CN212103679U - A construction platform for installation of assembled tower - Google Patents

A construction platform for installation of assembled tower Download PDF

Info

Publication number
CN212103679U
CN212103679U CN202020127716.9U CN202020127716U CN212103679U CN 212103679 U CN212103679 U CN 212103679U CN 202020127716 U CN202020127716 U CN 202020127716U CN 212103679 U CN212103679 U CN 212103679U
Authority
CN
China
Prior art keywords
tower
platform
operation panel
stand
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020127716.9U
Other languages
Chinese (zh)
Inventor
廖汝锋
秦大燕
罗小斌
杨茗钦
王彬鹏
江鑫泰
徐航
于远志
高丰
吴宇航
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Road and Bridge Engineering Group Co Ltd
Original Assignee
Guangxi Road and Bridge Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Road and Bridge Engineering Group Co Ltd filed Critical Guangxi Road and Bridge Engineering Group Co Ltd
Priority to CN202020127716.9U priority Critical patent/CN212103679U/en
Application granted granted Critical
Publication of CN212103679U publication Critical patent/CN212103679U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a construction platform for assembled tower installation, including at least three-layer operation panel and a plurality of stands, every layer the operation panel is three horn shapes, and all parallel intervals of operation panel set up, the operation panel side is located to the stand, two piece at least stands of every side, and every stand all links to each other with the corresponding side of three-layer operation panel, every still be equipped with two at least couples that are used for linking to each other with the pylon on the stand, still including the cat ladder that is used for communicateing all operation panels. When the tower is used, the whole construction platform can be arranged in the tower, due to the fact that multiple layers of operation platforms are arranged, the tower can be adapted to multiple stations of the tower assembly, the crawling ladder is communicated with all the operation platforms, construction personnel can conveniently flow on each operation platform, each layer of operation platform is located below the tower cross rod when the tower is used, the tower cross rod is ingeniously used as a fence of the operation platform, the safety of operation is improved, workers can conveniently apply and screw the tower bolts, the working efficiency is improved, and the construction period of the tower can be saved.

Description

A construction platform for installation of assembled tower
Technical Field
The utility model relates to an assembled tower erection construction field, concretely relates to a construction platform for assembled tower installation.
Background
A high tower is often required to be arranged in the arch bridge cable hoisting construction, and some components of the cable crane are supported at a certain height, so that the hoisting height of the crane can meet the installation requirement of bridge components. At present, an assembly type tower frame with a steel structure is adopted, and in the process of assembling the tower frame layer by layer, some temporary operation platforms need to be erected for ensuring the construction safety. At present, a bamboo springboard is adopted for fully paving a current construction area, people stand on the platform for operation, and a safety rope is hung on an installed tower component so as to guarantee the safety in the construction process. After the tower frame rod piece at the layer is installed, a new platform needs to be erected again to meet the construction requirement. The adoption of the operation platform has the following defects: firstly, the surrounding barriers of the operation platform are simple, the reliability is low, the operation platform is immovable and is frequently disassembled, and a great safety risk exists in the disassembling and assembling process; secondly, the gangplank is arranged on the cross bar of the tower frame, and the cross bar bolt is difficult to screw in the installation process of the tower frame, so that the operation is inconvenient; and thirdly, the bamboo gangplank is small, the hoisting time is long in the turnover process, and the construction progress of the tower can be influenced.
SUMMERY OF THE UTILITY MODEL
The utility model discloses aim at: in order to overcome the defect that the mode that adopts bamboo springboard to lay work platform at present exists, provide a construction platform for assembled tower installation, can regard as the fender that encloses of platform with the pylon horizontal pole during the use, increased the security of platform operation, and do not influence the pylon horizontal pole bolt and apply and twist, have enough to meet the need the use as a whole simultaneously, and the turnover process is few, practices thrift pylon construction period.
In order to realize the purpose, the utility model discloses a technical scheme be:
the utility model provides a construction platform for assembled tower installation, includes at least three-layer operation panel and a plurality of stands, every layer the operation panel is the triangle-shaped form, and all operation panel parallel interval sets up, the operation panel side is located to the stand, two piece at least stands of every side, and every stand all links to each other with the corresponding side of three-layer operation panel, every still be equipped with two at least couples that are used for linking to each other with the pylon on the stand, still including the cat ladder that is used for communicateing all operation panels.
The utility model is provided with at least three layers of operation platforms and a plurality of upright columns, each layer of the operation platform is in a triangular shape, all the operation platforms are arranged in parallel at intervals, the upright columns are arranged on the side surface of the operation platform, at least two upright columns are arranged on each side, each upright column is connected with the corresponding side surface of the three layers of operation platforms, at least two hooks used for being connected with the tower are arranged on each upright column, and the ladder stand also comprises a ladder stand used for being communicated with all the operation platforms; when the tower is used, the whole construction platform can be arranged in the tower and is connected with the tower through the hooks on the stand columns, due to the fact that the multilayer operation platforms are arranged, a plurality of stations for assembling the tower can be adapted, the crawling ladder is communicated with all the operation platforms, construction personnel can flow on each operation platform conveniently, each layer of operation platform is located below the tower cross rod during use, the tower cross rod is ingeniously used as a fence of the operation platform, the operation safety is improved, in addition, when the tower bolt is installed, the bolt is highly suitable, workers can conveniently apply and twist, the working efficiency is improved, in addition, the construction platform is used in a turnover mode as a whole, the time of the turnover process is short, and the construction period of the tower can be saved.
As the utility model discloses an optimal scheme, the cat ladder sets up in the operation panel side, can avoid the cat ladder to influence the construction space on the operation panel.
As the preferred scheme of the utility model, be equipped with the board that turns over that can open on the operation panel, the position and the cat ladder adaptation that turn over the board. Through set up the board that turns over that can open on the operation panel, when constructor need flow on each layer operation panel, only need open and turn over the board and can form the passageway that passes the operation panel, then along the cat ladder crawl from top to bottom can, make things convenient for constructor to arrive fast and go on each layer operation panel.
As the utility model discloses a preferred scheme, the operation panel side is equipped with the backplate, can avoid constructor to step on empty at the operation panel edge, also can prevent that construction tool from falling down from the operation panel edge.
As the utility model discloses an optimal scheme is equipped with a plurality of pull rods between the stand of every side, sets up the pull rod and can play the connection to the effect of drawing to the stand of every side, improves the connection rigidity of every side stand to increase whole construction platform's stability.
To sum up, owing to adopted above-mentioned technical scheme, the beneficial effects of the utility model are that:
the utility model is provided with at least three layers of operation platforms and a plurality of upright columns, each layer of the operation platform is in a triangular shape, all the operation platforms are arranged in parallel at intervals, the upright columns are arranged on the side surface of the operation platform, at least two upright columns are arranged on each side, each upright column is connected with the corresponding side surface of the three layers of operation platforms, at least two hooks used for being connected with the tower are arranged on each upright column, and the ladder stand also comprises a ladder stand used for being communicated with all the operation platforms; when the tower is used, the whole construction platform can be arranged in the tower and is connected with the tower through the hooks on the stand columns, due to the fact that the multilayer operation platforms are arranged, a plurality of stations for assembling the tower can be adapted, the crawling ladder is communicated with all the operation platforms, construction personnel can flow on each operation platform conveniently, each layer of operation platform is located below the tower cross rod during use, the tower cross rod is ingeniously used as a fence of the operation platform, the operation safety is improved, in addition, when the tower bolt is installed, the bolt is highly suitable, workers can conveniently apply and twist, the working efficiency is improved, in addition, the construction platform is used in a turnover mode as a whole, the time of the turnover process is short, and the construction period of the tower can be saved.
Drawings
Fig. 1 is a perspective view of a construction platform for mounting an assembled tower according to the present invention.
Fig. 2 is a vertical layout of the tower construction platform of the present invention.
Fig. 3 is a side layout view of the tower construction platform of the present invention.
Fig. 4 is a plan view of the tower construction platform of the present invention.
The labels in the figure are: 1-an operation table, 11-a channel, 12-a protection plate, 2-a vertical column, 3-a hook, 4-a ladder stand, 5-a pull rod and 6-a tower.
Detailed Description
The present invention will be described in detail with reference to the accompanying drawings.
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are for purposes of illustration only and are not intended to limit the invention.
Examples
The present embodiments provide a construction platform for assembly tower installation;
as shown in fig. 1-4, the construction platform for mounting the fabricated tower in this embodiment includes three layers of operation platforms 1 and a plurality of vertical columns 2, where each layer of the operation platform 1 is in a triangular shape, so that the whole construction platform can be placed in a tower 6 and can be conveniently moved up and down, all the operation platforms 1 are arranged in parallel at intervals, a steel panel is laid on the operation platform 1, the vertical columns 2 are arranged on the side surfaces of the operation platform 1, two vertical columns 2 are arranged on each side, each vertical column 2 is connected with the corresponding side surface of the three layers of operation platforms 1, each vertical column 2 is further provided with two hooks 3 for connecting with the tower 6, and the construction platform further includes a ladder 4 for communicating all the operation platforms 1.
The utility model discloses a three-layer operation panel and a plurality of stands are set up, each layer of the operation panel is triangle-shaped, all operation panels are arranged in parallel at intervals, the stand is arranged on the side of the operation panel, two stands are arranged on each side, and each stand is connected with the corresponding side of the three-layer operation panel, two hooks for connecting with the tower are arranged on each stand, and the ladder stand for communicating all operation panels is also included; when the tower is used, the whole construction platform can be arranged in the tower and is connected with the tower through the hooks on the stand columns, due to the fact that the multilayer operation platforms are arranged, a plurality of stations for assembling the tower can be adapted, the crawling ladder is communicated with all the operation platforms, construction personnel can flow on each operation platform conveniently, each layer of operation platform is located below the tower cross rod during use, the tower cross rod is ingeniously used as a fence of the operation platform, the operation safety is improved, in addition, when the tower bolt is installed, the bolt is highly suitable, workers can conveniently apply and twist, the working efficiency is improved, in addition, the construction platform is used in a turnover mode as a whole, the time of the turnover process is short, and the construction period of the tower can be saved.
In this embodiment, cat ladder 4 sets up in operation panel 1 side, can avoid cat ladder 4 to influence the construction space on the operation panel 1. The crawling ladder 4 comprises two vertical rods and a plurality of cross rods arranged between the two vertical rods, wherein the two vertical rods extend to the side face of the uppermost operation platform from the side face of the lowermost operation platform, and the crawling ladder is communicated with three layers of operation platforms.
In this embodiment, the operation table 1 is provided with an openable turning plate, and the position of the turning plate is adapted to the ladder stand 4. Through set up the board that turns over that can open on the operation panel, when constructor need flow on each layer operation panel, only need open and turn over the board and can form the passageway 11 that passes the operation panel, then along the cat ladder crawl from top to bottom can, make things convenient for constructor to arrive fast and go on each layer operation panel. Should turn over board one side and the operation panel is articulated, and the opposite side then carries out detachable fixed connection with the operation panel, when needs are gone up and down to each layer operation panel along the cat ladder on, only need loosen fixed connection department, then will turn over the board and can form the passageway 11 that passes the operation panel around the pin joint upset, and when need not opening, turn over the board and cover in the passageway top.
In this embodiment, the guard plate 12 is arranged on the side surface of the operating platform 1, so that a constructor can be prevented from stepping on the edge of the operating platform, and a construction tool can be prevented from falling from the edge of the operating platform.
In the embodiment, a plurality of pull rods 5 are arranged between the upright columns 2 on each side, and the pull rods 5 can play a role in connecting, oppositely pulling and reinforcing the two upright columns 2 on each side, so that the connecting rigidity of the upright columns on each side is improved, and the stability of the whole construction platform is improved.
The construction platform in this embodiment is used as follows: hoisting the tower standard segment upright column hoisting unit, hoisting the construction platform, firmly connecting the hook with the installed tower horizontal rod and the installed inclined rod, installing the residual horizontal rod and the installed inclined rod on the layer of the tower, installing a bolt on an operation table by a worker, hoisting the next layer of standard segment upright column hoisting unit, integrally hoisting the construction platform by the tower crane, and circulating to finish the whole installation of the tower.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not intended to limit the present invention, and any modifications, equivalents, improvements and the like made within the principles of the present invention should be included within the scope of the present invention.

Claims (5)

1. The utility model provides a construction platform for assembled tower installation, its characterized in that includes at least three-layer operation panel and a plurality of stands, every layer the operation panel is the triangle-shaped form, and all parallel intervals of operation panel set up, the operation panel side is located to the stand, two piece at least stands of every side, and every stand all links to each other with the corresponding side of three-layer operation panel, every still be equipped with two at least couples that are used for linking to each other with the pylon on the stand, still including the cat ladder that is used for communicateing all operation panels.
2. A construction platform for assembly tower installation according to claim 1, wherein the ladder stand is arranged at the side of the operation platform.
3. A construction platform for assembly tower installation according to claim 2, wherein an openable flap is provided on the operation platform, the position of the flap being adapted to the ladder.
4. A construction platform for assembly tower installation according to claim 3, wherein the operator's station is flanked by fenders.
5. A construction platform for erection of a prefabricated tower according to any of claims 1-4, characterised in that between the uprights on each side there are several tie rods.
CN202020127716.9U 2020-01-20 2020-01-20 A construction platform for installation of assembled tower Active CN212103679U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020127716.9U CN212103679U (en) 2020-01-20 2020-01-20 A construction platform for installation of assembled tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020127716.9U CN212103679U (en) 2020-01-20 2020-01-20 A construction platform for installation of assembled tower

Publications (1)

Publication Number Publication Date
CN212103679U true CN212103679U (en) 2020-12-08

Family

ID=73626349

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020127716.9U Active CN212103679U (en) 2020-01-20 2020-01-20 A construction platform for installation of assembled tower

Country Status (1)

Country Link
CN (1) CN212103679U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113668831A (en) * 2021-08-20 2021-11-19 舜元建设(集团)有限公司 Movable overhanging scaffold

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113668831A (en) * 2021-08-20 2021-11-19 舜元建设(集团)有限公司 Movable overhanging scaffold

Similar Documents

Publication Publication Date Title
CN106193568A (en) Mobile steel truss operating platform
CN212103679U (en) A construction platform for installation of assembled tower
CN111236613A (en) Protection platform for building construction and use method thereof
CN109653484B (en) Roofing superelevation faces external hanging flower basket mounting structure of empty curtain engineering
CN208686053U (en) A kind of elevator well sizing climbing platforms device
CN206707237U (en) Cable-stayed type top layer construction platform for elevator installation
CN110552495A (en) assembled building combined tool type outer protective frame system and construction method thereof
CN206928624U (en) A kind of heavy ladder cage for high-altitude building
CN210236926U (en) Folding type tower crane pedestrian safety passage
CN113719163A (en) Modular maintenance platform structure
CN202831591U (en) Special-shaped truss operation platform capable of hoisting to super high space
CN110817709A (en) High-rise tower crane driver climbing device
CN213328707U (en) Thin-wall pier high-altitude operation combined platform
CN217500855U (en) Externally hung stair case
CN213569261U (en) Attached lower hanging turnover plate type operating platform for installing tower crane
CN103899078A (en) Mounting method of attached automatic lifting protection shield
CN203878956U (en) Automatic lifting protection screen and construction platform combined system
CN217203889U (en) Mounting rack for rubber fender anti-collision plate of wharf
CN213802442U (en) Installation structure of maintenance platform of machine-room-less elevator
CN213710261U (en) Scaffold with safety protection structure for building construction
CN215671309U (en) Prefabricated temporary stair of going up people
CN210341651U (en) High-tower column longitudinal tie beam prestress construction platform
CN216662305U (en) Super high-rise tower crane bottom attached hydraulic self-climbing hard protection platform
CN213979855U (en) Construction hanging basket in urea prilling tower
CN215829984U (en) Climbing type scaffold for construction site

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant