CN212249325U - Jack unloading support device - Google Patents
Jack unloading support device Download PDFInfo
- Publication number
- CN212249325U CN212249325U CN202021407433.6U CN202021407433U CN212249325U CN 212249325 U CN212249325 U CN 212249325U CN 202021407433 U CN202021407433 U CN 202021407433U CN 212249325 U CN212249325 U CN 212249325U
- Authority
- CN
- China
- Prior art keywords
- jack
- unloading
- support
- joist
- column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本实用新型涉及一种千斤顶卸载支撑装置,包括支座和千斤顶,千斤顶固接在支座上,支座下端与底板固接,千斤顶上端设托梁,支座左右两侧固接立柱,立柱下端与底板固接;立柱上端顶面设有卸载垫板,卸载垫板顶面与千斤顶顶部等高,卸载垫板由若干钢板层叠而成,顶层钢板和千斤顶一起与托梁底面相连;托梁两端设贯穿孔,贯穿孔中安装定位杆;定位杆下端与立柱固接一体,上端安装压紧螺母,此装置用于大型构件支撑卸载,高度校正,其结构稳定,安全性高、成本低、操作简单,可以多次循环使用。
The utility model relates to a jack unloading support device, comprising a support and a jack. The jack is fixedly connected to the support, the lower end of the support is fixedly connected to the bottom plate, the upper end of the jack is provided with a joist, the left and right sides of the support are fixedly connected to a vertical column, and the lower end of the vertical column Fixed connection with the bottom plate; there is an unloading pad on the top surface of the upper end of the column, the top surface of the unloading pad is the same height as the top of the jack, the unloading pad is made of several steel plates stacked, and the top steel plate and the jack are connected to the bottom surface of the joist together; There is a through hole at the end, and a positioning rod is installed in the through hole; the lower end of the positioning rod is fixedly connected with the column, and the upper end is equipped with a compression nut. This device is used for supporting and unloading of large components, and height correction. The operation is simple and can be used repeatedly.
Description
技术领域technical field
本实用新型属于建筑工程领域,具体涉及一种千斤顶卸载支撑装置。The utility model belongs to the field of construction engineering, in particular to a jack unloading support device.
背景技术Background technique
当今社会随着人们对建筑功能要求越来越高,为了满足建筑外观和功能的需要,需要将建筑设计成大空间、大跨度、大悬挑的结构,由于整个结构有许多变形缝、沉降缝,需要根据变形缝每三榀桁架进行安装、卸载;而结构安装完成或达到设计要求前,需要采用临时支撑卸载装置作为安装时的临时支撑,待结构施工完毕后进行卸载、拆除支撑装置;当今施工最为常用的有支撑胎架切割技术,采用此种方法,在制作、安装、拆除过程中,工作量大、不利于节省材料,且操作危险高。In today's society, as people's requirements for building functions are getting higher and higher, in order to meet the needs of building appearance and function, it is necessary to design the building into a large space, large span, and large cantilever structure. Because the entire structure has many deformation joints, settlement joints , it is necessary to install and unload every three trusses according to the deformation joint; and before the structural installation is completed or the design requirements are met, a temporary support and unloading device needs to be used as a temporary support during installation, and the unloading and dismantling of the support device after the construction of the structure is completed; The most commonly used technology in construction is the cutting technology of the support tire frame. Using this method, in the process of production, installation and dismantling, the workload is large, which is not conducive to saving materials, and the operation is dangerous.
还有采用液压千斤顶及计算机同步控制系统进行卸载,此种方法虽然比较安全,但使用费用高,增加项目成本,而对于小范围的桁架卸载不适用。传统切割卸载安全性差,传统施工需要投入较多的技术措施,操作复杂,需要消耗大量氧气、乙炔能源,成本高。There are also hydraulic jacks and computer synchronous control systems for unloading. Although this method is relatively safe, it has high usage costs and increases project costs, and is not suitable for small-scale truss unloading. Traditional cutting and unloading have poor safety. Traditional construction requires a lot of technical measures, complicated operation, a large amount of oxygen and acetylene energy consumption, and high cost.
发明内容SUMMARY OF THE INVENTION
本实用新型要解决的技术问题是现有技术中空间大跨度悬臂构件安装和卸载施工安全性差,施工成本高的问题。The technical problem to be solved by the utility model is the problems of poor construction safety and high construction cost in the prior art for the installation and unloading of the large-span cantilever member.
针对现有技术中施工的缺陷,本发明提供的解决方案是:For the defects of construction in the prior art, the solution provided by the present invention is:
一种千斤顶卸载支撑装置,包括支座和千斤顶,千斤顶固接在支座上,支座下端与底板固接,千斤顶上端设托梁,支座左右两侧固接立柱,立柱下端与底板固接;立柱上端顶面设有卸载垫板,卸载垫板顶面与千斤顶顶部等高,卸载垫板由若干钢板层叠而成,顶层钢板和千斤顶一起与托梁底面相连;托梁两端设贯穿孔,贯穿孔中安装定位杆;定位杆下端与立柱固接一体,上端安装压紧螺母。A jack unloading support device includes a support and a jack, the jack is fixed on the support, the lower end of the support is fixed with the bottom plate, the upper end of the jack is provided with a joist, the left and right sides of the support are fixed with a column, and the lower end of the column is fixed with the bottom plate ;The top surface of the upper end of the column is provided with an unloading pad, the top surface of the unloading pad is the same height as the top of the jack, the unloading pad is formed by stacking several steel plates, and the top steel plate and the jack are connected to the bottom surface of the joist together; the two ends of the joist are provided with through holes , the positioning rod is installed in the through hole; the lower end of the positioning rod is fixedly connected with the column, and the upper end is installed with a compression nut.
此装置用于大型构件支撑卸载,高度校正,其结构稳定,安全性高、成本低、操作简单,可以多次循环使用。The device is used for supporting and unloading large components, height correction, stable structure, high safety, low cost, simple operation, and can be used repeatedly.
千斤顶为手动螺旋式千斤顶。The jack is a manual screw jack.
支座前后两侧设斜支撑,斜支撑下端与底板固接。The front and rear sides of the support are provided with inclined supports, and the lower ends of the inclined supports are fixedly connected with the bottom plate.
立柱为H型钢立柱,H型钢立柱顶部固接立柱顶板,所述卸载垫板设有立柱顶板上面。The column is an H-shaped steel column, the top of the H-shaped steel column is fixedly connected to the column top plate, and the unloading backing plate is provided on the column top plate.
托梁上设有托梁定位板,托梁定位板设有与构件形状匹配的槽。The joist is provided with a joist positioning plate, and the joist positioning plate is provided with a groove matching the shape of the component.
附图说明Description of drawings
图1为本发明的结构示意图;Fig. 1 is the structural representation of the present invention;
图2为卸载支撑装置操作工况一;Figure 2 is the first operating condition of the unloading support device;
图3为卸载支撑装置操作工况二;Figure 3 shows the second operating condition of the unloading support device;
图4为卸载支撑装置操作工况三;Figure 4 shows the third operating condition of the unloading support device;
图中:托梁1;千斤顶2;支座3;支座顶板301;底板4;立柱5;立柱顶板501;卸载垫板6;定位杆7;托梁定位板8;斜支撑9;构件10;压紧螺母11。In the figure:
具体实施方式Detailed ways
下面将结合附图对本实用新型的技术方案进行清楚、完整地描述,显然,所描述的实施例是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are a part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative work fall within the protection scope of the present invention.
如图1至图4所示,一种千斤顶卸载支撑装置,包括支座3和千斤顶2,千斤顶2固接在支座3上,支座3下端与底板4固接,千斤顶2上端设托梁1,支座3左右两侧固接立柱5,立柱5下端与底板4固接;立柱5上端顶面设有卸载垫板6,卸载垫板6由若干钢板层叠而成,卸载垫板6顶面与千斤顶2顶部等高;托梁1两端设贯穿孔,贯穿孔中安装定位杆7;定位杆7下端与立柱5固接一体,上端安装压紧螺母11。As shown in Figures 1 to 4, a jack unloading support device includes a
所述支座3为H型钢,为方便安装千斤顶,支座3顶部固接支座顶板301。本发明的千斤顶2为手动螺旋式千斤顶,它放置在支座顶板301上部。The
同样的支座两侧的立柱5也可以采用H型钢,顶部固接立柱顶板501,卸载垫板设6在立柱顶板501上,卸载垫板6的各钢板层叠式的放置在立柱顶板501上。Similarly, the
立柱5与支座3焊接一体。The
支座3前后两侧设斜支撑9,斜支撑9选用槽钢,槽钢下端与底板4焊接,上端支座3焊接。The front and rear sides of the
为了在构件支撑过程中保证构件稳定,托梁1上设置托梁定位板8,托梁定位板8设有与构件10形状匹配的槽。若需要施工的钢管桁架,该槽为弧形槽;若需要施工的是H型钢桁架,该槽则为方形槽。In order to ensure the stability of the component during the component supporting process, a
本发明定位杆7是防止托梁1偏移的定位结构,实质为托梁高度调整时的导向杆,托梁1上开制的贯穿孔应大于定位杆7,以便于托梁1高度调整时可以顺利移动,所述托梁1两端的贯穿孔直径大于定位杆7直径1-2mm。托梁1位置确定后通过压紧螺母11固定。The
本发明所述卸载垫板6为叠放在一起的若干片钢板的总称。本发明千斤顶2支撑在托梁1的中点上,卸载垫板6支撑托梁1两侧,从而保持托梁1支撑的平稳。卸载垫板6的各层钢板大小为长200mm*宽100*厚8~20mm,数量根据支撑高度在操作时随时调整。The unloading
本发明的托梁1采用两槽钢焊接成箱型,内部可以设置加劲板。托梁1设置在两侧立柱5上的卸载垫板6以及千斤顶2上,可以使托梁1与千斤顶2相连,也可以是放置在千斤顶顶部而不设计连接结构及连接构件。The
此装置用于大型构件支撑卸载,高度校正,结构稳定,使用安全,制成本低,容易操作,可循环使用。This device is used for support and unloading of large components, height correction, stable structure, safe use, low cost, easy operation, and can be recycled.
采用上述千斤顶卸载支撑装置进行桁架安装定位的施工方法:The construction method for truss installation and positioning using the above-mentioned jack unloading support device:
步骤一:在卸载单元的桁架端部构件下各卸载点位置分别设置一个卸载支撑装置;Step 1: Install an unloading support device at each unloading point position under the truss end member of the unloading unit;
步骤二:根据设计提供的结构桁架卸载的下挠值,确定托梁的安装标高;Step 2: Determine the installation elevation of the joist according to the deflection value of the unloaded structural truss provided by the design;
步骤三:根据托梁定位板的位置,调整千斤顶顶升高度以及两侧立柱上的垫板高度,待托梁定位板到设计标高时,拧紧两侧定位杆上的压紧螺母将托梁固定;Step 3: According to the position of the joist positioning plate, adjust the height of the jack and the height of the backing plate on the columns on both sides. When the joist positioning plate reaches the design level, tighten the compression nuts on the positioning rods on both sides to fix the joists. ;
步骤四,吊装桁架分别放置到各卸载支撑装置上,并再次对卸载支撑装置的定位进行微调,直至桁架达到设计标高后,进行桁架结构安装;Step 4: The hoisting trusses are respectively placed on each unloading support device, and the positioning of the unloading support device is fine-tuned again until the truss reaches the design elevation, and then the truss structure is installed;
步骤五:待桁架结构施工完毕后,开始桁架卸载,卸载将分步等距进行,三个千斤顶先同步稍微顶起,同时抽取一层垫板,然后再将三个千斤顶同步缓慢回落,每次回落位移为10mm,千斤顶每卸载一个行程将垫板拿掉一块,回落后停止2分钟,检查千斤顶、支座以及桁架的情况,回落过程中严格控制千斤顶的同步性;Step 5: After the construction of the truss structure is completed, start the unloading of the truss. The unloading will be carried out step by step and at equal intervals. The three jacks will be lifted up slightly at the same time, and a layer of backing plate will be extracted at the same time, and then the three jacks will be slowly lowered synchronously. The fallback displacement is 10mm, and the backing plate is removed for each unloading stroke of the jack. After falling back, stop for 2 minutes to check the condition of the jack, the support and the truss, and strictly control the synchronization of the jack during the fallback process;
步骤六:当桁架处于自由状态,则停止卸载,测量并记录桁架端部尺寸。Step 6: When the truss is in a free state, stop unloading, measure and record the dimensions of the end of the truss.
下面结合具体施工实例对本实用新型详细说明,本实施例具体操作过程如下:The present utility model is described in detail below in conjunction with specific construction examples, and the specific operation process of the present embodiment is as follows:
1)根据设计提供的结构桁架卸载的下挠值,确定卸载支撑架的安装标高,通过全站仪测控托梁定位板。1) Determine the installation elevation of the unloading support frame according to the unloading deflection value of the structural truss provided by the design, and measure and control the joist positioning plate through the total station.
2)根据托梁定位板的位置,调整本支撑装置的两个立柱上的垫板层数及螺旋式千斤顶顶升长度,待托梁定位板达到设计标高时,拧紧压紧螺母固定托梁,如图2示。2) According to the position of the joist positioning plate, adjust the number of layers of backing plates on the two uprights of the support device and the lifting length of the screw jack. When the joist positioning plate reaches the design elevation, tighten the compression nut to fix the joist. As shown in Figure 2.
3)重复上述两个步骤,完成其它桁架卸载支撑装置的安装定位。3) Repeat the above two steps to complete the installation and positioning of other truss unloading support devices.
4)成立卸载小组,卸载由总指挥统一指挥,采用对讲机。现场操作管理人员按区域划分,每个卸载点设2或3名操作人员,管理人员每人负责1个卸载点,各自对卸载点进行观测,如有问题及时与指挥人员联系。4) Set up an unloading team, and unloading is under the unified command of the commander-in-chief, using walkie-talkies. The on-site operation and management personnel are divided by area. Each unloading point is set up with 2 or 3 operators. Each manager is responsible for one unloading point.
5)在千斤顶上划出下移刻度线,刻度线每格10mm,将千斤顶缓慢回落,每次回落位移为10mm,回落过程中严格控制卸载垫板与千斤顶高度的同步性。回落后停止2分钟,检查千斤顶、支座及桁架的情况,千斤顶每卸载一个行程(10mm第一个行程)将垫板拿掉一层,调整结合图3所示。在整个卸载过程中,如果千斤顶发生意外,两侧的临时垫板可以支撑桁架下托架,起到保护作用。5) Draw a downward movement scale line on the jack, the scale line is 10mm per grid, and the jack is slowly lowered, and the displacement is 10mm each time. Stop for 2 minutes after falling back, and check the condition of the jack, the support and the truss. Every time the jack is unloaded for one stroke (the first stroke of 10mm), remove one layer of the backing plate, and adjust as shown in Figure 3. During the whole unloading process, if there is an accident with the jack, the temporary pads on both sides can support the lower bracket of the truss and play a protective role.
6)如图4所示,卸载直至桁架处于自由状态,则停止卸载。测量并记录桁架端部尺寸,在此过程中注意观察千斤顶及桁架的变化,如发生异样,应立即停止。6) As shown in Figure 4, unload until the truss is in a free state, then stop unloading. Measure and record the dimensions of the end of the truss. During this process, pay attention to observe the changes of the jack and the truss. If any abnormality occurs, it should be stopped immediately.
最后:重复前面实施过程,直至结构全部施工完成。Finally: Repeat the previous implementation process until the construction of the structure is completed.
本实用新型适用于空间大悬臂钢管桁架结构的安装卸载施工,解决传统切割卸载安全性差的问题,采用本实用新型方法卸载施工安全性高,施工投入少,支撑装置可以循环多次使用,更重要的是能够减少施工中技术措施的投入,节约氧气、乙炔能源、节约成本。The utility model is suitable for the installation and unloading construction of the large space cantilever steel pipe truss structure, and solves the problem of poor safety in the traditional cutting and unloading. The method of the utility model has high unloading construction safety, less construction investment, and the supporting device can be used repeatedly for many times. More important The most important thing is to reduce the investment in technical measures during construction, save oxygen, acetylene energy, and save costs.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202021407433.6U CN212249325U (en) | 2020-07-16 | 2020-07-16 | Jack unloading support device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202021407433.6U CN212249325U (en) | 2020-07-16 | 2020-07-16 | Jack unloading support device |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN212249325U true CN212249325U (en) | 2020-12-29 |
Family
ID=73980832
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202021407433.6U Active CN212249325U (en) | 2020-07-16 | 2020-07-16 | Jack unloading support device |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN212249325U (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN111719892A (en) * | 2020-07-16 | 2020-09-29 | 中国二十二冶集团有限公司 | Jack unloading support device and method of using the same |
| CN117145214A (en) * | 2023-07-31 | 2023-12-01 | 上海二十冶建设有限公司 | A method for unloading the grid ball hinge support |
-
2020
- 2020-07-16 CN CN202021407433.6U patent/CN212249325U/en active Active
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN111719892A (en) * | 2020-07-16 | 2020-09-29 | 中国二十二冶集团有限公司 | Jack unloading support device and method of using the same |
| CN111719892B (en) * | 2020-07-16 | 2024-05-14 | 中国二十二冶集团有限公司 | Use method of jack unloading supporting device |
| CN117145214A (en) * | 2023-07-31 | 2023-12-01 | 上海二十冶建设有限公司 | A method for unloading the grid ball hinge support |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN111719892A (en) | Jack unloading support device and method of using the same | |
| CN100549344C (en) | Adhered self-lifting highrise operation platform | |
| CN112049235A (en) | High-altitude and large-span cantilever structure construction platform and method | |
| CN217629489U (en) | Broken column jacking heightening and shaping combined hoop supporting system | |
| CN210086491U (en) | Supporting device is strengthened in building jacking control | |
| CN219175034U (en) | Bridge staple bolt construction braced system | |
| CN201110804Y (en) | Multifunctional test stand | |
| CN111364741A (en) | Construction process for integrally moving disc buckle type full-hall support | |
| CN110203856A (en) | A kind of hydraulic device of pair of supporting frame with steel structure unloading | |
| CN221920349U (en) | Steel structure hydraulic synchronous unloading tool | |
| CN212583217U (en) | Reduce damaged frame support built-in fitting that climbs of side fascia | |
| CN218881711U (en) | Do not need to return top conversion bearing structure | |
| CN202831628U (en) | Combined type bailey frame load-bearing shelving for pouring large span concrete beam | |
| CN202804054U (en) | Built-in truss based on providing support during process of installing C-shaped plate | |
| CN101774516B (en) | Lifting device and construction method for replacing rake crane bridge | |
| CN108331341A (en) | A kind of formwork support method and device of large size conversion beam | |
| CN112392261A (en) | Construction method for stably converting support system after slippage of large-span steel roof is completed | |
| CN116062650A (en) | A Whole Jacking Compensator for Large Metal Grid Frame | |
| CN206942191U (en) | A kind of temporary support of telescopic in height regulation reinforces combination steel construction | |
| CN212249280U (en) | Embedded part supporting device | |
| CN212562432U (en) | A connecting device for automatic lifting scaffolding | |
| CN221920290U (en) | A limit anti-deflection and anti-twist device used in modular low-position lifting steel platform formwork system | |
| CN202220438U (en) | Supporting system for steel formwork of diving platform | |
| CN208267371U (en) | A kind of mould plate supporting device of large size conversion beam | |
| CN207276133U (en) | A kind of jacking apparatus |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant |
