CN212371395U CN202020853125.XU CN202020853125U CN212371395U CN 212371395 U CN212371395 U CN 212371395U CN 202020853125 U CN202020853125 U CN 202020853125U CN 212371395 U CN212371395 U CN 212371395U
Authority
CN
China
Prior art keywords
mounting block
welded
pipeline
pipe
argon
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020853125.XU
Other languages
Chinese (zh)
Inventor
岳增义
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Sizhi Gas Co ltd
Original Assignee
Tianjin Sizhi Gas Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Sizhi Gas Co ltd filed Critical Tianjin Sizhi Gas Co ltd
Priority to CN202020853125.XU priority Critical patent/CN212371395U/en
Application granted granted Critical
Publication of CN212371395U publication Critical patent/CN212371395U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Arc Welding In General (AREA)

Abstract

The utility model belongs to the technical field of pipeline welding, in particular to a pipeline plug for argon arc welding, which comprises a pipeline to be welded and a clamping plate, wherein a water-soluble adhesive tape is pasted between the two pipelines to be welded, a welding bead is arranged between the two pipelines to be welded, the left end of the pipeline to be welded is sleeved with a first mounting block, the right end of the pipeline to be welded is sleeved with a second mounting block, the upper surfaces of the first mounting block and the second mounting block are provided with fixed clamping grooves, one side of the first mounting block and one side of the second mounting block are provided with first bolt holes, the pipeline to be welded can be better mounted and ventilated through the first mounting block and the second mounting block, thereby the installation is convenient, the time is saved, and then the argon can be better filled into the pipeline through the argon filling pipe and the exhaust pipe, thereby exhausting other gases.

Description

Pipeline plugging for argon shield welding
Technical Field
The utility model relates to a pipeline welding technology field, concretely relates to be used for argon gas shield welded pipeline shutoff.
Background
Argon gas shielded welding is a welding technique using argon gas as a shielding gas, namely: argon shield gas is introduced around the arc welding to isolate air from the weld zone, thereby preventing oxidation of the welding material. Therefore, non-ferrous metals such as stainless steel and aluminum can be welded.
At present, when welding by argon arc welding, the non-welding ends of two pipelines to be welded are usually sealed by water-soluble paper, and then the two pipelines which are butted are filled with argon to be used as protective gas for welding. Because a large amount of argon is required to be filled in the pipeline to be welded, the replacement time of the argon and air is long, and the required amount of the argon is far greater than the capacity in the actual sealing chamber, a large amount of argon is consumed, the production cost is increased, and the welding efficiency is reduced.
SUMMERY OF THE UTILITY MODEL
For solving the problem that provides in the above-mentioned background art, the utility model provides a be used for argon gas protection welded pipeline shutoff, through the first installation piece that is equipped with and second installation piece can be better to waiting to weld the pipeline installation ventilate to make simple to operate, save time, then can be better through the argon gas pipe and the blast pipe that fill that are equipped with fill argon gas to pipeline inside, thereby with other gaseous dischargings.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a pipeline shutoff for argon gas shielded welding, includes treats welded pipe and cardboard, two it has water-soluble sticky tape to wait to paste between the welded pipe, two it is provided with the welding bead to wait to be provided with between the welded pipe, the left end cover of waiting to weld the pipe has first installation piece, the right-hand member of treating the welded pipe has cup jointed the second installation piece, fixed slot has been seted up to the upper surface of first installation piece and second installation piece, first bolt hole has been seted up to one side of first installation piece and second installation piece, the opposite side fixedly connected with cover post of first installation piece and second installation piece, the bottom fixedly connected with high temperature resistant flexible material of cover post, the middle through connection of first installation piece and cover post has the gas tube, the middle through connection of second installation piece and cover post has the blast pipe.
In order to better fix the inserted clamping plate, the pipe plugging for argon protection welding of the embodiment is preferably as follows: a second bolt hole is formed in the surface of one side of the clamping plate.
In order to better improve the tightness of the device, the pipe plugging for argon arc welding of the embodiment is preferably as follows: the first mounting block and the second mounting block are fixedly connected with a sealing ring at the position fixedly connected with the sleeve joint column.
In order to better enable the introduction and discharge of argon and gas, the pipe plugging for argon arc welding of the present embodiment is preferably: the argon charging pipe and the exhaust pipe are both soft pipe materials.
In order to be able to carry out the card through the cardboard with filling argon gas pipe and blast pipe and hinder, this embodiment is a pipeline shutoff that is used for argon gas protection welding is preferred: the clamping plate is vertically inserted into the fixed clamping groove and is just matched with the fixed clamping groove.
In order to better connect the pipeline to be welded with the first mounting block and the second mounting block, the pipeline plugging for argon protection welding of the embodiment is preferably as follows: the first mounting block and the second mounting block are the same in size and shape.
Compared with the prior art, the beneficial effects of the utility model are that:
1. this kind of be used for argon gas protection welded pipeline shutoff, through first installation piece and the second installation piece that is equipped with can be better will treat that welded tube seals, then will treat that welded tube is inside to aerify through filling the argon gas pipe, then will inside other gas outgoing through the blast pipe to make the inflation time reduce, also saved the use amount of argon gas simultaneously.
2. This kind of be used for argon gas protection welded pipeline shutoff, can be better through the cardboard that is equipped with will fill argon gas pipe and blast pipe and carry out the card and hinder to prevent argon gas diffusion everywhere, made its can be better at the welded in-process carry out the guard action.
Drawings
The accompanying drawings are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description serve to explain the invention and not to limit the invention.
In the drawings:
FIG. 1 is an overall structure diagram of a pipeline plugging for argon arc welding according to the present invention;
FIG. 2 is a cross-sectional view of a pipe plugging for argon arc welding according to the present invention;
FIG. 3 is a structural diagram of a pipe plugging fixture block for argon arc welding of the present invention;
FIG. 4 is an enlarged view of the pipeline plug A for argon arc welding of the present invention;
in the figure, 1, a pipe to be welded; 2. water soluble adhesive tape; 3. a first mounting block; 4. a second mounting block; 5. filling an argon pipe; 6. an exhaust pipe; 7. fixing the clamping groove; 8. a first bolt hole; 9. welding a bead; 10. a high temperature resistant flexible material; 11. sleeving the column; 12. a seal ring; 13. clamping a plate; 14. a second bolt hole.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
In the description of the present invention, it is to be understood that the terms "length", "width", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", and the like indicate orientations or positional relationships based on those shown in the drawings, and are merely for convenience of description and simplicity of description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, should not be construed as limiting the present invention. In addition, in the description of the present invention, "a plurality" means two or more unless specifically limited otherwise.
Referring to fig. 1-4, the present invention provides the following technical solutions: the utility model provides a pipeline shutoff for argon gas shielded welding, including treating welded pipe 1 and cardboard 13, it has water soluble adhesive tape 2 to paste between the welded pipe 1 to treat for two, it is provided with welding bead 9 to treat for two between the welded pipe 1, the left end that treats welded pipe 1 has cup jointed first installation piece 3, the right-hand member that treats welded pipe 1 has cup jointed second installation piece 4, fixed slot 7 has been seted up to the upper surface of first installation piece 3 and second installation piece 4, first bolt hole 8 has been seted up to one side of first installation piece 3 and second installation piece 4, the opposite side fixedly connected with cover post 11 of first installation piece 3 and second installation piece 4, the bottom fixedly connected with high temperature resistant flexible material 10 of post 11 cup joints, the middle through connection of first installation piece 3 and cover post 11 has the argon gas pipe 5 that fills, second installation piece 4 and the middle through connection of cup jointing post 11 have blast pipe 6.
In the embodiment, the middle of the pipeline 1 to be welded is pasted through the water soluble adhesive tape 2, then the first mounting block 3 and the second mounting block 4 are sleeved and mounted at the two ends of the pipeline 1 to be welded, then a sealed space is formed for the inner part of the pipeline 1 to be welded through a sleeving column 11 connected with the bottoms of the first mounting block 3 and the second mounting block 4, then argon is introduced into the interior and the internal air is discharged through an argon charging pipe 5 and an exhaust pipe 6 connected between the first mounting block 3 and the second mounting block 4, when the argon is filled in the pipeline 1 to be welded, the argon filling pipe 5 and the exhaust pipe 6 are blocked by the clamping plate 13 through the fixed clamping groove 7, so that the argon is prevented from flowing out, then weld, after the welding is accomplished, wait for the splice to take out cardboard 13 after cooling to discharge argon gas, then with first installation piece 3 and second installation piece 4 dismantle retrieve can.
As a technical optimization scheme of the utility model, second bolt hole 14 has been seted up to a side surface of cardboard 13.
In this embodiment, the second bolt hole 14 is opened on one side surface of the card 13 to fix the inserted card 13 better.
As a technical optimization scheme of the utility model, first installation piece 3 and second installation piece 4 and the local fixedly connected with sealing ring 12 who cup joints post 11 fixed connection.
In this embodiment, the sealing rings 12 are fixedly connected to the positions where the first mounting block 3 and the second mounting block 4 are fixedly connected to the socket post 11, so as to improve the sealing performance of the device.
As a technical optimization scheme of the utility model, fill argon gas pipe 5 and blast pipe 6 and be soft tube material.
In the present embodiment, the argon gas-filled pipe 5 and the exhaust pipe 6 are both made of a flexible pipe material in order to allow the introduction and discharge of argon gas and gas to be performed more efficiently.
As a technical optimization scheme of the utility model, cardboard 13 inserts perpendicularly in fixed slot 7 and cardboard 13 just is identical with fixed slot 7.
In this embodiment, the clamping plate 13 is vertically inserted into the fixing slot 7, and the clamping plate 13 is just matched with the fixing slot 7 so as to block the argon charging pipe 5 and the exhaust pipe 6 through the clamping plate 13.
As a technical optimization scheme of the utility model, the size shape of first installation piece 3 and second installation piece 4 is the same.
In the present embodiment, the first mounting block 3 and the second mounting block 4 have the same size and shape so as to better connect the pipe 1 to be welded with the first mounting block 3 and the second mounting block 4.
The utility model discloses a theory of operation and use flow: firstly, pasting the middle of a pipeline 1 to be welded through a water soluble adhesive tape 2, then sleeving and installing a first installation block 3 and a second installation block 4 at the two ends of the pipeline 1 to be welded, then a sealed space is formed for the inner part of the pipeline 1 to be welded through a sleeving column 11 connected with the bottoms of the first mounting block 3 and the second mounting block 4, then argon is introduced into the interior and the internal air is discharged through an argon charging pipe 5 and an exhaust pipe 6 connected between the first mounting block 3 and the second mounting block 4, when the argon is filled in the pipeline 1 to be welded, the argon filling pipe 5 and the exhaust pipe 6 are blocked by the clamping plate 13 through the fixed clamping groove 7, so that the argon is prevented from flowing out, then weld, after the welding is accomplished, wait for the splice to take out cardboard 13 after cooling to discharge argon gas, then with first installation piece 3 and second installation piece 4 dismantle retrieve can.
The above description is only exemplary of the present invention and should not be construed as limiting the present invention, and any modifications, equivalents and improvements made within the spirit and principles of the present invention are intended to be included within the scope of the present invention.

Claims (6)

1. The utility model provides a pipeline shutoff for argon gas shielded welding, includes to weld pipeline (1) and cardboard (13), its characterized in that: a water soluble adhesive tape (2) is pasted between the two pipelines to be welded (1), a welding bead (9) is arranged between the two pipelines to be welded (1), a first mounting block (3) is sleeved at the left end of the pipeline to be welded (1), a second mounting block (4) is sleeved at the right end of the pipeline to be welded (1), a fixed clamping groove (7) is formed in the upper surfaces of the first mounting block (3) and the second mounting block (4), a first bolt hole (8) is formed in one side of the first mounting block (3) and one side of the second mounting block (4), a sleeving column (11) is fixedly connected to the other side of the first mounting block (3) and the second mounting block (4), a high-temperature resistant flexible material (10) is fixedly connected to the bottom end of the sleeving column (11), and an inflation pipe (5) is penetratingly connected between the first mounting block (3) and the sleeving column (11), and an exhaust pipe (6) is connected between the second mounting block (4) and the sleeving connection column (11) in a penetrating manner.
2. The pipe stopper for argon arc welding of claim 1, wherein: and a second bolt hole (14) is formed in the surface of one side of the clamping plate (13).
3. The pipe stopper for argon arc welding of claim 1, wherein: and the first mounting block (3) and the second mounting block (4) are fixedly connected with a sealing ring (12) at the position fixedly connected with the sleeving connection column (11).
4. The pipe stopper for argon arc welding of claim 1, wherein: the argon charging pipe (5) and the exhaust pipe (6) are both soft pipe materials.
5. The pipe stopper for argon arc welding of claim 1, wherein: the clamping plate (13) is vertically inserted into the fixed clamping groove (7) and the clamping plate (13) is exactly matched with the fixed clamping groove (7).
6. The pipe stopper for argon arc welding of claim 1, wherein: the first mounting block (3) and the second mounting block (4) are the same in size and shape.
CN202020853125.XU 2020-05-20 2020-05-20 Pipeline plugging for argon shield welding Expired - Fee Related CN212371395U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020853125.XU CN212371395U (en) 2020-05-20 2020-05-20 Pipeline plugging for argon shield welding

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020853125.XU CN212371395U (en) 2020-05-20 2020-05-20 Pipeline plugging for argon shield welding

Publications (1)

Publication Number Publication Date
CN212371395U true CN212371395U (en) 2021-01-19

Family

ID=74177218

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020853125.XU Expired - Fee Related CN212371395U (en) 2020-05-20 2020-05-20 Pipeline plugging for argon shield welding

Country Status (1)

Country Link
CN (1) CN212371395U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112872702A (en) * 2021-01-25 2021-06-01 天津建工城市建设发展有限公司 Sanitary seamless stainless steel pipe welding auxiliary device and construction method thereof
CN113042854A (en) * 2021-05-07 2021-06-29 郑州宇通重工有限公司 Titanium alloy pipe fitting welding method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112872702A (en) * 2021-01-25 2021-06-01 天津建工城市建设发展有限公司 Sanitary seamless stainless steel pipe welding auxiliary device and construction method thereof
CN113042854A (en) * 2021-05-07 2021-06-29 郑州宇通重工有限公司 Titanium alloy pipe fitting welding method

Similar Documents

Publication Publication Date Title
CN212371395U (en) Pipeline plugging for argon shield welding
CN201102129Y (en) Argon-in tube protection energy conservation equipment
CN202622210U (en) Argon filling shielded welding pipeline plugging device
CN220506155U (en) A variable diameter gas shielded welding sealing device
CN214444020U (en) Stainless steel pipeline welding argon filling device
CN210266394U (en) Leakage repairing device and leakage repairing system
CN209414877U (en) A kind of composite pipe structure with protective device
CN215999187U (en) Be used for zirconium material pipeline welding argon filling protection device
CN208304209U (en) A kind of medium-large caliber stainless steel tube back side argon-filling device
CN212652856U (en) Gas protection cover for welding inner hole of heat transfer pipe and pipe plate
CN214769605U (en) Secondary is joined in marriage nonrust steel pipe welding inert gas protection device
CN202423497U (en) Box used for containing sodium and sodium-sulfur (NaS) battery
CN205350675U (en) Heat sink condenser tube's connection structure
CN214558512U (en) Circumferential weld surrounds protection device entirely
CN209762545U (en) Plugging cap and plugging device for natural gas pipeline leakage
CN217045187U (en) Head welding position frock
CN218494465U (en) Low temperature pipeline's leakproofness detection device
CN204430539U (en) A kind of caisson for pipeline welding
CN209725601U (en) A kind of welder of leak repairing point with pressure
CN211925075U (en) Strength layer pressure test joint
CN215218152U (en) Closed sampling device of sodium-cooled fast reactor sodium valve
CN210306364U (en) Duckbilled argon filling device for welding
CN202655773U (en) Back surface argon filling device for welding of stainless steel pipe of boiler
CN209830685U (en) Protective gas aerating device and aerating component during metal welding
CN224210585U (en) Non-metallic pipe welding device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210119