CN212202062U - Pipe jacking construction equipment - Google Patents

Pipe jacking construction equipment Download PDF

Info

Publication number
CN212202062U
CN212202062U CN202020681326.6U CN202020681326U CN212202062U CN 212202062 U CN212202062 U CN 212202062U CN 202020681326 U CN202020681326 U CN 202020681326U CN 212202062 U CN212202062 U CN 212202062U
Authority
CN
China
Prior art keywords
plate
jack
push
pipe jacking
construction equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN202020681326.6U
Other languages
Chinese (zh)
Inventor
潘晨璐
袁凌超
彭开颜
陈大超
姚智琪
李静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Kaiyuan Highway And Bridge Co ltd
China Coal No 3 Construction Group Co Ltd
Original Assignee
Anhui Kaiyuan Highway And Bridge Co ltd
China Coal No 3 Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Kaiyuan Highway And Bridge Co ltd, China Coal No 3 Construction Group Co Ltd filed Critical Anhui Kaiyuan Highway And Bridge Co ltd
Priority to CN202020681326.6U priority Critical patent/CN212202062U/en
Application granted granted Critical
Publication of CN212202062U publication Critical patent/CN212202062U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本实用新型涉及一种顶管施工设备,包括设置在工作井的预埋钢板,预埋钢板上设置有用于固定千斤顶缸体的安装位,预埋钢板上设置有至少两个推动单元管节的推板,推板的板面立式布置且对称设置在预埋钢板上,千斤顶的油缸启动且连动推板水平移动,推板与单元管节的一端抵靠且朝向工作井的洞口移动,该顶管施工设备在实际施工过程中,在待施工的路径中段位置挖设工作井,将该顶管施工设备的预埋钢板吊送至工作井的低端位置,而后安装固定,并且将千斤顶缸体固定在预埋钢板的安装位,用于推送单元管节的推板对称设置在预埋钢板上,启动千斤顶能够实现对工作井双向的井孔进行顶管操作,显著机头的周转利用率,进而可显著提高顶管的施工效率。

Figure 202020681326

The utility model relates to a pipe jacking construction equipment, comprising a pre-embedded steel plate arranged in a working well, an installation position for fixing a jack cylinder body is arranged on the pre-embedded steel plate, and at least two push-unit pipe sections are arranged on the pre-embedded steel plate. Push plate, the plate surface of the push plate is arranged vertically and symmetrically on the embedded steel plate, the oil cylinder of the jack starts and moves the push plate horizontally, the push plate abuts one end of the unit pipe section and moves towards the hole of the working well, In the actual construction process of the pipe jacking construction equipment, a working well is dug at the middle of the path to be constructed, the pre-embedded steel plate of the pipe jacking construction equipment is hoisted to the low end of the working well, and then installed and fixed, and the jack The cylinder body is fixed at the installation position of the embedded steel plate, and the push plate used to push the unit pipe section is symmetrically arranged on the embedded steel plate. The start-up jack can realize the pipe jacking operation of the two-way well hole of the working well, and the turnover of the machine head can be greatly utilized. rate, which can significantly improve the construction efficiency of pipe jacking.

Figure 202020681326

Description

顶管施工设备Pipe jacking construction equipment

技术领域technical field

本实用新型涉及工程技术领域,尤其是一种顶管施工设备。The utility model relates to the technical field of engineering, in particular to a pipe jacking construction equipment.

背景技术Background technique

顶管机在常规的泥水平衡(土压平衡)施工中经常见到,上述泥水平衡施工工艺中,顶管机顶压住单元管节单次只能向一个方向顶进,这是因为用于顶压单元管节朝向洞口内移动的千斤顶缸体需要后靠背支撑,所述靠背设置在顶进的反方向,上述的靠背多为混凝土成型靠背,在单元管节顶入洞口施工之前,需要在工作井的底部用混凝土制作成靠背,待2到3天方能确保靠背完全凝固,而后对千斤顶的安装,因此在实施对单元管节顶管操作时,造成效率低下,在实施对洞口另一端的管节顶管操作时,需要重新安装轨道和重新调入机头,花费时间很长,降低了机头的周转利用率。The pipe jacking machine is often seen in the conventional mud-water balance (earth pressure balance) construction. In the above mud-water balance construction process, the pipe jacking machine can only push the unit pipe section in one direction at a time. The jack cylinder that pushes the unit tube section toward the hole needs to be supported by a backrest, and the backrest is arranged in the opposite direction of the jacking. The above-mentioned backrests are mostly concrete formed backrests. The bottom of the working well is made of concrete as the backrest. It takes 2 to 3 days to ensure that the backrest is completely solidified, and then the jack is installed. Therefore, when the pipe jacking operation of the unit pipe section is carried out, it will cause low efficiency. During the pipe jacking operation of the pipe section, it is necessary to re-install the track and re-adjust the machine head, which takes a long time and reduces the turnover rate of the machine head.

实用新型内容Utility model content

本实用新型的目的在于:提供一种顶管施工设备,可显著提高顶管施工的效率,能够同时实现对工作井多方向的顶管操作。The purpose of the utility model is to provide a pipe jacking construction equipment, which can significantly improve the efficiency of the pipe jacking construction, and can simultaneously realize the multi-directional pipe jacking operation of the working well.

本实用新型中的解决技术问题采用如下技术方案:Solving the technical problem in the utility model adopts the following technical scheme:

一种顶管施工设备,包括设置在工作井的预埋钢板,所述预埋钢板上设置有用于固定千斤顶缸体的安装位,所述预埋钢板上设置有至少两个推动单元管节的推板,所述推板的板面立式布置且对称设置在预埋钢板上,所述千斤顶的油缸启动且连动推板水平移动,所述推板与单元管节的一端抵靠且朝向工作井的洞口移动。A pipe jacking construction equipment includes a pre-embedded steel plate arranged in a working well, the pre-embedded steel plate is provided with a mounting position for fixing a jack cylinder, and at least two push-unit pipe sections are provided on the pre-embedded steel plate. Push plate, the plate surface of the push plate is vertically arranged and symmetrically arranged on the embedded steel plate, the oil cylinder of the jack is activated and moves horizontally in conjunction with the push plate, the push plate abuts against one end of the unit tube section and faces toward The opening of the working well moves.

本实用新型还存在以下技术特征:The utility model also has the following technical features:

所述千斤顶的缸体竖直布置,所述千斤顶通过连动机构与推板连接,所述千斤顶竖直移动且连动推板水平移动。The cylinder body of the jack is arranged vertically, the jack is connected with the push plate through a linkage mechanism, and the jack moves vertically and moves horizontally in conjunction with the push plate.

所述预埋钢板的周向方向间隔设置有撑杆,所述撑杆的杆端与工作井的内壁抵靠。The pre-embedded steel plate is provided with struts at intervals in the circumferential direction, and the rod ends of the struts abut against the inner wall of the working well.

所述撑杆的一端与预埋钢板铰接,所述撑杆的铰接轴水平布置,所述撑杆与支撑机构连接,所述支撑机构用于调节撑杆与预埋钢板之间的夹角。One end of the strut is hinged with the embedded steel plate, the hinge axis of the strut is arranged horizontally, and the strut is connected with a support mechanism for adjusting the angle between the strut and the embedded steel plate.

所述支撑机构包括支撑滚轮,所述支撑滚轮的轮芯水平且与撑杆长度方向垂直,所述支撑滚轮的轮缘与撑杆的杆身抵靠,所述支撑滚轮的轮架固定在调节板上,所述调节板上立式布置有调节丝杆,所述调节丝杆的上端伸出预埋钢板的上板面,所述调节丝杆的上端设置有调节螺母。The support mechanism includes a support roller, the wheel core of the support roller is horizontal and perpendicular to the length direction of the strut, the rim of the support roller is in contact with the shaft of the strut, and the wheel frame of the support roller is fixed on the adjusting rod. On the plate, an adjustment screw is vertically arranged on the adjustment plate, the upper end of the adjustment screw extends out of the upper plate surface of the pre-embedded steel plate, and the upper end of the adjustment screw is provided with an adjustment nut.

所述撑杆为伸缩杆结构,所述撑杆的前端铰接设置有弧形顶板,所述弧形顶板的外缘与工作井的内壁抵靠,所述弧形顶板的铰接轴水平且与撑杆垂直布置。The strut is a telescopic rod structure, the front end of the strut is hingedly provided with an arc top plate, the outer edge of the arc top plate abuts against the inner wall of the working well, and the hinge axis of the arc top plate is horizontal and is in line with the strut. The rods are arranged vertically.

所述推板的下端与轨道构成水平方向的滑动配合,所述轨道水平且平行间隔设置有两排。The lower end of the push plate and the rail form a horizontal sliding fit, and the rail is arranged in two rows horizontally and at a parallel interval.

所述轨道的前端设置有承接单元管节的接料滑架,所述接料滑架由多根接料滑杆水平间隔构成,所述多根接料滑杆与轨道平行布置,所述多根接料滑杆围合成弧形板结构,所述接料滑架与轨道构成长度方向的位置可调配合。The front end of the track is provided with a material receiving carriage for receiving the unit tube section, and the material receiving carriage is composed of a plurality of material receiving sliding bars at horizontal intervals, and the plurality of material receiving sliding bars are arranged in parallel with the track, and the The root splicing slide bar is enclosed into an arc-shaped plate structure, and the splicing carriage and the track form an adjustable fit in the length direction.

所述多根接料滑杆的两端设置有安装支杆,所述安装支杆竖直向下延伸且构成一体,所述推板的外缘整体呈圆弧形板状结构,所述推板的边缘设置有避让缺口,所述避让缺口沿着沿着推板的长度方向贯穿布置,所述避让缺口用于与接料滑杆形成避让。The two ends of the plurality of material receiving sliding rods are provided with installation support rods, the installation support rods extend vertically downward and form an integral body, and the outer edge of the push plate has an arc-shaped plate structure as a whole. The edge of the plate is provided with avoidance gaps, the avoidance gaps are arranged along the length direction of the push plate, and the avoidance gaps are used to form a gap with the material receiving slide bar.

所述预埋钢板上立式设置有立柱,所述立柱上设置有用于固定千斤顶的固定法兰盘,所述千斤顶的活塞杆竖直向下且与推杆的一端铰接,所述推杆的另一端与推板铰接,所述推杆两端的铰接轴水平且与推板的移动方向垂直,所述工作井的底部预制有底板,所述底板上立式设置有预留螺栓,所述预留螺栓上端伸出固定法兰盘的上板面且设置有螺母。The pre-embedded steel plate is vertically provided with a column, and the column is provided with a fixed flange for fixing the jack. The piston rod of the jack is vertically downward and is hinged with one end of the push rod. The other end is hinged with the push plate, the hinge shafts at both ends of the push rod are horizontal and perpendicular to the moving direction of the push plate, the bottom of the working well is prefabricated with a bottom plate, and the bottom plate is vertically provided with reserved bolts. The upper end of the left bolt protrudes from the upper plate surface of the fixed flange and is provided with a nut.

与已有技术相比,本实用新型的有益效果体现在:该顶管施工设备在实际施工过程中,在待施工的路径中段位置挖设工作井,将该顶管施工设备的预埋钢板吊送至工作井的低端位置,而后安装固定,并且将千斤顶缸体固定在预埋钢板的安装位,用于推送单元管节的推板对称设置在预埋钢板上,启动千斤顶能够实现对工作井双向的井孔进行顶管操作,显著机头的周转利用率,进而可显著提高顶管的施工效率。Compared with the prior art, the beneficial effect of the present utility model is reflected in: in the actual construction process of the pipe jacking construction equipment, a working well is dug at the middle of the path to be constructed, and the pre-embedded steel plate of the pipe jacking construction equipment is hoisted. It is sent to the low-end position of the working well, and then installed and fixed, and the jack cylinder is fixed at the installation position of the embedded steel plate, and the push plate used to push the unit pipe section is symmetrically arranged on the embedded steel plate. The pipe jacking operation is carried out in the two-way wellbore of the well, which can significantly improve the turnover rate of the machine head, thereby significantly improving the construction efficiency of the pipe jacking.

附图说明Description of drawings

图1和图2是顶管施工设备位于工作井内的两种视角结构示意图;Fig. 1 and Fig. 2 are two kinds of perspective structure schematic diagrams that the pipe jacking construction equipment is located in the working well;

图3是顶管施工设备位于工作井内且移出底板后的结构示意图;Fig. 3 is the structural schematic diagram after the pipe jacking construction equipment is located in the working well and removed from the bottom plate;

图4是顶管施工设备为与工作井内的主视图;Fig. 4 is the front view of pipe jacking construction equipment and working well;

图5是顶管施工设备的结构示意图;Fig. 5 is the structural representation of pipe jacking construction equipment;

图6是顶管施工设备的主视图;Fig. 6 is the front view of pipe jacking construction equipment;

图7和图8是顶管施工设备中部分结构的两种视角结构示意图;Fig. 7 and Fig. 8 are two kinds of perspective structure schematic diagrams of the partial structure in the pipe jacking construction equipment;

图9是推板的结构示意图。FIG. 9 is a schematic diagram of the structure of the push plate.

具体实施方式Detailed ways

参照图1至图9,对本顶管施工设备的结构特征详述如下:1 to 9, the structural features of the pipe jacking construction equipment are described in detail as follows:

一种顶管施工设备,包括设置在工作井10的预埋钢板20,所述预埋钢板20上设置有用于固定千斤顶30缸体的安装位,所述预埋钢板20上设置有至少两个推动单元管节的推板40,所述推板40的板面立式布置且对称设置在预埋钢板20上,所述千斤顶30的油缸启动且连动推板40水平移动,所述推板40与单元管节的一端抵靠且朝向工作井10的洞口移动;A pipe jacking construction equipment includes a pre-embedded steel plate 20 arranged on a working well 10, the pre-embedded steel plate 20 is provided with an installation position for fixing the cylinder body of the jack 30, and at least two Pushing the push plate 40 of the unit tube section, the plate surface of the push plate 40 is vertically arranged and symmetrically arranged on the embedded steel plate 20, the oil cylinder of the jack 30 is activated and moves the push plate 40 horizontally, the push plate 40 abuts one end of the unit pipe section and moves toward the opening of the working well 10;

结合图1至图5所示,该顶管设备设备吊送至工作井10内之前,首先需要进行工作井10的挖设,在顶管施工路径的中段位置挖设该工作井10,工作井10内预先预留安装螺栓用于安装预埋钢板20,利用桁吊将该预埋钢板20吊设在工作筋10内,并且通过预埋螺栓固定,而后,将千斤顶30的缸体安装在预埋钢板20的安装位上,启动千斤顶30,连动推板40朝向各自的洞口顶进,从而实现对工作井10双向的同时顶管操作,当工作井的井孔一侧的机头出现故障时,工作井另一侧还能正常行进,以减少由于单向顶进时出现机头故障导致整个工程停工的严重问题。1 to 5, before the pipe jacking equipment is hoisted into the working well 10, the working well 10 needs to be excavated first, and the working well 10 is dug at the middle position of the pipe jacking construction path. Installation bolts are reserved in advance in the 10 for installing the embedded steel plate 20. The embedded steel plate 20 is hoisted in the working rib 10 by a truss crane, and fixed by the embedded bolts. Then, the cylinder body of the jack 30 is installed in the On the installation position of the buried steel plate 20, the jack 30 is activated, and the push plate 40 is driven to advance toward the respective holes, so as to realize the simultaneous pipe jacking operation of the working well 10 in both directions. At the same time, the other side of the working well can still travel normally, so as to reduce the serious problem of shutdown of the whole project due to the failure of the machine head during one-way jacking.

作为本实用新型的优选方案,为减少千斤顶30占用工作井10的横向空间,使得工作井10留有充足的横向空间用来布置其他设备,所述千斤顶30的缸体竖直布置,所述千斤顶30通过连动机构与推板40连接,所述千斤顶30竖直移动且连动推板40水平移动;As a preferred solution of the present invention, in order to reduce the horizontal space of the working well 10 occupied by the jack 30, so that the working well 10 has sufficient lateral space for arranging other equipment, the cylinder body of the jack 30 is arranged vertically, and the jack 30 is arranged vertically. 30 is connected with the push plate 40 through a linkage mechanism, the jack 30 moves vertically and moves horizontally with the push plate 40;

上述的千斤顶30竖直移动,将竖直移动转化为推板40的水平移动,从而实现对单元管节一端的顶进操作,逐渐对顶管进行顶进,完成施工操作,上述的千斤顶30竖向布置,使得千斤顶30在工作井10内的横向占用空间较小,从而预留有足够的空间供其他设备安装。The above-mentioned jack 30 moves vertically, and the vertical movement is converted into the horizontal movement of the push plate 40, thereby realizing the jacking operation of one end of the unit pipe section, gradually jacking the jacking pipe, and completing the construction operation, the above-mentioned jack 30 is vertical. The horizontal arrangement of the jack 30 in the working well 10 is small, so that enough space is reserved for other equipment to be installed.

为实现对预埋钢板20的稳定可靠安装,所述预埋钢板20的周向方向间隔设置有撑杆50,所述撑杆50的杆端与工作井10的内壁抵靠;In order to realize the stable and reliable installation of the embedded steel plate 20, struts 50 are arranged at intervals in the circumferential direction of the embedded steel plate 20, and the rod ends of the struts 50 abut against the inner wall of the working well 10;

首先利用桁吊设备将预埋钢板20吊设在工作井10内,并且平稳安装,利用撑杆50的杆端与工作井10的内壁抵靠并且安装,从而可有效实现对该预埋钢板20进行有效的固定安装,避免千斤顶30工作时的反向作用下,使得预埋钢板20抬起;First, the embedded steel plate 20 is hoisted in the working well 10 by using the truss hoisting equipment, and installed smoothly. The rod end of the strut 50 is used to abut and install the inner wall of the working well 10, so that the embedded steel plate 20 can be effectively realized. Carry out effective fixed installation to avoid the lifting of the embedded steel plate 20 under the reverse action of the jack 30 during operation;

为实现对撑杆50与工作井10的内壁有效抵靠,确保整个设备的稳定安装,所述撑杆50的一端与预埋钢板20铰接,所述撑杆50的铰接轴水平布置,所述撑杆50与支撑机构连接,所述支撑机构用于调节撑杆50与预埋钢板20之间的夹角;In order to effectively abut the strut 50 with the inner wall of the working well 10 and ensure the stable installation of the entire equipment, one end of the strut 50 is hinged with the embedded steel plate 20, and the hinge shaft of the strut 50 is arranged horizontally. The strut 50 is connected with a support mechanism, and the support mechanism is used to adjust the angle between the strut 50 and the embedded steel plate 20;

桁吊设备吊送预埋钢板20时,撑杆50斜向下延伸,并且预埋钢板20水平状态沉入工作井10的井底位置,而后撑杆50的杆端与工作井10的内壁抵靠,调节支撑机构,减少撑杆50与预埋钢板20之间的夹角,使得夹角变小,进而能够使得撑杆50的杆端与工作井10的内壁稳定抵靠,以确保对整个设备的顶紧安装操作。When the truss hoisting equipment lifts the embedded steel plate 20, the support rod 50 extends downward obliquely, and the embedded steel plate 20 is sunk into the bottom of the working well 10 in a horizontal state, and the rod end of the rear support rod 50 is in contact with the inner wall of the working well 10. Rely, adjust the support mechanism to reduce the included angle between the strut 50 and the embedded steel plate 20, so that the included angle becomes smaller, so that the rod end of the strut 50 can be stably abutted against the inner wall of the working well 10 to ensure that the entire The jack-up installation operation of the device.

为实现对撑杆50与预埋钢板20之间夹角的调整,所述支撑机构包括支撑滚轮51,所述支撑滚轮51的轮芯水平且与撑杆50长度方向垂直,所述支撑滚轮51的轮缘与撑杆50的杆身抵靠,所述支撑滚轮51的轮架固定在调节板52上,所述调节板52上立式布置有调节丝杆53,所述调节丝杆53的上端伸出预埋钢板20的上板面,所述调节丝杆53的上端设置有调节螺母54;In order to realize the adjustment of the angle between the strut 50 and the embedded steel plate 20 , the support mechanism includes a support roller 51 . The wheel core of the support roller 51 is horizontal and perpendicular to the length direction of the strut 50 . The rim of the wheel is in contact with the shaft of the support rod 50, the wheel frame of the support roller 51 is fixed on the adjustment plate 52, and the adjustment screw 53 is vertically arranged on the adjustment plate 52. The upper end protrudes from the upper plate surface of the embedded steel plate 20, and the upper end of the adjusting screw rod 53 is provided with an adjusting nut 54;

在实际调节操作时,当预埋钢板20吊设在工作井10的井底后,利用大扳手工具拧动调节螺母54,使得调节板52向上抬升,从而使得支撑滚轮51朝向撑杆51的杆端移动,进而使得撑杆51与预埋钢板20之间的夹角变小,从而能够有效将预埋钢板20固定在工作井10内,以实现对设备的有效固定。During the actual adjustment operation, after the pre-embedded steel plate 20 is hung at the bottom of the working well 10, the adjustment nut 54 is twisted with a large wrench tool, so that the adjustment plate 52 is lifted upward, so that the support roller 51 faces the rod of the support rod 51 The ends move, so that the angle between the strut 51 and the embedded steel plate 20 is reduced, so that the embedded steel plate 20 can be effectively fixed in the working well 10 to effectively fix the equipment.

更为具体地,所述撑杆50为伸缩杆结构,所述撑杆50的前端铰接设置有弧形顶板55,所述弧形顶板55的外缘与工作井10的内壁抵靠,所述弧形顶板55的铰接轴水平且与撑杆50垂直布置;More specifically, the support rod 50 is a telescopic rod structure, the front end of the support rod 50 is hingedly provided with an arc-shaped top plate 55, and the outer edge of the arc-shaped top plate 55 abuts against the inner wall of the working well 10. The hinge axis of the arc-shaped top plate 55 is horizontal and vertically arranged with the strut 50;

上述的撑杆50为套杆状结构,从而方便实现对撑杆50长度进行调节,调节合适的长度后,将整个预埋钢板20及撑杆50吊设在工作井10内,以实现对预埋钢板20的固定,而后转动调节螺母54,使得弧形顶板55的边缘与工作井10的内壁抵靠,以实现对整个设备的稳定固定,并且调整好推板40的位置,使得推板40的移动方向恰好位于井孔的孔口位置处。The above-mentioned support rod 50 is a sleeve-shaped structure, so as to facilitate the adjustment of the length of the support rod 50. After adjusting the appropriate length, the entire embedded steel plate 20 and the support rod 50 are hoisted in the working well 10, so as to realize the adjustment of the pre-embedded steel plate 20 and the support rod 50. Fix the buried steel plate 20, and then rotate the adjusting nut 54 to make the edge of the arc top plate 55 abut against the inner wall of the working well 10 to achieve stable fixation of the entire equipment, and adjust the position of the push plate 40 so that the push plate 40 The direction of movement is exactly at the orifice position of the wellbore.

为实现对单元管节的水平渐进式推送,所述推板40的下端与轨道60构成水平方向的滑动配合,所述轨道60水平且平行间隔设置有两排。In order to realize the horizontal and progressive push of the unit tube section, the lower end of the push plate 40 and the rail 60 form a horizontal sliding fit, and the rail 60 is arranged in two rows horizontally and parallel to each other.

更为优选地,所述轨道60的前端设置有承接单元管节的接料滑架61,所述接料滑架61由多根接料滑杆611水平间隔构成,所述多根接料滑杆611与轨道60平行布置,所述多根接料滑杆611围合成弧形板结构,所述接料滑架61与轨道60构成长度方向的位置可调配合;More preferably, the front end of the rail 60 is provided with a material receiving carriage 61 for receiving the unit tube section. The rods 611 are arranged in parallel with the rails 60, the plurality of splicing sliding rods 611 are enclosed in an arc-shaped plate structure, and the splicing carriages 61 and the rails 60 form an adjustable fit in the length direction;

上述的接料滑架61能够有效实现对单个单元管节的兜起来,使得单元管节为管芯水平的状态与接料滑杆611的杆身抵靠,启动上述的千斤顶30,使得推板40水平移动且与接料滑杆611的移动方向平行,从而能够有效将单元管节水平推送至井孔内,以实现对单元管节的逐渐推送操作。The above-mentioned feeding carriage 61 can effectively realize the pocketing of a single unit tube section, so that the unit tube section is in a state where the tube core is horizontal and abuts the shaft of the feeding sliding rod 611, and the above-mentioned jack 30 is activated to make the push plate. 40 moves horizontally and is parallel to the moving direction of the material receiving slide bar 611, so that the unit pipe section can be effectively pushed horizontally into the wellbore, so as to realize the gradual pushing operation of the unit pipe section.

更为具体地,为有效将单元管节推送至井孔内,并且使得单元管节与滑架61分离,所述多根接料滑杆611的两端设置有安装支杆612,所述安装支杆612竖直向下延伸且构成一体,所述推板40的外缘整体呈圆弧形板状结构,所述推板40的边缘设置有避让缺口41,所述避让缺口41沿着沿着推板40的长度方向贯穿布置,所述避让缺口41用于与接料滑杆611形成避让;More specifically, in order to effectively push the unit pipe section into the wellbore and separate the unit pipe section from the carriage 61, the two ends of the plurality of material receiving sliding rods 611 are provided with installation support rods 612. The support rod 612 extends vertically downward and is integrally formed. The outer edge of the push plate 40 has a circular arc-shaped plate structure as a whole. The push plate 40 is arranged through the length direction, and the avoidance gap 41 is used to form a gap with the material receiving slide bar 611;

千斤顶30启动后,连动推板40水平移动,推板40水平移动且使得避让缺口41与接料滑杆611形成水平方向移动时的避让,从而能够有效将接料滑杆611上的单元管节从井孔的一端逐渐顶入,以完成顶管操作,通过调节接料滑架61与轨道60的位置,以适配接料滑架61与井孔的位置,以确保单元管节顶入井孔后,能够与接料滑架61有效脱离。After the jack 30 is activated, the push plate 40 moves horizontally, and the push plate 40 moves horizontally so that the avoidance gap 41 and the material receiving slide bar 611 form an avoidance when moving in the horizontal direction, so that the unit tube on the material receiving slide bar 611 can be effectively removed. The section is gradually pushed in from one end of the well hole to complete the pipe jacking operation. By adjusting the position of the material catching carriage 61 and the track 60, the position of the material catching carriage 61 and the well hole is adjusted to ensure that the unit pipe section is pushed into the well. After the hole is drilled, it can be effectively separated from the material receiving carriage 61 .

最后,为实现对推板40的水平驱动,所述预埋钢板20上立式设置有立柱71,所述立柱71的上端设置有用于固定千斤顶30的固定法兰盘72,所述千斤顶30的活塞杆竖直向下且与推杆73的一端铰接,所述推杆73的另一端与推板40铰接,所述推杆73两端的铰接轴水平且与推板40的移动方向垂直,所述工作井10的底部预制有底板80,所述底板80上立式设置有预留螺栓81,所述预留螺栓81上端伸出固定法兰盘72的上板面且设置有螺母;Finally, in order to realize the horizontal driving of the push plate 40 , the pre-embedded steel plate 20 is vertically provided with a column 71 , and the upper end of the column 71 is provided with a fixing flange 72 for fixing the jack 30 . The piston rod is vertically downward and is hinged with one end of the push rod 73, the other end of the push rod 73 is hinged with the push plate 40, and the hinge axes at both ends of the push rod 73 are horizontal and perpendicular to the moving direction of the push plate 40, so A bottom plate 80 is prefabricated at the bottom of the working well 10, and reserved bolts 81 are vertically arranged on the bottom plate 80. The upper ends of the reserved bolts 81 protrude from the upper plate surface of the fixing flange 72 and are provided with nuts;

上述的千斤顶30活塞竖直布置,通过固定法兰盘72能够实现对千斤顶30缸体的有效固定,千斤顶30竖直移动且对推杆73的驱动时,连动推板40沿着轨道60滑动,从而实现对单元管节一端的水平顶进操作,完成对顶管施工;The above-mentioned piston of the jack 30 is arranged vertically, and the cylinder body of the jack 30 can be effectively fixed by the fixing flange 72. When the jack 30 moves vertically and drives the push rod 73, the push plate 40 slides along the track 60. , so as to realize the horizontal jacking operation of one end of the unit pipe section and complete the pipe jacking construction;

在实际操作时,根据工作井10的直径和所需要推进的管节数量、管节直径以及推进长度,对千斤顶30的尺寸作出合适的选择,针对与现有施工时,千斤顶30的长度多为1.5m,固定法兰盘72的直径多为2m,所述底板80的直径为2~3m,所述预留螺栓81沿着底板80周向方向等角度间隔设置16到24组,并且在固定法兰盘72上设置同样数量的穿孔;In actual operation, the size of the jack 30 is appropriately selected according to the diameter of the working well 10 and the number of pipe sections to be pushed, the diameter of the pipe section and the push length. For the current construction, the length of the jack 30 is mostly 1.5m, the diameter of the fixing flange 72 is mostly 2m, the diameter of the bottom plate 80 is 2-3m, and the reserved bolts 81 are arranged in 16 to 24 groups at equal angular intervals along the circumferential direction of the bottom plate 80, and are fixed at the same angle. The flange 72 is provided with the same number of perforations;

当实施对千斤顶30安装时,利用起吊设备将千斤顶30吊挂至工作井10内,而后使得固定法兰盘72上的穿孔全部穿过预留螺栓81,使得固定法兰盘72与底板80贴合,而后在预留螺栓81上分别设置螺母,从而可有效实现对千斤顶30的有效固定,确保与工作井10底部固定的可靠度。When carrying out the installation of the jack 30 , the jack 30 is suspended into the working well 10 by means of a hoisting device, and then all the perforations on the fixing flange 72 pass through the reserved bolts 81 , so that the fixing flange 72 is attached to the bottom plate 80 . Then, nuts are respectively arranged on the reserved bolts 81, so that the effective fixing of the jack 30 can be effectively achieved, and the reliability of the fixing with the bottom of the working well 10 can be ensured.

上述的千斤顶30推送推杆73的受力分析可以得出,千斤顶30的缸体承受竖直向上的反向分力,因此,该预制有底板80与预留螺栓81通过多个安装位实现紧固,进而实现对设备的稳定安装。The above-mentioned force analysis of the push rod 73 of the jack 30 shows that the cylinder of the jack 30 bears a vertical upward reverse component force. Therefore, the prefabricated bottom plate 80 and the reserved bolts 81 are tightened through a plurality of installation positions. to ensure stable installation of the equipment.

下面介绍一下该顶管施工工艺,所述顶管施工工艺使用了上述的设备,所述顶管施工工艺包含如下步骤:The pipe jacking construction process is described below. The pipe jacking construction process uses the above-mentioned equipment, and the pipe jacking construction process includes the following steps:

第一步、确定好顶进路线,在顶进路线的中段位置挖设工作井10;The first step is to determine the jacking route, and dig a working well 10 in the middle of the jacking route;

第二步、在工作井10的底部浇筑混凝土基预埋螺栓,在工作井内壁上同样设置预埋螺栓;The second step is to pour concrete-based embedded bolts at the bottom of the working well 10, and also set the embedded bolts on the inner wall of the working well;

第三步、在工作井10的底部挖设基坑,在基坑内浇筑混凝土,而后混凝土凝固后,将底板80放置在基坑内,使得底板80摆放平整,在基坑内再次浇筑混凝土,将混凝土覆盖住底板80,在底板80的周向方向间隔布置预留螺栓81,在工作井内壁上同样设置预埋螺栓;In the third step, a foundation pit is dug at the bottom of the working well 10, concrete is poured in the foundation pit, and then after the concrete is solidified, the bottom plate 80 is placed in the foundation pit, so that the bottom plate 80 is placed flat, concrete is poured again in the foundation pit, and the concrete Cover the bottom plate 80, arrange reserved bolts 81 at intervals in the circumferential direction of the bottom plate 80, and also set pre-embedded bolts on the inner wall of the working well;

第四步、调节支撑机构,使得撑杆50与预埋钢板20之间的夹角变小,并且使得撑杆50的杆端与工作筋10的孔壁抵靠,并且通过螺母与工作井10内壁的预埋螺栓紧固;The fourth step is to adjust the support mechanism so that the angle between the strut 50 and the embedded steel plate 20 becomes smaller, and the rod end of the strut 50 abuts against the hole wall of the working rib 10, and is connected to the working well 10 through the nut. Tighten the embedded bolts on the inner wall;

第五步、调试好液压站,将单个单元管节吊送至接料滑架61上,使得单元管节的管口与井孔的孔口对应;The fifth step is to debug the hydraulic station, and hoist the single unit pipe section to the material receiving carriage 61, so that the nozzle of the unit pipe section corresponds to the orifice of the well hole;

第六步、启动千斤顶30,使得千斤顶30的活塞杆伸长,连动推板40水平移动,且推送单元管节顶入井孔内,完成对单个单元管节的顶进;The sixth step, start the jack 30, so that the piston rod of the jack 30 is elongated, and the push plate 40 is moved horizontally, and the unit pipe section is pushed into the well hole, and the jacking of the single unit pipe section is completed;

第七步、重复第五步及第六步,直至将井孔内排布好单元管节。Step 7: Repeat steps 5 and 6 until the unit pipe sections are arranged in the wellbore.

对于本领域技术人员而言,显然本实用新型不限于上述示范性实施例的细节,而且在不背离本实用新型的精神或基本特征的情况下,能够以其他的具体形式实现本实用新型。因此,无论从哪一点来看,均应将实施例看作是示范性的,而且是非限制性的,本实用新型的范围由所附权利要求而不是上述说明限定,因此旨在将落在权利要求的等同要件的含义和范围内的所有变化囊括在本实用新型内。不应将权利要求中的任何附图标记视为限制所涉及的权利要求。It will be apparent to those skilled in the art that the present invention is not limited to the details of the above-described exemplary embodiments, and that the present invention can be implemented in other specific forms without departing from the spirit or essential characteristics of the present invention. Therefore, the embodiments are to be considered in all respects as exemplary and not restrictive, and the scope of the present invention is defined by the appended claims rather than the foregoing description, and it is therefore intended that the All changes within the meaning and range of the required equivalents are embraced within the present invention. Any reference signs in the claims shall not be construed as limiting the involved claim.

此外,应当理解,虽然本说明书按照实施方式加以描述,但并非每个实施方式仅包含一个独立的技术方案,说明书的这种叙述方式仅仅是为清楚起见,本领域技术人员应当将说明书作为一个整体,各实施例中的技术方案也可以经适当组合,形成本领域技术人员可以理解的其他实施方式。In addition, it should be understood that although this specification is described in terms of embodiments, not each embodiment only includes an independent technical solution, and this description in the specification is only for the sake of clarity, and those skilled in the art should take the specification as a whole , the technical solutions in each embodiment can also be appropriately combined to form other implementations that can be understood by those skilled in the art.

Claims (10)

1. The utility model provides a push pipe construction equipment which characterized in that: including setting up pre-buried steel sheet (20) at work well (10), be provided with the installation position that is used for fixed jack (30) cylinder body on pre-buried steel sheet (20), be provided with push pedal (40) of two at least promotion unit tube couplings on pre-buried steel sheet (20), the face of push pedal (40) is vertical to be arranged and the symmetry sets up on pre-buried steel sheet (20), the hydro-cylinder of jack (30) starts and interlock push pedal (40) horizontal migration, push pedal (40) support with the one end of unit tube coupling and lean on and move towards the entrance to a cave of work well (10).
2. The pipe jacking construction equipment according to claim 1, wherein: the cylinder body of the jack (30) is vertically arranged, the jack (30) is connected with the push plate (40) through the linkage mechanism, and the jack (30) vertically moves and is linked with the push plate (40) to horizontally move.
3. The pipe jacking construction equipment according to claim 1 or 2, wherein: and support rods (50) are arranged at intervals in the circumferential direction of the embedded steel plate (20), and rod ends of the support rods (50) are abutted against the inner wall of the working well (10).
4. The pipe jacking construction equipment according to claim 3, wherein: the one end of vaulting pole (50) is articulated with pre-buried steel sheet (20), the articulated shaft level of vaulting pole (50) is arranged, vaulting pole (50) are connected with supporting mechanism, supporting mechanism is used for adjusting the contained angle between vaulting pole (50) and pre-buried steel sheet (20).
5. The pipe jacking construction equipment according to claim 4, wherein: the supporting mechanism comprises a supporting roller (51), the wheel core level of the supporting roller (51) is perpendicular to the length direction of a support rod (50), the wheel rim of the supporting roller (51) is abutted to the rod body of the support rod (50), the wheel carrier of the supporting roller (51) is fixed on an adjusting plate (52), an adjusting screw rod (53) is vertically arranged on the adjusting plate (52), the upper end of the adjusting screw rod (53) extends out of the upper plate surface of a pre-embedded steel plate (20), and an adjusting nut (54) is arranged at the upper end of the adjusting screw rod (53).
6. The pipe jacking construction equipment according to claim 5, wherein: vaulting pole (50) are telescopic rod structure, the front end of vaulting pole (50) is articulated to be provided with arc roof (55), the outer fringe of arc roof (55) supports with the inner wall of working well (10) and leans on, the articulated shaft level of arc roof (55) just arranges with vaulting pole (50) are perpendicular.
7. The pipe jacking construction equipment according to claim 2, wherein: the lower end of the push plate (40) and the rail (60) form sliding fit in the horizontal direction, and the rail (60) is horizontally arranged in two rows at intervals in parallel.
8. The pipe jacking construction equipment according to claim 7, wherein: the front end of track (60) is provided with connects material balladeur train (61) of accepting the unit tube section, connect material balladeur train (61) to constitute by many material receiving slide bars (611) horizontal interval, many material receiving slide bars (611) and track (60) parallel arrangement, many material receiving slide bars (611) enclose into the arc structure, connect material balladeur train (61) and track (60) to constitute the adjustable cooperation in length direction's position.
9. The pipe jacking construction equipment according to claim 8, wherein: many connect the both ends of material slide bar (611) to be provided with installation branch (612), the vertical downwardly extending of installation branch (612) just constitutes integratively, the whole arc platelike structure that is of outer fringe of push pedal (40), the edge of push pedal (40) is provided with dodges breach (41), dodge breach (41) and run through along the length direction of push pedal (40) and arrange, dodge breach (41) be used for with connect material slide bar (611) to form dodge.
10. The pipe jacking construction equipment according to claim 9, wherein: vertical stand (71) that is provided with on pre-buried steel sheet (20), be provided with fixed flange dish (72) that are used for fixed jack (30) on stand (71), the piston rod of jack (30) is vertical downwards and articulated with the one end of push rod (73), the other end and the push pedal (40) of push rod (73) are articulated, the articulated shaft level at push rod (73) both ends just is perpendicular with the moving direction of push pedal (40), the bottom prefabrication of working well (10) has bottom plate (80), vertically on bottom plate (80) be provided with reserve bolt (81), the last face that stretches out fixed flange dish (72) on reserve bolt (81) upper end just is provided with the nut.
CN202020681326.6U 2020-04-29 2020-04-29 Pipe jacking construction equipment Withdrawn - After Issue CN212202062U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020681326.6U CN212202062U (en) 2020-04-29 2020-04-29 Pipe jacking construction equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020681326.6U CN212202062U (en) 2020-04-29 2020-04-29 Pipe jacking construction equipment

Publications (1)

Publication Number Publication Date
CN212202062U true CN212202062U (en) 2020-12-22

Family

ID=73831939

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020681326.6U Withdrawn - After Issue CN212202062U (en) 2020-04-29 2020-04-29 Pipe jacking construction equipment

Country Status (1)

Country Link
CN (1) CN212202062U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111396076A (en) * 2020-04-29 2020-07-10 安徽开源路桥有限责任公司 Pipe jacking construction equipment

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111396076A (en) * 2020-04-29 2020-07-10 安徽开源路桥有限责任公司 Pipe jacking construction equipment
CN111396076B (en) * 2020-04-29 2025-01-21 安徽开源路桥有限责任公司 Pipe jacking equipment

Similar Documents

Publication Publication Date Title
CN111472789B (en) Pipe jacking construction process
CN107311015B (en) Construction elevator installed downwards and installation platform thereof
CN110510527A (en) Installation system of high slope variable cross-section slope precast block and construction method thereof
CN212202062U (en) Pipe jacking construction equipment
CN107119966B (en) A pole-holding upside-down assembly lifting device
CN111396076A (en) Pipe jacking construction equipment
CN113479787B (en) Side-feeding gallery machine and pipeline gallery construction technology
CN115012950A (en) A construction method for pipe jacking of water-rich sand layer near subway
CN114908745A (en) A kind of high slope bolt anchor cable support operation platform and construction method thereof
CN111877165B (en) Bailey beam translation device in limited space and construction method thereof
CN101599619A (en) Installation device and installation method for spanning column
CN102305035B (en) Device for adjusting centration of complete vehicle-mounted service machine to wellhead
CN206815943U (en) A kind of pole upside-down mounting group founds lifting device
CN219431845U (en) Tunnel supporting system penetrating through existing slide-resistant pile
CN219691551U (en) Tunnel arch frame mounting system
CN218320407U (en) Lifting and jacking integrated crown block system
CN117246893A (en) A core-piercing hoisting device in a restricted space for large motors and its use method
CN116219896A (en) Bridge substructure prefabrication and installation device and construction method
CN111945572B (en) Multi-connected arch bridge erecting machine and multi-connected arch bridge erecting method
CN212202063U (en) Unit pipe joint pushing mechanism for pipe jacking machine
CN108840234B (en) Hoisting device for prefabricated section and hoisting method thereof
CN216198095U (en) Underground passage steel platform construction structure
CN221027332U (en) Complex interactive boulder stratum rotary digging pore-forming cast-in-place pile
CN115288038B (en) Bracket device for installing railway box girder anti-falling beam stop block and use method
CN214423202U (en) Cast-in-place concrete beam construction support of municipal works

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20201222

Effective date of abandoning: 20250121

AV01 Patent right actively abandoned

Granted publication date: 20201222

Effective date of abandoning: 20250121

AV01 Patent right actively abandoned
AV01 Patent right actively abandoned