CN211898365U - Pile drilling device for highway engineering - Google Patents
Pile drilling device for highway engineering Download PDFInfo
- Publication number
- CN211898365U CN211898365U CN202020092057.XU CN202020092057U CN211898365U CN 211898365 U CN211898365 U CN 211898365U CN 202020092057 U CN202020092057 U CN 202020092057U CN 211898365 U CN211898365 U CN 211898365U
- Authority
- CN
- China
- Prior art keywords
- pile
- plate
- drilling device
- blocks
- wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000005553 drilling Methods 0.000 title claims abstract description 33
- 238000009434 installation Methods 0.000 abstract description 3
- 238000010586 diagram Methods 0.000 description 3
- 230000003111 delayed effect Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000003780 insertion Methods 0.000 description 2
- 230000037431 insertion Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
The utility model discloses a pile drilling device for highway engineering, which comprises a bottom plate, a fixing plate and a pile driver, wherein connecting seats are symmetrically and fixedly arranged at the top of the bottom plate, the outer walls of the two opposite sides of each connecting seat are hinged with connecting plates, the bottoms of the connecting plates are provided with fixing rods, and the number of the fixing rods is a plurality; and the outer wall of one side of the fixed plate is provided with a lifting mechanism. The utility model provides a pair of bore a device that highway engineering was used, can install the pile driver on the fixed plate, then through rotating carousel gang screw, make the movable plate rise or descend on the connecting rod, make the staff need not hold up, stability when having increased and bored the stake, can not bore askewly when making to bore the stake, thereby work efficiency is improved, and the convenient quick installation of pile driver and dismantlement, thereby work efficiency is improved, insert the dead lever underneath again, make the device fixed, stability when having increased the pile, moreover, the steam generator is simple in structure.
Description
Technical Field
The utility model relates to an engineering construction technical field relates to a bore a device that highway engineering used particularly.
Background
Pile drilling, commonly called as pile driving, is to drill foundation holes by using a machine, piles which are not deep are usually dug manually, the pile drilling is called as pile digging, the time efficiency of pile drilling is high, so most of owners adopt pile drilling, various pile drilling equipment in the market is also numerous, large-sized piles and small-sized piles are available, and the pile drilling equipment can be selected appropriately according to the self requirements of the owners.
At present, the existing pile drilling device is usually manually supported by the pile drilling device and then slowly pressed to the ground to drill a pile, but when the pile drilling device shakes, a worker cannot effectively support the pile drilling device, so that the pile drilling device can be askew when the pile drilling device drills the pile, and then the pile drilling device needs to drill the pile again, so that the work progress is delayed, and the pile drilling efficiency is reduced.
SUMMERY OF THE UTILITY MODEL
In view of the above problems in the prior art, an aspect of the present invention is to provide a pile drilling device for road engineering to solve the above problems.
Technical scheme
In order to achieve the purpose, the utility model provides a pile drilling device for highway engineering, which comprises a bottom plate, a fixing plate and a pile driver, wherein the top of the bottom plate is symmetrically and fixedly provided with connecting seats, the outer walls of two opposite sides of each connecting seat are hinged with connecting plates, the bottom of each connecting plate is provided with a plurality of fixing rods;
the outer wall of one side of the fixed plate is provided with a lifting mechanism, the lifting mechanism comprises a movable plate, and the outer wall of one side of the movable plate is symmetrically provided with clamping grooves;
the outer wall symmetry fixed mounting of pile driver one side has the supporting seat, the outer wall of the relative both sides of supporting seat articulates there is the inserted block, the one end of inserted block peg graft in the draw-in groove, the outer wall of pile driver one side is equipped with the bolt, the pile driver pass through the bolt with movable plate threaded connection.
Preferably, the lifting mechanism further comprises four connecting blocks and four fixing blocks, and the four connecting blocks are fixedly mounted on the outer wall of one side of the moving plate in a pairwise symmetrical mode.
Preferably, the number of the fixed blocks is two, the two fixed blocks are symmetrically and fixedly installed at the middle shaft of the outer wall of one side of the moving plate, and a connecting rod is fixedly installed between the outer walls of two opposite sides of each connecting block.
Preferably, a threaded rod is movably mounted between the outer walls of the two opposite sides of the fixed block, one end of the threaded rod penetrates through and extends to one of the top of the fixed block, a rotary table is fixedly mounted on the top of the fixed block, and a movable plate is movably mounted on the outer walls of the connecting rod and the threaded rod.
Preferably, the universal wheels are fixedly mounted at the bottom of the bottom plate in pairwise symmetry.
Preferably, one end of the pile driver is provided with a drill rod, the top of the base plate is provided with a through hole, and one end of the drill rod penetrates through and extends to the bottom of the through hole.
Advantageous effects
Compared with the prior art, the utility model provides a pair of bore stake device that highway engineering used possesses following beneficial effect:
1. the utility model discloses a, can install the pile driver on the fixed plate, then through rotating carousel linkage threaded rod, make the movable plate rise or descend on the connecting rod, make the staff need not hold up, increased the stability when boring the stake, can not bore askew when making to bore the stake to work efficiency has been improved.
2. The utility model discloses a, cooperate through inserted block and bolt, make the pile driver convenient quick installation and dismantlement on the movable plate to improve work efficiency, and the connecting plate passes through the connecting seat arc motion, inserts the dead lever beneath, make the device fixed, increased the stability when piling.
3. The utility model discloses a, simple structure, the operation is the first hand easy, low in production cost.
It is to be understood that both the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the disclosure.
This document provides an overview of various implementations or examples of the technology described in this disclosure, and is not a comprehensive disclosure of the full scope or all features of the disclosed technology.
Drawings
FIG. 1 is a schematic front view of the present invention;
FIG. 2 is a schematic diagram of the fixing plate structure of the present invention;
FIG. 3 is a schematic view of the bottom plate structure of the present invention;
FIG. 4 is a schematic diagram of the structure of the connection plate of the present invention;
fig. 5 is a schematic diagram of the structure of the movable plate of the present invention.
The main reference numbers:
1. a base plate; 2. a fixing plate; 3. a pile driver; 4. a universal wheel; 101. a connecting seat; 102. a connecting plate; 103. fixing the rod; 104. a through hole; 201. connecting blocks; 202. a connecting rod; 203. a threaded rod; 204. moving the plate; 205. a turntable; 206. a fixed block; 207. a bolt; 208. a card slot; 209. inserting a block; 210. a supporting seat; 301. a drill stem; 222. a lifting mechanism.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present disclosure more clear, the technical solutions of the embodiments of the present disclosure will be described below clearly and completely with reference to the accompanying drawings of the embodiments of the present disclosure. It is to be understood that the described embodiments are only a few embodiments of the present disclosure, and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the described embodiments of the disclosure without any inventive step, are within the scope of protection of the disclosure.
Unless otherwise defined, technical or scientific terms used herein shall have the ordinary meaning as understood by one of ordinary skill in the art to which this disclosure belongs. The use of the word "comprising" or "comprises", and the like, in this disclosure is intended to mean that the elements or items listed before that word, include the elements or items listed after that word, and their equivalents, without excluding other elements or items. The terms "connected" or "coupled" and the like are not restricted to physical or mechanical connections, but may also include electrical connections, whether direct or indirect. "upper", "lower", "left", "right", and the like are used merely to indicate relative positional relationships, and when the absolute position of the object being described is changed, the relative positional relationships may also be changed accordingly.
To maintain the following description of the embodiments of the present disclosure clear and concise, a detailed description of known functions and known components have been omitted from the present disclosure.
Referring to fig. 1-5, a pile drilling device for highway engineering is used for solving the problem that the pile drilling efficiency is reduced because a worker cannot effectively hold the pile drilling device when the existing pile drilling device is used, the pile drilling device is inclined when the pile drilling device shakes, and the pile drilling device needs to be drilled again, so that the working progress is delayed.
The utility model discloses in the further technical scheme that provides:
as shown in fig. 1, connecting seats 101 are symmetrically and fixedly installed at the top of a bottom plate 1, connecting plates 102 are hinged to the outer walls of two opposite sides of the connecting seats 101, fixing rods 103 are arranged at the bottoms of the connecting plates 102, and the number of the fixing rods 103 is several;
as shown in fig. 1, the outer wall of one side of the fixed plate 2 is provided with a lifting mechanism 222, the lifting mechanism 222 includes a moving plate 204, and the outer wall of one side of the moving plate 204 is symmetrically provided with clamping grooves 208;
as shown in fig. 1 and 2, a support base 210 is symmetrically and fixedly mounted on the outer wall of one side of the pile driver 3, the outer walls of two opposite sides of the support base 210 are hinged with an insertion block 209, one end of the insertion block 209 is inserted into the clamping groove 208, a bolt 207 is arranged on the outer wall of one side of the pile driver 3, and the pile driver 3 is in threaded connection with the moving plate 204 through the bolt 207.
As shown in fig. 1, the lifting mechanism 222 further includes four connecting blocks 201 and four fixing blocks 206, and the four connecting blocks 201 are symmetrically and fixedly mounted on the outer wall of one side of the moving plate 204 in pairs.
As shown in fig. 2, the number of the fixed blocks 206 is two, the two fixed blocks 206 are symmetrically and fixedly mounted on the middle axis of the outer wall of one side of the moving plate 204, and the connecting rods 202 are respectively and fixedly mounted between the outer walls of two opposite sides of each two connecting blocks 201.
As shown in fig. 2, a threaded rod 203 is movably mounted between the outer walls of the two opposite sides of the fixed blocks 206, one end of the threaded rod 203 penetrates and extends to the top of one of the fixed blocks 206, a rotating disc 205 is fixedly mounted, and a moving plate 204 is movably mounted on the outer walls of the connecting rod 202 and the threaded rod 203.
As shown in figure 1, universal wheels 4 are fixedly arranged at the bottom of the bottom plate 1 in pairwise symmetry.
As shown in fig. 1, one end of the pile driver 3 is provided with a drill rod 301, the top of the base plate 1 is provided with a through hole 104, and one end of the drill rod 301 penetrates and extends to the bottom of the through hole 104.
Further, in operation, the pile driver 3 can pass through the through hole 104.
When the pile driver 3 needs to be installed on the movable plate 204, the inserting block 209 is inserted into the clamping groove 208 through the support base 210 in an arc-shaped motion mode, then the pile driver 3 is connected with the movable plate 204 through the bolt 207 in a threaded mode, installation is completed, and the reverse step is carried out during disassembly.
When the device during operation, earlier remove the device to the position that needs to bore the stake through universal wheel 4, with connecting plate 102 through connecting seat 101 arc motion, insert the dead lever 103 underground and fix the device, then start pile driver 3, the staff is slowly rotating carousel 205, make threaded rod 203 linkage movable plate 204, let movable plate 204 can reciprocate perpendicularly on connecting rod 202 and slide, thereby pile driver 3 slowly descends, utilize drilling rod 301 to pile to ground, make the staff need not hold up, stability when having increased the stake of boring, it is askew not to bore when making the stake of boring, thereby work efficiency has been improved.
It will be appreciated by those skilled in the art that other similar connections may be used to implement the present invention. Such as welding, bonding, or screwing.
The above embodiments are merely exemplary embodiments of the present invention, which is not intended to limit the present invention, and the scope of the present invention is defined by the appended claims. Various modifications and equivalents may be made by those skilled in the art to the present invention without departing from the spirit and scope of the invention, and such modifications and equivalents should be considered to be within the scope of the invention.
Claims (6)
1. The utility model provides a pile drilling device that highway engineering was used, includes bottom plate (1), fixed plate (2) and pile driver (3), its characterized in that:
the top of the bottom plate (1) is symmetrically and fixedly provided with connecting seats (101), the outer walls of two opposite sides of each connecting seat (101) are hinged with connecting plates (102), the bottom of each connecting plate (102) is provided with a plurality of fixing rods (103);
the outer wall of one side of the fixed plate (2) is provided with a lifting mechanism (222), the lifting mechanism (222) comprises a moving plate (204), and the outer wall of one side of the moving plate (204) is symmetrically provided with clamping grooves (208);
the outer wall of one side of the pile driver (3) is symmetrically and fixedly provided with a supporting seat (210), the outer walls of two opposite sides of the supporting seat (210) are hinged with inserting blocks (209), one ends of the inserting blocks (209) are inserted into the clamping grooves (208), the outer wall of one side of the pile driver (3) is provided with bolts (207), and the pile driver (3) is in threaded connection with the movable plate (204) through the bolts (207).
2. The pile drilling device for the highway engineering according to claim 1, wherein the lifting mechanism (222) further comprises four connecting blocks (201) and four fixing blocks (206), and the four connecting blocks (201) are fixedly mounted on the outer wall of one side of the moving plate (204) in a pairwise symmetry manner.
3. The pile drilling device for the road engineering as claimed in claim 2, wherein the number of the fixed blocks (206) is two, two fixed blocks (206) are symmetrically and fixedly installed at the central axis of the outer wall of one side of the moving plate (204), and a connecting rod (202) is respectively and fixedly installed between the outer walls of two opposite sides of each two connecting blocks (201).
4. The pile drilling device for the road engineering as claimed in claim 3, wherein a threaded rod (203) is movably mounted between the outer walls of the two opposite sides of the fixed block (206), one end of the threaded rod (203) penetrates and extends to the top of one of the fixed blocks (206), a rotating disc (205) is fixedly mounted, and the moving plate (204) is movably mounted on the outer walls of the connecting rod (202) and the threaded rod (203).
5. A pile drilling device for highway engineering according to claim 4, wherein the bottom of the bottom plate (1) is fixedly provided with universal wheels (4) in pairwise symmetry.
6. Pile drilling device for highway engineering according to claim 5, wherein a drill rod (301) is arranged at one end of the pile driver (3), a through hole (104) is formed at the top of the base plate (1), and one end of the drill rod (301) penetrates and extends to the bottom of the through hole (104).
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202020092057.XU CN211898365U (en) | 2020-01-16 | 2020-01-16 | Pile drilling device for highway engineering |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202020092057.XU CN211898365U (en) | 2020-01-16 | 2020-01-16 | Pile drilling device for highway engineering |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN211898365U true CN211898365U (en) | 2020-11-10 |
Family
ID=73304127
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202020092057.XU Expired - Fee Related CN211898365U (en) | 2020-01-16 | 2020-01-16 | Pile drilling device for highway engineering |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN211898365U (en) |
-
2020
- 2020-01-16 CN CN202020092057.XU patent/CN211898365U/en not_active Expired - Fee Related
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN205393612U (en) | Copper pipe punch hole technology isolated plant | |
| CN211898365U (en) | Pile drilling device for highway engineering | |
| CN114508304A (en) | Site drilling equipment for engineering geological investigation | |
| CN221568394U (en) | Drilling device for rock and soil blasting | |
| CN219034628U (en) | Assembled deep ground drill for power transmission and transformation engineering | |
| CN217027117U (en) | Long and narrow type foundation pit supporting structure with multiple miniature piles | |
| CN212317869U (en) | Static hydraulic pile machine additionally provided with drill tower base | |
| CN211889093U (en) | Arch frame connecting plate combined type accurate positioning drilling machine | |
| CN210264506U (en) | Drilling rig for geotechnical engineering investigation | |
| CN209837027U (en) | Foundation construction is with pile equipment | |
| CN215979195U (en) | Support stable highway engineering and use bore a device | |
| CN210597304U (en) | Pile pressing equipment | |
| CN222349668U (en) | Simple positioning and support structure on bored pile casing | |
| CN113323582A (en) | Square percussion drill structure, rotary excavating machine drill bit with same and application | |
| CN208841008U (en) | A kind of drilling device based on industrial machinery | |
| CN212452627U (en) | Simple foundation pit piling device | |
| CN223634645U (en) | Photovoltaic pile foundation construction positioning device | |
| CN222501642U (en) | Frame for land engineering exploration drilling | |
| CN222478635U (en) | Wall grouting drilling construction device | |
| CN105569008A (en) | Rectangular splicing equipment for T-shaped piles and rectangular piles | |
| CN214091741U (en) | Tunnel inner tube canopy support hole construction equipment | |
| CN101555691B (en) | Pile-driver tower | |
| CN219864876U (en) | Building construction drilling appurtenance | |
| CN218029494U (en) | Portable isolated column for drilling | |
| CN116838262B (en) | A multifunctional temporary grounding pile drilling machine |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20201110 |