CN212077657U - 一种步履顶推装置 - Google Patents

一种步履顶推装置 Download PDF

Info

Publication number
CN212077657U
CN212077657U CN201921111760.4U CN201921111760U CN212077657U CN 212077657 U CN212077657 U CN 212077657U CN 201921111760 U CN201921111760 U CN 201921111760U CN 212077657 U CN212077657 U CN 212077657U
Authority
CN
China
Prior art keywords
jacking
walking
base
bridge
machine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921111760.4U
Other languages
English (en)
Inventor
王东伟
张朝亮
吕牧
肖黎
潘强
卜祥干
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Engineering Co Ltd
No 2 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Original Assignee
CCCC First Highway Engineering Co Ltd
No 2 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Engineering Co Ltd, No 2 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd filed Critical CCCC First Highway Engineering Co Ltd
Priority to CN201921111760.4U priority Critical patent/CN212077657U/zh
Application granted granted Critical
Publication of CN212077657U publication Critical patent/CN212077657U/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本实用新型公开了一种步履顶推装置,由扁担梁、步履式顶推机、横移梁、顶推机底座、横移油缸组成,扁担梁直接放置于横移梁上,步履式顶推机放置于顶推机底座上并内置于扁担梁内部,顶推机底座放置于横移梁上并内置于扁担梁内部,横移油缸通过螺钉安装于顶推机底座上。本实用新型能够实现桥梁顶推过程中,步履式顶推机可以自适应桥梁的横向宽度变化,有效降低了现场人力劳动强度,设备整体操作简便,安全可靠。

Description

一种步履顶推装置
技术领域
本实用新型涉及一种变截面桥梁的顶推的应用场合,具体涉及一种可横桥向自横移的顶推机装置。
背景技术
目前,在连续桥梁顶推施工中,采用步履式顶推机进行顶推作业,其桥梁自身的结构特性为横桥向线性为等宽不变,桥梁自身受力腹板位置的宽度不变,这种桥梁顶推施工时,步履式顶推机和临时支撑不需要考虑横桥向移动的问题。一旦桥梁自身的结构设计为变截面时,桥梁自身的受力腹板位置的横向宽度随着顶推过程中在变化,此时需要步履式顶推机和临时支撑需要跟随腹板位置产生横桥向的移动。步履式顶推机和临时支撑由于单体重量都较大,在临时墩上横向移动,属于高空作业,大型作业设备无法进入参与工作,人工横移又很难实现,并且横移距离大时,对底部横移梁的用量要求非常大,现场施工的临时措施需求也会变得非常大,项目成本也会很高,经济性变差。因为步履式顶推机和临时支撑是分别对桥梁进行受力支撑,现场采用人工和受拉葫芦的方式进行横移的话,整体效率低下,作业强度大。
实用新型内容
针对以上技术中存在的缺陷,本实用新型的目的在于提供了一种步履顶推装置,既解决了装置横向自平移的功能,又实现了顶升的受力集中。
为实现以上目的,本实用新型采用如下的技术方案:一种步履顶推装置,由扁担梁、步履式顶推机、横移梁、顶推机底座、横移油缸组成,扁担梁直接放置于横移梁上,步履式顶推机放置于顶推机底座上并内置于扁担梁内部,顶推机底座放置于横移梁上并内置于扁担梁内部,横移油缸通过螺钉安装于顶推机底座上。
本实用新型装置的有益效果如下:自动实现步履式顶推机和扁担梁的横向移动,扁担梁的设计,降低了临时墩的建设强度要求,节约了横移梁的使用需求,横移油缸的使用,有效降低了对工人劳动强度的要求。
附图说明
图1是本实用新型主视图。
图2是图1的侧视图。
图3是图1的俯视图。
图4是图1的等轴测视图1。
图5是图1的等轴测视图2。
具体实施方式
下面结合附图和实施例进一步说明本实用新型的技术方案。
如图1、图2、图3、图4、图5所示,所述的一种步履顶推装置,由扁担梁、步履式顶推机、横移梁、顶推机底座、横移油缸组成,扁担梁直接放置于横移梁上,步履式顶推机放置于顶推机底座上并内置于扁担梁内部,顶推机底座放置于横移梁上并内置于扁担梁内部,横移油缸通过螺钉安装于顶推机底座上;
其中,扁担梁用于当作桥梁顶推过程中的临时支撑使用,步履式顶推机用于桥梁的顶升、顶推和纠偏使用,横移梁既可以承受上部的载荷、又可以用于步履顶推装置的横移轨道,顶推机底座用于放置步履式顶推机,横移油缸通过螺钉安装于顶推机底座上,当桥梁的腹板位置在横敲向发生变化,设备整体需要横向移动,此时可以先使步履式顶推机脱空,桥梁整体受力转移至扁担梁受力,横移油缸通过换向阀控制方向,由于横移油缸的移动,由于此时扁担梁被桥梁压住,不会产生横移,油缸会带动整个顶推机底板和步履式顶推机一起移动,当横移油缸一个行程移动到位后,步履式顶推机顶升受力,扁担梁脱空,此时横移油缸反向受力加载,由于此时步履式顶推机被桥梁压住,不会产生横移,油缸会带动扁担梁产生横移;在本实施例中,用扁担梁来带代替传统的临时支撑,受力中心线和步履式顶推机的受力中心线均在临时墩中线上,空间尺寸小,对底部临时墩要求降低;并且横向调整采用液压系统实现,有效节约现场的人员劳动强度,效率更高更安全;在本实施例中,横向调整时,通过扁担梁和步履式顶推机互为支撑,不需要外部再增加横向工装,操作简便。

Claims (1)

1.一种步履顶推装置,其特征在于:由扁担梁、步履式顶推机、横移梁、顶推机底座、横移油缸组成,扁担梁直接放置于横移梁上,步履式顶推机放置于顶推机底座上并内置于扁担梁内部,顶推机底座放置于横移梁上并内置于扁担梁内部,横移油缸通过螺钉安装于顶推机底座上。
CN201921111760.4U 2019-07-16 2019-07-16 一种步履顶推装置 Expired - Fee Related CN212077657U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921111760.4U CN212077657U (zh) 2019-07-16 2019-07-16 一种步履顶推装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921111760.4U CN212077657U (zh) 2019-07-16 2019-07-16 一种步履顶推装置

Publications (1)

Publication Number Publication Date
CN212077657U true CN212077657U (zh) 2020-12-04

Family

ID=73556607

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921111760.4U Expired - Fee Related CN212077657U (zh) 2019-07-16 2019-07-16 一种步履顶推装置

Country Status (1)

Country Link
CN (1) CN212077657U (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110685231A (zh) * 2019-07-16 2020-01-14 中交一公局第二工程有限公司 一种步履顶推装置

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110685231A (zh) * 2019-07-16 2020-01-14 中交一公局第二工程有限公司 一种步履顶推装置

Similar Documents

Publication Publication Date Title
CN102323100B (zh) 集成小车式电动葫芦试验台
CN212077657U (zh) 一种步履顶推装置
CN206318663U (zh) 一种简易式可移动升降平台
CN106044537B (zh) 一种活动吊装水平板状物的桁架
CN211517937U (zh) 一种大型混凝土块体陆上顶升和平移设施
CN202092861U (zh) 集成小车式电动葫芦试验台
CN210001467U (zh) 用于受限空间车间内吊装装置
CN202785368U (zh) 一种四吊点轻型阴极搬运天车系统
CN205295944U (zh) 挂篮轨道行走装置
CN218434693U (zh) 一种工字钢移动台车
CN203128113U (zh) 一种上料升降平台
CN210998602U (zh) 一种用于汽车油泥模型的操作支撑架
CN205836871U (zh) 一种制砖用砖块运输手推车
CN105672910B (zh) 油管牵引举升辅助机械
CN110685231A (zh) 一种步履顶推装置
CN210655905U (zh) 一种旋转回程吊机
CN205873699U (zh) 一种更换吊车车轮的组合装置
CN205772985U (zh) 一种土建用的龙门吊设备
CN206521242U (zh) 一种液压升降装置
CN220053897U (zh) 一种500kV电容式电压互感器运输小车
CN204057706U (zh) 一种桥式起重机主梁箱体结构
CN211762452U (zh) 一种钢筋模块化运输装置
CN204627003U (zh) 一种钢结构快速定位装置
CN203214090U (zh) 一种液压支架就位机
CN206203672U (zh) 一种行车机械抓斗

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201204

Termination date: 20210716

CF01 Termination of patent right due to non-payment of annual fee