CN211874505U - A modular tie-barless hydraulic formwork trolley for cast-in-place integrated pipe gallery construction - Google Patents

A modular tie-barless hydraulic formwork trolley for cast-in-place integrated pipe gallery construction Download PDF

Info

Publication number
CN211874505U
CN211874505U CN202020306959.9U CN202020306959U CN211874505U CN 211874505 U CN211874505 U CN 211874505U CN 202020306959 U CN202020306959 U CN 202020306959U CN 211874505 U CN211874505 U CN 211874505U
Authority
CN
China
Prior art keywords
formwork
truss
telescopic device
pipe gallery
cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020306959.9U
Other languages
Chinese (zh)
Inventor
陈沿松
董彬
商东风
纪鹏飞
吴晨飞
郭志龙
苏阳阳
骆成虎
吴为民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Engineering Co
CCCC SHEC Fourth Engineering Co Ltd
Original Assignee
CCCC Second Harbor Engineering Co
CCCC SHEC Fourth Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Engineering Co, CCCC SHEC Fourth Engineering Co Ltd filed Critical CCCC Second Harbor Engineering Co
Priority to CN202020306959.9U priority Critical patent/CN211874505U/en
Application granted granted Critical
Publication of CN211874505U publication Critical patent/CN211874505U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

本实用新型公开了一种现浇综合管廊施工用模块化无拉杆液压模板台车,包括模块化装配而成的支撑系统和模板系统;所述支撑系统为设有导向槽的桁架,所述桁架包括节段式的纵杆、横杆、竖杆和斜杆;所述模板系统包括具有与所述导向槽配合的导向杆的侧模板和设于所述桁架顶部的顶模板;还包括伸缩系统,所述伸缩系统包括用于顶升所述桁架的第一动力伸缩装置,用于推拉所述侧模板的第二动力伸缩装置,设于所述桁架下方的第一支撑伸缩装置,设于所述桁架与侧模板之间的第二支撑伸缩装置,以及用于调整所述桁架与行走系统横向相对位置的第三动力伸缩装置。本实用新型的实施,能够提高模板台车的适应性,提升管廊的施工工效、外观质量和结构防水性。

Figure 202020306959

The utility model discloses a modular tie-bar-less hydraulic formwork trolley used for the construction of a cast-in-place integrated pipe gallery, comprising a support system and a formwork system assembled by modularization; the support system is a truss provided with guide grooves, and the The truss includes segmented longitudinal rods, transverse rods, vertical rods and inclined rods; the formwork system includes a side formwork with guide rods matched with the guide grooves and a top formwork set on the top of the truss; also includes telescopic The telescopic system includes a first power telescopic device for jacking up the truss, a second power telescopic device for pushing and pulling the side formwork, and a first support telescopic device under the truss, located in the A second support telescopic device between the truss and the side formwork, and a third power telescopic device for adjusting the lateral relative position of the truss and the traveling system. The implementation of the utility model can improve the adaptability of the formwork trolley, and improve the construction work efficiency, appearance quality and structural waterproofness of the pipe gallery.

Figure 202020306959

Description

一种现浇综合管廊施工用模块化无拉杆液压模板台车A modular tie-barless hydraulic formwork trolley for cast-in-place integrated pipe gallery construction

技术领域technical field

本实用新型涉及综合管廊结构施工技术领域,尤其涉及一种现浇综合管廊施工用模块化无拉杆液压模板台车。The utility model relates to the technical field of integrated pipe gallery structure construction, in particular to a modular tie-bar-less hydraulic formwork trolley for cast-in-place integrated pipe gallery construction.

背景技术Background technique

从国内已建的地下综合管廊工程来看,综合管廊多以明挖现浇法为主,常规尺寸管廊一般分两次浇筑,第一次浇筑底板及一小部分侧墙,第二次浇筑剩余侧墙和顶板。Judging from the underground comprehensive pipe gallery projects that have been built in China, the comprehensive pipe gallery is mostly cast-in-place method, and the conventional size pipe gallery is generally poured in two times. Pour the remaining side walls and roof a second time.

侧墙顶板施工所用的模板多为木模板或小型钢模板,需要搭设满堂支架并逐块拼装,同样支拆除架及模板也非常麻烦,消耗大量的人工和时间。一般单块模板的尺寸较小,导致模板拼缝较多,影响外观质量。侧墙模板需设置拉杆固定,留下的拉杆眼不仅影响外观质量,还成为管廊结构的潜在渗漏点。Most of the formwork used in the construction of the side wall roof are wooden formwork or small steel formwork, which needs to be erected full of brackets and assembled piece by piece. Likewise, it is very troublesome to dismantle the brackets and formwork, which consumes a lot of labor and time. Generally, the size of a single template is small, which leads to more seams on the template, which affects the appearance quality. The side wall formwork needs to be fixed with tie rods, and the left tie rod eyes not only affect the appearance quality, but also become a potential leakage point of the pipe gallery structure.

借鉴隧道施工工艺,用于管廊施工的液压模板台车应运而生,可利用液压系统实现模板快速安装、落架并行走至下一个施工节段,模板一般为大块钢模板且拉杆较少,可大幅提高管廊施工工效并提升管廊外观质量。Drawing on the tunnel construction technology, the hydraulic formwork trolley for pipe gallery construction came into being. The hydraulic system can be used to quickly install the formwork, drop the frame and travel to the next construction section. The formwork is generally a large steel formwork with few tie rods. It can greatly improve the construction efficiency of the pipe gallery and improve the appearance quality of the pipe gallery.

虽然模板台车有其自身的优点,但目前采用模板台车施工管廊的项目占比较小,主要是台车一次性投入高且适应性低,遇到管廊节点位置无法通过需要频繁进出基坑,往往需要大型吊车辅助转场,项目结束后则很难再次利用。Although the formwork trolley has its own advantages, the proportion of projects that use formwork trolleys to construct pipe corridors is relatively small at present, mainly because the trolleys have high one-time investment and low adaptability. The pit often requires a large crane to assist in the transition, and it is difficult to reuse it after the project is over.

实用新型内容Utility model content

本实用新型的目的在于:针对现有管廊模板台车存在的不足,提出了一种模块化无拉杆液压模板台车,提升其适用性和改造空间,并进一步提升管廊混凝土外观质量和结构防水性。The purpose of the utility model is: aiming at the shortcomings of the existing pipe gallery formwork trolleys, a modular tie-barless hydraulic formwork trolley is proposed, which improves its applicability and transformation space, and further improves the appearance quality and structure of the pipe gallery concrete. Waterproof.

本实用新型的目的通过下述技术方案来实现:The purpose of the present utility model is achieved through the following technical solutions:

一种现浇综合管廊施工用模块化无拉杆液压模板台车,其特征在于:A modular tie-barless hydraulic formwork trolley for cast-in-place integrated pipe gallery construction, characterized in that:

包括模块化装配而成的支撑系统和模板系统;所述支撑系统为设有导向槽的桁架,所述桁架包括节段式的纵杆、横杆、竖杆和斜杆;所述模板系统包括具有与所述导向槽配合的导向杆的侧模板和设于所述桁架顶部的顶模板;It includes a modularly assembled support system and a formwork system; the support system is a truss with guide grooves, and the truss includes segmented longitudinal rods, transverse rods, vertical rods and inclined rods; the formwork system includes a side formwork with a guide rod matched with the guide groove and a top formwork set on the top of the truss;

还包括伸缩系统,所述伸缩系统包括用于顶升所述桁架的第一动力伸缩装置,用于推拉所述侧模板的第二动力伸缩装置,设于所述桁架下方的第一支撑伸缩装置,设于所述桁架与侧模板之间的第二支撑伸缩装置,以及用于调整所述桁架与行走系统横向相对位置的第三动力伸缩装置。It also includes a telescopic system, which includes a first power telescopic device for jacking up the truss, a second power telescopic device for pushing and pulling the side formwork, and a first support telescopic device under the truss , a second support telescopic device arranged between the truss and the side formwork, and a third power telescopic device for adjusting the lateral relative position of the truss and the traveling system.

在一些实施例中,所述现浇综合管廊施工用模块化无拉杆液压模板台车还包括设于所述桁架下方并由电机驱动或由卷扬机牵引的行走轮,以及用于制动所述行走轮的制动系统。In some embodiments, the modular tie-rod-free hydraulic formwork trolley for the construction of the cast-in-place integrated pipe gallery further includes a traveling wheel arranged under the truss and driven by a motor or pulled by a hoist, and used for braking the Braking system for traveling wheels.

在一些实施例中,所述伸缩系统的动力伸缩装置为液压油缸,支撑伸缩装置为丝杆。In some embodiments, the power telescopic device of the telescopic system is a hydraulic cylinder, and the support telescopic device is a screw rod.

在一些实施例中,所述纵杆、横杆、竖杆和斜杆的节段均为由型钢加工而成的标准化定尺的杆件,所述侧模板和顶模板均由标准化定尺的钢板拼装而成。在至少一个实施例中,所述纵杆、横杆、竖杆和斜杆的节段的两端设有用于连接的法兰板。In some embodiments, the segments of the longitudinal rods, the horizontal rods, the vertical rods and the inclined rods are all standardized and fixed-length rods processed from section steel, and the side formwork and the top formwork are made of standardized fixed-length rods. Assembled from steel plates. In at least one embodiment, both ends of the segments of the longitudinal rods, transverse rods, vertical rods and inclined rods are provided with flange plates for connection.

在一些实施例中,所述导向槽和所述导向杆为嵌套设置的方钢,使得所述导向杆可相对于所述导向槽沿水平横向伸缩。In some embodiments, the guide groove and the guide rod are nested square steels, so that the guide rod can expand and contract horizontally and laterally relative to the guide groove.

在一些实施例中,所述第一支撑伸缩装置和所述第二支撑伸缩装置的最大伸缩调节范围不小于20cm。In some embodiments, the maximum telescopic adjustment range of the first support telescopic device and the second support telescopic device is not less than 20 cm.

在一些实施例中,所述桁架与侧模板、顶模板通过螺栓和/或销轴连接。In some embodiments, the truss is connected with the side formwork and the top formwork by bolts and/or pins.

通过综合采用上述技术方案,能够取得如下有益效果:By comprehensively adopting the above technical solutions, the following beneficial effects can be achieved:

1、侧模板安装到位后,通过调节第二支撑伸缩装置,使侧模板与架体形成受力整体,桁架采用钢度足够大的节段式杆件拼接而成,拼接节点处设置的第二支撑伸缩装置可为侧模板提供支点;通过控制节段数量可为侧模板提供足够多的支点,抵抗来自混凝土的侧向不平衡压力,因此模板上无需设置拉杆,能够有效提升管廊外观质量和结构防水性;1. After the side formwork is installed in place, by adjusting the second support telescopic device, the side formwork and the frame body form a force-bearing whole. The truss is spliced by segmental rods with sufficient rigidity. The support telescopic device can provide a fulcrum for the side formwork; by controlling the number of segments, it can provide enough fulcrum points for the side formwork to resist the lateral unbalanced pressure from the concrete, so there is no need to set tie rods on the formwork, which can effectively improve the appearance quality of the pipe gallery. structural waterproofness;

2、通过模块化装配支撑系统和模板系统,可灵活组合以适应不同管廊结构尺寸,且连接方式简单可靠,可快速完成拆装,具有便于转场倒运和二次改造利用的特点,大幅提高液压模板台车的适用性和利用率。2. Through the modular assembly support system and formwork system, it can be flexibly combined to adapt to different pipe gallery structure sizes, and the connection method is simple and reliable, and the disassembly and assembly can be completed quickly. Applicability and utilization of hydraulic formwork trolleys.

附图说明Description of drawings

本实用新型将通过例子并参照附图的方式说明,其中:The present invention will be described by way of example and with reference to the accompanying drawings, wherein:

图1是本实用新型中一个示例性实施例中液压模板台车的整体结构示意图;1 is a schematic diagram of the overall structure of a hydraulic formwork trolley in an exemplary embodiment of the present invention;

图2是图1中液压模板台车的第一部分结构示意图;Fig. 2 is the first part structural schematic diagram of the hydraulic formwork trolley in Fig. 1;

图3是图1中液压模板台车的第二部分结构示意图;Fig. 3 is the second part structural representation of the hydraulic formwork trolley in Fig. 1;

图4是图1中液压模板台车的第三部分结构示意图;Fig. 4 is the third part structural schematic diagram of the hydraulic formwork trolley in Fig. 1;

图5是图2中A-A处的剖面示意图。FIG. 5 is a schematic cross-sectional view at A-A in FIG. 2 .

附图标记说明:Description of reference numbers:

1、横杆,2、纵杆,3、斜杆,4、竖杆,5、法兰板,6、第二支撑伸缩装置,7、第一支撑伸缩装置,8、顶模板,9、侧模板,10、导向杆,11、导向槽,12、第二动力伸缩装置,13、第一动力伸缩装置,14、第三动力伸缩装置,15、行走轮。1. Horizontal rod, 2. Vertical rod, 3. Inclined rod, 4. Vertical rod, 5. Flange plate, 6. Second support telescopic device, 7. First support telescopic device, 8. Top formwork, 9. Side Template, 10, guide rod, 11, guide groove, 12, second power telescopic device, 13, first power telescopic device, 14, third power telescopic device, 15, walking wheel.

具体实施方式Detailed ways

下述公开了多种不同的实施所述的主题技术方案的实施方式或实施例。The following discloses a variety of different implementations or examples for implementing the described subject solutions.

本实用新型公开的一种现浇综合管廊施工用模块化无拉杆液压模板台车,包括模块化装配而成的支撑系统和模板系统。支撑系统为设有导向槽的桁架,桁架包括节段式的纵杆、横杆、竖杆和斜杆。模板系统包括具有与导向槽配合的导向杆的侧模板和设于桁架顶部的顶模板。支撑系统和模板系统均采用模块化装配而成,即桁架采用节段式杆件进行可拆卸地组装,侧模板和顶模板可拆卸地装配在桁架上,在遇到非标准尺寸管廊时,只需额外加工少量杆件、模板即可完成台车改造,以用于其他尺寸管廊施工。侧模板则通过导向杆和导向槽的配合实现与桁架的连接,可快速完成侧模板和桁架之间的拆装,方便管廊转场倒运。The utility model discloses a modular tie-bar-less hydraulic formwork trolley for the construction of a cast-in-place integrated pipe gallery, which comprises a support system and a formwork system assembled in a modular fashion. The support system is a truss with guide grooves, and the truss includes segmented longitudinal rods, transverse rods, vertical rods and inclined rods. The formwork system includes side formwork with guide rods matched with guide grooves and a top formwork set on top of the truss. Both the support system and the formwork system are assembled modularly, that is, the truss is detachably assembled with segmental rods, and the side formwork and top formwork are detachably assembled on the truss. When encountering non-standard size pipe gallery, Only a few additional rods and templates are needed to complete the transformation of the trolley, which can be used for the construction of other sizes of pipe gallery. The side formwork is connected to the truss through the cooperation of the guide rod and the guide groove, which can quickly complete the disassembly and assembly between the side formwork and the truss, which is convenient for the transfer of the pipe gallery.

在一些实施例中,现浇综合管廊施工用模块化无拉杆液压模板台车还包括伸缩系统,伸缩系统包括用于顶升桁架的第一动力伸缩装置,用于推拉侧模板的第二动力伸缩装置,设于桁架下方的第一支撑伸缩装置,设于桁架与侧模板之间的第二支撑伸缩装置,以及用于调整桁架与行走系统横向相对位置的第三动力伸缩装置。通过设置第二支撑伸缩装置,能够使侧模板与桁架形成受力整体,进而使得侧模板上可不设置拉杆,能够有效提升管廊外观质量和结构防水性。即使在侧模板均采用大块钢模板时,由于第二支撑伸缩装置能够为侧模板提供支撑力,使得侧模板能够抵抗来自混凝土的侧向不平衡压力。通过设置第一支撑伸缩装置,可以在顶模板、侧模板均安装到位后,将桁架、侧模板和顶模板整体固定。根据伸缩系统的至少一个实施例,伸缩系统的动力伸缩装置为液压油缸,支撑伸缩装置为丝杆。In some embodiments, the modular tie-barless hydraulic formwork trolley for the construction of the cast-in-place integrated pipe gallery further includes a telescopic system, and the telescopic system includes a first power telescopic device for jacking up the truss, and a second power for pushing and pulling the side formwork. The telescopic device includes a first supporting telescopic device arranged under the truss, a second supporting telescopic device arranged between the truss and the side formwork, and a third power telescopic device for adjusting the lateral relative position of the truss and the traveling system. By arranging the second support telescopic device, the side formwork and the truss can form a force-bearing whole, so that the side formwork may not be provided with tie rods, which can effectively improve the appearance quality and structural waterproofness of the pipe gallery. Even when the side formwork adopts a large steel formwork, the side formwork can resist the lateral unbalanced pressure from the concrete because the second support telescopic device can provide a supporting force for the side formwork. By arranging the first support telescopic device, the truss, the side formwork and the top formwork can be integrally fixed after the top formwork and the side formwork are installed in place. According to at least one embodiment of the telescopic system, the power telescopic device of the telescopic system is a hydraulic oil cylinder, and the supporting telescopic device is a screw rod.

在一些实施例中,现浇综合管廊施工用模块化无拉杆液压模板台车还包括设于桁架下方并由电机驱动或由卷扬机牵引的行走轮,以及用于制动行走轮的制动系统,从而可实现液压模板台车方便、快捷地行走至下一个施工节段。In some embodiments, the modular tie-barless hydraulic formwork trolley for the construction of the cast-in-place integrated pipe gallery further includes a traveling wheel arranged under the truss and driven by a motor or pulled by a hoist, and a braking system for braking the traveling wheel , so that the hydraulic formwork trolley can travel to the next construction section conveniently and quickly.

在一些实施例中,纵杆、横杆、竖杆和斜杆的节段均为由型钢加工而成的标准化定尺的杆件,侧模板和顶模板均由标准化定尺的钢板拼装而成。所述“标准化定尺”包括多种尺寸,例如,竖杆加工长度有2m、1.5m、1m、0.5m、0.3m、0.2m。在至少一个实施例中,纵杆、横杆、竖杆和斜杆的节段的两端设有用于连接的法兰板。由于均采用标准化定尺,能够减少模具类型,降低生产成本。而且,通过选择合适尺寸的标准化定尺的杆件、钢板进行组合,能够使支撑系统满足不同管廊结构尺寸的要求,提高液压模板台车的适应性。In some embodiments, the segments of the longitudinal rods, the horizontal rods, the vertical rods and the inclined rods are all standardized and fixed-length rods processed from section steel, and the side formwork and the top formwork are assembled from standardized and fixed-length steel plates. . The "standardized length" includes various sizes, for example, the processing lengths of the vertical bars are 2m, 1.5m, 1m, 0.5m, 0.3m, and 0.2m. In at least one embodiment, both ends of the segments of the longitudinal, transverse, vertical and oblique rods are provided with flange plates for connection. Due to the use of standardized fixed lengths, the types of molds can be reduced and the production cost can be reduced. Moreover, by selecting the appropriate size of standardized fixed-length rods and steel plates for combination, the support system can meet the requirements of different pipe gallery structure sizes, and the adaptability of the hydraulic formwork trolley can be improved.

在一些实施例中,导向槽和导向杆为嵌套设置的方钢,使得导向杆可相对于导向槽沿水平横向伸缩。如此设置,简单可靠,具有成本低、操作方便的优点。In some embodiments, the guide groove and the guide rod are nested square steels, so that the guide rod can expand and contract horizontally and laterally relative to the guide groove. Such an arrangement is simple and reliable, and has the advantages of low cost and convenient operation.

在一些实施例中,第一支撑伸缩装置和第二支撑伸缩装置的最大伸缩调节范围不小于20cm。In some embodiments, the maximum telescopic adjustment range of the first support telescopic device and the second support telescopic device is not less than 20 cm.

在一些实施例中,桁架与侧模板、顶模板通过螺栓和/或销轴连接。In some embodiments, the truss is connected to the side formwork and the top formwork by bolts and/or pins.

现结合附图提供至少一个示例性实施例,附图中提供的示例性实施例的详细描述并非旨在限制要求保护的本实用新型的范围,仅仅表示本实用新型中提供的示例性实施例而已。At least one exemplary embodiment is now provided in conjunction with the accompanying drawings. The detailed description of the exemplary embodiments provided in the accompanying drawings is not intended to limit the scope of the claimed invention, but merely represents the exemplary embodiments provided in the present invention. .

示例性实施例1:Exemplary Embodiment 1:

参见图1~5,一种现浇综合管廊施工用模块化无拉杆液压模板台车,包括支撑系统、模板系统、伸缩系统和行走系统。支撑系统为桁架,包括纵杆2、横杆1、竖杆4和斜杆3,均为由型钢加工而成的标准杆件,在各杆件的两端或节点位置设有用于连接的法兰板5,部分横杆1上设有导向槽11。模板系统包括具有与导向槽11配合的导向杆10的侧模板9和设于桁架顶部的顶模板8。支撑系统和模板系统通过螺栓和/或销轴连接。伸缩系统包括用于顶升桁架的第一动力伸缩装置13,用于推拉侧模板9的第二动力伸缩装置12,用于调整桁架与行走系统横向相对位置的第三动力伸缩装置14,设于桁架下方的第一支撑伸缩装置7,以及设于桁架与侧模板9之间的第二支撑伸缩装置6;其中,动力伸缩装置为液压油缸,支撑伸缩装置为丝杆。行走系统包括设于桁架下方并由电机驱动或由卷扬机牵引的行走轮15,以及用于制动行走轮15的制动系统。Referring to Figures 1 to 5, a modular tie-barless hydraulic formwork trolley for cast-in-place integrated pipe gallery construction includes a support system, a formwork system, a telescopic system and a walking system. The support system is a truss, including longitudinal rods 2, transverse rods 1, vertical rods 4 and inclined rods 3, which are standard rods processed from section steel. The blue plate 5 and part of the cross bar 1 are provided with guide grooves 11 . The formwork system includes a side formwork 9 with guide rods 10 matched with guide grooves 11 and a top formwork 8 provided on the top of the truss. The support system and the formwork system are connected by bolts and/or pins. The telescopic system includes a first power telescopic device 13 for jacking up the truss, a second power telescopic device 12 for pushing and pulling the side formwork 9, and a third power telescopic device 14 for adjusting the lateral relative position of the truss and the walking system. The first supporting telescopic device 7 under the truss, and the second supporting telescopic device 6 between the truss and the side template 9; wherein, the power telescopic device is a hydraulic cylinder, and the supporting telescopic device is a screw rod. The traveling system includes traveling wheels 15 arranged under the truss and driven by a motor or pulled by a hoist, and a braking system for braking the traveling wheels 15 .

液压模板台车采用分节装配,单节车长按6m计,则纵杆2长度为6m,竖杆4和横杆1间距1.5m设置一道,丝杆最大调节范围为30cm。标准的杆件具有多种加工尺寸,如竖杆4加工长度有2m、1.5m、1m、0.5m、0.3m、0.2m。第一动力伸缩装置13、第二动力伸缩装置12、第三动力伸缩装置14分别设有4、4和2个/套,分别控制侧模板9的安装宽度、顶模板8的安装高度以及台车整体的横向位置。The hydraulic formwork trolley is assembled in sections. The length of a single car is 6m, the length of the vertical rod 2 is 6m, the vertical rod 4 and the horizontal rod 1 are set at a distance of 1.5m, and the maximum adjustment range of the lead screw is 30cm. Standard rods have a variety of processing sizes, such as vertical rod 4 processing lengths of 2m, 1.5m, 1m, 0.5m, 0.3m, 0.2m. The first power telescopic device 13, the second power telescopic device 12, and the third power telescopic device 14 are respectively provided with 4, 4 and 2 pieces/set, respectively controlling the installation width of the side formwork 9, the installation height of the top formwork 8 and the trolley Overall lateral position.

采用上述液压模板台车进行综合管廊施工的施工方法,包括如下步骤:The construction method of using the above-mentioned hydraulic formwork trolley for the construction of the integrated pipe gallery includes the following steps:

1)单节台车行走就位,采用台车上的第三动力伸缩装置14进行调整桁架相对于行走轮15的横向位置;1) The single-section trolley is in place, and the third power telescopic device 14 on the trolley is used to adjust the lateral position of the truss relative to the traveling wheel 15;

2)先采用第一动力伸缩装置13顶升顶模板8使其就位,再伸出第二动力伸缩装置12使侧模板9就位,顶模板8和侧模板9就位后再安装第一支撑伸缩装置7和第二支撑伸缩装置6;2) First use the first power telescopic device 13 to lift the top formwork 8 to make it in place, then extend the second power telescopic device 12 to make the side formwork 9 in place, and then install the first formwork after the top formwork 8 and the side formwork 9 are in place. Support telescopic device 7 and second support telescopic device 6;

3)单节台车长度为6m,可配置多节台车,各节台车间采用螺栓连接,完成模板安装后,进行现浇施工;3) The length of a single-section trolley is 6m, and multiple trolleys can be configured. The workshops of each section are connected by bolts. After the installation of the formwork is completed, the cast-in-place construction is carried out;

4)单节台车脱模前先拆除第一支撑伸缩装置7和第二支撑伸缩装置6,再收缩第二动力伸缩装置12使侧模板9脱模,再收缩第一动力伸缩装置13使顶模板8脱模。4) Before demoulding the single-section trolley, first remove the first support telescopic device 7 and the second support telescopic device 6, then shrink the second power expansion device 12 to demould the side formwork 9, and then shrink the first power expansion device 13 to make the top Template 8 is demolded.

本实用新型并不局限于前述的具体实施方式。本实用新型扩展到任何在本说明书中披露的新特征或任何新的组合,以及披露的任一新的方法或过程的步骤或任何新的组合。The present invention is not limited to the foregoing specific embodiments. The present invention extends to any new features or any new combination disclosed in this specification, as well as any new method or process steps or any new combination disclosed.

在本实用新型的描述中,需要说明的是,术语“中心”、“上”、“下”、“左”、“右”、“竖直”、“水平”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,或者是该实用新型产品使用时惯常摆放的方位或位置关系,仅是为了便于描述本实用新型和简化描述,而不是指示或暗示所指的机构或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本实用新型的限制。In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner" and "outer" The orientation or positional relationship indicated by etc. is based on the orientation or positional relationship shown in the accompanying drawings, or the orientation or positional relationship that is usually placed when the utility model product is used, only for the convenience of describing the present utility model and simplifying the description, not It is indicated or implied that the referred mechanism or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of the present invention.

Claims (8)

1.一种现浇综合管廊施工用模块化无拉杆液压模板台车,其特征在于:1. a modular tie-rod-free hydraulic formwork trolley for cast-in-place integrated pipe gallery construction is characterized in that: 包括模块化装配而成的支撑系统和模板系统;所述支撑系统为设有导向槽的桁架,所述桁架包括节段式的纵杆、横杆、竖杆和斜杆;所述模板系统包括具有与所述导向槽配合的导向杆的侧模板和设于所述桁架顶部的顶模板;It includes a modularly assembled support system and a formwork system; the support system is a truss with guide grooves, and the truss includes segmented longitudinal rods, transverse rods, vertical rods and inclined rods; the formwork system includes a side formwork with a guide rod matched with the guide groove and a top formwork set on the top of the truss; 还包括伸缩系统,所述伸缩系统包括用于顶升所述桁架的第一动力伸缩装置,用于推拉所述侧模板的第二动力伸缩装置,设于所述桁架下方的第一支撑伸缩装置,设于所述桁架与侧模板之间的第二支撑伸缩装置,以及用于调整所述桁架与行走系统横向相对位置的第三动力伸缩装置。It also includes a telescopic system, which includes a first power telescopic device for jacking up the truss, a second power telescopic device for pushing and pulling the side formwork, and a first support telescopic device under the truss , a second support telescopic device arranged between the truss and the side formwork, and a third power telescopic device for adjusting the lateral relative position of the truss and the traveling system. 2.根据权利要求1所述的现浇综合管廊施工用模块化无拉杆液压模板台车,其特征在于:还包括设于所述桁架下方并由电机驱动或由卷扬机牵引的行走轮,以及用于制动所述行走轮的制动系统。2. The modular tie-bar-less hydraulic formwork trolley for cast-in-place integrated pipe gallery construction according to claim 1, characterized in that: it further comprises a traveling wheel arranged under the truss and driven by a motor or pulled by a hoist, and A braking system for braking the traveling wheels. 3.根据权利要求1或2所述的现浇综合管廊施工用模块化无拉杆液压模板台车,其特征在于:所述伸缩系统的动力伸缩装置为液压油缸,支撑伸缩装置为丝杆。3. The modular tie-rod-less hydraulic formwork trolley for cast-in-place integrated pipe gallery construction according to claim 1 or 2, characterized in that: the power expansion device of the expansion system is a hydraulic cylinder, and the support expansion device is a screw rod. 4.根据权利要求1或2所述的现浇综合管廊施工用模块化无拉杆液压模板台车,其特征在于:所述纵杆、横杆、竖杆和斜杆的节段均为由型钢加工而成的标准化定尺的杆件,所述侧模板和顶模板均由标准化定尺的钢板拼装而成。4. The modular tie-bar-less hydraulic formwork trolley for cast-in-place integrated pipe gallery construction according to claim 1 or 2, characterized in that: the segments of the longitudinal bar, the horizontal bar, the vertical bar and the oblique bar are made of Standardized fixed-length rods processed from section steel, the side formwork and top formwork are assembled from standardized fixed-length steel plates. 5.根据权利要求4所述的现浇综合管廊施工用模块化无拉杆液压模板台车,其特征在于:所述纵杆、横杆、竖杆和斜杆的节段的两端设有用于连接的法兰板。5. The modular tie-bar-less hydraulic formwork trolley for cast-in-place integrated pipe gallery construction according to claim 4, characterized in that: the two ends of the segments of the longitudinal rod, the transverse rod, the vertical rod and the oblique rod are provided with Flange plate for connection. 6.根据权利要求1或2所述的现浇综合管廊施工用模块化无拉杆液压模板台车,其特征在于:所述导向槽和所述导向杆为嵌套设置的方钢,使得所述导向杆可相对于所述导向槽沿水平横向伸缩。6. The modular tie-bar-less hydraulic formwork trolley for cast-in-place integrated pipe gallery construction according to claim 1 or 2, characterized in that: the guide groove and the guide rod are nested square steels, so that all the The guide rod can be extended and retracted horizontally and laterally relative to the guide groove. 7.根据权利要求1或2所述的现浇综合管廊施工用模块化无拉杆液压模板台车,其特征在于:所述第一支撑伸缩装置和所述第二支撑伸缩装置的最大伸缩调节范围不小于20cm。The modular tie-bar-less hydraulic formwork trolley for cast-in-place integrated pipe gallery construction according to claim 1 or 2, characterized in that: the maximum telescopic adjustment of the first support telescopic device and the second support telescopic device The range is not less than 20cm. 8.根据权利要求1或2所述的现浇综合管廊施工用模块化无拉杆液压模板台车,其特征在于:所述桁架与侧模板、顶模板通过螺栓和/或销轴连接。8. The modular tie-bar-less hydraulic formwork trolley for cast-in-place integrated pipe gallery construction according to claim 1 or 2, wherein the truss is connected with the side formwork and the top formwork by bolts and/or pins.
CN202020306959.9U 2020-03-12 2020-03-12 A modular tie-barless hydraulic formwork trolley for cast-in-place integrated pipe gallery construction Expired - Fee Related CN211874505U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020306959.9U CN211874505U (en) 2020-03-12 2020-03-12 A modular tie-barless hydraulic formwork trolley for cast-in-place integrated pipe gallery construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020306959.9U CN211874505U (en) 2020-03-12 2020-03-12 A modular tie-barless hydraulic formwork trolley for cast-in-place integrated pipe gallery construction

Publications (1)

Publication Number Publication Date
CN211874505U true CN211874505U (en) 2020-11-06

Family

ID=73258895

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020306959.9U Expired - Fee Related CN211874505U (en) 2020-03-12 2020-03-12 A modular tie-barless hydraulic formwork trolley for cast-in-place integrated pipe gallery construction

Country Status (1)

Country Link
CN (1) CN211874505U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114382516A (en) * 2022-03-03 2022-04-22 中铁五局集团第五工程有限责任公司 Secondary lining platform truck template structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114382516A (en) * 2022-03-03 2022-04-22 中铁五局集团第五工程有限责任公司 Secondary lining platform truck template structure

Similar Documents

Publication Publication Date Title
CN102966121B (en) Integrally movable mould frame for pipe rack cast-in-site construction
CN201982108U (en) Single-track railway tunnel integral type full-hydraulic lining trolley
CN203022024U (en) Integrally-movable formwork for pipe gallery cast-in-situ construction
CN101408019B (en) Low altitude prefabricated case beam internal mold construction method
CN104234723B (en) A kind of open trench tunnel square-section self-propelled mobile falsework chassis
CN204151823U (en) Along building the one-sided cantilever hydraulic template trolley of side wall under covered back-digging structural slab
CN110714785A (en) Pipe gallery top plate construction trolley, trolley set and construction method
CN112681162A (en) Construction method for movable split mounting type light formwork cast-in-situ box culvert
CN107326930A (en) On-site rapid prototyping machine for urban underground comprehensive pipe gallery and its working method
CN106401173A (en) Sliding reverse formwork device and construction method thereof
CN208203298U (en) A kind of big punching block of rail type side wall
CN108005684B (en) Separated steel mould trolley and construction method thereof
CN211874505U (en) A modular tie-barless hydraulic formwork trolley for cast-in-place integrated pipe gallery construction
CN102322138A (en) The modular sliding formwork
CN205400756U (en) Variable section platform truck
CN208121805U (en) Utility tunnel construction equipment
CN110714480A (en) Construction method of pipe gallery
CN207526506U (en) separated steel mould trolley
CN214883863U (en) Template system is pour to utility tunnel
CN209703467U (en) A mobile formwork system for ship lock water delivery corridor
CN212054734U (en) A template that is used for quick lining cutting of city portal tunnel
CN220415352U (en) Integral lifting die carrier for vertical shaft
CN217810535U (en) From climbing formula steel bar locating support
CN218699918U (en) Movable forming die for cast-in-situ comprehensive pipe trench
CN201841594U (en) Internal mold dolly for manufacturing concrete box beam of bridge

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201106