CN212176169U - Precast concrete component with straight thread connected with grouting sleeve - Google Patents
Precast concrete component with straight thread connected with grouting sleeve Download PDFInfo
- Publication number
- CN212176169U CN212176169U CN202020234902.2U CN202020234902U CN212176169U CN 212176169 U CN212176169 U CN 212176169U CN 202020234902 U CN202020234902 U CN 202020234902U CN 212176169 U CN212176169 U CN 212176169U
- Authority
- CN
- China
- Prior art keywords
- grouting
- connecting steel
- precast concrete
- grout
- threaded
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000011178 precast concrete Substances 0.000 title claims abstract description 8
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 39
- 239000010959 steel Substances 0.000 claims abstract description 39
- 239000011440 grout Substances 0.000 claims abstract description 11
- 239000002002 slurry Substances 0.000 claims description 10
- 230000003014 reinforcing effect Effects 0.000 claims description 5
- 239000004567 concrete Substances 0.000 abstract description 10
- 230000000694 effects Effects 0.000 abstract description 3
- 230000002787 reinforcement Effects 0.000 abstract description 3
- 239000007788 liquid Substances 0.000 abstract 4
- 239000000463 material Substances 0.000 description 17
- 230000005540 biological transmission Effects 0.000 description 3
- 239000012141 concentrate Substances 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 239000011148 porous material Substances 0.000 description 2
- 230000000717 retained effect Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
Images
Landscapes
- Reinforcement Elements For Buildings (AREA)
Abstract
Description
技术领域technical field
本实用新型涉及建筑工程装配混凝土结构的技术领域,尤其是涉及一种直螺纹与灌浆套筒连接的预制混凝土构件。The utility model relates to the technical field of assembling concrete structures in construction projects, in particular to a prefabricated concrete member connected with a straight thread and a grouting sleeve.
背景技术Background technique
目前,预制混凝土构件的连接主要采用套筒、波纹管和预留孔洞灌浆连接。这些连接方式都是将要连接的钢筋拉开一段距离或者搭接,然后在孔洞内灌入高强灌浆料;硬化后,钢筋和套筒、波纹管或者孔洞外侧的混凝土牢固结合在一起形成统一整体。At present, the connection of precast concrete components mainly adopts sleeve, corrugated pipe and reserved hole grouting connection. In these connection methods, the steel bars to be connected are pulled apart or overlapped, and then high-strength grouting material is poured into the holes; after hardening, the steel bars and the sleeves, corrugated pipes or the concrete outside the holes are firmly combined to form a unified whole.
钢筋的拉力主要依靠灌浆料和周围套筒的粘结传力,为了保证钢筋拉力的稳定性,套筒、波纹管或者孔洞的长度和直径都会比较大,导致用钢量以及灌浆料用量很大,成本高;如果套筒、波纹管或者孔洞的长度和直径没有设置较大,则无法保证钢筋拉力的稳定性。The tensile force of the steel bar mainly depends on the bonding force transmission between the grouting material and the surrounding sleeve. In order to ensure the stability of the tensile force of the steel bar, the length and diameter of the sleeve, corrugated pipe or hole will be relatively large, resulting in a large amount of steel and grouting material. , the cost is high; if the length and diameter of the sleeve, corrugated pipe or hole are not set larger, the stability of the tensile force of the steel bar cannot be guaranteed.
实用新型内容Utility model content
针对现有技术存在的不足,本实用新型的目的是提供一种直螺纹与灌浆套筒连接的预制混凝土构件,其具有的效果是:在保证钢筋拉力的稳定性的同时降低成本。Aiming at the deficiencies of the prior art, the purpose of the present invention is to provide a prefabricated concrete member connected with a straight thread and a grouting sleeve, which has the effect of reducing the cost while ensuring the stability of the tensile force of the steel bar.
本实用新型的上述实用新型目的是通过以下技术方案得以实现的:The above-mentioned utility model purpose of the present utility model is achieved through the following technical solutions:
一种直螺纹与灌浆套筒连接的预制混凝土构件,包括预制墙体,所述预制墙体上端面以及下端面均延伸有带螺纹的连接钢筋,所述连接钢筋螺纹连接有灌浆套筒;A prefabricated concrete member connected with a straight thread and a grouting sleeve, comprising a prefabricated wall body, the upper end surface and the lower end surface of the prefabricated wall body are extended with connecting steel bars with threads, and the connecting steel bars are threadedly connected with the grouting sleeve;
所述灌浆套筒包括进浆部以及转动连接于所述进浆部两端的螺纹部,所述螺纹部与连接钢筋螺纹连接,所述进浆部上设置有进浆口。The grouting sleeve includes a grouting portion and a threaded portion rotatably connected to both ends of the grouting portion, the threaded portion is threadedly connected with the connecting steel bars, and a grouting port is provided on the grouting portion.
通过采用上述技术方案,使用该预制混凝土构件的时候,将灌浆套筒的两个螺纹部分别和需要连接的两个预制墙体上的连接钢筋螺纹连接,然后在进浆口处灌注灌浆料至灌浆至灌浆料填满整个灌浆套筒,带灌浆料冷却后完成连接,两根钢筋之间通过灌浆料和周围套筒的粘结以及连接钢筋以及灌浆套筒之间的螺纹进行传力,保证钢筋拉力的稳定性的同时降低成本。By adopting the above technical solution, when using the prefabricated concrete member, the two threaded parts of the grouting sleeve are respectively connected with the connecting steel bars on the two prefabricated walls to be connected, and then the grouting material is poured at the grouting inlet to the Grout until the grouting material fills the entire grouting sleeve, and the connection is completed after the grouting material is cooled. Rebar tension stability while reducing costs.
本实用新型进一步设置为:所述螺纹部外壁上开有转动槽,所述进浆部外侧壁两端分别凸出有转动凸环,所述转动凸环卡嵌于所述转动槽内。The utility model is further provided that: the outer wall of the threaded portion is provided with a rotating groove, two ends of the outer side wall of the slurry feeding portion are respectively protruded with rotating convex rings, and the rotating convex rings are clamped and embedded in the rotating grooves.
通过采用上述技术方案,实现了螺纹部以及进浆部之间的转动连接的同时保证了进浆部以及螺纹部之间的不易分离。By adopting the above technical solution, the rotational connection between the screw portion and the slurry feeding portion is realized, and the difficult separation between the slurry feeding portion and the screw portion is ensured.
本实用新型进一步设置为:所述转动凸环卡嵌于所述转动槽内的部分呈弧形,所述转动槽的槽底呈弧形。The utility model is further provided that: the part of the rotating convex ring that is clamped and embedded in the rotating groove is arc-shaped, and the groove bottom of the rotating groove is arc-shaped.
通过采用上述技术方案,使得转动凸环易于在转动槽内滑动。By adopting the above technical solution, the rotating convex ring is easy to slide in the rotating groove.
本实用新型进一步设置为:所述进浆口开设于内腔的一侧靠近螺纹的位置。The utility model is further arranged as follows: the slurry inlet is opened at a position close to the thread on one side of the inner cavity.
通过采用上述技术方案,使得灌浆料能从灌浆套筒的一端填满整个灌浆套筒,使得灌注更为充分,不易存留孔隙。By adopting the above technical solution, the grouting material can fill the entire grouting sleeve from one end of the grouting sleeve, so that the grouting is more sufficient and pores are not easily retained.
本实用新型进一步设置为:所述螺纹部沿长度方向开有连接槽。The utility model is further provided that: the threaded portion is provided with a connecting groove along the length direction.
通过采用上述技术方案,灌浆料可灌注至连接连接槽位置,使得连接钢筋与连接套筒之间的连接更为稳定。By adopting the above technical solution, the grouting material can be poured into the position of the connecting groove, so that the connection between the connecting steel bar and the connecting sleeve is more stable.
本实用新型进一步设置为:所述连接钢筋开有螺纹的部分凹陷有加固环槽。The utility model is further configured as follows: a reinforcing ring groove is recessed in the threaded part of the connecting steel bar.
通过采用上述技术方案,灌注浆灌注至加固环槽位置,成型之后使得连接钢筋不易于连接套筒分离,使得连接更为稳定。By adopting the above technical solution, the grouting slurry is poured into the position of the reinforcement ring groove, so that the connecting steel bar is not easy to be separated from the connecting sleeve after forming, so that the connection is more stable.
本实用新型进一步设置为:所述连接钢筋设置为两排且均匀间隔分布。The utility model is further configured as follows: the connecting steel bars are arranged in two rows and are evenly spaced.
通过采用上述技术方案,将两个预制墙体之间拉力分散开,同时均匀间隔分布使得应力不易集中,使得连接更为稳定。By adopting the above technical solution, the tension between the two prefabricated walls is dispersed, and at the same time, the uniform spacing distribution makes it difficult to concentrate the stress and makes the connection more stable.
综上所述,本实用新型包括以下至少一种有益技术效果:To sum up, the present utility model includes at least one of the following beneficial technical effects:
1.使用该预制混凝土构件的时候,将灌浆套筒的两个螺纹部分别和需要连接的两个预制墙体上的连接钢筋螺纹连接,然后在进浆口处灌注灌浆料至灌浆至灌浆料填满整个灌浆套筒,带灌浆料冷却后完成连接,两根钢筋之间通过灌浆料和周围套筒的粘结以及连接钢筋以及灌浆套筒之间的螺纹进行传力,保证钢筋拉力的稳定性的同时降低成本;1. When using the prefabricated concrete component, connect the two threaded parts of the grouting sleeve to the connecting steel bars on the two prefabricated walls to be connected respectively, and then pour the grouting material at the grouting inlet to grouting to grouting. The whole grouting sleeve is filled, and the connection is completed after the grouting material is cooled, and the force transmission between the two steel bars is carried out through the bonding between the grouting material and the surrounding sleeve and the thread between the connecting steel bar and the grouting sleeve, so as to ensure the stability of the tensile force of the steel bar. while reducing costs;
2.通过设置连接槽以及加固环槽使得连接钢筋与连接套筒之间的连接更为稳定。2. The connection between the connecting steel bar and the connecting sleeve is made more stable by setting the connecting groove and the reinforcing ring groove.
附图说明Description of drawings
图1是本实用新型一实施方式的整体结构示意图;1 is a schematic diagram of the overall structure of an embodiment of the present utility model;
图2是本实用新型一实施方式的连接钢筋以及连接套筒的装配关系示意图;2 is a schematic diagram of the assembly relationship of the connecting steel bar and the connecting sleeve according to an embodiment of the present invention;
图3是本实用新型一实施方式的连接钢筋以及连接套筒的剖视图。3 is a cross-sectional view of a connecting steel bar and a connecting sleeve according to an embodiment of the present invention.
图中,1、预制墙体;11、连接钢筋;111、加固环槽;2、灌浆套筒;21、进浆部;22、螺纹部;211、进浆口;212、转动凸环;221、转动槽;222、连接槽。In the figure, 1. Prefabricated wall body; 11. Connecting steel bar; 111. Reinforcing ring groove; 2. Grouting sleeve; 21. Grouting part; 22. Thread part; , rotating groove; 222, connecting groove.
具体实施方式Detailed ways
以下结合附图对本实用新型作进一步详细说明。The present utility model will be described in further detail below in conjunction with the accompanying drawings.
参照图1以及图2,为本实用新型公开的一种直螺纹与灌浆套筒连接的预制混凝土构件,包括预制墙体1,预制墙体1上端面以及下端面均延伸有带螺纹的连接钢筋11,连接钢筋11螺纹连接有灌浆套筒2;灌浆套筒2包括进浆部21以及转动连接于进浆部21两端的螺纹部22,螺纹部22与连接钢筋11螺纹连接,进浆部21上设置有进浆口211。Referring to Figure 1 and Figure 2, a prefabricated concrete member with straight threads connected to a grouting sleeve disclosed by the present utility model includes a
连接钢筋11设置为两排且均匀间隔分布。将两个预制墙体1之间拉力分散开,同时均匀间隔分布使得应力不易集中,使得连接更为稳定。The connecting
参照图3,具体的,螺纹部22外壁上开有转动槽221,进浆部21外侧壁两端分别凸出有转动凸环212,转动凸环212卡嵌于转动槽221内。实现了螺纹部22以及进浆部21之间的转动连接的同时保证了进浆部21以及螺纹部22之间的不易分离。3 , specifically, a rotating
为了使得转动凸块212便于转动,进一步的,转动凸块212卡嵌于转动槽221内的部分呈弧形状,转动槽221的槽底呈弧形。使得转动凸块212易于在转动槽221内滑动。In order to facilitate the rotation of the
参照图2以及图3,具体的,进浆口211开设于内腔的一侧靠近螺纹的位置。使得灌浆料能从灌浆套筒2的一端填满整个灌浆套筒2,使得灌注更为充分,不易存留孔隙。Referring to FIG. 2 and FIG. 3 , specifically, the
为了使得钢筋与连接套筒之间的连接更为稳定,进一步的,螺纹部22沿长度方向开有连接槽222,连接钢筋11开有螺纹的部分凹陷有加固环槽111。灌浆料可灌注至连接连接槽222位置,使得连接钢筋11与连接套筒之间的连接更为稳定;灌注浆灌注至加固环槽111位置,成型之后使得连接钢筋11不易于连接套筒分离,使得连接更为稳定。In order to make the connection between the steel bar and the connecting sleeve more stable, further, the threaded portion 22 is provided with a connecting groove 222 along the length direction, and the threaded portion of the connecting
本实施例的实施原理为:The implementation principle of this embodiment is:
使用该预制混凝土构件的时候,将灌浆套筒2的两个螺纹部22分别和需要连接的两个预制墙体1上的连接钢筋11螺纹连接,然后在进浆口211处灌注灌浆料至灌浆至灌浆料填满整个灌浆套筒2,带灌浆料冷却后完成连接,两根钢筋之间通过灌浆料和周围套筒的粘结以及连接钢筋11以及灌浆套筒2之间的螺纹进行传力,保证钢筋拉力的稳定性的同时降低成本。When using the prefabricated concrete component, the two threaded portions 22 of the
本具体实施方式的实施例均为本实用新型的较佳实施例,并非依此限制本实用新型的保护范围,故:凡依本实用新型的结构、形状、原理所做的等效变化,均应涵盖于本实用新型的保护范围之内。The examples of this specific embodiment are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Therefore: all equivalent changes made according to the structure, shape and principle of the present invention are not It should be covered within the protection scope of the present invention.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202020234902.2U CN212176169U (en) | 2020-03-02 | 2020-03-02 | Precast concrete component with straight thread connected with grouting sleeve |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202020234902.2U CN212176169U (en) | 2020-03-02 | 2020-03-02 | Precast concrete component with straight thread connected with grouting sleeve |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN212176169U true CN212176169U (en) | 2020-12-18 |
Family
ID=73777246
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202020234902.2U Active CN212176169U (en) | 2020-03-02 | 2020-03-02 | Precast concrete component with straight thread connected with grouting sleeve |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN212176169U (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113863486A (en) * | 2021-10-24 | 2021-12-31 | 湖南同进装饰材料有限公司 | Prefabricated wallboard structure |
| CN114658145A (en) * | 2022-04-18 | 2022-06-24 | 华川建设集团有限公司 | Connecting piece for partition board installation and installation method |
-
2020
- 2020-03-02 CN CN202020234902.2U patent/CN212176169U/en active Active
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113863486A (en) * | 2021-10-24 | 2021-12-31 | 湖南同进装饰材料有限公司 | Prefabricated wallboard structure |
| CN114658145A (en) * | 2022-04-18 | 2022-06-24 | 华川建设集团有限公司 | Connecting piece for partition board installation and installation method |
| CN114658145B (en) * | 2022-04-18 | 2022-10-14 | 华川建设集团有限公司 | Connecting piece for partition board installation and installation method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN202391019U (en) | End part thickened grouting connector of steel bar | |
| CN205935422U (en) | Novel half grout sleeve that can spacing reinforcing bar | |
| CN205935421U (en) | Novel full grout sleeve that can spacing reinforcing bar | |
| CN212176169U (en) | Precast concrete component with straight thread connected with grouting sleeve | |
| CN113700144B (en) | A prefabricated TRC-steel tube composite confinement concrete column and its installation method | |
| CN205617661U (en) | Short sleeve grout steel bar connection connects and connecting sleeve and pressure -bearing ring that have thereof | |
| CN208072778U (en) | A kind of grout sleeve structure of energy non-return | |
| CN212001932U (en) | A full grouting sleeve and a prefabricated beam connecting structure with the sleeve | |
| CN208884849U (en) | A self-locking steel bar connection grouting sleeve | |
| CN106149874A (en) | Prefabricated assembled concrete structure reinforcing bars Novel connecting method | |
| CN212129691U (en) | Tenon and tenon joints | |
| CN204456670U (en) | Fabricated construction straight screw sleeve connection joint | |
| CN106240749B (en) | Grouting formula suction anchor and its installation method | |
| CN210857596U (en) | Prefabricated assembly type non-reinforced concrete shear wall | |
| CN203846679U (en) | Tie bar of embedded sleeve of infilled wall | |
| CN207121994U (en) | A kind of concrete component attachment structure | |
| CN108118834B (en) | Key-type steel connection structure for prefabricated concrete structure | |
| CN110284659A (en) | It is a kind of for double and muscle connect can the fixed grout sleeve of self compaction | |
| CN110424573A (en) | A prefabricated unreinforced concrete shear wall and its construction method | |
| CN110284661A (en) | It is a kind of for isosceles triangle three and muscle connection can the fixed grout sleeve of self compaction | |
| CN210500792U (en) | Double-tube type steel bar connecting structure between precast concrete components | |
| CN206034656U (en) | Novel connected node of prefabricated prefabricated concrete structure reinforcing bar | |
| CN205712762U (en) | A kind of grout sleeve and prefabricated component | |
| CN207063244U (en) | A kind of connecting node of non-bearing precast concrete external wall panel | |
| CN206971214U (en) | A kind of foundation pit supporting project anchor pole of recoverable |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant |