CN212224594U - Steel structure three-dimensional climbing device for super high-rise building - Google Patents

Steel structure three-dimensional climbing device for super high-rise building Download PDF

Info

Publication number
CN212224594U
CN212224594U CN202020243433.0U CN202020243433U CN212224594U CN 212224594 U CN212224594 U CN 212224594U CN 202020243433 U CN202020243433 U CN 202020243433U CN 212224594 U CN212224594 U CN 212224594U
Authority
CN
China
Prior art keywords
fixedly connected
climbing device
rise building
super high
steel structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020243433.0U
Other languages
Chinese (zh)
Inventor
张海峰
张峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Triumpher Steel Structure Group Co ltd
Original Assignee
Triumpher Steel Structure Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Triumpher Steel Structure Group Co ltd filed Critical Triumpher Steel Structure Group Co ltd
Priority to CN202020243433.0U priority Critical patent/CN212224594U/en
Application granted granted Critical
Publication of CN212224594U publication Critical patent/CN212224594U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a three-dimensional climbing device of steel construction for super high-rise building, include the check baffle and put the thing board, the outer fixed surface of check baffle is connected with the fixed block, the top fixedly connected with rotation motor of check baffle, the first bevel gear of output fixedly connected with of rotation motor, the equal fixedly connected with fixed plate in both sides around the check baffle top, two rotate between the fixed plate and be connected with the axis of rotation, the utility model relates to a three-dimensional climbing device technical field. This a three-dimensional climbing device of steel construction for super high-rise building sets up the threaded rod through the bottom at the bracing piece, cooperates two nuts, not only can play the supporting role, is convenient for simultaneously to the dismantlement of putting the thing device, recycles the dead lever of rings both sides and the through-hole on the bracing piece, fixes the bracing piece through the cooperation between gag lever post and the spacing hole, is convenient for dismantle and install it through this structure, easily promotes.

Description

Steel structure three-dimensional climbing device for super high-rise building
Technical Field
The utility model relates to a three-dimensional climbing device technical field specifically is a three-dimensional climbing device of steel construction for surpassing high-rise building.
Background
With the rapid development of economy, the construction industry in China and even all over the world is rapidly developed, more and more machine devices for construction enter the visual field of people, a large number of high-rise buildings, dams and bridges are constructed every year, the engineering buildings continuously climb to high heights, higher requirements are put on the safety of the buildings, higher requirements are put on the safety of peripheral maintenance during the construction of the horizontal structure of the high-rise buildings under different building climatic conditions, the super high-rise buildings refer to buildings with the height of more than 100 meters, and the general climbing devices are troublesome in maintenance or installation operations such as scrubbing, painting and the like of the outer wall of the building.
The steel structure three-dimensional climbing device of the existing building is high in cost, large in size and limited in supporting height, so that the existing three-dimensional climbing device is not suitable for super high-rise buildings, and the existing three-dimensional climbing device is not easy to detach, and is difficult to carry after starting or finishing work at every time, so that the practicability of the existing climbing device is low.
SUMMERY OF THE UTILITY MODEL
The utility model provides a not enough to prior art, the utility model provides a three-dimensional climbing device of steel construction for surpassing high-rise building has solved three-dimensional climbing device, and not only the cost is higher, and is bulky, and the support highly limited moreover to be difficult to the problem of dismantling.
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: the utility model provides a three-dimensional climbing device of steel construction for super high-rise building, includes check baffle and puts the thing board, the outer fixed surface of check baffle is connected with the fixed block, the top fixedly connected with of check baffle rotates the motor, the first bevel gear of output fixedly connected with of motor rotates, the equal fixedly connected with fixed plate in both sides around the check baffle top, two rotate between the fixed plate and be connected with the axis of rotation, the outer fixed surface of axis of rotation is connected with the cylinder, the one end of axis of rotation runs through the fixed plate and extends to the outside of fixed plate, the surface of axis of rotation just is located the back fixedly connected with second bevel gear of cylinder, the surface of first bevel gear meshes with the surface of second bevel gear mutually.
Preferably, the front surface of the fixed block is fixedly connected with a short shaft, one end of the short shaft penetrates through the fixed block and extends to the outside of the fixed block, the outer surface of the short shaft is fixedly connected with a roller, the outer surface of the roller is fixedly connected with a steel wire rope, and the outer surface of the steel wire rope is in contact with the outer surface of the roller.
Preferably, the equal swing joint in both sides at thing board top has the bracing piece, the bottom fixedly connected with threaded rod of bracing piece, the bottom of threaded rod runs through and puts the thing board and extend to the outside of putting the thing board, the surface threaded connection of threaded rod has the nut, the through-hole has been seted up to one side of bracing piece.
Preferably, wire rope's bottom fixedly connected with connecting rod, the both ends fixedly connected with rings of connecting rod, the sliding tray has been seted up to both sides in the rings, the equal sliding connection in both sides of sliding tray internal surface has a sliding block, two one side fixedly connected with dead lever that the sliding block was kept away from relatively, the one end of dead lever and the internal surface swing joint of through-hole.
Preferably, one side of the fixing rod is provided with a limiting hole, and the inner surface of the limiting hole is connected with a limiting rod in a sliding manner.
Preferably, the bottom fixedly connected with spacing ring of putting the thing board, the bottom of putting the thing board just is located the right side fixedly connected with limiting plate of spacing ring.
Preferably, the number of the supporting rods is four, and the supporting rods are distributed around the object placing plate.
Advantageous effects
The utility model provides a three-dimensional climbing device of steel construction for surpassing high-rise building. Compared with the prior art, the method has the following beneficial effects:
(1) the steel structure three-dimensional climbing device for the super high-rise building is characterized in that two sides of the top of the object placing plate are movably connected with supporting rods, the bottom of each supporting rod is fixedly connected with a threaded rod, the bottom end of each threaded rod penetrates through the object placing plate and extends to the outside of the object placing plate, nuts are connected to the outer surface of each threaded rod in a threaded manner, one side of each supporting rod is provided with a through hole, the bottom end of each steel wire rope is fixedly connected with a connecting rod, two ends of each connecting rod are fixedly connected with lifting rings, sliding grooves are formed in two sides in each lifting ring, sliding blocks are slidably connected to two sides of the inner surface of each sliding groove, a fixing rod is fixedly connected to one side, which is far away from each sliding block, one end of each fixing rod is movably, not only can play the supporting role, be convenient for simultaneously to the dismantlement of putting the thing device, recycle the dead lever of rings both sides and the through-hole on the bracing piece, fix the bracing piece through the cooperation between gag lever post and the spacing hole, be convenient for dismantle and install it through this structure, easily promote.
(2) The steel structure three-dimensional climbing device for the super high-rise building comprises a rotary motor fixedly connected to the top of a grid baffle, a first bevel gear fixedly connected to the output end of the rotary motor, fixing plates fixedly connected to the front side and the rear side of the top of the grid baffle, a rotary shaft rotatably connected between the two fixing plates, a roller fixedly connected to the outer surface of the rotary shaft, one end of the rotary shaft penetrates through the fixing plates and extends to the outer parts of the fixing plates, a second bevel gear fixedly connected to the outer surface of the rotary shaft and positioned on the back of the roller, the outer surface of the first bevel gear is meshed with the outer surface of the second bevel gear, a short shaft is fixedly connected to the front of the fixing block, one end of the short shaft penetrates through the fixing block and extends to the outer parts of the fixing block, a, through the rotation of rotating the motor, the meshing of cooperation first bevel gear and second bevel gear drives, drives the rotation of cylinder to can put down or rise wire rope, recycle the gyro wheel on the fixed block and can avoid wire rope's friction, it is less not only to occupy the volume as drive structure through this structure, and the cost is lower simultaneously.
Drawings
FIG. 1 is a front view of the external structure of the climbing device of the present invention;
FIG. 2 is a partial structure plan view of the lattice baffle of the present invention;
fig. 3 is a side view of the external structure of the object placing plate of the present invention.
In the figure: 1-grid baffle, 2-object placing plate, 3-fixed block, 4-rotating motor, 5-first bevel gear, 6-fixed plate, 7-rotating shaft, 8-roller, 9-second bevel gear, 10-short shaft, 11-roller, 12-steel wire rope, 13-supporting rod, 14-threaded rod, 15-nut, 16-through hole, 17-connecting rod, 18-lifting ring, 19-sliding groove, 20-sliding block, 21-fixed rod, 22-limiting hole, 23-limiting rod, 24-limiting ring and 25-limiting plate.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, the present invention provides a technical solution: a steel structure three-dimensional climbing device for a super high-rise building comprises a lattice baffle plate 1 and a storage plate 2, wherein the lattice baffle plate 1 is prevented from being placed on the wall of a top-layer building when the steel structure three-dimensional climbing device is used, a worker stands above the storage plate 2 to operate, the worker needs an additional safety device to fix the storage plate 2, the bottom of the storage plate 2 is fixedly connected with a limiting ring 24, the lattice baffle plate 1 can be connected with other heavy objects through the limiting ring 24, the bottom of the storage plate 2 is fixedly connected with a limiting plate 25 positioned on the right side of the limiting ring 24, the limiting plate 25 is contacted with the wall on the other side to limit the lattice baffle plate 1, two sides of the top of the storage plate 2 are movably connected with supporting rods 13, the number of the supporting rods 13 is four, the supporting rods 13 are distributed around the storage plate 2, the bottom ends of the supporting rods 13 are fixedly connected with threaded rods 14, the bottom ends of the threaded rods, the outer surface of the threaded rod 14 is in threaded connection with a nut 15, the nut 15 is provided with two nuts capable of further enhancing stability, one side of the supporting rod 13 is provided with a through hole 16, the outer surface of the grid baffle 1 is fixedly connected with a fixed block 3, the front surface of the fixed block 3 is fixedly connected with a short shaft 10, one end of the short shaft 10 penetrates through the fixed block 3 and extends to the outside of the fixed block 3, the outer surface of the short shaft 10 is fixedly connected with a roller 11, friction of a steel wire rope 12 can be reduced through the roller 11, so that the service life of the steel wire rope is prolonged, the outer surface of the roller 8 is fixedly connected with the steel wire rope 12, the bottom end of the steel wire rope 12 is fixedly connected with a connecting rod 17, the outer surface of the connecting rod 17 is provided with a groove, the, a fixed rod 21 is fixedly connected to one side of the two sliding blocks 20 which are far away from each other, the hanging ring 18 is lifted during disassembly, the fixed rod 21 is enabled to rotate to the position below the hanging ring 18, a limiting hole 22 is formed in one side of the fixed rod 21, a limiting rod 23 is connected to the inner surface of the limiting hole 22 in a sliding mode, one end of the fixed rod 21 is movably connected with the inner surface of the through hole 16, the outer surface of the steel wire rope 12 is in contact with the outer surface of the roller 11, a rotating motor 4 is fixedly connected to the top of the lattice baffle 1, the rotating motor 4 is electrically connected with an external power source and is controlled by external control light, forward and reverse rotation of the rotating motor 4 can be achieved, a first bevel gear 5 is fixedly connected to the output end of the rotating motor 4, fixed plates 6 are fixedly connected to the front side and the rear side, one end of the rotating shaft 7 penetrates through the fixing plate 6 and extends to the outside of the fixing plate 6, a second bevel gear 9 is fixedly connected to the outer surface of the rotating shaft 7 and positioned on the back surface of the roller 8, and the outer surface of the first bevel gear 5 is meshed with the outer surface of the second bevel gear 9.
When the device works, firstly, the grid baffle 1 is prevented from being placed on the wall of a top-level building, the grid baffle 1 is connected with other heavy objects through the limiting ring 24, then, the rotation of the rotating motor 4 is controlled through an external control switch, the rotation of the rotating motor 4 drives the first bevel gear 5 to rotate, and further drives the second bevel gear 9 to rotate, so that the rotating shaft 7 rotates in a sexual mode, the roller 8 is further driven to rotate, the steel wire rope 12 is put down or rolled up, meanwhile, the roller 11 on the fixing block 3 rotates, so that ascending or descending is realized, when the device needs to be disassembled, the nut 15 on the threaded rod 14 is firstly rotated, all the threaded rod is unscrewed, then the support plate is pulled out of the object placing plate 2, the limiting rod 23 is pulled out of the limiting hole 22, the fixing rod 21 is separated from the support rod 13, and finally the fixing rod 21 slides on the hanging ring 18, and sliding to the bottom.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. The utility model provides a three-dimensional climbing device of steel construction for surpassing high-rise building, includes check baffle (1) and puts thing board (2), the surface fixedly connected with fixed block (3) of check baffle (1), its characterized in that: the utility model discloses a check baffle, including check baffle (1), the top fixedly connected with of check baffle (1) rotates motor (4), the first bevel gear (5) of output fixedly connected with of rotating motor (4), the equal fixedly connected with fixed plate (6) in both sides around check baffle (1) top, two rotate between fixed plate (6) and be connected with axis of rotation (7), the outer fixed surface of axis of rotation (7) is connected with cylinder (8), the one end of axis of rotation (7) runs through fixed plate (6) and extends to the outside of fixed plate (6), the surface of axis of rotation (7) just is located back fixedly connected with second bevel gear (9) of cylinder (8), the surface of first bevel gear (5) meshes with the surface of second bevel gear (9) mutually.
2. The steel structure stereo climbing device for the super high-rise building according to claim 1, wherein: the front fixedly connected with minor axis (10) of fixed block (3), the outside that fixed block (3) and extended to fixed block (3) is run through to the one end of minor axis (10), the external fixed surface of minor axis (10) is connected with gyro wheel (11), the external fixed surface of cylinder (8) is connected with wire rope (12), the surface of wire rope (12) contacts with the surface of gyro wheel (11).
3. The steel structure stereo climbing device for the super high-rise building according to claim 1, wherein: the equal swing joint in both sides at thing board (2) top has bracing piece (13), the bottom fixedly connected with threaded rod (14) of bracing piece (13), the bottom of threaded rod (14) runs through to put thing board (2) and extend to the outside of putting thing board (2), the surface threaded connection of threaded rod (14) has nut (15), through-hole (16) have been seted up to one side of bracing piece (13).
4. The steel structure stereo climbing device for the super high-rise building according to claim 2, wherein: the bottom fixedly connected with connecting rod (17) of wire rope (12), both ends fixedly connected with rings (18) of connecting rod (17), sliding tray (19) have been seted up to both sides in rings (18), the equal sliding connection in both sides of sliding tray (19) internal surface has sliding block (20), two one side fixedly connected with dead lever (21) that sliding block (20) kept away from relatively, the internal surface swing joint of the one end of dead lever (21) and through-hole (16).
5. The steel structure stereo climbing device for the super high-rise building according to claim 4, wherein: one side of the fixing rod (21) is provided with a limiting hole (22), and the inner surface of the limiting hole (22) is connected with a limiting rod (23) in a sliding mode.
6. The steel structure stereo climbing device for the super high-rise building according to claim 1, wherein: the bottom fixedly connected with spacing ring (24) of putting thing board (2), the bottom of putting thing board (2) just is located right side fixedly connected with limiting plate (25) of spacing ring (24).
7. The steel structure stereo climbing device for the super high-rise building according to claim 3, wherein: the number of the supporting rods (13) is four, and the supporting rods (13) are distributed around the object placing plate (2).
CN202020243433.0U 2020-03-03 2020-03-03 Steel structure three-dimensional climbing device for super high-rise building Active CN212224594U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020243433.0U CN212224594U (en) 2020-03-03 2020-03-03 Steel structure three-dimensional climbing device for super high-rise building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020243433.0U CN212224594U (en) 2020-03-03 2020-03-03 Steel structure three-dimensional climbing device for super high-rise building

Publications (1)

Publication Number Publication Date
CN212224594U true CN212224594U (en) 2020-12-25

Family

ID=73913666

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020243433.0U Active CN212224594U (en) 2020-03-03 2020-03-03 Steel structure three-dimensional climbing device for super high-rise building

Country Status (1)

Country Link
CN (1) CN212224594U (en)

Similar Documents

Publication Publication Date Title
CN109095278B (en) Building site uses abandonment cable coiling mechanism
CN111977529A (en) Hoisting tool for construction machinery equipment
CN109629814A (en) A kind of wind-powered electricity generation concrete tower mounting platform
CN212224594U (en) Steel structure three-dimensional climbing device for super high-rise building
CN213060113U (en) Adjustable construction platform for assembly type building
CN219509125U (en) Movable scaffold
CN209482685U (en) A kind of wind-powered electricity generation concrete tower mounting platform
CN213509479U (en) Construction platform convenient to remove
CN214879778U (en) Auxiliary structure is demolishd to tower machine balance arm end attachment piece
CN212541707U (en) Novel architectural design module
CN210460064U (en) Novel building structure supports device
CN210239082U (en) Temporary hydropower integrated bracket for construction site
CN209482686U (en) A kind of revolving platform device of wind-powered electricity generation concrete tower mounting platform
CN219325211U (en) Yaw brake replacing device of wind generating set
CN213539745U (en) Hoist device is used in building engineering construction
CN212406015U (en) Safe building scaffold convenient to move and capable of being automatically lifted
CN216190896U (en) Overhanging type lifting construction platform
CN220098314U (en) Herringbone ladder type water pump overhauling device
CN213476627U (en) Device is demolishd to support for bridge construction
CN214880030U (en) Indoor outer for decoration scaffold frame convenient to adjust
CN212656578U (en) Wind power generation basis crab-bolt cage stock mounting tool
CN216516765U (en) Safety frame for construction site of building engineering
CN220787869U (en) Lifting platform for radial arm crane
CN215291657U (en) Movable multifunctional lifting kiosk
CN219262268U (en) Decoration tool ladder convenient to remove has firm base

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant