of this structure plays the effect that holds connecting piece fixed block 4, block connecting piece fixed block 4, improve the fixed effect of connecting piece fixed block 4 in fixed block installed part 2.
The working principle is as follows: when using this combination formula building scaffold, at first set up the device's vertical support rod 1 in suitable place, make the fixed cover 7 of installed part of 1 outer lane of vertical support rod be in suitable height, later directly with the fixed union coupling spare 3 card of horizontal fixed pipe 5 both sides to fixed block installed part 2 in, and the inboard connecting piece fixed block 4 of fixed block installed part 2 can block in fixed block mounting groove 10, pass first bolt mounting hole 8 and second bolt mounting hole 9 with fixing bolt 6 again at last, with fixed block installed part 2, fixed union coupling spare 3 and connecting piece fixed block 4 are fixed together, thereby accomplish a series of work.
Although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments or portions thereof without departing from the spirit and scope of the invention.
Claims (6)
1. The utility model provides a modular construction scaffold, includes vertical support pole (1), its characterized in that: vertical support rod (1) outside cover is equipped with the fixed cover of installed part (7), and the section of the fixed cover of installed part (7) is the rectangle to the fixed cover of installed part (7) outer wall is equipped with fixed block installed part (2) of a plurality of "U" shape, the inboard center part welding of fixed block installed part (2) has connecting piece fixed block (4) of rectangle, and fixed block installed part (2) inboard block has fixed union coupling spare (3) of "U" shape, and first bolt mounting hole (8) have all been seted up to the upper and lower side of fixed block installed part (2), fixed block mounting groove (10) have been seted up to fixed union coupling spare (3) one side, and the welding of fixed union coupling spare (3) opposite side has horizontal fixed pipe (5) to second bolt mounting hole (9) have all been seted up to the upper.
2. A modular construction scaffold according to claim 1, wherein: fixed block installed part (2) are equipped with four altogether, and fixed block installed part (2) evenly distributed is around the fixed cover of installed part (7).
3. A modular construction scaffold according to claim 1, wherein: the outer wall of the connecting piece fixing block (4) is provided with a through hole, and the position of the through hole in the connecting piece fixing block (4) corresponds to the positions of the first bolt mounting hole (8) and the second bolt mounting hole (9).
4. A modular construction scaffold according to claim 1, wherein: the transverse fixing pipe (5) is a round steel pipe, and the transverse fixing pipe (5) is located on the transverse central line of the fixing pipe connecting piece (3).
5. A modular construction scaffold according to claim 1, wherein: and fixing bolts (6) are arranged in the first bolt mounting holes (8) and the second bolt mounting holes (9).
6. A modular construction scaffold according to claim 1, wherein: the inner shape of the fixing block mounting groove (10) is matched with the outer shape of the connecting piece fixing block (4).
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202020569428.9U CN212671160U (en) | 2020-04-17 | 2020-04-17 | Combined building scaffold |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202020569428.9U CN212671160U (en) | 2020-04-17 | 2020-04-17 | Combined building scaffold |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN212671160U true CN212671160U (en) | 2021-03-09 |
Family
ID=74811612
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202020569428.9U Expired - Fee Related CN212671160U (en) | 2020-04-17 | 2020-04-17 | Combined building scaffold |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN212671160U (en) |
-
2020
- 2020-04-17 CN CN202020569428.9U patent/CN212671160U/en not_active Expired - Fee Related
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN113152873A (en) | Heightening hanging basket system | |
| CN211470603U (en) | Telescopic tower crane passageway | |
| CN211173004U (en) | Hanging basket for high-altitude welding steel structure | |
| CN212671160U (en) | Combined building scaffold | |
| CN215167932U (en) | Flower basket pull rod type hanging scaffold support | |
| CN218522613U (en) | Vertical climbing hanging ladder | |
| CN216546634U (en) | Engine room upside down hanging scaffold | |
| CN216444884U (en) | Hoisting device for mounting shock insulation support | |
| CN101597956A (en) | Suspended scaffold | |
| CN216197796U (en) | Welding equipment is used in cat ladder unit processing for building engineering construction | |
| CN215803104U (en) | Wall-riding type hanging basket frame | |
| CN213834250U (en) | Auxiliary lifting device for manhole cover | |
| CN213139095U (en) | Adjustable cage hanging scaffold operation tool for ship construction | |
| CN213062885U (en) | High-tolerance node support for steel structure engineering | |
| CN210685313U (en) | Safe convenient house steel connection structure | |
| CN201245965Y (en) | Hanging scaffold | |
| CN220502518U (en) | Tower crane platform convenient to disassemble and assemble | |
| CN222541968U (en) | A hanging basket bracket for super-high parapet wall or flower rack beam on roof | |
| CN208604911U (en) | A kind of novel suspention beam bracket | |
| CN222757825U (en) | A tower crane attachment frame installation tool | |
| CN217326383U (en) | Parapet hanging basket structure | |
| CN218562948U (en) | Construction bearing frame for building management | |
| CN222759350U (en) | Wall-attached connection node of electric bridge scaffold | |
| CN219138315U (en) | A hanging basket construction platform | |
| CN218642290U (en) | Crane handrail |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20210309 |