CN212245928U - Indoor switch cabinet installation portal frame - Google Patents

Indoor switch cabinet installation portal frame Download PDF

Info

Publication number
CN212245928U
CN212245928U CN202021766555.4U CN202021766555U CN212245928U CN 212245928 U CN212245928 U CN 212245928U CN 202021766555 U CN202021766555 U CN 202021766555U CN 212245928 U CN212245928 U CN 212245928U
Authority
CN
China
Prior art keywords
plate
lever
bracket
gantry
hydraulic cylinder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021766555.4U
Other languages
Chinese (zh)
Inventor
吕卫民
马军
柴天富
姚强
毋林慧
张东
杨小斌
李朝辉
李卫东
张祖河
魏风云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiaozuo Light Source Power Group Co ltd
Jiaozuo Power Supply Co of State Grid Henan Electric Power Co Ltd
Original Assignee
Jiaozuo Light Source Power Group Co ltd
Jiaozuo Power Supply Co of State Grid Henan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiaozuo Light Source Power Group Co ltd, Jiaozuo Power Supply Co of State Grid Henan Electric Power Co Ltd filed Critical Jiaozuo Light Source Power Group Co ltd
Priority to CN202021766555.4U priority Critical patent/CN212245928U/en
Application granted granted Critical
Publication of CN212245928U publication Critical patent/CN212245928U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Patch Boards (AREA)

Abstract

本实用新型属于安装龙门架技术领域,具体涉及室内开关柜安装龙门架;它包括左支架、右支架和横梁,左支架包括底梁、立柱、中间梁、支架斜撑和顶板;右支架与左支架的主体结构相同;顶板之间连接有横梁,横梁顶部设置绞座,绞座连接杠杆;杠杆右端连接起重链,起重链连接起重梁;左支架上设置有移动梁,移动梁两侧立柱上设置有补强板,移动梁两端连接导向板,导向板连接导向柱,移动梁的中部固定连接有液压缸连接板,液压缸连接板转动连接液压推杆的液压缸,液压推杆的液压杆转动连接杠杆的左端;本实用新型能够辅助施工人员快速、安全、高效地进行室内开关柜的安装,降低了工作人员的劳动强度,提高了工作效率。

Figure 202021766555

The utility model belongs to the technical field of installation gantry, in particular to an indoor switch cabinet installation gantry; the utility model comprises a left bracket, a right bracket and a beam; The main structure of the bracket is the same; a beam is connected between the top plates, the top of the beam is provided with a hinge, and the hinge is connected with a lever; the right end of the lever is connected with a lifting chain, and the lifting chain is connected with the lifting beam; A reinforcing plate is arranged on the side column, the two ends of the moving beam are connected to the guide plate, the guide plate is connected to the guide column, the middle part of the moving beam is fixedly connected with a hydraulic cylinder connecting plate, and the hydraulic cylinder connecting plate is rotated and connected to the hydraulic cylinder of the hydraulic push rod. The hydraulic rod of the rod is rotated to connect the left end of the lever; the utility model can assist the construction personnel to install the indoor switch cabinet quickly, safely and efficiently, reduce the labor intensity of the staff, and improve the work efficiency.

Figure 202021766555

Description

室内开关柜安装龙门架Indoor switch cabinet installation gantry

技术领域technical field

本实用新型属于安装龙门架技术领域,具体涉及室内开关柜安装龙门架。The utility model belongs to the technical field of installation gantry, in particular to an installation gantry of an indoor switch cabinet.

背景技术Background technique

开关柜是在电力系统输配电和电能转换过程中,进行开合、控制和保护用电设备的一种电气设备,开关柜内的部件主要有断路器、隔离开关、负荷开关、操作机构、互感器以及各种保护装置等;随着用电量需求的不断增加,对用电安全的要求不断提高,开关柜的使用数量也越来越多,而开关柜快速合格的安装是保证其能够投入工作且长期稳定运行的前提;开关柜进行安装时,需要根据需要移动其位置或者升高其高度,以和其它相关电气设备完成连接,因此经常需要借助其它吊装设备来完成其安装,而室内开关柜安装时,由于室内空间有限,而其它吊装设备体积太大不便于室内的施工,因此,提供一种能够辅助施工人员快速、安全、高效地进行室内开关柜安装的室内开关柜安装龙门架是很有必要的。Switchgear is a kind of electrical equipment that switches, controls and protects electrical equipment in the process of power transmission and distribution and power conversion in power systems. The components in the switchgear mainly include circuit breakers, isolation switches, load switches, operating mechanisms, Transformers and various protection devices, etc. With the increasing demand for electricity, the requirements for electricity safety are constantly improving, and the number of switchgears is also increasing, and the fast and qualified installation of switchgear is to ensure that it can be put into work. And the premise of long-term stable operation; when the switchgear is installed, it needs to move its position or raise its height as needed to complete the connection with other related electrical equipment, so it is often necessary to use other hoisting equipment to complete its installation, while indoor switchgear During installation, due to the limited indoor space and the large size of other hoisting equipment, it is inconvenient for indoor construction. Therefore, it is very important to provide an indoor switch cabinet installation gantry that can assist construction personnel to install indoor switch cabinets quickly, safely and efficiently. Necessary.

实用新型内容Utility model content

本实用新型的目的是为了克服现有技术的不足,而提供一种结构合理,操作使用方便,能够辅助施工人员快速、安全、高效地进行室内开关柜安装的室内开关柜安装龙门架。The purpose of the utility model is to overcome the deficiencies of the prior art, and provide an indoor switch cabinet installation gantry with reasonable structure, convenient operation and use, which can assist construction personnel to install the indoor switch cabinet quickly, safely and efficiently.

本实用新型的目的是这样实现的:室内开关柜安装龙门架,它包括有左支架、右支架和横梁,所述左支架包括有底梁,所述底梁中部连接有两个立柱,两个所述立柱之间连接有中间梁,所述立柱的上部与所述底梁的端部之间连接有支架斜撑,所述底梁的底部设置有滚轮,两个所述立柱的顶部之间连接有顶板;所述右支架与所述左支架的主体结构相同;所述左支架上的所述顶板与所述右支架上的所述顶板之间连接有两个所述横梁,两个所述横梁左端的顶部设置有绞座,所述绞座转动连接有杠杆;所述杠杆的右端连接有起重链,所述起重链连接有起重梁,所述起重梁的左右两侧均连接有吊链;所述左支架的两个所述立柱之间设置有移动梁,所述移动梁设置于所述立柱的下部,所述移动梁左右两侧的所述立柱上均设置有补强板,所述补强板中部设置有导向槽,所述移动梁两端均连接有导向板,所述导向板穿过所述导向槽并连接有导向柱,所述导向柱位于所述立柱内并与所述立柱滑动连接,所述移动梁的中部固定连接有液压缸连接板,所述液压缸连接板转动连接液压推杆的液压缸,所述液压推杆的液压杆转动连接所述杠杆的左端。The purpose of this utility model is achieved in this way: an indoor switch cabinet is installed with a gantry, which includes a left bracket, a right bracket and a beam, the left bracket includes a bottom beam, and the middle of the bottom beam is connected with two uprights, two A middle beam is connected between the uprights, a bracket diagonal brace is connected between the upper part of the upright and the end of the bottom beam, a roller is arranged at the bottom of the bottom beam, and the tops of the two uprights are A top plate is connected; the main structure of the right bracket is the same as that of the left bracket; two beams are connected between the top plate on the left bracket and the top plate on the right bracket, and the two The top of the left end of the beam is provided with a hinge, and the hinge is rotatably connected with a lever; the right end of the lever is connected with a hoisting chain, and the hoisting chain is connected with a hoisting beam, and the left and right sides of the hoisting beam are connected are connected with a hanging chain; a moving beam is arranged between the two columns of the left bracket, the moving beam is arranged at the lower part of the column, and the columns on the left and right sides of the moving beam are provided with A reinforcing plate, the middle of the reinforcing plate is provided with a guide groove, both ends of the moving beam are connected with a guide plate, the guide plate passes through the guide groove and is connected with a guide column, and the guide column is located in the A hydraulic cylinder connecting plate is fixedly connected to the middle of the moving beam, and the hydraulic cylinder connecting plate is connected to the hydraulic cylinder of the hydraulic push rod in rotation, and the hydraulic rod of the hydraulic push rod is rotated and connected to the hydraulic cylinder. the left end of the lever.

所述滚轮为万向轮。The roller is a universal wheel.

所述横梁与所述左支架之间通过侧面的加强联板和螺栓连接副连接,所述横梁与右支架之间通过侧面的所述加强联板和螺栓连接副连接。The cross beam and the left bracket are connected by the reinforcing connecting plate and the bolt connection pair on the side, and the cross beam and the right bracket are connected by the reinforcing connecting plate and the bolt connecting pair on the side.

所述横梁为可调整长度的伸缩横梁。The beam is a telescopic beam with adjustable length.

所述左支架的两个所述立柱的下部设置有锁紧螺栓,所述锁紧螺栓的一端可选择地抵压于所述导向柱上。The lower parts of the two upright columns of the left bracket are provided with locking bolts, and one end of the locking bolts can be selectively pressed against the guide columns.

所述绞座通过绞座连接螺栓与所述横梁连接,所述绞座通过第一转轴与所述杠杆转动连接,所述第一转轴上设置有限位套。The hinged base is connected with the beam through a hinged base connecting bolt, the hinged base is rotatably connected with the lever through a first rotating shaft, and a limiting sleeve is arranged on the first rotating shaft.

所述起重梁上的两侧均设置有锁定孔,所述起重梁上滑动连接有调节滑块,所述调节滑块上设置有调节旋钮,所述调节滑块底部连接有连接挂板,所述连接挂板连接有所述吊链。Both sides of the lifting beam are provided with locking holes, an adjustment slider is slidably connected to the lifting beam, an adjustment knob is arranged on the adjustment slider, and a connection hanging plate is connected to the bottom of the adjustment slider , the connecting hanging plate is connected with the hanging chain.

所述液压缸底部连接有连接夹板,所述连接夹板通过第二转轴与所述液压缸连接板转动连接。The bottom of the hydraulic cylinder is connected with a connecting splint, and the connecting splint is rotatably connected with the hydraulic cylinder connecting plate through a second rotating shaft.

所述室内开关柜安装龙门架的使用方法,它包括有以下步骤:The use method of the indoor switch cabinet installation gantry includes the following steps:

步骤1)、将所述左支架、所述右支架、所述横梁、所述液压推杆和所述杠杆等部件运送至工作现场进行组装;Step 1), transport the left bracket, the right bracket, the beam, the hydraulic push rod, the lever and other components to the work site for assembly;

步骤2)、连接液压系统并进行空载测试,检查所有连接件是否牢固及运动件转动灵活度;Step 2), connect the hydraulic system and carry out no-load test to check whether all the connecting parts are firm and the flexibility of the moving parts rotation;

步骤3)、将需要安装的开关柜移动至龙门架相应位置,开启液压泵站正向开关,所述液压推杆向前推进其所述液压杆,所述杠杆带动所述吊链的吊钩端下降至开关柜吊环处,正确安装好起吊挂具,启动液压泵站反向开关,所述液压推杆回缩,在杠杆力的作用下所述起重梁将开关柜吊起一定高度;Step 3), move the switch cabinet to be installed to the corresponding position of the gantry, turn on the forward switch of the hydraulic pump station, the hydraulic push rod pushes the hydraulic rod forward, and the lever drives the hook of the hanging chain The end is lowered to the lifting ring of the switch cabinet, the hoisting device is correctly installed, the reverse switch of the hydraulic pump station is activated, the hydraulic push rod retracts, and the lifting beam lifts the switch cabinet to a certain height under the action of the lever force;

步骤4)、取下开关柜底部的轮系装置,将开关柜下降至距地面10mm左右,移动龙门架使开关柜母线对接槽进入相应连接位置后,将开关柜落至地面即可。Step 4), remove the gear train device at the bottom of the switchgear, lower the switchgear to about 10mm from the ground, move the gantry so that the busbar docking slot of the switchgear enters the corresponding connection position, and then drop the switchgear to the ground.

本实用新型的有益效果:本实用新型的室内开关柜安装龙门架主要包括有左支架、右支架、横梁、液压推杆、杠杆和超重梁,两个横梁将左支架和右支架连接起来,左支架顶部通过绞座连接杠杆,杠杆在液压推杆的作用下可通过起重链带动起重梁升降,从而通过吊链对开关柜进行吊装施工操作,在吊装开关柜过程中,可通过滚轮推动本龙门架以改变其位置,使其有更多的可操作性,适应更多复杂施工情景;通过左支架上设置的移动梁可调整液压推杆的整体高度,进而调整杠杆的初始抬升高度,以适应对不同情况下吊装开关柜的要求,进一步提高本龙门架的实用性;左支架、右支架和横梁采用高强度标准件进行连接,可方便拆装;本龙门架工作时整体负载主要集中在左支架上,双立柱采用矩形钢管,垂直受力,横梁不承受径向力,只作为左右支架连接用,不仅结构稳定,且可有效减小本龙门架的整体体积和操作难度,提高吊装效率;本实用新型的室内开关柜安装龙门架,能够辅助施工人员快速、安全、高效地进行室内开关柜的安装,降低了工作人员的劳动强度,提高了工作效率。The beneficial effects of the utility model: the indoor switch cabinet installation gantry of the utility model mainly includes a left bracket, a right bracket, a beam, a hydraulic push rod, a lever and an overweight beam, and the two beams connect the left bracket and the right bracket, and the left bracket and the right bracket are connected. The top of the bracket is connected to the lever through the hinge, and the lever can drive the lifting beam up and down through the lifting chain under the action of the hydraulic push rod, so that the switch cabinet can be hoisted and constructed through the lifting chain. The gantry can change its position to make it more maneuverable and adapt to more complex construction scenarios; the overall height of the hydraulic push rod can be adjusted through the moving beam set on the left bracket, and then the initial lifting height of the lever can be adjusted. In order to meet the requirements for hoisting switch cabinets in different situations, and further improve the practicability of the gantry; the left bracket, right bracket and beam are connected by high-strength standard parts, which can be easily disassembled; the overall load of the gantry is mainly concentrated during operation. On the left bracket, the double columns are made of rectangular steel pipes, which are subjected to vertical force, and the beam does not bear radial force, and is only used for the connection of the left and right brackets. Efficiency; the indoor switch cabinet installation gantry of the utility model can assist construction personnel to install the indoor switch cabinet quickly, safely and efficiently, reduce the labor intensity of the staff, and improve the work efficiency.

附图说明Description of drawings

图1为本实用新型室内开关柜安装龙门架的正视结构示意图。Fig. 1 is the front view structure schematic diagram of the installation gantry of the indoor switch cabinet of the utility model.

图2为本实用新型室内开关柜安装龙门架左支架的结构示意图。FIG. 2 is a schematic structural diagram of the left bracket of the gantry frame installed in the indoor switch cabinet of the utility model.

图3为本实用新型室内开关柜安装龙门架主体的俯视结构示意图。Fig. 3 is a top-view structural schematic diagram of the main body of the gantry frame installed in the indoor switch cabinet of the present invention.

图4为本实用新型室内开关柜安装龙门架起重梁与吊链的结构示意图。FIG. 4 is a schematic structural diagram of the gantry hoisting beam and the hoisting chain installed in the indoor switch cabinet of the utility model.

图5为本实用新型室内开关柜安装龙门架移动梁连接的剖视结构示意图。FIG. 5 is a schematic cross-sectional structural diagram of the connection between the moving beams of the gantry frame installed in the indoor switch cabinet of the present invention.

图6为图5中A-A方向的结构示意图。FIG. 6 is a schematic view of the structure in the direction A-A in FIG. 5 .

图7为本实用新型室内开关柜安装龙门架绞座与杠杆连接的结构示意图。FIG. 7 is a schematic structural diagram of the connection between the gantry hanger and the lever for installing the indoor switch cabinet of the utility model.

图8为本实用新型室内开关柜安装龙门架液压缸与移动梁连接的结构示意图。FIG. 8 is a schematic structural diagram of the connection between the hydraulic cylinder of the gantry frame installed in the indoor switch cabinet of the utility model and the moving beam.

图中:1、滚轮 2、左支架 3、液压缸 4、液压推杆 5、加强联板 6、液压杆 7、绞座 8、杠杆 9、横梁 10、起重链 11、吊链 12、起重梁 13、右支架 14、底梁 15、支架斜撑 16、锁紧螺栓 17、移动梁 18、液压缸连接板 19、补强板 20、中间梁 21、立柱 22、顶板 23、绞座连接螺栓 24、锁定孔 25、调节滑块 26、调节旋钮 27、连接挂板 28、导向槽 29、导向板 30、导向柱 31、第一转轴 32、限位套 33、第二转轴34、连接夹板。In the figure: 1. Roller 2, Left bracket 3, Hydraulic cylinder 4, Hydraulic push rod 5, Reinforcing connecting plate 6, Hydraulic rod 7, Hook base 8, Lever 9, Beam 10, Lifting chain 11, Hanging chain 12, Lifting Heavy beam 13, right bracket 14, bottom beam 15, bracket diagonal brace 16, locking bolt 17, moving beam 18, hydraulic cylinder connecting plate 19, reinforcing plate 20, middle beam 21, column 22, top plate 23, hinge connection Bolt 24, locking hole 25, adjusting slider 26, adjusting knob 27, connecting hanging plate 28, guide groove 29, guide plate 30, guide column 31, first rotating shaft 32, limit sleeve 33, second rotating shaft 34, connecting splint .

具体实施方式Detailed ways

下面结合附图对本实用新型做进一步的说明。The utility model will be further described below in conjunction with the accompanying drawings.

实施例1Example 1

如图1-6所示,室内开关柜安装龙门架,它包括有左支架2、右支架13和横梁9,所述左支架2包括有底梁14,所述底梁14中部连接有两个立柱21,两个所述立柱21之间连接有中间梁20,所述立柱21的上部与所述底梁14的端部之间连接有支架斜撑15,所述底梁14的底部设置有滚轮1,两个所述立柱21的顶部之间连接有顶板22;所述右支架13与所述左支架2的主体结构相同;所述左支架2上的所述顶板22与所述右支架13上的所述顶板22之间连接有两个所述横梁9,两个所述横梁9左端的顶部设置有绞座7,所述绞座7转动连接有杠杆8;所述杠杆8的右端连接有起重链10,所述起重链10连接有起重梁12,所述起重梁12的左右两侧均连接有吊链11;所述左支架2的两个所述立柱21之间设置有移动梁17,所述移动梁17设置于所述立柱21的下部,所述移动梁17左右两侧的所述立柱21上均设置有补强板19,所述补强板19中部设置有导向槽28,所述移动梁17两端均连接有导向板29,所述导向板29穿过所述导向槽28并连接有导向柱30,所述导向柱30位于所述立柱21内并与所述立柱21滑动连接,所述移动梁17的中部固定连接有液压缸连接板18,所述液压缸连接板18转动连接液压推杆4的液压缸3,所述液压推杆4的液压杆6转动连接所述杠杆8的左端。As shown in Figures 1-6, the indoor switch cabinet is installed with a gantry, which includes a left bracket 2, a right bracket 13 and a beam 9. The left bracket 2 includes a bottom beam 14, and the middle of the bottom beam 14 is connected with two Upright column 21, an intermediate beam 20 is connected between the two upright columns 21, a bracket diagonal brace 15 is connected between the upper part of the upright column 21 and the end of the bottom beam 14, and the bottom of the bottom beam 14 is provided with Roller 1, a top plate 22 is connected between the tops of the two uprights 21; the main structure of the right bracket 13 is the same as that of the left bracket 2; the top plate 22 on the left bracket 2 is connected to the right bracket The top plate 22 on the 13 is connected with two of the beams 9, the top of the left ends of the two beams 9 is provided with a hinge 7, and the hinge 7 is rotatably connected with a lever 8; the right end of the lever 8 A hoisting chain 10 is connected, the hoisting chain 10 is connected with a hoisting beam 12, and the left and right sides of the hoisting beam 12 are connected with a suspending chain 11; A moving beam 17 is arranged in between, the moving beam 17 is arranged at the lower part of the column 21, and reinforcing plates 19 are provided on the columns 21 on the left and right sides of the moving beam 17. The middle of the reinforcing plate 19 A guide groove 28 is provided, both ends of the moving beam 17 are connected with guide plates 29 , the guide plates 29 pass through the guide groove 28 and are connected with a guide column 30 , and the guide column 30 is located in the column 21 . It is slidably connected with the upright column 21 , and a hydraulic cylinder connecting plate 18 is fixedly connected to the middle of the moving beam 17 . The hydraulic cylinder connecting plate 18 is rotatably connected to the hydraulic cylinder 3 of the hydraulic push rod 4 . The hydraulic rod 6 is rotatably connected to the left end of the lever 8 .

所述室内开关柜安装龙门架的使用方法,它包括有以下步骤:The use method of the indoor switch cabinet installation gantry includes the following steps:

步骤1)、将所述左支架2、所述右支架13、所述横梁9、所述液压推杆4和所述杠杆8等部件运送至工作现场进行组装;Step 1), transport the left bracket 2, the right bracket 13, the beam 9, the hydraulic push rod 4 and the lever 8 to the work site for assembly;

步骤2)、连接液压系统并进行空载测试,检查所有连接件是否牢固及运动件转动灵活度;Step 2), connect the hydraulic system and carry out no-load test to check whether all the connecting parts are firm and the flexibility of the moving parts rotation;

步骤3)、将需要安装的开关柜移动至龙门架相应位置,开启液压泵站正向开关,所述液压推杆4向前推进其所述液压杆6,所述杠杆8带动所述吊链11的吊钩端下降至开关柜吊环处,正确安装好起吊挂具,启动液压泵站反向开关,所述液压推杆4回缩,在杠杆力的作用下所述起重梁12将开关柜吊起一定高度;Step 3), move the switch cabinet to be installed to the corresponding position of the gantry, turn on the forward switch of the hydraulic pump station, the hydraulic push rod 4 pushes the hydraulic rod 6 forward, and the lever 8 drives the hanging chain The hook end of 11 is lowered to the lifting ring of the switch cabinet, the hoisting device is correctly installed, the reverse switch of the hydraulic pump station is activated, the hydraulic push rod 4 retracts, and the lifting beam 12 switches the switch under the action of the lever force. The cabinet is lifted to a certain height;

步骤4)、取下开关柜底部的轮系装置,将开关柜下降至距地面10mm左右,移动龙门架使开关柜母线对接槽进入相应连接位置后,将开关柜落至地面即可。Step 4), remove the gear train device at the bottom of the switchgear, lower the switchgear to about 10mm from the ground, move the gantry so that the busbar docking slot of the switchgear enters the corresponding connection position, and then drop the switchgear to the ground.

本实用新型的室内开关柜安装龙门架主要包括有左支架2、右支架13、横梁9、液压推杆4、杠杆8和超重梁12,两个横梁9将左支架2和右支架13连接起来,左支架2顶部通过绞座7连接杠杆8,杠杆8在液压推杆4的作用下可通过起重链10带动起重梁12升降,从而通过吊链11对开关柜进行吊装施工操作,在吊装开关柜过程中,可通过滚轮1推动本龙门架以改变其位置,使其有更多的可操作性,适应更多复杂施工情景;通过左支架2上设置的移动梁17可调整液压推杆4的整体高度,进而调整杠杆8的初始抬升高度,以适应对不同情况下吊装开关柜的要求,进一步提高本龙门架的实用性;左支架2、右支架13和横梁9采用高强度标准件进行连接,可方便拆装;本龙门架工作时整体负载主要集中在左支架2上,双立柱21采用矩形钢管,垂直受力,横梁9不承受径向力,只作为左右支架连接用,不仅结构稳定,且可有效减小本龙门架的整体体积和操作难度,提高吊装效率;本实用新型的室内开关柜安装龙门架,能够辅助施工人员快速、安全、高效地进行室内开关柜的安装,降低了工作人员的劳动强度,提高了工作效率。The indoor switch cabinet installation gantry of the utility model mainly includes a left bracket 2, a right bracket 13, a beam 9, a hydraulic push rod 4, a lever 8 and an overweight beam 12, and the two beams 9 connect the left bracket 2 and the right bracket 13. , the top of the left bracket 2 is connected to the lever 8 through the hinge 7, and the lever 8 can drive the lifting beam 12 to rise and fall through the lifting chain 10 under the action of the hydraulic push rod 4, so that the switch cabinet can be hoisted through the lifting chain 11. During the process of hoisting the switchgear, the gantry can be pushed through the roller 1 to change its position, making it more maneuverable and adapting to more complex construction scenarios; the hydraulic pusher can be adjusted through the moving beam 17 set on the left bracket 2 The overall height of the rod 4, and then the initial lifting height of the lever 8 is adjusted to meet the requirements for hoisting the switchgear under different circumstances, and further improve the practicability of the gantry; the left bracket 2, the right bracket 13 and the beam 9 adopt high-strength standards It is easy to disassemble and assemble; when the gantry works, the overall load is mainly concentrated on the left bracket 2, the double column 21 is made of rectangular steel pipe, and is subjected to vertical force, and the beam 9 does not bear radial force, and is only used for the connection of the left and right brackets. Not only the structure is stable, but also the overall volume and operation difficulty of the gantry can be effectively reduced, and the hoisting efficiency can be improved; the indoor switch cabinet installation gantry of the utility model can assist the construction personnel to install the indoor switch cabinet quickly, safely and efficiently. , reducing the labor intensity of staff and improving work efficiency.

实施例2Example 2

如图1-8所示,室内开关柜安装龙门架,它包括有左支架2、右支架13和横梁9,所述左支架2包括有底梁14,所述底梁14中部连接有两个立柱21,两个所述立柱21之间连接有中间梁20,所述立柱21的上部与所述底梁14的端部之间连接有支架斜撑15,所述底梁14的底部设置有滚轮1,两个所述立柱21的顶部之间连接有顶板22;所述右支架13与所述左支架2的主体结构相同;所述左支架2上的所述顶板22与所述右支架13上的所述顶板22之间连接有两个所述横梁9,两个所述横梁9左端的顶部设置有绞座7,所述绞座7转动连接有杠杆8;所述杠杆8的右端连接有起重链10,所述起重链10连接有起重梁12,所述起重梁12的左右两侧均连接有吊链11;所述左支架2的两个所述立柱21之间设置有移动梁17,所述移动梁17设置于所述立柱21的下部,所述移动梁17左右两侧的所述立柱21上均设置有补强板19,所述补强板19中部设置有导向槽28,所述移动梁17两端均连接有导向板29,所述导向板29穿过所述导向槽28并连接有导向柱30,所述导向柱30位于所述立柱21内并与所述立柱21滑动连接,所述移动梁17的中部固定连接有液压缸连接板18,所述液压缸连接板18转动连接液压推杆4的液压缸3,所述液压推杆4的液压杆6转动连接所述杠杆8的左端。As shown in Figures 1-8, the indoor switch cabinet is installed with a gantry, which includes a left bracket 2, a right bracket 13 and a beam 9, the left bracket 2 includes a bottom beam 14, and two bottom beams 14 are connected in the middle Upright column 21, an intermediate beam 20 is connected between two of the upright columns 21, a bracket diagonal brace 15 is connected between the upper part of the upright column 21 and the end of the bottom beam 14, and the bottom of the bottom beam 14 is provided with Roller 1, a top plate 22 is connected between the tops of the two uprights 21; the main structure of the right bracket 13 is the same as that of the left bracket 2; the top plate 22 on the left bracket 2 is connected to the right bracket The top plate 22 on the 13 is connected with two beams 9, the top of the left ends of the two beams 9 is provided with a hinge 7, and the hinge 7 is rotatably connected with a lever 8; the right end of the lever 8 A hoisting chain 10 is connected, the hoisting chain 10 is connected with a hoisting beam 12, and the left and right sides of the hoisting beam 12 are connected with a suspending chain 11; A moving beam 17 is arranged between the two sides, the moving beam 17 is arranged at the lower part of the column 21, and reinforcing plates 19 are arranged on the columns 21 on the left and right sides of the moving beam 17. The middle part of the reinforcing plate 19 A guide groove 28 is provided, both ends of the moving beam 17 are connected with guide plates 29 , the guide plates 29 pass through the guide groove 28 and are connected with a guide column 30 , and the guide column 30 is located in the column 21 . It is slidably connected with the upright column 21 , and a hydraulic cylinder connecting plate 18 is fixedly connected to the middle of the moving beam 17 . The hydraulic cylinder connecting plate 18 is rotatably connected to the hydraulic cylinder 3 of the hydraulic push rod 4 . The hydraulic rod 6 is rotatably connected to the left end of the lever 8 .

为了更好的效果,所述滚轮1为万向轮,方便吊装前后和吊装过程中移动本开关柜龙门架,提高其实用性和可操作性。For better effect, the roller 1 is a universal wheel, which is convenient for moving the switch cabinet gantry before and after hoisting and during the hoisting process, so as to improve its practicability and operability.

为了更好的效果,所述横梁9与所述左支架2之间通过侧面的加强联板5和螺栓连接副连接,所述横梁9与右支架13之间通过侧面的所述加强联板5和螺栓连接副连接,提高本龙门架结构的稳定性,同时便于拆装。For better effect, the cross beam 9 and the left bracket 2 are connected by the side reinforcing connecting plate 5 and the bolt connection pair, and the cross beam 9 and the right bracket 13 are connected by the side reinforcing connecting plate 5 It is connected with the bolt connection pair, which improves the stability of the gantry structure and facilitates disassembly and assembly.

为了更好的效果,所述横梁9为可调整长度的伸缩横梁,可根据不同开关柜宽度的需要进行调整,进一步提高本龙门架实用性。For better effect, the beam 9 is a telescopic beam with adjustable length, which can be adjusted according to the needs of different switch cabinet widths, further improving the practicability of the gantry.

为了更好的效果,所述左支架2的两个所述立柱21的下部设置有锁紧螺栓16,所述锁紧螺栓16的一端可选择地抵压于所述导向柱30上,可通过所述锁紧螺栓16调整或固定所述移动梁17的位置,操作简单高效。For better effect, locking bolts 16 are provided at the lower parts of the two upright columns 21 of the left bracket 2 , and one end of the locking bolts 16 can be selectively pressed against the guide column 30 and can be passed through The locking bolt 16 adjusts or fixes the position of the moving beam 17, and the operation is simple and efficient.

为了更好的效果,所述绞座7通过绞座连接螺栓23与所述横梁9连接,连接稳定且方向拆装,所述绞座7通过第一转轴31与所述杠杆8转动连接,所述第一转轴31上设置有限位套32,所述限位套32可对所述杠杆8进行限位,保证其工作时的稳定性。For better effect, the hinged base 7 is connected to the beam 9 through the hinged base connecting bolt 23, the connection is stable and the direction is disassembled, and the hinged base 7 is rotatably connected with the lever 8 through the first rotating shaft 31, so A limiting sleeve 32 is arranged on the first rotating shaft 31 , and the limiting sleeve 32 can limit the position of the lever 8 to ensure its stability during operation.

为了更好的效果,所述起重梁12上的两侧均设置有锁定孔24,所述起重梁12上滑动连接有调节滑块25,所述调节滑块25上设置有调节旋钮26,所述调节滑块25底部连接有连接挂板27,所述连接挂板27连接有所述吊链11,可通过所述调节滑块25调整两个所述吊链11之间的距离,以适应不同宽度开关柜的需要,提高本龙门架的适应性和实用性。For better effect, locking holes 24 are provided on both sides of the lifting beam 12 , an adjustment slider 25 is slidably connected to the lifting beam 12 , and an adjustment knob 26 is arranged on the adjustment slider 25 , the bottom of the adjustment slider 25 is connected with a connecting hanging plate 27, the connecting hanging plate 27 is connected with the hanging chain 11, and the distance between the two hanging chains 11 can be adjusted through the adjusting slider 25, In order to meet the needs of switch cabinets of different widths, the adaptability and practicability of the gantry are improved.

为了更好的效果,所述液压缸3底部连接有连接夹板34,所述连接夹板34通过第二转轴33与所述液压缸连接板18转动连接,结构简单,连接稳定高效。For better effect, the bottom of the hydraulic cylinder 3 is connected with a connecting splint 34, and the connecting splint 34 is rotatably connected with the hydraulic cylinder connecting plate 18 through the second shaft 33, with a simple structure and stable and efficient connection.

所述室内开关柜安装龙门架的使用方法,它包括有以下步骤:The use method of the indoor switch cabinet installation gantry includes the following steps:

步骤1)、将所述左支架2、所述右支架13、所述横梁9、所述液压推杆4和所述杠杆8等部件运送至工作现场进行组装;Step 1), transport the left bracket 2, the right bracket 13, the beam 9, the hydraulic push rod 4 and the lever 8 to the work site for assembly;

步骤2)、连接液压系统并进行空载测试,检查所有连接件是否牢固及运动件转动灵活度;Step 2), connect the hydraulic system and carry out no-load test to check whether all the connecting parts are firm and the flexibility of the moving parts rotation;

步骤3)、将需要安装的开关柜移动至龙门架相应位置,开启液压泵站正向开关,所述液压推杆4向前推进其所述液压杆6,所述杠杆8带动所述吊链11的吊钩端下降至开关柜吊环处,正确安装好起吊挂具,启动液压泵站反向开关,所述液压推杆4回缩,在杠杆力的作用下所述起重梁12将开关柜吊起一定高度;Step 3), move the switch cabinet to be installed to the corresponding position of the gantry, turn on the forward switch of the hydraulic pump station, the hydraulic push rod 4 pushes the hydraulic rod 6 forward, and the lever 8 drives the hanging chain The hook end of 11 is lowered to the lifting ring of the switch cabinet, the hoisting device is correctly installed, the reverse switch of the hydraulic pump station is activated, the hydraulic push rod 4 retracts, and the lifting beam 12 switches the switch under the action of the lever force. The cabinet is lifted to a certain height;

步骤4)、取下开关柜底部的轮系装置,将开关柜下降至距地面10mm左右,移动龙门架使开关柜母线对接槽进入相应连接位置后,将开关柜落至地面即可。Step 4), remove the gear train device at the bottom of the switchgear, lower the switchgear to about 10mm from the ground, move the gantry so that the busbar docking slot of the switchgear enters the corresponding connection position, and then drop the switchgear to the ground.

本实用新型的室内开关柜安装龙门架主要包括有左支架2、右支架13、横梁9、液压推杆4、杠杆8和超重梁12,两个横梁9将左支架2和右支架13连接起来,左支架2顶部通过绞座7连接杠杆8,杠杆8在液压推杆4的作用下可通过起重链10带动起重梁12升降,从而通过吊链11对开关柜进行吊装施工操作,在吊装开关柜过程中,可通过滚轮1推动本龙门架以改变其位置,使其有更多的可操作性,适应更多复杂施工情景;通过左支架2上设置的移动梁17可调整液压推杆4的整体高度,进而调整杠杆8的初始抬升高度,以适应对不同情况下吊装开关柜的要求,进一步提高本龙门架的实用性;左支架2、右支架13和横梁9采用高强度标准件进行连接,可方便拆装;本龙门架工作时整体负载主要集中在左支架2上,双立柱21采用矩形钢管,垂直受力,横梁9不承受径向力,只作为左右支架连接用,不仅结构稳定,且可有效减小本龙门架的整体体积和操作难度,提高吊装效率;本实用新型的室内开关柜安装龙门架,能够辅助施工人员快速、安全、高效地进行室内开关柜的安装,降低了工作人员的劳动强度,提高了工作效率。The indoor switch cabinet installation gantry of the utility model mainly includes a left bracket 2, a right bracket 13, a beam 9, a hydraulic push rod 4, a lever 8 and an overweight beam 12, and the two beams 9 connect the left bracket 2 and the right bracket 13. , the top of the left bracket 2 is connected to the lever 8 through the hinge 7, and the lever 8 can drive the lifting beam 12 to rise and fall through the lifting chain 10 under the action of the hydraulic push rod 4, so that the switch cabinet can be hoisted through the lifting chain 11. During the process of hoisting the switchgear, the gantry can be pushed through the roller 1 to change its position, making it more maneuverable and adapting to more complex construction scenarios; the hydraulic pusher can be adjusted through the moving beam 17 set on the left bracket 2 The overall height of the rod 4, and then the initial lifting height of the lever 8 is adjusted to meet the requirements for hoisting the switchgear under different circumstances, and further improve the practicability of the gantry; the left bracket 2, the right bracket 13 and the beam 9 adopt high-strength standards It is easy to disassemble and assemble; when the gantry works, the overall load is mainly concentrated on the left bracket 2, the double column 21 is made of rectangular steel pipe, and is subjected to vertical force, and the beam 9 does not bear radial force, and is only used for the connection of the left and right brackets. Not only the structure is stable, but also the overall volume and operation difficulty of the gantry can be effectively reduced, and the hoisting efficiency can be improved; the indoor switch cabinet installation gantry of the utility model can assist the construction personnel to install the indoor switch cabinet quickly, safely and efficiently. , reducing the labor intensity of staff and improving work efficiency.

Claims (8)

1. Indoor cubical switchboard installation portal frame, it includes left socle (2), right branch frame (13) and crossbeam (9), its characterized in that: the left support (2) comprises a bottom beam (14), the middle of the bottom beam (14) is connected with two upright posts (21), a middle beam (20) is connected between the two upright posts (21), a support diagonal brace (15) is connected between the upper parts of the upright posts (21) and the end part of the bottom beam (14), the bottom of the bottom beam (14) is provided with a roller (1), and a top plate (22) is connected between the tops of the two upright posts (21); the main structures of the right bracket (13) and the left bracket (2) are the same; two cross beams (9) are connected between the top plate (22) on the left support (2) and the top plate (22) on the right support (13), a hinge base (7) is arranged at the top of the left ends of the two cross beams (9), and the hinge base (7) is rotatably connected with a lever (8); the right end of the lever (8) is connected with a hoisting chain (10), the hoisting chain (10) is connected with a hoisting beam (12), and the left side and the right side of the hoisting beam (12) are both connected with hoisting chains (11); a moving beam (17) is arranged between the two upright posts (21) of the left bracket (2), the movable beam (17) is arranged at the lower part of the upright post (21), the upright posts (21) at the left side and the right side of the movable beam (17) are provided with reinforcing plates (19), a guide groove (28) is arranged in the middle of the reinforcing plate (19), guide plates (29) are connected to both ends of the movable beam (17), the guide plate (29) passes through the guide groove (28) and is connected with a guide column (30), the guide post (30) is positioned in the upright post (21) and is connected with the upright post (21) in a sliding way, the middle part of the movable beam (17) is fixedly connected with a hydraulic cylinder connecting plate (18), the hydraulic cylinder connecting plate (18) is rotationally connected with a hydraulic cylinder (3) of the hydraulic push rod (4), and a hydraulic rod (6) of the hydraulic push rod (4) is rotatably connected with the left end of the lever (8).
2. The indoor switchgear installation gantry of claim 1, wherein: the roller (1) is a universal wheel.
3. The indoor switchgear installation gantry of claim 1, wherein: crossbeam (9) with strengthen yoke plate (5) and bolted connection pair through the side between left socle (2) is connected, through the side between crossbeam (9) and right branch frame (13) strengthen yoke plate (5) and bolted connection pair is connected.
4. The indoor switchgear installation gantry of claim 1, wherein: the beam (9) is a telescopic beam with adjustable length.
5. The indoor switchgear installation gantry of claim 1, wherein: and locking bolts (16) are arranged at the lower parts of the two upright columns (21) of the left bracket (2), and one ends of the locking bolts (16) can selectively abut against the guide columns (30).
6. The indoor switchgear installation gantry of claim 1, wherein: the hinge seat (7) is connected with the cross beam (9) through a hinge seat connecting bolt (23), the hinge seat (7) is connected with the lever (8) in a rotating mode through a first rotating shaft (31), and a limiting sleeve (32) is arranged on the first rotating shaft (31).
7. The indoor switchgear installation gantry of claim 1, wherein: both sides on load beam (12) all are provided with locking hole (24), sliding connection has adjusting block (25) on load beam (12), be provided with adjust knob (26) on adjusting block (25), adjusting block (25) bottom is connected with connection link plate (27), connection link plate (27) are connected with sling (11).
8. The indoor switchgear installation gantry of claim 1, wherein: the bottom of the hydraulic cylinder (3) is connected with a connecting clamp plate (34), and the connecting clamp plate (34) is rotatably connected with the hydraulic cylinder connecting plate (18) through a second rotating shaft (33).
CN202021766555.4U 2020-08-21 2020-08-21 Indoor switch cabinet installation portal frame Active CN212245928U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021766555.4U CN212245928U (en) 2020-08-21 2020-08-21 Indoor switch cabinet installation portal frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021766555.4U CN212245928U (en) 2020-08-21 2020-08-21 Indoor switch cabinet installation portal frame

Publications (1)

Publication Number Publication Date
CN212245928U true CN212245928U (en) 2020-12-29

Family

ID=73981835

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021766555.4U Active CN212245928U (en) 2020-08-21 2020-08-21 Indoor switch cabinet installation portal frame

Country Status (1)

Country Link
CN (1) CN212245928U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112061977A (en) * 2020-08-21 2020-12-11 国网河南省电力公司焦作供电公司 Indoor switch cabinet installation gantry and use method
CN118848538A (en) * 2024-07-10 2024-10-29 江苏宁兴恒力智能设备有限公司 An electromagnet automatic unloading mechanism and a steel plate sawing and milling machine including the same

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112061977A (en) * 2020-08-21 2020-12-11 国网河南省电力公司焦作供电公司 Indoor switch cabinet installation gantry and use method
CN118848538A (en) * 2024-07-10 2024-10-29 江苏宁兴恒力智能设备有限公司 An electromagnet automatic unloading mechanism and a steel plate sawing and milling machine including the same

Similar Documents

Publication Publication Date Title
CN203850679U (en) Elevating disassembly and assembly platform with limiting support for current transformer in high-voltage switchgear
CN212245928U (en) Indoor switch cabinet installation portal frame
CN104682238A (en) Lifting platform for replacing mutual inductor in switch cabinet of 35KV or below
CN207200097U (en) Handcart erecting device for switch cubicle in power system
CN204558968U (en) Based on instrument transformer replacing hoistable platform in 35kV and following switch cubicle
CN108557698A (en) Liftable type station trolley
CN104167677A (en) Adjustable special hydraulic moving lifting truck
CN109687329B (en) Rear cabinet door positioning device of switch cabinet
CN203903830U (en) Small framework quickly-assembled jack for equipment
CN218786479U (en) Novel 35kV transformer substation circuit breaker hoist and mount device
CN218708738U (en) Switch cabinet assembly assistance conveyor
WO2026052151A1 (en) Gantry crane mounting and dismounting system and mounting and dismounting method therefor
CN209374992U (en) A kind of withdraw-type switch cabinet inspection platform
CN112061977A (en) Indoor switch cabinet installation gantry and use method
CN113948993B (en) Device for overhauling and maintaining power module of support type converter valve
CN204324741U (en) Load switch of transformer suspended core apparatus
CN205472437U (en) Integrated type machine of lifting in flexible arm and slope
CN218025219U (en) Lifting platform for automobile maintenance
CN214295720U (en) GIS equipment transfer base
CN202026014U (en) Special isolation frame for overhauling GW16 type disconnecting link
CN203855897U (en) Crossing type multifunctional cantilever outer anti-collision wall mounting and moving device
CN209024116U (en) A kind of support device for switchgear CT replacement
CN210307596U (en) Device for replacing current transformer of switch cabinet
CN210779767U (en) A 10kV handcart-type circuit breaker maintenance platform
CN217656297U (en) Large-scale current transformer dismouting device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant