CN212050185U - Tubular product hanging flower basket with buffering base - Google Patents

Tubular product hanging flower basket with buffering base Download PDF

Info

Publication number
CN212050185U
CN212050185U CN202020432397.2U CN202020432397U CN212050185U CN 212050185 U CN212050185 U CN 212050185U CN 202020432397 U CN202020432397 U CN 202020432397U CN 212050185 U CN212050185 U CN 212050185U
Authority
CN
China
Prior art keywords
pipe
supporting steel
steel bar
top plate
pipe supporting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020432397.2U
Other languages
Chinese (zh)
Inventor
李晋宇
张可
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN202020432397.2U priority Critical patent/CN212050185U/en
Application granted granted Critical
Publication of CN212050185U publication Critical patent/CN212050185U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

A pipe hanging basket with a buffer base comprises a bottom plate, a top plate and a stand column, wherein the top plate is erected on the bottom plate through a spring, and the stand column is detachably connected with the center of the surface of the top plate; the upper end and the lower end of the spring are respectively fixedly connected with the top plate and the bottom plate; the upright post is provided with a pipe supporting steel bar which is tensioned by a cable and then horizontally unfolded to support the inner wall of the pipe. In the utility model, the alignment of a plurality of tubes which are overlapped up and down is automatically completed in the process of tensioning the cable rope by arranging the tube supporting steel bars which are tensioned by the cable rope and then horizontally unfolded to support the inner wall of the tube, and the alignment of the tubes can be kept constantly in the process of hoisting, so that a plurality of tubes are allowed to be hoisted at one time, and the tube hoisting efficiency is improved; the utility model discloses in, the base of placing tubular product is provided with buffer, allows handling in-process hanging flower basket to land fast, has improved tubular product hoist and mount efficiency.

Description

Tubular product hanging flower basket with buffering base
Technical Field
The utility model relates to a construction technical field especially relates to a tubular product hanging flower basket with buffer base.
Background
In the building construction, the prefabricated concrete pipe is often used, the pipe is not resistant to collision, great care is needed during hoisting, and only one pipe can be hoisted at a time to avoid collision.
The existing concrete pipe hoisting method is to use a rope to pass through a building pipe, and then use a lifting hook of a crane to hook the rope for hoisting. The operation method can only hoist one building pipe at a time, and rope binding and dismantling are carried out during hoisting at each time, so that the operation is troublesome; and the stability is not good when the lifting is carried, the concrete pipe can not be ensured to be stably landed in the lifting process, and the lifted concrete pipe is easy to be damaged.
SUMMERY OF THE UTILITY MODEL
The utility model provides a tubular product hanging flower basket with buffering base.
The technical problem to be solved is that: in the building construction, when the concrete pipe and other large-diameter fragile pipes are hoisted, the efficiency is low.
In order to solve the technical problem, the utility model adopts the following technical scheme:
a pipe hanging basket with a buffer base comprises a bottom plate, a top plate and a stand column, wherein the top plate is erected on the bottom plate through a spring, and the stand column is detachably connected with the center of the surface of the top plate; the upper end and the lower end of the spring are respectively fixedly connected with the top plate and the bottom plate;
the upright post is provided with a pipe supporting steel bar, one end of the pipe supporting steel bar is rotatably connected with the upright post and rotates up and down around a horizontal shaft, and the other end of the pipe supporting steel bar is arranged by being attached to the inner wall of a pipe to be hoisted; the pipe supporting steel bars are uniformly arranged in supporting steel bar layers at intervals along the circumferential direction of the cross section of the upright column, each supporting steel bar layer comprises at least three pipe supporting steel bars, and the supporting steel bar layers are arranged at intervals along the length direction of the upright column;
the pipe supporting steel bars are detachably connected with the lifting hook of the crane through cables, and the lengths of the cables between each pipe supporting steel bar in the same supporting steel bar layer and the lifting hook are the same.
Furthermore, the mooring rope is hung on a lifting hook of the crane through a lifting ring.
Furthermore, the support reinforcing steel bar layers are arranged in an up-and-down alignment mode, and each cable extends downwards and is connected with each pipe support reinforcing steel bar with downward overlapped projections in sequence.
Furthermore, a soft cushion is laid on the top plate.
Further, the upright posts penetrate the top plate downwards and then are locked through the locking pins.
Further, the distance between the roots of two adjacent pipe supporting steel bars does not exceed half of the length of a single pipe to be hoisted.
Further, the length of the pipe supporting steel bar is not less than 1.2 times of the inner radius of the pipe to be hoisted, and the length of the steel bar between the connection point of the cable and the pipe supporting steel bar and the root of the pipe supporting steel bar is not less than 20 cm.
The utility model relates to a tubular product hanging flower basket with buffer base compares with prior art, has following beneficial effect:
in the utility model, the alignment of a plurality of tubes which are overlapped up and down is automatically completed in the process of tensioning the cable rope by arranging the tube supporting steel bars which are tensioned by the cable rope and then horizontally unfolded to support the inner wall of the tube, and the alignment of the tubes can be kept constantly in the process of hoisting, so that a plurality of tubes are allowed to be hoisted at one time, and the tube hoisting efficiency is improved;
in the utility model, the base for placing the pipe is provided with the buffer device, which allows the hanging basket to quickly land in the hoisting process, thereby improving the hoisting efficiency of the pipe;
note that the utility model discloses in, the pulling force of hawser does not rely on the friction between tubular product support reinforcement and the tubular product inner wall to transmit, and after tubular product retrained the angle between tubular product support reinforcement and the stand, the pulling force of hawser just transmitted the stand through tubular product support reinforcement on, and then transmitted to the roof on, consequently, the smooth tubular product of inner wall also can adopt the utility model discloses hoist and mount.
Drawings
FIG. 1 is a schematic structural view of a pipe hanging basket with a buffering base according to the present invention;
FIG. 2 is a schematic structural view of a tubular hanging basket with a buffering base according to the present invention in a use state;
the steel wire rope comprises a base plate 1, a spring 11, a top plate 2, a cushion 21, a stand column 3, a pipe supporting steel bar 31, a cable 4, a hanging ring 41 and a pipe 5.
Detailed Description
As shown in fig. 1-2, a pipe hanging basket with a buffer base comprises a bottom plate 1, a top plate 2 erected on the bottom plate 1 through a spring 11, and a vertical column 3 detachably connected with the center of the surface of the top plate 2; the upper end and the lower end of the spring 11 are respectively fixedly connected with the top plate 2 and the bottom plate 1, and the spring 11 plays a role in buffering and allows the hanging basket to quickly land;
a pipe supporting steel bar 31 is arranged on the upright post 3, one end of the pipe supporting steel bar 31 is rotationally connected with the upright post 3 and rotates up and down around a horizontal shaft, and the other end of the pipe supporting steel bar 31 is arranged by being attached to the inner wall of the pipe 5 to be hoisted; the pipe supporting steel bars 31 are uniformly arranged at intervals along the circumferential direction of the cross section of the upright post 3 to form supporting steel bar layers, and the supporting steel bar layers are arranged at intervals along the length direction of the upright post 3; note that each support rebar layer should include at least three pipe support rebars 31, too few of which are not effective in supporting the pipe 5;
the pipe supporting steel bars 31 are detachably connected with the lifting hooks of the crane through the mooring ropes 4, the length of the mooring ropes 4 between each pipe supporting steel bar 31 and the lifting hook in the same supporting steel bar layer is the same, so that the end parts of the pipe supporting steel bars 31 cannot abut against the inner wall of the pipe 5, the length of the mooring ropes 4 is controlled, and after the rope is tensioned, all the pipe supporting steel bars 31 abut against the inner wall of the pipe 5.
The cable 4 is hung on a hook of the crane through a hanging ring 41.
The support rebar layers are aligned one above the other and each cable 4 extends downward and is in turn connected to a respective tube support rebar 31 whose downward projection overlaps, noting that the length of the cable segment between adjacent support rebar layers should be kept consistent so as not to affect the alignment of the tubes 5. Thus, only the same number of cables 4 as the number of the pipe support bars 31 in one support bar layer are needed, and the use amount of the cables 4 can be saved. It is of course also possible to equip each tube support bar 31 with a separate cable 4, but that is too wasteful.
The top plate 2 is provided with a cushion 21 to provide a cushioning effect when the tubes 5 are stacked.
The stand 3 is locked through the stop pin after penetrating through the roof 2 downwards, only needs to pull down the stop pin like this and can dismantle stand 3, is convenient for lift tubular product 5 off.
The distance between the roots of the two adjacent pipe supporting steel bars 31 is not more than half of the length of a single pipe 5 to be hoisted, so that the pipe 5 cannot be supported by the pipe supporting steel bars 31.
The length of the pipe supporting steel bar 31 is not less than 1.2 times of the inner radius of the pipe 5 to be hoisted, so that the pipe supporting steel bar 31 is prevented from slipping; the length of the steel bar section between the connecting point of the cable 4 and the pipe supporting steel bar 31 and the root of the pipe supporting steel bar 31 is not less than 20 cm, so that the tension of the cable 4 to the pipe supporting steel bar 31 is not enough.
The utility model relates to a tubular product hanging flower basket with buffering base, its installation and use include following step:
firstly, stacking a pipe 5 to be hoisted on a top plate 2 in a manner that the end part is horizontal, and ensuring that the overhanging end of a pipe supporting steel bar 31 is in a sagging state when placing;
step two, hoisting, the pipe 5 will align automatically after the cable 4 is strained, pay attention to the utility model, the pulling force of the cable 4 does not depend on the friction between the pipe supporting steel bar 31 and the inner wall of the pipe 5 to transmit, after the pipe 5 restrains the angle between the pipe supporting steel bar 31 and the upright post 3, the pulling force of the cable 4 is transmitted to the upright post 3 through the pipe supporting steel bar 31, and then transmitted to the top plate 2, therefore, the pipe 5 with smooth inner wall can also adopt the utility model to hoist;
and step three, pulling down the locking pin on the upright post 3, detaching the upright post 3 and sequentially detaching the pipe 5.
The above-mentioned embodiments are only for describing the preferred embodiments of the present invention, and are not intended to limit the scope of the present invention, and various modifications and improvements made by those skilled in the art without departing from the design spirit of the present invention should fall into the protection scope defined by the claims of the present invention.

Claims (7)

1. The utility model provides a tubular product hanging flower basket with buffering base which characterized in that: comprises a bottom plate (1), a top plate (2) erected on the bottom plate (1) through a spring (11), and an upright post (3) detachably connected with the center of the surface of the top plate (2); the upper end and the lower end of the spring (11) are respectively fixedly connected with the top plate (2) and the bottom plate (1);
a pipe supporting steel bar (31) is arranged on the upright post (3), one end of the pipe supporting steel bar (31) is rotatably connected with the upright post (3) and rotates up and down around a horizontal shaft, and the other end of the pipe supporting steel bar is arranged by being attached to the inner wall of the pipe (5) to be hoisted; the pipe supporting steel bars (31) are uniformly arranged into supporting steel bar layers at intervals along the circumferential direction of the cross section of the upright post (3), each supporting steel bar layer comprises at least three pipe supporting steel bars (31), and the supporting steel bar layers are arranged at intervals along the length direction of the upright post (3);
the pipe supporting steel bars (31) are detachably connected with the lifting hook of the crane through cables (4), and the lengths of the cables (4) between each pipe supporting steel bar (31) in the same supporting steel bar layer and the lifting hook are the same.
2. The pipe hanging basket with the buffering base as claimed in claim 1, wherein: the mooring rope (4) is hung on a lifting hook of the crane through a lifting ring (41).
3. The pipe hanging basket with the buffering base as claimed in claim 2, wherein: the supporting reinforcing steel bar layers are arranged in an up-and-down alignment mode, and each cable (4) extends downwards and is connected with each pipe supporting reinforcing steel bar (31) with downward overlapped projections in sequence.
4. The pipe hanging basket with the buffering base as claimed in claim 3, wherein: the top plate (2) is laid with a soft cushion (21).
5. The pipe hanging basket with the buffering base as claimed in claim 4, wherein: the upright post (3) penetrates through the top plate (2) downwards and then is locked by a locking pin.
6. The pipe hanging basket with the buffering base as claimed in claim 5, wherein: the distance between the roots of two adjacent pipe supporting steel bars (31) is not more than half of the length of a single pipe (5) to be hoisted.
7. A pipe hanging basket with a buffer base according to any one of claims 1 to 6, wherein: the length of the pipe supporting steel bar (31) is not less than 1.2 times of the inner radius of the pipe (5) to be hoisted, and the length of the steel bar between the connecting point of the cable (4) and the pipe supporting steel bar (31) and the root of the pipe supporting steel bar (31) is not less than 20 cm.
CN202020432397.2U 2020-03-30 2020-03-30 Tubular product hanging flower basket with buffering base Expired - Fee Related CN212050185U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020432397.2U CN212050185U (en) 2020-03-30 2020-03-30 Tubular product hanging flower basket with buffering base

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020432397.2U CN212050185U (en) 2020-03-30 2020-03-30 Tubular product hanging flower basket with buffering base

Publications (1)

Publication Number Publication Date
CN212050185U true CN212050185U (en) 2020-12-01

Family

ID=73539360

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020432397.2U Expired - Fee Related CN212050185U (en) 2020-03-30 2020-03-30 Tubular product hanging flower basket with buffering base

Country Status (1)

Country Link
CN (1) CN212050185U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112548977A (en) * 2020-12-09 2021-03-26 大连中远海运重工有限公司 Tool for storing section bar and pipe

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112548977A (en) * 2020-12-09 2021-03-26 大连中远海运重工有限公司 Tool for storing section bar and pipe

Similar Documents

Publication Publication Date Title
CN113387267B (en) Safe hoisting and lowering method for underground diaphragm wall reinforcement cage
CN212050185U (en) Tubular product hanging flower basket with buffering base
CN210366620U (en) A hang muscle system for steel reinforcement cage
CN112943549A (en) Concrete tower cylinder steel strand pulling construction method
CN202926333U (en) Hanging system of whole-circle integral upside down hanging formwork
CN204983692U (en) Concrete panel's hoist device
CN201027135Y (en) Hanging tool mechanism for swinging 55mPHC pipe pile
CN112193984B (en) Steel reinforcement cage lifting and fixing device and steel reinforcement cage lifting method
CN114590697A (en) High-span concrete support dismantling method based on reserved lifting hook for closed space
CN213653457U (en) Steel reinforcement cage lifts by crane and mounting structure
CN113353832A (en) Steel template hoist device of wallboard is pour to prefabricated construction now
CN108644471B (en) Pipeline sliding transportation structure system on large-area water area and construction method thereof
CN218027231U (en) Simple device for lowering bottom basket of hanging basket
CN107364820A (en) A kind of simple hoisting frame and application method
CN211419396U (en) Integral hoisting device for amplitude-variable derrick mast of large equipment
CN216918357U (en) Hoisting device utilizing building internal structure
CN218538992U (en) Wallboard auxiliary erection gallows device
CN110172965B (en) Sectional construction device and construction method for underground continuous wall reinforcing steel bars
CN109941900A (en) A kind of sound barrier plate simply installs equipment
CN218620047U (en) Large-scale steel reinforcement cage continuous lowering device
CN220815137U (en) Multifunctional suspension cage suitable for chimney construction
CN217148246U (en) Large-tonnage steel reinforcement cage hoisting accessory
CN218758804U (en) Guide rail frame dismouting auxiliary device
CN214462524U (en) Cast-in-place floor formwork hanging system for steel structure building
CN217126648U (en) Overhead hoist suitable for bridge template and bridge

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201201

CF01 Termination of patent right due to non-payment of annual fee