CN212224588U - Aerial splicing platform for super-large box-type steel column - Google Patents

Aerial splicing platform for super-large box-type steel column Download PDF

Info

Publication number
CN212224588U
CN212224588U CN201922451430.6U CN201922451430U CN212224588U CN 212224588 U CN212224588 U CN 212224588U CN 201922451430 U CN201922451430 U CN 201922451430U CN 212224588 U CN212224588 U CN 212224588U
Authority
CN
China
Prior art keywords
platform
steel column
plate
lug plate
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201922451430.6U
Other languages
Chinese (zh)
Inventor
于亚会
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Advocating Creation Shanghai Consulting Management Firm
Original Assignee
Advocating Creation Shanghai Consulting Management Firm
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Advocating Creation Shanghai Consulting Management Firm filed Critical Advocating Creation Shanghai Consulting Management Firm
Priority to CN201922451430.6U priority Critical patent/CN212224588U/en
Application granted granted Critical
Publication of CN212224588U publication Critical patent/CN212224588U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Ladders (AREA)

Abstract

The utility model relates to an aerial splicing platform for super-large box-type steel columns, which comprises a guardrail, a steel column, bolts, a lifting lug plate, a steel ladder, an upper manhole, a platform plate, an upper supporting lug plate, an installation bolt hole, a platform, a supporting rod, a connecting plate, a lower supporting lug plate and an installation connecting plate; a lifting lug plate is arranged on the inner side of an upper port of the steel column, and an installation bolt hole is formed in the lifting lug plate; the inner side of the lower port of the steel column is provided with a mounting connecting plate, and a mounting bolt hole is formed in the mounting connecting plate; the platforms are symmetrically arranged on two sides of the steel column, and the upper supporting lug plate and the lower supporting lug plate are respectively symmetrically arranged on the steel column below the platforms; the support rod is arranged between the platform and the lower support lug plate. The utility model has the advantages that: the utility model discloses the aerial concatenation platform that sets up, easy dismounting, the support otic placode and the bracing piece of setting have improved the bearing capacity of whole aerial concatenation platform, have ensured the stability and the security of platform to do benefit to many people and carry out the construction operation simultaneously.

Description

Aerial splicing platform for super-large box-type steel column
Technical Field
The utility model relates to a box steel column field especially relates to an aerial concatenation platform of super large box steel column.
Background
At present, the steel structure construction technology in China is rapidly developed, all components are generally connected into a unit body by welding seams, bolts or rivets, and then are installed, so that the steel structure is widely applied to the fields of large-scale factory buildings, venues, super-high floors and the like. The steel column is one of the main components of the steel structure, and is used for constructing large-scale factories, large-span buildings, bridges and the like, and plays a key role in the quality of the whole steel structure. Due to the limitations of assembly technology, installation technology and construction site, the large box-type steel column can meet the building height by two-section or multi-section welding and splicing. Need the installation to set up aerial concatenation platform when large-scale box steel column concatenation installation and be used for assisting workman's welding concatenation operation, but traditional welded platform often bearing capacity is limited, has the potential safety hazard, also can not satisfy many people's operation simultaneously, causes the construction progress slow.
In summary, it is very important to find an air splicing platform for super-large box-type steel columns, which can be quickly spliced and greatly improve the bearing capacity of the platform.
SUMMERY OF THE UTILITY MODEL
The utility model aims at overcoming not enough among the prior art, providing an aerial concatenation platform of super large box steel column.
The air splicing platform for the oversized box-type steel column comprises guardrails, the steel column, bolts, lifting lug plates, a steel ladder stand, an upper manhole, a platform plate, upper supporting lug plates, mounting bolt holes, a platform, supporting rods, a connecting plate, lower supporting lug plates and mounting connecting plates; a lifting lug plate is arranged on the inner side of an upper port of the steel column, and an installation bolt hole is formed in the lifting lug plate; the inner side of the lower port of the steel column is provided with a mounting connecting plate, and a mounting bolt hole is formed in the mounting connecting plate; the platforms are symmetrically arranged on two sides of the steel column, and the upper supporting lug plate and the lower supporting lug plate are respectively symmetrically arranged on the steel column below the platforms; the supporting rod is arranged between the platform and the lower supporting lug plate, the lower end of the supporting rod is provided with a connecting plate, and the connecting plate is connected with the lower supporting lug plate through a bolt; the upper manhole is arranged at a suspension part at one side between the two symmetrical platforms; the platform plate is arranged at a suspension part between the two symmetrical platforms and is connected with the platforms through bolts; the steel crawling ladder is arranged on one side of the upper manhole; the guardrail sets up around the platform.
Preferably, the method comprises the following steps: the upper supporting lug plate is connected with the platform through a bolt.
Preferably, the method comprises the following steps: the connecting part of the platform and the platform plate is correspondingly provided with a bolt hole.
The utility model has the advantages that: the utility model discloses the aerial concatenation platform that sets up, easy dismounting, the support otic placode and the bracing piece of setting have improved the bearing capacity of whole aerial concatenation platform, have ensured the stability and the security of platform to do benefit to many people and carry out the construction operation simultaneously.
Drawings
FIG. 1 is a top view of an aerial splicing platform for oversized box-type steel columns;
fig. 2 is a sectional view a-a in fig. 1.
Description of reference numerals: 1-a guardrail; 2-steel column; 3-bolt; 4-bolt holes; 5-lifting lug plate; 6-steel ladder; 7-upper manhole; 8-a platform plate; 9-upper supporting ear plate; 10-mounting bolt hole; 11-a platform; 12-a support bar; 13-connecting plate; 14-lower supporting ear plate; 15-mounting the connecting plate.
Detailed Description
The present invention will be further described with reference to the following examples. The following description of the embodiments is merely provided to aid in understanding the invention. It should be noted that, for those skilled in the art, without departing from the principle of the present invention, the present invention can be further modified and modified, and such modifications and modifications also fall within the protection scope of the appended claims.
As shown in fig. 1-2, firstly, the steel column 2 is welded and assembled in the finalized ground assembly system, and then the aerial assembly platform is welded and installed. The inboard welding of 2 one end ports on steel column lifts by crane otic placode 5, the inboard welding erection joint board 15 of 2 other end ports on steel column, it all is provided with mounting key hole 10 on otic placode 5 and the erection joint board 15 to lift by crane, platform 11 symmetry sets up in 2 both sides on the steel column, it installs on steel column 2 of platform 11 below to go up support otic placode 9 and lower support otic placode 14 symmetry respectively, bracing piece 12 lower extreme welding joint board 13, and link to each other through bolt 3 with lower support otic placode 14, one side suspended portion sets up manhole 7 between the platform 11 of two symmetries, platform 8 is installed and is suspended portion between the platform 11 of two symmetries, use bolt 3 to link to each other with platform 11, steel cat ladder 6 sets up in last manhole 7 one side, guardrail 1. And (3) temporarily and fixedly mounting the assembled aerial splicing platform on the top of the steel column 2 in advance, and hoisting the assembled aerial splicing platform and the steel column 2 at the same time.
The upper support lug 9 is connected to the platform 11 by means of bolts 3.
The connecting part of the platform 11 and the platform plate 8 is correspondingly provided with a bolt hole 4.

Claims (3)

1. Aerial splicing platform of super large box steel column, its characterized in that: the steel lifting device comprises guardrails (1), steel columns (2), bolts (3), lifting lug plates (5), steel crawling ladders (6), upper manholes (7), platform plates (8), upper supporting lug plates (9), mounting bolt holes (10), platforms (11), supporting rods (12), connecting plates (13), lower supporting lug plates (14) and mounting connecting plates (15); a lifting lug plate (5) is arranged on the inner side of the upper port of the steel column (2), and a mounting bolt hole (10) is formed in the lifting lug plate (5); a mounting connecting plate (15) is arranged on the inner side of the lower port of the steel column (2), and a mounting bolt hole (10) is formed in the mounting connecting plate (15); the platforms (11) are symmetrically arranged on two sides of the steel column (2), and the upper supporting lug plates (9) and the lower supporting lug plates (14) are respectively symmetrically arranged on the steel column (2) below the platforms (11); the supporting rod (12) is arranged between the platform (11) and the lower supporting lug plate (14), the lower end of the supporting rod (12) is provided with a connecting plate (13), and the connecting plate (13) is connected with the lower supporting lug plate (14) through a bolt (3); the upper manhole (7) is arranged at one side of a suspension part between two symmetrical platforms (11); the platform plate (8) is arranged at a suspension part between the two symmetrical platforms (11) and is connected with the platforms (11) through bolts (3); the steel crawling ladder (6) is arranged on one side of the upper manhole (7); the guardrail (1) is arranged around the platform (11).
2. The aerial splicing platform for extra-large box-type steel columns according to claim 1, characterized in that: the upper supporting lug plate (9) is connected with the platform (11) through a bolt (3).
3. The aerial splicing platform for extra-large box-type steel columns according to claim 1, characterized in that: the connecting part of the platform (11) and the platform plate (8) is correspondingly provided with a bolt hole (4).
CN201922451430.6U 2019-12-30 2019-12-30 Aerial splicing platform for super-large box-type steel column Active CN212224588U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922451430.6U CN212224588U (en) 2019-12-30 2019-12-30 Aerial splicing platform for super-large box-type steel column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922451430.6U CN212224588U (en) 2019-12-30 2019-12-30 Aerial splicing platform for super-large box-type steel column

Publications (1)

Publication Number Publication Date
CN212224588U true CN212224588U (en) 2020-12-25

Family

ID=73901696

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922451430.6U Active CN212224588U (en) 2019-12-30 2019-12-30 Aerial splicing platform for super-large box-type steel column

Country Status (1)

Country Link
CN (1) CN212224588U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115874797A (en) * 2022-11-29 2023-03-31 浙江精工钢结构集团有限公司 Portable bolt type steel column operating platform and installing and detaching method thereof
CN116290705A (en) * 2023-02-17 2023-06-23 淮安市建筑设计研究院有限公司 Spliced box-type steel column construction platform and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115874797A (en) * 2022-11-29 2023-03-31 浙江精工钢结构集团有限公司 Portable bolt type steel column operating platform and installing and detaching method thereof
CN116290705A (en) * 2023-02-17 2023-06-23 淮安市建筑设计研究院有限公司 Spliced box-type steel column construction platform and construction method thereof

Similar Documents

Publication Publication Date Title
CN104847123B (en) Connect the building method of steel corridor
CN108862045B (en) Special-shaped steel truss beam member turning device and method for turning member
CN209025103U (en) Pile base structures for emergency access or emergency bridges
CN212224588U (en) Aerial splicing platform for super-large box-type steel column
CN114197325A (en) Pier shaft construction safety protection platform
CN204753397U (en) Temporary mounting hanger for steel box bridge
CN109653517B (en) Multidirectional unloading system and construction method for assembling steel corridor by using same
CN204282803U (en) To encorbelment formwork structure for mounting platform
CN107761543A (en) A kind of apparatus and method of rapid build large span lightweight emergency bridge
CN208071235U (en) A kind of bearing and lifting system of steel truss frame integral hoisting
CN103723638B (en) Climbing frame of tower crane and tower crane
CN211689948U (en) A suspension operation platform device for the construction of a cable-stayed bridge tower
CN211340840U (en) Tower crane foundation of internal climbing tower crane
CN102071794B (en) Unit member attached with elevating scaffold horizontal support truss standard section
CN106522207A (en) Reinforcement cage bracket and reinforcement cage mounting device
CN116657955A (en) A BIM-based prefabricated steel structure support system and its application method
CN212129965U (en) Interim securing device is assembled in air to box steel construction post
CN218541445U (en) Hanging type construction protection platform device
CN110886225A (en) Construction method of cable tower stay cable installation system
CN205840289U (en) A kind of suspension type vertical operating platform
CN212224669U (en) Super large box steel column installation system
CN206337555U (en) Steel reinforcement cage support and steel reinforcement cage erecting device
CN102127962B (en) The bidirectional stress base section of the attached lift scaffold improved
CN214062433U (en) Temporary supporting structure of assembled steel structure
CN214885399U (en) Adjustable operation construction equipment of steel column

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant