CN212247875U - Stand construction equipment - Google Patents

Stand construction equipment Download PDF

Info

Publication number
CN212247875U
CN212247875U CN202020041199.3U CN202020041199U CN212247875U CN 212247875 U CN212247875 U CN 212247875U CN 202020041199 U CN202020041199 U CN 202020041199U CN 212247875 U CN212247875 U CN 212247875U
Authority
CN
China
Prior art keywords
construction equipment
equipment according
standard section
stand
platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020041199.3U
Other languages
Chinese (zh)
Inventor
许青宏
何昌连
孙银鹏
杨祺焜
茅能德
傅珺
胡家锡
吴永敏
谢圣浩
张存才
张波
王杰昌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hongrun Construction Group Co Ltd
Original Assignee
Hongrun Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hongrun Construction Group Co Ltd filed Critical Hongrun Construction Group Co Ltd
Priority to CN202020041199.3U priority Critical patent/CN212247875U/en
Application granted granted Critical
Publication of CN212247875U publication Critical patent/CN212247875U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Ladders (AREA)

Abstract

The utility model discloses a stand construction equipment relates to engineering construction field. One embodiment of the column construction equipment includes: the operation platform is a horizontal supporting platform; the standard section template is a vertical steel support frame, and the operating platform is fixed at the upper end of the standard section template; the upper end and the lower end of the adjacent standard section templates are fixedly connected; the ladder stand is fixed on the outer side of the standard section formwork. The utility model discloses an in the stand work progress, cancelled the help of scaffold frame, ladder cage, car of ascending a height, realized that the stand does not have the scaffold frame construction that falls to the ground, consequently fine promotion economic benefits and progress benefit.

Description

Stand construction equipment
Technical Field
The utility model relates to an engineering construction field especially relates to a stand construction equipment.
Background
With the development of social economy, the technical process is also continuously innovated and improved. More and more upright posts are constructed by adopting a non-floor scaffold. The construction of the bridge stand column without the floor scaffold has the advantages of obviously shortening the construction period, reducing risks, reducing labor, improving work efficiency and the like, and the construction efficiency of the bridge stand column can be effectively improved. The existing construction without the floor scaffold mainly integrates the traditional scaffold erecting and formwork erecting processes, adopts formwork integration, and adds an operation platform on a top section formwork for concrete pouring construction operation.
SUMMERY OF THE UTILITY MODEL
In view of this, the embodiment of the utility model provides a stand construction equipment can cancel scaffold frame, ladder cage, the help of ascending a height car in the stand work progress, has realized that the stand does not have the scaffold frame construction that falls to the ground, consequently fine promotion economic benefits and progress benefit.
To achieve the above object, according to an aspect of the embodiment of the present invention, there is provided a column construction apparatus.
The utility model discloses stand construction equipment includes: the operation platform is a horizontal supporting platform; the standard section template is a vertical steel support frame, and the operating platform is fixed at the upper end of the standard section template; the upper end and the lower end of the adjacent standard section templates are fixedly connected; the ladder stand is fixed on the outer side of the standard section formwork.
Optionally, the operating platform is formed by machining and welding 8# channel steel and is connected to the periphery of the upper end of the standard section template through bolts.
Optionally, a steel mesh is laid on the bottom surface of the operating platform, and a guardrail is detachably connected to the periphery of the operating platform.
Optionally, the guardrail is a vertically arranged mesh; and/or the height of the guardrail is 1.2 meters.
Optionally, the standard segment formwork is a 4-piece column structure.
Optionally, the utility model discloses stand construction equipment still includes the support, the one end of support is fixed on the standard festival section template, the other end of support is fixed operation platform is last.
Optionally, adjacent standard segment templates are connected by M30 tie rods.
Optionally, the ladder is formed by welding and combining an L5 angle steel foot bar and an L8 angle steel upright, and is connected to the standard section formwork through bolts.
Optionally, a protection cage is additionally arranged on the periphery of the ladder stand, and the protection cage and the ladder stand form a manhole.
Optionally, the utility model discloses stand construction equipment still includes supplementary cage device, supplementary cage device is the horn mouth.
An embodiment in the above-mentioned utility model has following advantage or beneficial effect: utilize standard segmental template as the scaffold to and all install operation platform and cat ladder on every standard segmental template, operation platform both can regard as standard segmental template assembly platform to use under the unable fashioned condition of once only hoist and mount of high column template, also can regard as the rest of personnel when climbing the ladder from top to bottom, overhaul the platform and use, and can cancel construction with car and the ladder cage of ascending a height after having installed the cat ladder additional, can realize the no support construction in the true sense. Compared with the prior art, after the auxiliary construction of a climbing vehicle and a ladder cage is cancelled, the construction cost is greatly reduced, the construction process is simplified, and the utilization rate of a construction site is improved. The operation platform is not only used as a construction platform for pouring concrete, but also can be used as a rest and maintenance platform for multiple purposes. And each part is removable, and the utilization ratio is higher, and it is also comparatively convenient in stand work progress to replace alone, has cancelled the help of scaffold frame, ladder cage, car of ascending a height, has realized that the stand does not have the scaffold frame construction that falls to the ground, consequently fine promotion economic benefits and progress benefit.
Further effects of the above-mentioned non-conventional alternatives will be described below in connection with the embodiments.
Drawings
The accompanying drawings are included to provide a better understanding of the present invention and are not intended to constitute an undue limitation on the invention. Wherein:
fig. 1 is a schematic view of a column construction apparatus according to an embodiment of the present invention;
fig. 2 is a schematic diagram of a top view of a column construction apparatus according to an embodiment of the present invention;
fig. 3 is a schematic diagram of a side view of a standard segment template single piece according to an embodiment of the present invention;
fig. 4 is a schematic view of a guard rail according to an embodiment of the present invention;
fig. 5 is a schematic diagram of a top view of a protective cage according to an embodiment of the present invention;
wherein, 1-standard segment template; 2-climbing a ladder; 3-operating the platform; 4-supporting; 5, protecting the fence; 6-a protective cage; 7-square tube; 8-mesh sheet; 9-fixed steel; 10-connecting mechanism.
Detailed Description
Exemplary embodiments of the invention are described below with reference to the accompanying drawings, in which various details of embodiments of the invention are included to assist understanding, and which are to be considered exemplary only. Accordingly, those of ordinary skill in the art will recognize that various changes and modifications of the embodiments described herein can be made without departing from the scope and spirit of the invention. Also, descriptions of well-known functions and constructions are omitted in the following description for clarity and conciseness.
Fig. 1 is according to the utility model discloses stand construction equipment's schematic diagram, and fig. 2 is according to the utility model discloses stand construction equipment's schematic diagram of the top view. As shown in fig. 1, the column construction equipment of the embodiment of the present invention includes an operation platform 3, a standard segment formwork 1, and a ladder 2. The operation platform 3 is a horizontal support platform. The standard section template 1 is a vertical steel support frame, and the operating platform is fixed at the upper end of the standard section template. And the upper end and the lower end of the adjacent standard segment templates 1 are fixedly connected. Further, a connecting mechanism 10 is arranged on the operation platform 3 so as to facilitate the connection between the adjacent standard section templates. A ladder 2 is fixed to the outside of the standard segment formwork 1 so that a person can climb to the operating platform 3 through the ladder 2.
The embodiment of the utility model provides an utilize standard festival section template as the scaffold frame to and all install operation platform and cat ladder on every standard festival section template, operation platform both can use as standard festival section template assembly platform under the unable one-time hoist and mount fashioned condition of high stand template, also can regard as the personnel rest when climbing ladder from top to bottom, overhaul the platform and use, and can cancel construction with ascending a height car and ladder cage after having installed the cat ladder additional, can realize the most genuine construction of no support. Compared with the prior art, after the auxiliary construction of a climbing vehicle and a ladder cage is cancelled, the construction cost is greatly reduced, the construction process is simplified, and the utilization rate of a construction site is improved. The operation platform is not only used as a construction platform for pouring concrete, but also can be used as a rest and maintenance platform for multiple purposes. And each part is removable, and the utilization ratio is higher, and it is also comparatively convenient in stand work progress to replace alone, has cancelled the help of scaffold frame, ladder cage, car of ascending a height, has realized that the stand does not have the scaffold frame construction that falls to the ground, consequently fine promotion economic benefits and progress benefit. To enhance the structural robustness, a fixed steel 9 is fixed to the periphery of the standard segment formwork 1.
Fig. 3 is a schematic diagram of a side view of a standard segment template single piece according to an embodiment of the present invention; fig. 4 is a schematic view of a guard rail according to an embodiment of the present invention; fig. 5 is a schematic diagram of a top view of a protective cage according to an embodiment of the present invention.
Wherein, operation platform 3 adopts 8# channel-section steel processing weld forming, and through bolted connection in the periphery of the 1 upper end of standard segment template for this operation platform 3 has stronger holding power, and operating personnel stands the operation of being convenient for on this operation platform 3. And a steel bar net is laid on the bottom surface of the operating platform 3, and the periphery of the operating platform 3 is connected with a guardrail 5 in a detachable mode. Guardrail 5 is vertical net piece 8 that sets up, guardrail 5's height is 1.2 meters, and then security when can guaranteeing the operation of operating personnel.
As shown in fig. 2 and 3, the standard segment formwork 1 has a 4-piece pillar structure. The utility model discloses stand construction equipment is still including supporting 4, the one end of supporting 4 is fixed on standard festival section template 1, the other end of supporting 4 is fixed on operation platform 3. And adjacent standard segment templates are connected by M30 tie rods.
The ladder stand 2 is formed by welding and combining an L5 angle steel foot pedal rod and an L8 angle steel vertical rod and is connected to the standard segment formwork 1 through bolts. Protection cage 6 has been installed additional to the periphery of cat ladder 2, protection cage 6 with cat ladder 2 forms the manhole for personnel's accessible cat ladder 2 is from top to bottom, and protection cage 6 has guaranteed the security of personnel in crawling.
The utility model discloses stand construction equipment still includes supplementary cage device, supplementary cage device is the horn mouth.
The existing upright column is constructed without a floor scaffold, auxiliary construction can be carried out without using a climbing car or a ladder cage during construction, support-free construction in the true sense can not be achieved, and the construction efficiency and the construction cost are not obviously improved. The embodiment of the utility model provides a through carrying out integration combination formula machine-shaping with operation panel, cat ladder, steel form, constructor only needs pass through the utility model discloses can carry out the whole work progress operation behind the stand reinforcement, need not rethread climbing car or ladder cage and assist the construction, all show the promotion at economic benefits and progress benefit. In addition, the existing formwork integrated product has the problems that the steel reinforcement cage is difficult to enter when being sleeved in the steel reinforcement cage, the steel reinforcement cage is easy to collide, and the phenomenon that the steel reinforcement cage protection cushion block falls off is caused. Therefore, the embodiment of the utility model provides an through installing an auxiliary cage device additional (being "horn mouth" structure), fine solution above problem.
The utility model discloses stand construction equipment has set up an auxiliary lantern ring device in addition mainly by standard festival section template 1, operation platform 3, these three group layers of cat ladder 2. Wherein:
(1) the standard segmental templates (steel templates) are 4 pieces, two layers of steel frameworks are welded on the back of a steel panel, no inner pull rod is designed, and the templates are connected by M30 pull rods;
(2) the operating platform is formed by machining and welding 8# channel steel, and is connected to purlin surrounding steel sections at the upper part of a steel template through bolts after forming, 2 supports are arranged on each surface of the steel template to form a triangular support system, a reinforcing steel mesh is laid on the bottom surface of the operating platform, a 1.2 m-high square pipe guardrail (which can be disassembled) is arranged at the periphery of the operating platform, black yellow paint is brushed, 100 x 4 mesh is adopted for sealing, and 4 holes at the bottom of the square pipe of the guardrail are connected with the operating platform through bolts;
(3) the ladder stand is formed by welding and combining an L5 angle steel foot pedal rod and an L8 angle steel vertical rod, and is connected to the upright post formwork through bolts. In order to ensure the safety, a protective cage is additionally arranged on the ladder stand. The protective cage is composed of 6 × 40 steel plates and 6 × 50 steel plates, the steel plates are made into curved surfaces and welded on the ladder stand to form a manhole of 60cm × 63cm, and people are prevented from falling;
(4) the auxiliary steel bar sleeving device is made of the same structural material as the steel template, and adopts a horn mouth in the structural form, so that the combined steel template is convenient to sleeve the upright steel bar cage, and the collision and falling of the steel bar protection cushion block and the template are reduced.
The utility model discloses stand construction equipment continues to use thinking of die carrier integration, utilizes the steel form as the scaffold frame, nevertheless is different from only setting up operation platform on the top section template at present, the embodiment of the utility model discloses all install operation platform and cat ladder on every standard festival section template, operation platform both can use as template assembly platform under the unable fashioned condition of once only hoisting of high-rise column template, also can regard as the rest of personnel when going up and down the cat ladder, overhaul the platform and use to can cancel construction with climbing car and ladder cage after having installed the cat ladder additional, can realize the most genuine no support construction. Compared with the prior art, after the auxiliary construction of a climbing vehicle and a ladder cage is cancelled, the construction cost is greatly reduced, the construction procedures are simplified, and the utilization rate of a construction site is improved. The operation platform is not only used as a construction platform for pouring concrete, but also can be used as a rest and maintenance platform for multiple purposes. Just the utility model discloses each part is can dismantle, and the utilization ratio is higher, and it is also comparatively convenient to replace alone. According to the construction of on-the-spot practice application, the embodiment of the utility model provides a safety, technical aspect are reliable, can be applied to the construction.
The above detailed description does not limit the scope of the present invention. Those skilled in the art will appreciate that various modifications, combinations, sub-combinations, and substitutions can occur, depending on design requirements and other factors. Any modification, equivalent replacement, and improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (10)

1. An upright post construction apparatus, comprising:
the operation platform is a horizontal supporting platform;
the standard section template is a vertical steel support frame, and the operating platform is fixed at the upper end of the standard section template; the upper end and the lower end of the adjacent standard section templates are fixedly connected;
the ladder stand is fixed on the outer side of the standard section formwork.
2. The column construction equipment according to claim 1, wherein the operation platform is formed by machining and welding 8# channel steel and is connected to the periphery of the upper end of the standard section formwork through bolts.
3. The column construction equipment according to claim 1, wherein a steel mesh is laid on a bottom surface of the operation platform, and a guardrail is detachably attached to a periphery of the operation platform.
4. The column construction equipment according to claim 3, wherein the guard rail is a vertically arranged mesh; and/or the height of the guardrail is 1.2 meters.
5. The column construction equipment according to claim 1, wherein the standard segment formwork is a 4-piece column structure.
6. The column construction equipment according to claim 1, further comprising a support, one end of which is fixed to the standard segment formwork and the other end of which is fixed to the operation platform.
7. The column construction equipment according to claim 1, wherein adjacent standard segment formworks are connected by using M30 tie rods.
8. The column construction equipment according to claim 1, wherein the ladder is formed by welding and combining an L5 angle foot bar and an L8 angle upright bar and is connected to a standard section formwork through bolts.
9. The column construction equipment according to claim 1, wherein a protective cage is additionally installed on the periphery of the ladder stand, and the protective cage and the ladder stand form a manhole.
10. The column construction equipment according to claim 1, further comprising an auxiliary cage device, wherein the auxiliary cage device is a bell mouth.
CN202020041199.3U 2020-01-10 2020-01-10 Stand construction equipment Active CN212247875U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020041199.3U CN212247875U (en) 2020-01-10 2020-01-10 Stand construction equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020041199.3U CN212247875U (en) 2020-01-10 2020-01-10 Stand construction equipment

Publications (1)

Publication Number Publication Date
CN212247875U true CN212247875U (en) 2020-12-29

Family

ID=73990500

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020041199.3U Active CN212247875U (en) 2020-01-10 2020-01-10 Stand construction equipment

Country Status (1)

Country Link
CN (1) CN212247875U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112727079A (en) * 2021-01-27 2021-04-30 北京市住宅产业化集团股份有限公司 Protection integrated shaping combined type template and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112727079A (en) * 2021-01-27 2021-04-30 北京市住宅产业化集团股份有限公司 Protection integrated shaping combined type template and construction method

Similar Documents

Publication Publication Date Title
CN103635643A (en) Constructing method for concrete cylinder of construction steel bar of high-rise steel structure
CN202706503U (en) Electric lifting discharging platform for main building construction
CN108360380A (en) A kind of bridge pier column construction operation platform and its construction method
CN206873307U (en) Movable type bridge justifies pier stud work high above the ground operating platform
CN212247875U (en) Stand construction equipment
CN205475250U (en) Pin -connected panel steel stair in foundation ditch
CN103291116A (en) Grid-type formwork supporting and operating platform for construction of water tank on top of inverted-cone water tower
CN210564332U (en) Movable safety steel cat ladder
CN105951599B (en) High column mould bases integrated construction technique
CN212561215U (en) Back cage platform channel device
CN212837823U (en) Open cut tunnel side wall construction trolley
CN105755959B (en) Suitable for the Sarasota construction auxiliary stand system and building method of different cross section
CN215291305U (en) Hydroelectric station generator overhauls combination platform
CN212895943U (en) Operation platform device for binding small-section pier column reinforcing steel bars
CN213328707U (en) Thin-wall pier high-altitude operation combined platform
CN211974269U (en) From climbing formula elevartor shaft steel platform
CN217680774U (en) Encircling ladder cage for pier construction
CN203755178U (en) Novel ultra-wide large-span specially-shaped steel arch bridge construction device
CN208219432U (en) Cast-in-place support device for 0# block of box girder of continuous rigid frame bridge
CN214362896U (en) Detachable pier stud template work platform
CN112647701A (en) Hydroelectric station generator overhauls combination platform
CN206220547U (en) A kind of operating platform for steel structure column installation
CN110118014A (en) A kind of outer wall template system and its construction method for exempting from external scaffolding
CN213679551U (en) Tower crane pedestrian passageway
CN216690358U (en) Pier stud outer skeleton construction platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant