CN212506117U - Reservoir bottom geomembrane scour prevention water filling structure - Google Patents

Reservoir bottom geomembrane scour prevention water filling structure Download PDF

Info

Publication number
CN212506117U
CN212506117U CN202020504282.XU CN202020504282U CN212506117U CN 212506117 U CN212506117 U CN 212506117U CN 202020504282 U CN202020504282 U CN 202020504282U CN 212506117 U CN212506117 U CN 212506117U
Authority
CN
China
Prior art keywords
water
steel pipe
geomembrane
reservoir
filled steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020504282.XU
Other languages
Chinese (zh)
Inventor
罗书靖
王爱林
薛阳
吴航通
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Huadong Engineering Corp Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Priority to CN202020504282.XU priority Critical patent/CN212506117U/en
Application granted granted Critical
Publication of CN212506117U publication Critical patent/CN212506117U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model provides a reservoir bottom geomembrane scour prevention water filling structure, which comprises a concrete precast block, a geotextile protective layer, a geomembrane, a drainage layer, cement bentonite, a concrete block, a water filling steel pipe and a protective layer; the water-filled steel pipe is arranged in a groove body provided with the water-filled steel pipe at the bottom of the reservoir, the tail end of the water-filled steel pipe is bent upwards to extend out of the reservoir bottom, and a pit is formed at the reservoir bottom near the outlet at the tail end of the water-filled steel pipe; in the tank body, the protective layer is arranged outside the flat pipe section of the water-filled steel pipe, and the anchor blocks are arranged at the bent positions of the tail ends of the water-filled steel pipe; cement bentonite is backfilled in the excavated groove body; paving the drainage layer at the bottom of the warehouse, paving a geomembrane on the drainage layer, and paving a geotextile protective layer and an overlying concrete precast block on the geomembrane in the range of the pits; and the geomembrane is laid along the pits and then anchored at the tail end of the water-filled steel pipe. The utility model discloses simple structure, practicality, reliable can protect the bottom of a reservior geomembrane not receiving to erode filling the water in-process.

Description

Reservoir bottom geomembrane scour prevention water filling structure
Technical Field
A reservoir bottom geomembrane anti-scouring water filling structure is mainly suitable for a seepage prevention system adopting a geomembrane at the reservoir bottom of a pumped storage reservoir, a water conservancy project reservoir, a still water pool and the like.
Background
The geomembrane has the advantages of excellent seepage-proofing performance, quick construction, investment conservation and the like, and is widely applied to seepage-proofing systems for seepage-proofing by adopting the geomembrane at the bottoms of pumped storage reservoirs, water conservancy project reservoirs, water storage pools, still water pools and the like. In a reservoir which cannot store water by natural conditions due to small watershed area or other reasons, an external water source is generally required to be connected for water filling at the initial stage, and water is required to be supplemented during the reservoir operation period. At present, a common water filling structure is formed by embedding a pipeline along a slope surface from top to bottom into a reservoir bottom, a falling water flow is formed at a certain height from an outlet position to the bottom, the centralized water filling can generate a large water flow velocity at the outlet position, and the reservoir bottom is directly washed by the water flow, so that the washing damage to a reservoir bottom geomembrane or other anti-seepage bodies is easily caused.
SUMMERY OF THE UTILITY MODEL
The utility model aims at: aiming at the problems, the geomembrane anti-scouring water filling structure at the bottom of the reservoir is provided and is mainly suitable for an anti-seepage system for seepage prevention by adopting a geomembrane at the bottom of reservoirs such as a pumped storage reservoir, a water conservancy project reservoir, a still water pool and the like.
Therefore, the utility model adopts the following technical scheme:
the utility model provides a bottom of reservior geomembrane scour prevention fills water structure which characterized in that: the concrete waterproof layer comprises a concrete precast block, a geotextile protective layer, a geomembrane, a drainage layer, cement bentonite, a concrete anchor block, a water-filled steel pipe and a protective layer;
the water-filled steel pipe is arranged in a groove body provided with the water-filled steel pipe at the bottom of the reservoir, the tail end of the water-filled steel pipe is bent upwards to extend out of the reservoir bottom, and a pit is formed at the reservoir bottom near the outlet at the tail end of the water-filled steel pipe;
in the tank body, the protective layer is arranged outside the flat pipe section of the water-filled steel pipe, and the anchor blocks are arranged at the bent positions of the tail ends of the water-filled steel pipe; cement bentonite is backfilled in the excavated groove body; paving the drainage layer at the bottom of the warehouse, paving a geomembrane on the drainage layer, and paving a geotextile protective layer and an overlying concrete precast block on the geomembrane in the range of the pits; and the geomembrane is laid along the pits and then anchored at the tail end of the water-filled steel pipe.
Further: the thickness of the ballast block outside each side of the steel pipe is not less than the diameter of the steel pipe.
Further: the range of the geotextile is slightly larger than that of the precast concrete block.
Further: the top elevation of the drainage layer in a certain range around the water filling steel pipe is lower than the bottom elevation of the reservoir, and the drainage layer at the periphery of the pit is connected with the drainage layer at the bottom of the reservoir according to a slope which is slower than 1: 4.
Further: the horizontal section range of the pit is not less than 5 times of the diameter of the water filling pipeline.
Further: the protective layer adopts a reinforced concrete layer.
The utility model discloses a fill the water steel pipe and pierce through behind the reservoir bottom geomembrane, emit rivers from the reservoir bottom steel pipe and distributed inflow reservoir bottom, improved the great problem of centralized water flow velocity of flow that fills, utilize the excavation or reserve pit and form the water blanket, and geomembrane covers protective structure in the pit, avoids rivers directly to erode to prevent that the geomembrane from erodeing and destroying.
Adopt the utility model discloses a scheme, simple structure, practicality, reliable can protect the bottom of a reservior geomembrane not receiving to erode filling the water in-process.
Drawings
Fig. 1 is a schematic cross-sectional view of an embodiment of the present invention.
Detailed Description
Referring to the drawings, the utility model provides a pair of bottom of reservior geomembrane scour protection fills water structure, including concrete prefabricated section 1, geotechnological cloth protective layer 8, geomembrane 2, drainage blanket 3, cement bentonite 4, concrete anchor block 5, fill water steel pipe 6, add reinforced concrete protective layer 7.
The water-filled steel pipe 6 is laid at the bottom of the reservoir, and the tail end of the water-filled steel pipe is bent to be vertical to the horizontal plane and extends out of the reservoir bottom.
Reserve earlier or excavate the cell body and supply to mat formation and fill water steel pipe 6 before laying drainage blanket 3, geomembrane 2, fill water steel pipe 6 at the plain tube section peripheral hardware of storehouse bottom with muscle concrete layer 7 protection, prevent that inhomogeneous settlement from causing the steel pipe atress to destroy, fill 6 terminal curved perpendicular to horizontal planes of water steel pipe, 6 terminal department of bending of water steel pipe sets up anchor block 5 and prevents that rivers from arousing vibrations, anchor block 5 is suitable with not being less than the steel pipe diameter in the thickness of 6 each sides of steel pipe outside.
After the water-filled steel pipe 6, the concrete anchor 5 and the reinforced concrete protective layer 8 are laid, the cement bentonite 4 is backfilled in the excavated groove body, and the problem that the upright edge of the anchor 5 is difficult to roll is solved by utilizing the advantages of high fluidity during construction and certain strength after solidification.
And pouring cement bentonite, laying a drainage layer 3 within the range of laying the geomembrane 2 at the bottom of the reservoir after a certain time interval, wherein the drainage layer 3 can adopt sand gravel or a geotechnical mat (geotextile and geotechnical mesh) and the like. In order to form a pit 9 around the outlet of the water filling steel pipe 6, the top elevation of a drainage layer 3 in a certain range around the water filling steel pipe 6 is 0.4-0.6 m lower than the bottom elevation, the drainage layer at the periphery of the pit 9 is connected with the bottom drainage layer according to a slope which is 1:4 slower, the height of the steel pipe outlet 60 is 1.0m higher than the bottom elevation, and the horizontal section range B of the pit 9 is not less than 5 times of the diameter d of the water filling pipeline.
After the operation is finished, the geomembrane 2 is laid, the geotextile protective layer 8 and the overlying concrete precast block 1 are laid on the geomembrane 2 within the range of the pit 9 and used for protecting the geomembrane from being scoured and damaged by water flow in the water filling process of the reservoir, and the thickness of the geotextile is not less than 400g/m2The thickness of the precast concrete block is preferably 25 cm-40 cm, and the range of the geotextile 8 is slightly larger than that of the precast concrete block 1.
And (3) paving the geomembrane 2 along the pits, and finally anchoring the geomembrane 2 at the tail ends of the water-filled steel pipes 6 by adopting an anchoring structure 10 to prevent leakage. The anchoring structure 10 may employ a stainless steel adjustment clamp.
Of course, the above description is not intended to limit the present invention, and the present invention is not limited to the above examples, and those skilled in the art can change, add or replace the above examples within the scope of the present invention.

Claims (6)

1. The utility model provides a bottom of reservior geomembrane scour prevention fills water structure which characterized in that: the concrete waterproof layer comprises a concrete precast block, a geotextile protective layer, a geomembrane, a drainage layer, cement bentonite, a concrete anchor block, a water-filled steel pipe and a protective layer;
the water-filled steel pipe is arranged in a groove body provided with the water-filled steel pipe at the bottom of the reservoir, the tail end of the water-filled steel pipe is bent upwards to extend out of the reservoir bottom, and a pit is formed at the reservoir bottom near the outlet at the tail end of the water-filled steel pipe;
in the tank body, the protective layer is arranged outside the flat pipe section of the water-filled steel pipe, and the anchor blocks are arranged at the bent positions of the tail ends of the water-filled steel pipe; cement bentonite is backfilled in the excavated groove body; paving the drainage layer at the bottom of the warehouse, paving a geomembrane on the drainage layer, and paving a geotextile protective layer and an overlying concrete precast block on the geomembrane in the range of the pits; and the geomembrane is laid along the pits and then anchored at the tail end of the water-filled steel pipe.
2. The bottom-of-reservoir geomembrane scour prevention water-filling structure according to claim 1, wherein: the thickness of the ballast block outside each side of the steel pipe is not less than the diameter of the steel pipe.
3. The bottom-of-reservoir geomembrane scour prevention water-filling structure according to claim 1, wherein: the range of the geotextile is slightly larger than that of the precast concrete block.
4. The bottom-of-reservoir geomembrane scour prevention water-filling structure according to claim 1, wherein: the top elevation of the drainage layer in a certain range around the water filling steel pipe is lower than the bottom elevation of the reservoir, and the drainage layer at the periphery of the pit is connected with the drainage layer at the bottom of the reservoir according to a slope which is slower than 1: 4.
5. The bottom-of-reservoir geomembrane scour prevention water-filling structure according to claim 1, wherein: the horizontal section range of the pit is not less than 5 times of the diameter of the water filling pipeline.
6. The bottom-of-reservoir geomembrane scour prevention water-filling structure according to claim 1, wherein: the protective layer adopts a reinforced concrete layer.
CN202020504282.XU 2020-04-08 2020-04-08 Reservoir bottom geomembrane scour prevention water filling structure Active CN212506117U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020504282.XU CN212506117U (en) 2020-04-08 2020-04-08 Reservoir bottom geomembrane scour prevention water filling structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020504282.XU CN212506117U (en) 2020-04-08 2020-04-08 Reservoir bottom geomembrane scour prevention water filling structure

Publications (1)

Publication Number Publication Date
CN212506117U true CN212506117U (en) 2021-02-09

Family

ID=74431441

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020504282.XU Active CN212506117U (en) 2020-04-08 2020-04-08 Reservoir bottom geomembrane scour prevention water filling structure

Country Status (1)

Country Link
CN (1) CN212506117U (en)

Similar Documents

Publication Publication Date Title
CN104711994A (en) Foundation pit deep well rainfall and plugging construction method
CN103046565B (en) Draining method for ultra-deep batholith deep foundation pit
CN102535488B (en) Waterproof construction method for bottom plate of high-water-level basement
US11566390B2 (en) Construction method of reclaiming land from the sea based on basement utilization
CN100510281C (en) Semi-inverse construction method of super large diameter, ultra-burial depth storage pond
CN103334450B (en) Construction method of pile precast slab retaining wall with drainage ditch
CN108951649B (en) Foundation pit supporting structure
CN109208545B (en) Construction method of artificial landscape overflow dam with energy dissipation effect
CN104164895A (en) Basement generating no water buoyant force
CN105970882B (en) Solve the structure and its building method of face dam construction time dam body reverse osmosis water problems
CN212506117U (en) Reservoir bottom geomembrane scour prevention water filling structure
CN203475486U (en) Basement producing no water buoyancy
CN113123358B (en) Ship pool deformation prevention and control structure under action of uneven settlement of coal mining and construction method
CN216615890U (en) Novel native side slope protection reinforced structure expands
CN104846837A (en) Construction method for ultra-deep well pit in surface drainage foundation pit
CN114855846A (en) Underground seepage-proofing pressure-reducing anti-floating blind pipe structure and construction method thereof
CN211547830U (en) Structure for preventing ground from being wetted
CN208815550U (en) A kind of rich water powder land floor precipitation and recharge construction system
CN112832288A (en) Anti-floating structure of sloping field building basement and construction method thereof
CN206815381U (en) A kind of tidal land tidal bore area vcehicular tunnel builds structure
CN217923677U (en) Foundation anti-impact structure
CN215165753U (en) Toe board low reaches foundation ditch ponding positive pump drainage facility
CN217150275U (en) High water level weak foundation pit supporting device
CN215857806U (en) Earth work membrane level prevention of seepage membrane underground spring drainage structures down
CN212200440U (en) Water leakage prevention structure for bottom sealing concrete in deep and large foundation pit

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant