CN212027054U - Overhanging scaffold - Google Patents

Overhanging scaffold Download PDF

Info

Publication number
CN212027054U
CN212027054U CN202020404335.0U CN202020404335U CN212027054U CN 212027054 U CN212027054 U CN 212027054U CN 202020404335 U CN202020404335 U CN 202020404335U CN 212027054 U CN212027054 U CN 212027054U
Authority
CN
China
Prior art keywords
wire rope
steel wire
cantilever beam
internal force
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020404335.0U
Other languages
Chinese (zh)
Inventor
张奇
徐优斌
朱纪泽
许勇
徐满
岳高飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hefei Construction Engineering Group Co ltd
Original Assignee
Hefei Construction Engineering Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hefei Construction Engineering Group Co ltd filed Critical Hefei Construction Engineering Group Co ltd
Priority to CN202020404335.0U priority Critical patent/CN212027054U/en
Application granted granted Critical
Publication of CN212027054U publication Critical patent/CN212027054U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model discloses a scaffold frame encorbelments, including cantilever beam, scaffold frame, first wire rope, second wire rope, internal force monitoring devices and rings device, cantilever beam fixes on the floor and stretches out the floor and encorbelments the scaffold frame, first wire rope one end with the end connection of encorbelmenting of cantilever beam, the other end passes through the one end that second wire rope is connected to internal force monitoring devices, the concrete beam that one deck was passed through rings device and floor is connected to the one end that internal force detection devices was kept away from to second wire rope. The utility model has the advantages that the original process that the hanging ring needs to be embedded is cancelled, the assembly and disassembly are convenient and quick, and the hanging ring device can be repeatedly used after being disassembled, thereby reducing the construction cost; simultaneously, can realize carrying out real-time supervision to wire rope internal force to can learn wire rope's atress situation, prevent that wire rope atress is uneven or the too big phenomenon of atress from taking place, improve this scaffold frame that encorbelments's factor of safety.

Description

Overhanging scaffold
Technical Field
The utility model relates to a construction scaffolding technical field specifically is a scaffold frame encorbelments.
Background
The scaffold is a working platform which is erected for ensuring that each construction process is smoothly carried out. The scaffold is divided into an outer scaffold and an inner scaffold according to the erected positions; the scaffold can be divided into a wood scaffold, a bamboo scaffold and a steel pipe scaffold according to different materials; divide into pole setting formula scaffold frame, bridge type scaffold frame, gate-type scaffold frame, the scaffold frame of encorbelmenting, hanging scaffold frame, the formula scaffold frame of encorbelmenting, climbing formula scaffold frame according to the structural style.
Generally, when a high-rise building is constructed, a section steel cantilever scaffold is a common construction technology, and according to related technical regulations, an inclined steel wire rope is arranged at the outer end of a section steel cantilever beam and is tied with the building to serve as a safety guarantee measure of a main stress component of the scaffold. One end of the steel wire rope is tied with the cantilever beam, and the other end of the steel wire rope is tied with a hanging ring embedded in an upper structure (a side beam, a shear wall and a column) of the building, so that the load of the scaffold is transmitted to the structure of the building.
However, the length of the hanging ring exposed outside the concrete is difficult to control when the hanging ring is buried underground, the length of the hanging ring exposed outside the concrete is too short after the concrete pouring is finished, the steel wire rope cannot conveniently pass through the hanging ring or even cannot pass through the hanging ring, the mounting is difficult, the hanging ring is difficult to dismount in a pre-buried mode in a later period, the material is wasted, the hanging ring cannot be recycled, and the construction cost is high.
SUMMERY OF THE UTILITY MODEL
The utility model discloses the technical problem that will solve lies in: the utility model provides a can easy dismounting, reduce construction cost's scaffold frame of encorbelmenting to solve the current scaffold frame of encorbelmenting dismouting difficulty and the higher problem of construction cost.
In order to solve the technical problem, the utility model provides a following technical scheme:
the utility model provides a scaffold frame encorbelments, includes cantilever beam, scaffold frame, first wire rope, second wire rope, internal force monitoring devices and rings device, cantilever beam fixes on the floor and stretches out the floor and encorbelment the scaffold frame, first wire rope one end with cantilever beam's the end connection of encorbelmenting, the other end passes through internal force monitoring devices connects second wire rope's one end, second wire rope keeps away from the one end of internal force detection devices and passes through rings device and floor upper story concrete beam and be connected, rings device and concrete beam go up screw hole cooperation and detachable fix on concrete beam.
The utility model discloses when concrete installation, will hang cantilever beam and fix on the floor to the end of encorbelmenting of cantilever beam stretches out the floor, then utilize first wire rope to connect the end of encorbelmenting of cantilever beam, and connect second wire rope one end through internal force monitoring devices, the second wire rope other end then through connecting screw rod hole cooperation and detachable fixing on the concrete beam on rings device and the concrete beam, install the scaffold frame at last and hold in encorbelmenting of the cantilever beam that stretches out the floor.
The template is fixed through the wall-penetrating screw during construction of the concrete beam, the screw hole is reserved on the concrete beam after the template and the wall-penetrating screw are removed, and the second steel wire rope is matched with the screw hole through the hanging ring device and is detachably fixed on the concrete beam, so that the original process of embedding the hanging ring is omitted, the assembly and the disassembly are convenient and quick, and the hanging ring device can be reused after being disassembled, so that the construction cost is reduced; simultaneously, through internal force monitoring devices connects first wire rope and second wire rope can realize carrying out real-time supervision to the wire rope internal force to can learn wire rope's atress situation, prevent that wire rope atress is uneven or the too big phenomenon of atress from taking place, improve this scaffold frame of encorbelmenting's factor of safety.
Preferably, the internal force monitoring device comprises a steel bar stress meter, a connecting rod and a connecting sleeve, wherein two ends of the steel bar stress meter are connected with one end of the connecting rod, the other end of the connecting rod is connected with the connecting sleeve, and the two connecting sleeves are respectively connected with the first steel wire rope and the second steel wire rope.
Utilize the adapter sleeve at internal force monitoring devices both ends respectively with first wire rope and second wire rope are connected, realize the connection to the cantilever beam to the bar stressometer passes through the connecting rod adapter sleeve, thereby realizes right through the bar stressometer the internal force of first wire rope and second wire rope carries out real-time supervision, thereby can learn wire rope's atress situation, prevents that the uneven or too big phenomenon of atress of wire rope from taking place, and then improves this scaffold frame of encorbelmenting's factor of safety.
Preferably, the connecting sleeve is a U-shaped sleeve, the connecting rod is fixedly clamped between two parallel ends of the U-shaped sleeve, and the bending ends of the two U-shaped sleeves are correspondingly connected with the first steel wire rope and the second steel wire rope.
Preferably, the two parallel ends of the U-shaped sleeve and the connecting rod are fixed by welding through double-sided upper strips.
Preferably, the rings device includes screw rod rings, fastening steel sheet and fastening nut, the screw rod rings include screw rod section and hoist ring section, the screw rod hole and the fastening steel sheet that the screw rod section passed the concrete beam are fixed inboard at the concrete beam with fastening nut threaded connection, the hoist ring section is closed form setting in the outside of concrete beam and connects the second wire rope.
The second steel wire rope is connected with the hanging ring section on the screw rod hanging ring, then the screw rod section sequentially penetrates through the screw rod hole of the concrete beam and the fastening steel plate and is fixed on the inner side of the concrete beam through the fastening nut, the installation is convenient, the detachable connection is realized, the connection and the fixation of the second steel wire rope are realized, and the connection of the cantilever beam cantilever end is realized.
Through the screw section threaded connection on fastening bolt and the screw rod rings, simple to operate has cancelled the original process that needs pre-buried rings to only need unscrew fastening bolt when dismantling, can take out the screw rod rings, the dismouting is all convenient quick, and dismantle the back the rings device can also reuse, reduces construction cost.
Preferably, the tangent point of the hanging ring section of the screw rod hanging ring in the vertical direction is attached to the outer wall of the concrete beam, and a gasket is arranged between the tangent point of the hanging ring section in the vertical direction and the outer wall of the concrete beam, so that abrasion of the concrete beam caused by stress between the hanging ring section and the outer wall of the concrete beam is prevented.
Preferably, each end of the first steel wire rope and the second steel wire rope is wound around the corresponding connecting end of the cantilever beam, the internal force monitoring device and the hanging ring device and then fixed through at least four rope clamps.
Preferably, safety bends are arranged on the steel wire rope between the two rope clamps at each end of the first steel wire rope and on the steel wire rope between the two rope clamps at each end of the second steel wire rope and are used for detecting whether the rope clamps are loose in fixing the ends of the first steel wire rope and the second steel wire rope, if the safety bends shrink, the end of the steel wire rope is proved to be loose in fixing, reinforcement measures need to be taken, and the safety factor of the cantilever scaffold is further improved.
Preferably, the scaffold comprises vertical rods and a cross rod, wherein a plurality of parallel vertical rods are vertically arranged at the top ends of the cantilever beams, and the cross rod is horizontally fixed between the vertical rods and forms a frame structure with the vertical rods.
Preferably, the cantilever beam is shaped steel cantilever beam, the end of encorbelmenting of shaped steel cantilever beam is equipped with the hole for hoist of connecting first wire rope, the top of shaped steel cantilever beam end of encorbelmenting still is equipped with the anti-skidding stake that can insert the pole setting bottom, prevents that the pole setting is in shaped steel cantilever beam top slides, guarantees the safety of this scaffold frame of encorbelmenting.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the lifting ring device is matched with the screw rod hole and is detachably fixed on the concrete beam, the original working procedure of pre-embedding the lifting ring is omitted, the assembly and disassembly are convenient and quick, the lifting ring device can be reused after being disassembled, and the construction cost is reduced; simultaneously, through internal force monitoring devices connects first wire rope and second wire rope can realize carrying out real-time supervision to the wire rope internal force to can learn wire rope's atress situation, prevent that wire rope atress is uneven or the too big phenomenon of atress from taking place, improve this scaffold frame of encorbelmenting's factor of safety.
2. The gasket is arranged between the tangent point of the hanging ring section in the vertical direction and the outer wall of the concrete beam, so that the concrete beam is prevented from being abraded due to stress between the hanging ring section and the outer wall of the concrete beam.
3. The safety bend is arranged on the ends of the first steel wire rope and the second steel wire rope and used for detecting whether the end fixing of the first steel wire rope and the end fixing of the second steel wire rope are loosened or not, if the safety bend shrinks, the end fixing of the steel wire rope is proved to be loosened, reinforcement measures need to be taken, and the safety factor of the cantilever scaffold is further improved.
4. Through set up the anti-skidding stake on the cantilever beam, prevent that the pole setting is in the shaped steel cantilever beam top slides, guarantees this scaffold frame of encorbelmenting's safety.
Drawings
Fig. 1 is a schematic structural view of an overhanging scaffold according to an embodiment of the present invention;
fig. 2 is a schematic structural view of an overhanging beam according to an embodiment of the present invention;
fig. 3 is a schematic structural diagram of an internal force monitoring device according to an embodiment of the present invention;
fig. 4 is a schematic structural view of a hanging ring device according to an embodiment of the present invention.
Detailed Description
In order to facilitate the understanding of the technical solutions of the present invention by those skilled in the art, the technical solutions of the present invention will now be further described with reference to the drawings attached to the specification.
In this application, unless expressly stated or limited otherwise, the terms "mounted," "connected," "secured," and the like are to be construed broadly and can include, for example, fixed connections, removable connections, or integral parts; the connection can be mechanical connection, electrical connection or communication; either directly or indirectly through intervening media, either internally or in any other relationship. The specific meaning of the above terms in the present application can be understood by those of ordinary skill in the art as appropriate.
The terms "first", "second" and "first" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of the present application, "a plurality" means two or more unless specifically limited otherwise.
Example one
Referring to fig. 1, this embodiment discloses a scaffold frame of encorbelmenting, including cantilever beam 1, scaffold frame 2, first wire rope 3, second wire rope 4, internal force monitoring devices 5 and rings device 6, cantilever beam 1 is fixed on floor 7 and is stretched out floor 7 and encorbelments scaffold frame 2, first wire rope 3 one end with cantilever beam 1's the end connection of encorbelmenting, the other end passes through internal force monitoring devices 5 connects the one end of second wire rope 4, the one end that internal force detection devices 5 was kept away from to second wire rope 4 is passed through rings device 6 and is connected with the concrete beam 8 of floor 7 upper story, rings device 6 and concrete beam 8 go up the screw rod hole 81 cooperation and detachable the fixing on concrete beam 8.
The cantilever beam 1 is fixed on a floor slab 7, the cantilever beam 1 is cantilevered out of the floor slab 7, then the first steel wire rope 3 is used for connecting the cantilever beam 1, the internal force monitoring device 5 is used for connecting one end of a second steel wire rope 4, the other end of the second steel wire rope 4 is matched with a screw hole 81 on a concrete beam 8 through a connecting lifting ring device 6 and is detachably fixed on the concrete beam 8, and finally, a scaffold 2 is arranged on the cantilever beam 1 which extends out of the floor slab 7.
Because the template is fixed through the wall-penetrating screw during the construction of the concrete beam, the screw hole 81 is left on the concrete beam 8 after the template and the wall-penetrating screw are removed, the second steel wire rope is matched with the screw hole 81 through the lifting ring device 6 and is detachably fixed on the concrete beam 8, the original working procedure of pre-embedding the lifting ring is cancelled, the dismounting and the mounting are convenient and quick, the lifting ring device 6 can be reused after the dismounting, the construction cost is reduced, and the same is also realized, and the lifting device 6 can also be suitable for the concrete shear wall; simultaneously, through internal force monitoring devices 5 are connected first wire rope 3 and second wire rope 4 can realize carrying out real-time supervision to the wire rope internal force to can learn wire rope's atress situation, prevent that the uneven or too big phenomenon of atress of wire rope from taking place, improve this scaffold frame of encorbelmenting's factor of safety.
The scaffold 2 comprises upright rods 21 and cross rods 22, wherein a plurality of parallel upright rods 21 are vertically arranged at the top end of the cantilever beam 1, and the cross rods 22 are horizontally fixed between the upright rods 21 and form a frame structure with the upright rods 21.
Referring to fig. 2, cantilever beam 1 is shaped steel cantilever beam, shaped steel cantilever beam's the end of encorbelmenting is equipped with the hole for hoist 11 of connecting first wire rope 3, shaped steel cantilever beam encorbelments the top of end and still is equipped with the anti-skidding stake 12 that can insert pole setting 21 bottom, prevents that pole setting 21 from being in shaped steel cantilever beam top slides, guarantees this scaffold frame's of encorbelmenting safety.
The internal force monitoring device 5 comprises a steel bar stress meter 51, a connecting rod 52 and a connecting sleeve 53, wherein two ends of the steel bar stress meter 51 are connected with one end of the connecting rod 52 in an internal thread mode, the other end of the connecting rod 52 is connected with the connecting sleeve 53, and the connecting sleeve 53 is connected with the first steel wire rope 3 and the second steel wire rope 4 respectively.
Utilize the adapter sleeve 53 at 5 both ends of internal force monitoring devices respectively with first wire rope 3 and second wire rope 4 are connected, realize the connection to cantilever beam 1 to bar stress meter 51 passes through connecting rod 52 adapter sleeve 53, thereby realizes right through bar stress meter 51 the internal force of first wire rope 3 and second wire rope 4 carries out real-time supervision, thereby can learn wire rope's atress situation, prevents that the wire rope atress is uneven or the too big phenomenon of atress from taking place, and then improves this scaffold frame of encorbelmenting's factor of safety.
The connecting sleeve 53 is a U-shaped sleeve, the connecting rod 52 is fixedly clamped between two parallel ends of the U-shaped sleeve through double-sided batten welding, the bent ends of the two U-shaped sleeves are correspondingly connected with the first steel wire rope 3 and the second steel wire rope 4, the length of a welding seam between the two parallel ends of the U-shaped sleeve and the connecting rod 52 is not less than 150mm, and the connecting strength between the two parallel ends of the U-shaped sleeve and the connecting rod 52 is ensured.
The hoisting ring device 6 comprises a screw hoisting ring 61, a fastening steel plate 62 and a fastening nut 63, the screw hoisting ring 61 comprises a screw section 611 and a hoisting ring section 612, the screw section 611 passes through a screw hole 81 of the concrete beam 8 and the fastening steel plate 62 is in threaded connection with the fastening nut 63 and is fixed on the inner side of the concrete beam 8, and the hoisting ring section 612 is arranged on the outer side of the concrete beam 8 in a closed manner and is connected with the second steel wire rope 4.
The second steel wire rope 4 is connected with the hanging ring segment 612 on the screw hanging ring 61, then the screw segment 611 sequentially penetrates through the screw hole 81 of the concrete beam 8 and the fastening steel plate 62 and is fixed on the inner side of the concrete beam 8 through the fastening nut 63, the installation is convenient, the detachable connection is realized, the connection and the fixation of the second steel wire rope 4 are realized, and the connection of the cantilever end of the cantilever beam 1 is further realized.
Through fastening bolt 63 and the screw section 611 threaded connection on the screw rod rings 61, simple to operate has cancelled the original process that needs pre-buried rings to only need to unscrew fastening bolt 63 when dismantling, can take out screw rod rings 61, the dismouting is all convenient quick, and dismantle the back the rings device 6 can also reuse, reduces construction cost.
The tangent point of the hanging ring section 612 of the screw rod hanging ring 61 in the vertical direction is attached to the outer wall of the concrete beam 8, and a gasket (not marked in the figure) is arranged between the tangent point of the hanging ring section 612 in the vertical direction and the outer wall of the concrete beam 8, so that abrasion of the concrete beam 8 caused by stress between the hanging ring section 612 and the outer wall of the concrete beam 8 is prevented; in this embodiment, the gasket is a rubber gasket or a template gasket.
The working principle of the embodiment is as follows: fixing the cantilever beam 1 on a floor slab 7, extending the cantilever end of the cantilever beam 1 out of the floor slab 7, connecting the cantilever end of the cantilever beam 1 by using one end of a first steel wire rope 3 to pass through a hoisting hole 11, connecting the other end of the first steel wire rope to the bending end of a connecting sleeve 53 at one end of an internal force monitoring device 5, connecting the bending end of the connecting sleeve 53 at the other end of the internal force monitoring device 5 to one end of a second steel wire rope 4, connecting the other end of the second steel wire rope 4 to a hanging ring section 612 of a screw hanging ring 61, sequentially passing the screw section 611 through a screw hole 81 of a concrete beam 8 and a fastening steel plate 62 and fixing the screw section 611 on the inner side of the concrete beam 8 through a fastening nut 63, locking the fastening nut 63, and arranging a gasket between the vertical tangent point of the hanging ring section 612 and the outer wall of the concrete beam 8 to prevent the concrete beam 8 from being, finally, vertically fixing the upright rod 21 of the scaffold 2 at the top end of the cantilever beam 1, inserting the anti-skid pile 12 into the upright rod 21, preventing the upright rod 21 from sliding on the cantilever beam 1, ensuring the safety of the cantilever scaffold, and then installing the cross rod 22 on the upright rod 21 to form the scaffold with a frame structure; and when the construction, carry out real-time supervision through steel bar stressometer 51 to first wire rope 3 and second wire rope 4's internal force to can learn wire rope's stress situation, prevent that the wire rope atress is uneven or the too big phenomenon of atress from taking place, and then improve this scaffold frame's of encorbelmenting factor of safety.
Example two
Referring to fig. 3 and 4, in this embodiment, on the basis of the first embodiment, the ends of the two ends of the first steel wire rope 3 are respectively and correspondingly wound around the hoisting hole 11 of the cantilever beam 1 and one end of the internal force monitoring device 5, and each end is fixed by at least four rope clips 9; similarly, the ends of the two ends of the second steel wire rope 4 are respectively and correspondingly wound on the other end of the internal force monitoring device 5 and one end of the lifting ring device, and each end is fixed through at least four rope clamps 9, so that the connection strength of the ends of the two ends of the first steel wire rope 3 and the second steel wire rope 4 is ensured.
Furthermore, safety bends 10 are arranged on the steel wire rope between two rope clamps 9 at each end of the first steel wire rope 3 and the steel wire rope between two rope clamps 9 at each end of the second steel wire rope 4 and used for detecting whether the end fixing of the first steel wire rope 3 and the end fixing of the second steel wire rope 4 are loosened or not through the rope clamps 9, if the safety bends 10 are contracted, the end fixing of the steel wire rope is proved to be loosened, reinforcing measures need to be taken, and the safety factor of the cantilever scaffold is further improved.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein, and any reference signs in the claims are not intended to be construed as limiting the claim concerned.
The above embodiments only show the embodiments of the present invention, and the protection scope of the present invention is not limited to the above embodiments, and for those skilled in the art, a plurality of modifications and improvements can be made without departing from the concept of the present invention, and these modifications and improvements all belong to the protection scope of the present invention.

Claims (10)

1. The utility model provides a scaffold frame of encorbelmenting which characterized in that: including cantilever beam, scaffold frame, first wire rope, second wire rope, internal force monitoring devices and rings device, the cantilever beam is fixed on the floor and is stretched out the floor and encorbelment the scaffold frame, first wire rope one end with the end connection of encorbelmenting of cantilever beam, the other end passes through the one end of second wire rope is connected to internal force monitoring devices, the one end that internal force detection devices was kept away from to second wire rope is passed through rings device and is connected with the concrete beam of floor upper story, rings device and concrete beam go up screw rod hole cooperation and detachable fix on concrete beam.
2. An overhanging scaffold according to claim 1, wherein: the internal force monitoring device comprises a steel bar stress meter, a connecting rod and connecting sleeves, wherein two ends of the steel bar stress meter are connected with one end of the connecting rod, the other end of the connecting rod is connected with the connecting sleeves, and the connecting sleeves are respectively connected with the first steel wire rope and the second steel wire rope.
3. An overhanging scaffold according to claim 2, wherein: the connecting sleeve is a U-shaped sleeve, the connecting rod is fixedly clamped between two parallel ends of the U-shaped sleeve, and the bent ends of the two U-shaped sleeves are correspondingly connected with the first steel wire rope and the second steel wire rope.
4. A cantilever scaffold according to claim 3, wherein: and the two parallel ends of the U-shaped sleeve are welded and fixed with the connecting rod through double-sided upper strips.
5. An overhanging scaffold according to claim 1, wherein: the lifting ring device comprises a screw lifting ring, a fastening steel plate and a fastening nut, the screw lifting ring comprises a screw rod section and a lifting ring section, the screw rod section penetrates through a screw rod hole of the concrete beam, the fastening steel plate is in threaded connection with the fastening nut and is fixed on the inner side of the concrete beam, and the lifting ring section is closed and is arranged on the outer side of the concrete beam and connected with the second steel wire rope.
6. An overhanging scaffold according to claim 5, wherein: the tangent point of the vertical direction of the lifting ring section of the screw lifting ring is attached to the outer wall of the concrete beam, and a gasket is arranged between the tangent point of the vertical direction of the lifting ring section and the outer wall of the concrete beam.
7. An overhanging scaffold according to claim 1, wherein: and the ends of the first steel wire rope and the second steel wire rope are wound with the corresponding connecting ends of the cantilever beam, the internal force monitoring device and the hanging ring device and then are fixed through at least four rope clamps.
8. An overhanging scaffold according to claim 7, wherein: and safety bends are arranged on the steel wire rope between the two rope clamps at each end of the first steel wire rope and the steel wire rope between the two rope clamps at each end of the second steel wire rope.
9. An overhanging scaffold according to claim 1, wherein: the scaffold comprises upright rods and cross rods, wherein the parallel upright rods are vertically arranged at the top ends of the cantilever beams, and the cross rods are horizontally fixed between the upright rods and form a frame structure with the upright rods.
10. An overhanging scaffold according to claim 9, wherein: the cantilever beam is a profile steel cantilever beam, a hoisting hole for connecting a first steel wire rope is formed in the cantilever end of the profile steel cantilever beam, and an anti-slip pile capable of being inserted into the bottom end of the vertical rod is further arranged at the top of the cantilever end of the profile steel cantilever beam.
CN202020404335.0U 2020-03-24 2020-03-24 Overhanging scaffold Active CN212027054U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020404335.0U CN212027054U (en) 2020-03-24 2020-03-24 Overhanging scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020404335.0U CN212027054U (en) 2020-03-24 2020-03-24 Overhanging scaffold

Publications (1)

Publication Number Publication Date
CN212027054U true CN212027054U (en) 2020-11-27

Family

ID=73488182

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020404335.0U Active CN212027054U (en) 2020-03-24 2020-03-24 Overhanging scaffold

Country Status (1)

Country Link
CN (1) CN212027054U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112942778A (en) * 2021-03-23 2021-06-11 中铁二十局集团第六工程有限公司 Overhanging type double-row scaffold and construction method thereof
CN113152871A (en) * 2021-04-18 2021-07-23 广西建工第一建筑工程集团有限公司 Tool type temporary cantilever steel beam foundation system device and mounting and dismounting use method
CN116464271A (en) * 2023-05-25 2023-07-21 中国十七冶集团有限公司 A cantilever support frame based on BIM technology and its installation method
CN118032180A (en) * 2023-12-28 2024-05-14 北京城建集团有限责任公司 A monitoring and early warning system for steel cantilever frame

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112942778A (en) * 2021-03-23 2021-06-11 中铁二十局集团第六工程有限公司 Overhanging type double-row scaffold and construction method thereof
CN113152871A (en) * 2021-04-18 2021-07-23 广西建工第一建筑工程集团有限公司 Tool type temporary cantilever steel beam foundation system device and mounting and dismounting use method
CN116464271A (en) * 2023-05-25 2023-07-21 中国十七冶集团有限公司 A cantilever support frame based on BIM technology and its installation method
CN118032180A (en) * 2023-12-28 2024-05-14 北京城建集团有限责任公司 A monitoring and early warning system for steel cantilever frame

Similar Documents

Publication Publication Date Title
CN112064519B (en) Long platform guy cable hanging basket and main beam segment construction method
JP6725559B2 (en) Hanging material replacement device and hanging material replacement method using the same
CN102677890B (en) Chimney building formwork lifting device and construction method
CN108360380B (en) A kind of bridge pier column construction work platform and construction method thereof
CN109555257B (en) Combined supporting and hanging rod type suspended ceiling and construction method
CN205036072U (en) A shaped steel formwork support that encorbelments for high altitude structure of encorbelmenting
CN103147582A (en) Overhead cantilever formwork construction method
CN213173317U (en) A construction device for cantilevered wet joints of T beams
CN112411386A (en) Method for erecting and dismantling continuous beam No. 0 block reinforced concrete-filled steel tube support
CN115538678B (en) Construction method for small side surface platform of large-angle overhanging view platform
CN109083395A (en) A kind of Excitations for Long Span Suspension operating platform and its erection method
CN110439249B (en) A cantilever bearing frame and installation method thereof
CN106284997A (en) The big punching block construction method for lifting whole of reinforced concrete chimney
CN217351253U (en) Coke oven flue bent pipe integral suspension fixing frame
CN114991126B (en) Non-prestress post-inserted composite anchor cable anti-pulling pile construction equipment
CN212336694U (en) Connecting device for embedded steel pipe and scaffold cross rod
CN216474585U (en) A bridge body widening construction device
CN215167862U (en) A non-counterweight hanging basket for parapet
CN212335788U (en) Device for mounting thin-wall box-shaped structural steel bars of bridge tower
CN215212243U (en) Overhanging type double-row scaffold
CN216339062U (en) Auxiliary assembly for mounting bridge diaphragm beam template
CN208934380U (en) A kind of Excitations for Long Span Suspension operating platform
CN220266312U (en) Device for bridge deck wet joint template construction
CN112942778A (en) Overhanging type double-row scaffold and construction method thereof
CN218264949U (en) Concrete cantilever member support system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant