- CN212559093U CN212559093U CN202020956160.4U CN202020956160U CN212559093U CN 212559093 U CN212559093 U CN 212559093U CN 202020956160 U CN202020956160 U CN 202020956160U CN 212559093 U CN212559093 U CN 212559093U
- Authority
- CN
- China
- Prior art keywords
- carrier
- lifting frame
- panel
- construction
- frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 23
- 229910000831 Steel Inorganic materials 0.000 claims description 7
- 239000010959 steel Substances 0.000 claims description 7
- 238000009435 building construction Methods 0.000 claims description 4
- 238000000034 method Methods 0.000 description 6
- 230000000694 effects Effects 0.000 description 4
- 230000008569 process Effects 0.000 description 4
- 230000009471 action Effects 0.000 description 3
- 230000006835 compression Effects 0.000 description 2
- 238000007906 compression Methods 0.000 description 2
- 235000004443 Ricinus communis Nutrition 0.000 description 1
- 230000004075 alteration Effects 0.000 description 1
- 230000001174 ascending effect Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005034 decoration Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
The utility model discloses a panel handling frame for construction, including the carrier, the fixed bottom plate that is provided with of lower extreme of carrier, the right side both ends of bottom plate are all fixed and are provided with the guardrail, logical groove has all been seted up on the lower extreme left and right sides of bottom plate, the handling frame has been cup jointed to the outside of carrier, the lower extreme left and right sides of handling frame is the fixed mount that is provided with all, two the mount all includes the first backup pad of two vertical settings and the second backup pad that a level set up, the both ends and two of second backup pad the equal fixed connection of lower extreme of first backup pad. Through the cooperation that sets up mount, lifting frame, hanging piece, guardrail, logical groove and carrier frame and use, solved current construction and hung the unable convenient loading panel of frame with panel, it is comparatively complicated that fixed panel bindes when the handling, increases staff intensity of labour's problem.
Description
Technical Field
The utility model belongs to the technical field of the building, especially, relate to a panel lifting frame for construction.
Background
The building construction refers to production activities in the engineering construction implementation stage, is a construction process of various buildings, and can also be a process of changing various lines on a design drawing into a real object at a specified place, and comprises foundation engineering construction, main structure construction, roofing engineering construction, decoration engineering construction and the like, and the place of the construction operation is called a building construction site or a construction site.
Need use overhead hoist to carry out the handling to panel in the building work progress, carry out the handling to panel and need use the lifting frame device, the unable convenient panel that loads of present panel lifting frame all needs to be carried panel respectively near the lifting frame, further places in lifting frame top, and it is fixed to bind at carrying out the complicacy, increases intensity of labour, and efficiency is lower.
SUMMERY OF THE UTILITY MODEL
Problem to prior art exists, the utility model provides a panel lifting frame for construction possesses the loading panel of being convenient for, and does not need the complicacy to bind fixedly, has solved the unable convenient loading panel of panel lifting frame for construction now, and fixed panel bindes comparatively complicatedly when the handling, increases staff intensity of labour's problem.
The utility model discloses a realize like this, including the carrier, the fixed bottom plate that is provided with of lower extreme of carrier, the equal fixed guardrail that is provided with in both ends of the left and right sides of bottom plate, logical groove has all been seted up on the lower extreme left and right sides of bottom plate, the lifting frame has been cup jointed to the outside of carrier, the lower extreme left and right sides of lifting frame is the fixed mount that is provided with all, two the mount all includes the first backup pad of two vertical settings and the second backup pad that a level set up, the both ends and two of second backup pad the equal fixed connection of lower extreme of first backup pad, two the second backup pad leads to the groove joint with two correspondences respectively, the fixed hanging piece that is provided with in top of mount, the top welding of hanging piece has the couple.
As the utility model discloses preferred, two the guardrail all includes the montant of many vertical settings and the horizontal pole of a level setting at the top.
Preferably, the lower end of the object carrier is uniformly provided with six universal wheels, and the six universal wheels are arranged in a rectangular shape.
Preferably, a cushion pad is fixedly arranged at the center of the upper end face of the carrier, and a plurality of plates are fixedly arranged above the cushion pad.
Preferably, the inner height of the lifting frame is slightly larger than the sum of the heights of the carrier frame and the universal wheels.
As the utility model discloses it is preferred, the upper end four corners department of lifting frame is all fixed and is provided with the fixed block, four the upper end of fixed block is all fixed and is provided with the wire rope, four the top of wire rope all with the lower extreme fixed connection who hangs the piece.
Compared with the prior art, the beneficial effects of the utility model are as follows:
1. the utility model discloses a set up mount, lifting frame, hang piece, guardrail, lead to the cooperation of groove and carrier and use, solved current construction and used panel lifting frame unable convenient loading panel, fixed panel bindes comparatively complicacy when the handling, increases staff intensity of labour's problem.
2. The utility model discloses a set up many montants and a horizontal pole and constitute the guardrail, can be so that guardrail stable in structure reduces the weight of whole carrier simultaneously, can also guarantee that panel can not drop from the both ends of carrier and fall out the carrier.
3. The utility model discloses a set up the universal wheel, can be so that the carrier can set up the convenient removal of universal wheel through the bottom, the staff can load near panel through removing the carrier, convenient to panel, then with the convenient removal of carrier to the inside joint of lifting frame, carry out the panel handling.
4. The utility model discloses a set up the blotter, place panel above the blotter, can be so that a plurality of panel place in the blotter top, can play the effect of protection panel, panel compression blotter simultaneously for have great frictional force between panel and the blotter, can be so that panel can not the optional shift position.
5. The utility model discloses a set up the height slightly and be greater than the lift truck of carrier and universal wheel height and, can make the staff remove near board shipment panel with the carrier earlier after, remove the lift truck inside, the lift truck rises the logical groove of lower extreme second backup pad joint for the carrier rises simultaneously, even the carrier takes place certain slope, also can make lift truck joint carrier, make the carrier can not drop, avoid the panel of handling to fall out.
6. The utility model discloses a set up four fixed blocks and steel cable rope and connect the piece of hanging, can be so that the more stable handling of lifting frame rises, more stable when guaranteeing handling panel, efficiency is higher.
Drawings
Fig. 1 is an overall schematic diagram provided by an embodiment of the present invention;
fig. 2 is a schematic view of a structure of a carrier according to an embodiment of the present invention;
fig. 3 is a schematic structural view of a lifting frame provided in an embodiment of the present invention;
in the figure: 1. a lifting frame; 101. a fixed mount; 102. a fixed block; 103. a steel cable; 104. a hanging block; 105. hooking; 106. a first support plate; 107. a second support plate; 2. a carrier; 201. a base plate; 202. a universal wheel; 203. a guardrail; 204. a cushion pad; 205. a through groove; 206. a cross bar; 207. a vertical rod; 3. a plate material.
Detailed Description
In order to further understand the contents, features and effects of the present invention, the following embodiments are illustrated and described in detail with reference to the accompanying drawings.
The structure of the present invention will be described in detail with reference to the accompanying drawings.
As shown in fig. 1 to 3, the embodiment of the present invention provides a panel lifting frame for building construction, including a carrier 2, a bottom plate 201 is fixedly disposed at a lower end of the carrier 2, a guardrail 203 is fixedly disposed at both ends of a left side and a right side of the bottom plate 201, a through groove 205 is disposed at both sides of a left side and a right side of a lower end of the bottom plate 201, the lifting frame 1 is sleeved outside the carrier 2, a fixing frame 101 is fixedly disposed at both sides of a left side and a right side of a lower end of the lifting frame 1, the two fixing frames 101 include two vertically disposed first supporting plates 106 and a horizontally disposed second supporting plate 107, both ends of the second supporting plate 107 and lower ends of the two first supporting plates 106 are fixedly connected, the two second supporting plates 107 are respectively connected with the corresponding two through grooves 205, a lifting block 104 is fixedly disposed above the fixing frame 101, and a hook 105 is welded.
Referring to fig. 1 and 2, both guardrails 203 include a plurality of vertically disposed vertical posts 207 and a horizontally disposed top cross-bar 206.
Adopt above-mentioned scheme: the guardrail 203 is formed by the vertical rods 207 and the cross rod 206, so that the guardrail 203 is stable in structure, the weight of the whole carrier frame 2 is reduced, and the plates 3 can be prevented from falling off from the two ends of the carrier frame 2 to fall out of the carrier frame 2.
Referring to fig. 1 and 2, six universal wheels 202 are uniformly arranged at the lower end of the carrier rack 2, and the six universal wheels 202 are arranged in a rectangular shape.
Adopt above-mentioned scheme: through setting up universal wheel 202, can be so that carrier 2 can set up the convenient removal of universal wheel 202 through the bottom, the staff can be through removing carrier 2 to near panel 3, convenient loading panel 3, then with 2 convenient removals of carrier to 1 inside joint of lifting frame, carry out the handling of panel 3.
Referring to fig. 1 and 2, a cushion 204 is fixedly disposed at the center of the upper end surface of the carrier 2, and a plurality of plates 3 are fixedly disposed above the cushion 204.
Adopt above-mentioned scheme: through setting up blotter 204, place panel 3 above blotter 204, can be so that a plurality of panel 3 place in blotter 204 top, can play the effect of protection panel 3, panel 3 compression blotter 204 simultaneously for have great frictional force between panel 3 and the blotter 204, can be so that panel 3 can not the random shift position.
Referring to figure 1, the internal height of the lifting frame 1 is slightly greater than the sum of the heights of the carrier frame 2 and the castor 202.
Adopt above-mentioned scheme: through the lifting frame 1 that sets up the height slightly to be greater than carrier 2 and universal wheel 202 height sum, can make the staff remove near panel 3 shipment panel 3 back with carrier 2 earlier, with the inside of lifting frame 1 of carrier 2 removal, the logical groove 205 of the ascending lower extreme second backup pad 107 joint of lifting frame 1, make carrier 2 rise simultaneously, even carrier 2 takes place certain slope, also can make lifting frame 1 joint carrier 2, make carrier 2 can not drop, avoid the panel 3 of handling to fall out.
Referring to fig. 1, four corners of the upper end of the lifting frame 1 are fixedly provided with fixing blocks 102, the upper ends of the four fixing blocks 102 are fixedly provided with steel cables 103, and the top ends of the four steel cables 103 are fixedly connected with the lower end of a lifting block 104.
Adopt above-mentioned scheme: the four fixing blocks 102 and the steel cable 103 are connected with the lifting block 104, so that the lifting frame 1 can be lifted more stably, the plate 3 can be lifted more stably, and the efficiency is higher. The utility model discloses a theory of operation:
when in use, after the lifting frame 1 and the carrier frame 2 are lifted to the ground by the lifting device, a worker completely contacts the lower end of the lifting frame 1 with the ground, then pushes the carrier frame 2 to the vicinity of the plate 3 by the universal wheel 202 arranged at the lower end, places the plate 3 above the cushion 204, can protect the bottom plate 3, can also increase the friction force between the plate 3 and the cushion 204 to prevent the plate 3 from moving, then moves the carrier frame 2 into the lifting frame 1, enables the two through grooves 205 at the lower end to correspond to the two second supporting plates 107, then lifts the carrier frame 2 by the lifting device, the guardrails 203 arranged at the two ends of the carrier frame 2 are provided with a plurality of vertical rods 207 and a cross rod 206, reduces the whole weight, enables the plate 3 not to fall out through the two ends of the carrier frame 2, and simultaneously passes through the plurality of first supporting plates 106 arranged at the front end and the rear end of the lifting frame 1, make panel 3 can not fall out from the front and back end of lifting frame 1, and then lifting frame 1 is a little higher than carrier 2 for even carrier 2 takes place the slope, also can not make carrier 2 fall out inside lifting frame 1, make the handling that panel 3 can be convenient.
In summary, the following steps: this warning mechanism for construction through the cooperation that sets up mount 101, lifting frame 1, fixed block 102, wire rope 103, hangs piece 104, couple 105, guardrail 203, logical groove 205, blotter 204, universal wheel 202 and carrier 2 and uses, has solved the unable convenient loading panel of current construction panel lifting frame, and it is comparatively complicated to bind when fixed panel when the handling, increases staff intensity of labour's problem.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (6)
1. A panel lifting frame for building construction comprises a carrier (2), and is characterized in that: a bottom plate (201) is fixedly arranged at the lower end of the luggage carrier (2), guardrails (203) are fixedly arranged at the two ends of the left side and the right side of the bottom plate (201), through grooves (205) are respectively arranged on the left side and the right side of the lower end of the bottom plate (201), a lifting frame (1) is sleeved outside the carrier (2), the left side and the right side of the lower end of the lifting frame (1) are both fixedly provided with a fixed frame (101), the two fixed frames (101) both comprise two vertically arranged first supporting plates (106) and a horizontally arranged second supporting plate (107), the two ends of the second supporting plates (107) are fixedly connected with the lower ends of the two first supporting plates (106), the two second supporting plates (107) are respectively clamped with the two corresponding through grooves (205), a hanging block (104) is fixedly arranged above the fixing frame (101), and a hook (105) is welded at the top end of the hanging block (104).
2. A panel lifting frame for construction as claimed in claim 1, wherein: two guardrail (203) all include many vertical poles (207) of vertical setting and a horizontal pole (206) that the level set up at the top.
3. A panel lifting frame for construction as claimed in claim 1, wherein: the lower end of the carrier (2) is uniformly provided with six universal wheels (202), and the six universal wheels (202) are arranged in a rectangular shape.
4. A panel lifting frame for construction as claimed in claim 1, wherein: a buffer pad (204) is fixedly arranged at the center of the upper end face of the luggage carrier (2), and a plurality of plates (3) are fixedly arranged above the buffer pad (204).
5. A panel lifting frame for construction as claimed in claim 1, wherein: the inner height of the lifting frame (1) is slightly larger than the sum of the heights of the carrier (2) and the universal wheels (202).
6. A panel lifting frame for construction as claimed in claim 1, wherein: the four corners of the upper end of the lifting frame (1) are fixedly provided with fixing blocks (102), the upper ends of the four fixing blocks (102) are fixedly provided with steel cables (103), and the top ends of the four steel cables (103) are fixedly connected with the lower end of a lifting block (104).
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202020956160.4U CN212559093U (en) | 2020-05-31 | 2020-05-31 | Panel lifting frame for construction |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202020956160.4U CN212559093U (en) | 2020-05-31 | 2020-05-31 | Panel lifting frame for construction |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN212559093U true CN212559093U (en) | 2021-02-19 |
Family
ID=74636765
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202020956160.4U Expired - Fee Related CN212559093U (en) | 2020-05-31 | 2020-05-31 | Panel lifting frame for construction |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN212559093U (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN112919362A (en) * | 2021-03-01 | 2021-06-08 | 杭州职业技术学院 | Building indoor decoration is with roof board hoisting device |
| CN113213366A (en) * | 2021-04-16 | 2021-08-06 | 郭道彬 | Energy-absorbing protection device for processing high-altitude falling stones of geological exploration machine |
-
2020
- 2020-05-31 CN CN202020956160.4U patent/CN212559093U/en not_active Expired - Fee Related
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN112919362A (en) * | 2021-03-01 | 2021-06-08 | 杭州职业技术学院 | Building indoor decoration is with roof board hoisting device |
| CN113213366A (en) * | 2021-04-16 | 2021-08-06 | 郭道彬 | Energy-absorbing protection device for processing high-altitude falling stones of geological exploration machine |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN212559093U (en) | Panel lifting frame for construction | |
| CN207192617U (en) | A kind of gantry crane of stable operation | |
| CN204642850U (en) | A kind of wallboard piling bin | |
| CN214615372U (en) | Assembled double-deck construction hanging flower basket | |
| CN210658016U (en) | Trolley for movably dismounting bridge guardrail template | |
| CN110526126A (en) | Adjustable spacing electrical cabinet lifting frame and its handling method | |
| CN104743437A (en) | Electric precipitation anode plate hoisting device | |
| CN209988489U (en) | Product storage is with rack of being convenient for get material | |
| CN207732338U (en) | A kind of substation's cabinet installation hand push frame | |
| CN217128907U (en) | Scaffold frame for building engineering construction convenient to material loading | |
| CN216109906U (en) | Device for replacing and installing curtain wall stone | |
| CN211521340U (en) | Lifting appliance for preventing hanging basket from falling off | |
| CN212387560U (en) | Hoisting device for assembly type building | |
| CN203997408U (en) | Gantry suspension hook storage rack of lifting steel scrap | |
| CN201296597Y (en) | Welded steel fabric hanger | |
| CN215666641U (en) | Turnover supporting seat for hoisting dome structure steel truss | |
| CN213976621U (en) | Auxiliary steel frame for hoisting unit plate from ground | |
| CN219791022U (en) | Door frame moving frame | |
| CN216476426U (en) | Safe platform of unloading for construction | |
| CN212686916U (en) | Automatic charging device for metal sleeves | |
| CN213201482U (en) | Multipurpose glass rack | |
| CN215261157U (en) | A crucible holder for vacuum arc consumable furnace | |
| CN201633014U (en) | Shoulder pole hanger storing frame | |
| CN217518116U (en) | Lifting operation platform for construction of steel structure factory building top layer | |
| CN214217233U (en) | An electric flat car hoisting platform |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20210219 Termination date: 20210531 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |