CN212078880U CN202020689719.1U CN202020689719U CN212078880U CN 212078880 U CN212078880 U CN 212078880U CN 202020689719 U CN202020689719 U CN 202020689719U CN 212078880 U CN212078880 U CN 212078880U
Authority
CN
China
Prior art keywords
sleeve
bottom plate
baffles
power line
temporary power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020689719.1U
Other languages
Chinese (zh)
Inventor
王健
陆杰
鞠玲
张杭
周凯
陶伟
徐兴春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Jiangsu Electric Power Co Ltd
Taizhou Power Supply Co of State Grid Jiangsu Electric Power Co Ltd
Original Assignee
State Grid Jiangsu Electric Power Co Ltd
Taizhou Power Supply Co of State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Jiangsu Electric Power Co Ltd, Taizhou Power Supply Co of State Grid Jiangsu Electric Power Co Ltd filed Critical State Grid Jiangsu Electric Power Co Ltd
Priority to CN202020689719.1U priority Critical patent/CN212078880U/en
Application granted granted Critical
Publication of CN212078880U publication Critical patent/CN212078880U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The utility model discloses a power line strutting arrangement temporarily, be square structure's bottom plate including the cross section, bottom plate central point puts the department and pegs graft there is open-top's sleeve, and all articulates on the bottom plate four sides outer wall has a baffle, four the baffle loops through the hasp lock and connects, and four baffles and bottom plate constitution hold the case, the sleeve internal fixation has the sleeve pipe, and overlaps the intraductal sliding connection of pipe and have the bracing piece, top one side of bracing piece articulates through the hinge has the horizontal pole. The utility model discloses in, constitute between four baffles and the bottom plate and hold the case, can hold the case and put into the foundation ditch after having dug the foundation ditch, hold grit, earth in holding the incasement simultaneously, backfill earth, increase strutting arrangement's stability, need not concreting, it is convenient to retrieve, conveniently adjusts strutting arrangement's height, and the spring can be drawn together two sliders each other and be close to, and sleeve pipe arc splint can the centre gripping cable.

Description

Temporary power line supporting device
Technical Field
The utility model relates to an electric power support frame technical field especially relates to an interim power line strutting arrangement.
Background
The current interim power cable is laid through the wire pole, can carry out deep excavation foundation ditch in order to ensure the steadiness of wire pole usually to concreting is in order to bury the wire pole, and the concrete setting time is long, and uses the back with the power cable temporarily, when removing the wire pole, and concrete and wire pole bond together, can not retrieve the wire pole, can not utilize the wire pole once more.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the defects existing in the prior art and providing a temporary power line supporting device.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides an interim power line strutting arrangement, includes that the cross section is the bottom plate of square structure, bottom plate central point puts the department and pegs graft there is open-top's sleeve, and all articulates on the bottom plate four sides outer wall has a baffle, four the baffle loops through the hasp lock and connects, and just four baffles and bottom plate constitution hold the case, the sleeve internal fixation has the sleeve pipe, and overlaps the internal sliding connection and have the bracing piece, top one side of bracing piece articulates through the hinge has the horizontal pole, and the bottom of horizontal pole and bracing piece top joint mutually, all welding has rings bottom the horizontal pole both ends, and bracing piece top both sides all articulate has the pull rod, two the couple has all been welded at the pull rod top, and two couples articulate with two rings respectively, the cable fixture that the equidistance distributes is installed at the.
Preferably, the middle parts of the four baffles are provided with bayonets which are of semicircular structures and matched with the outer wall of the sleeve, rubber pads are bonded on the inner walls of the bayonets, two opposite baffles are clamped on the upper part of the sleeve, and the other two opposite baffles are clamped on the bottom of the sleeve.
Preferably, the top position of the outer wall of the sleeve is connected with a fastening bolt through threads, and the fastening bolt is in fastening fit with the outer wall of the support rod.
Preferably, the top of the support rod is of a hemispherical structure, and a groove matched with the top of the support rod is formed in the center of the bottom of the cross rod.
Preferably, the cable clamping mechanism comprises two sliding blocks, a spring for connecting the two sliding blocks and two arc-shaped clamping plates welded to the tops of the outer walls on the opposite sides of the two sliding blocks, and the initial length of the spring is smaller than the distance between the two sliding blocks.
Preferably, the top of the cross rod is provided with mounting grooves distributed equidistantly, one sliding block in the cable clamping mechanism is welded with the inner wall of the mounting groove, and the other sliding block is connected with the inner wall of the mounting groove in a sliding manner.
The utility model has the advantages that:
1. after the four baffles are connected through the hasp lock in sequence, the containing box is formed between the four baffles and the bottom plate, after the foundation pit is dug, the containing box is placed into the foundation pit, meanwhile, gravels and soil are contained in the containing box, the soil is backfilled, the stability of the supporting device is improved, concrete does not need to be poured, and the recovery is convenient;
2. sleeve pipe and bracing piece sliding connection conveniently adjust strutting arrangement's height, and the spring can be drawn close to two sliders each other, and the arc splint can the centre gripping cable.
Drawings
Fig. 1 is a schematic structural view of a temporary power line supporting device according to the present invention;
fig. 2 is a schematic top view of a bottom plate of a temporary power line supporting device according to the present invention;
fig. 3 is an enlarged schematic structural view of a cross bar portion of a temporary power line supporting device according to the present invention;
fig. 4 is a cross-sectional structural diagram of a cross bar of the temporary power line supporting device according to the present invention.
In the figure: the device comprises a base plate 1, a sleeve 2, a baffle 3, bayonets 4, sleeves 5, a support rod 6, a cross rod 7, grooves 8, lifting rings 9, a pull rod 10, hooks 11, mounting grooves 12, sliding blocks 13, arc-shaped clamping plates 14 and springs 15.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1-4, a temporary power line supporting device, including bottom plate 1 with a square cross section, bottom plate 1 central point puts the department and pegs graft there is open-topped sleeve 2, all articulated on bottom plate 1 four sides outer wall have baffle 3, four baffles 3 loop through the hasp lock and connect, four baffles 3 and bottom plate 1 constitute and hold the case, sleeve 5 is fixed with in sleeve 2, sliding connection has bracing piece 6 in the sleeve 5, top one side of bracing piece 6 articulates through the hinge has horizontal pole 7, the bottom of horizontal pole 7 and 6 tops of bracing piece are connected mutually, rings 9 have all been welded to horizontal pole 7 both ends bottom, 6 tops of bracing piece both sides all articulate has pull rod 10, two pull rod 10 tops all weld and have couple 11, two couple 11 articulate with two rings 9 respectively, 7 tops of horizontal pole install the equidistant cable fixture that distributes.
In the utility model, the middle parts of four baffles 3 are all provided with bayonets 4 which are matched with the outer wall of a sleeve 2 in a semicircular structure, rubber pads are bonded on the inner walls of the bayonets 4, two opposite baffles 3 are clamped on the upper part of the sleeve 2, the other two opposite baffles 3 are clamped on the bottom 2 of the sleeve 2, the top position of the outer wall of a sleeve 5 is connected with a fastening bolt through screw threads, the fastening bolt is tightly matched with the outer wall of a support rod 6, the top part of the support rod 6 is in a hemispherical structure, the central position of the bottom part of a cross rod 7 is provided with a groove 8 matched with the top part of the support rod 6, a cable clamping mechanism comprises two sliders 13, a spring 15 used for connecting the two sliders 13 and two arc-shaped splints 14 welded on the top part of the outer wall on the opposite side of the two sliders 13, the initial length, one sliding block 13 in the cable clamping mechanism is welded with the inner wall of the mounting groove 12, and the other sliding block 13 is connected with the inner wall of the mounting groove 12 in a sliding mode.
The working principle is as follows: four baffles 3 loop through the hasp lock and connect the back, it holds the case to constitute between four baffles 3 and the bottom plate 1, can be after digging the foundation ditch, will hold the case and put into the foundation ditch, hold the grit in holding the incasement simultaneously, earth, backfill earth, increase strutting arrangement's stability, need not to pour the concrete, it is convenient to retrieve, sleeve pipe 5 and 6 sliding connection of bracing piece, conveniently adjust strutting arrangement's height, and spring 15 can draw two sliders 13 each other and be close to, arc splint 14 can the centre gripping cable.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (6)

1. The temporary power line supporting device comprises a bottom plate (1) with a square cross section, and is characterized in that a sleeve (2) with an open top is inserted in the center of the bottom plate (1), baffles (3) are hinged to the outer walls of four sides of the bottom plate (1), the baffles (3) are sequentially connected through a hasp lock, the four baffles (3) and the bottom plate (1) form a containing box, a sleeve (5) is fixed in the sleeve (2), a supporting rod (6) is connected in the sleeve (5) in a sliding mode, one side of the top of the supporting rod (6) is hinged to a cross rod (7) through a hinge, the bottom of the cross rod (7) is clamped to the top of the supporting rod (6), hanging rings (9) are welded to the bottoms of two ends of the cross rod (7), pull rods (10) are hinged to two sides of the top of the supporting rod (6), and hooks (11) are welded to the tops of the pull rods, and the two hooks (11) are respectively articulated with the two lifting rings (9), and cable clamping mechanisms distributed at equal intervals are installed at the top of the cross rod (7).
2. The temporary power line supporting device according to claim 1, wherein the middle parts of the four baffles (3) are respectively provided with a bayonet (4) which is of a semicircular structure and is matched with the outer wall of the sleeve (2), and rubber pads are bonded on the inner walls of the bayonets (4), wherein two opposite baffles (3) are clamped on the upper part of the sleeve (2), and the other two opposite baffles (3) are clamped on the bottom of the sleeve (2).
3. A temporary power line support apparatus according to claim 1, wherein a fastening bolt is threadedly attached to the outer wall of the casing (5) at a top position thereof, and forms a fastening engagement with the outer wall of the support pole (6).
4. The temporary power line supporting device according to claim 1, wherein the top of the supporting rod (6) is a hemispherical structure, and a groove (8) matched with the top of the supporting rod (6) is formed at the central position of the bottom of the cross rod (7).
5. A temporary power line support apparatus according to claim 1, wherein the cable holding mechanism includes two sliders (13), a spring (15) for connecting the two sliders (13), and two arc-shaped clamps (14) welded to tops of outer walls of opposite sides of the two sliders (13), and an initial length of the spring (15) is smaller than a space between the two sliders (13).
6. The temporary power line supporting device according to claim 5, wherein the top of the cross bar (7) is provided with mounting grooves (12) which are distributed at equal intervals, one sliding block (13) of the cable clamping mechanism is welded with the inner wall of the mounting groove (12), and the other sliding block (13) is connected with the inner wall of the mounting groove (12) in a sliding manner.
CN202020689719.1U 2020-04-29 2020-04-29 Temporary power line supporting device Active CN212078880U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020689719.1U CN212078880U (en) 2020-04-29 2020-04-29 Temporary power line supporting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020689719.1U CN212078880U (en) 2020-04-29 2020-04-29 Temporary power line supporting device

Publications (1)

Publication Number Publication Date
CN212078880U true CN212078880U (en) 2020-12-04

Family

ID=73588175

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020689719.1U Active CN212078880U (en) 2020-04-29 2020-04-29 Temporary power line supporting device

Country Status (1)

Country Link
CN (1) CN212078880U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU219518U1 (en) * 2023-05-30 2023-07-21 Федеральное государственное бюджетное учреждение науки Федеральный исследовательский центр Якутский научный центр Сибирского отделения Российской академии наук Temporary transmission tower

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU219518U1 (en) * 2023-05-30 2023-07-21 Федеральное государственное бюджетное учреждение науки Федеральный исследовательский центр Якутский научный центр Сибирского отделения Российской академии наук Temporary transmission tower
RU220429U1 (en) * 2023-08-01 2023-09-13 Публичное акционерное общество "Якутскэнерго" (ПАО "Якутскэнерго") Temporary mobile power line support

Similar Documents

Publication Publication Date Title
CN212078880U (en) Temporary power line supporting device
CN215759234U (en) Pile foundation reinforcing apparatus for highway design
CN212691051U (en) Support frame for installing building water and electricity pipelines
CN210917388U (en) Easy dismouting formula underground structure
CN213145569U (en) Rocky desertification area administers with irrigation pipe laying device
CN209875183U (en) Tunnel IV-level surrounding rock full-circle excavation inverted arch longitudinal water stop fixing device
CN210430742U (en) Cable support for tunnel
CN214999782U (en) Municipal administration sewage pipe laying device
CN217419628U (en) Civil engineering pile foundation construction auxiliary positioning device
CN217003406U (en) Socket pipe line that can establish ties suspends protection in midair and uses staple bolt
CN213420146U (en) Convenient fixed antidetonation piping lane gallows
CN216067414U (en) Novel municipal works pipeline puts frame
CN212875352U (en) Quick-construction underground pipeline protection device
JP2849934B2 (en) Shaft excavation equipment
CN218405091U (en) Protector is used in bridge construction
CN211475094U (en) Hydraulic pipeline for hydraulic engineering
CN213597011U (en) Interim drainage structures of construction are built in room
CN220503885U (en) Supporting structure for preventing backfill from extruding pile body
CN214169076U (en) Socket joint formula concrete sewage pipe suspends protection device in midair
CN211873031U (en) Adjustable support connecting piece
CN217811092U (en) Civil engineering construction is with protection type supporting rack of being convenient for to build
CN219825264U (en) Pouring device
CN215715362U (en) Steel encloses purlin connecting device
CN212374721U (en) Building pipeline handling mounting structure
CN215594962U (en) Can have enough to meet need beam column joint concrete isolating device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant