CN211736326U - Fabricated outer wall climbing frame for building construction - Google Patents
Fabricated outer wall climbing frame for building construction Download PDFInfo
- Publication number
- CN211736326U CN211736326U CN202020063396.5U CN202020063396U CN211736326U CN 211736326 U CN211736326 U CN 211736326U CN 202020063396 U CN202020063396 U CN 202020063396U CN 211736326 U CN211736326 U CN 211736326U
- Authority
- CN
- China
- Prior art keywords
- wall
- support
- main frame
- building construction
- guide rail
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 230000009194 climbing Effects 0.000 title claims abstract description 36
- 238000009435 building construction Methods 0.000 title claims description 10
- 238000010276 construction Methods 0.000 claims abstract description 14
- 230000007246 mechanism Effects 0.000 claims abstract description 7
- 229910000831 Steel Inorganic materials 0.000 claims description 20
- 239000010959 steel Substances 0.000 claims description 20
- 238000009434 installation Methods 0.000 abstract description 6
- 238000005507 spraying Methods 0.000 description 7
- 239000007921 spray Substances 0.000 description 4
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 4
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 238000005303 weighing Methods 0.000 description 2
- 229910001335 Galvanized steel Inorganic materials 0.000 description 1
- 230000008901 benefit Effects 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 239000000428 dust Substances 0.000 description 1
- 239000008397 galvanized steel Substances 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000002372 labelling Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Landscapes
- Working Measures On Existing Buildindgs (AREA)
Abstract
The utility model discloses an assembly type outer wall climbing frame for construction, attach wall support group including setting firmly a plurality of rows in the wall body outside, hang in the wall body and choose the main frame that has a plurality of guide rails that climb along vertical extension, each the guide rail that climbs attaches wall support group sliding connection with corresponding, be equipped with a plurality of horizontal truss groups along vertical interval on the main frame, each horizontal truss group includes the horizontal truss who connects gradually along the horizontal direction, each attaches wall support group and is located the upper end and attaches wall support and be connected through electric block with main frame bottom department of correspondence, be constructed anti-falling mechanism between each attaches wall support group and corresponding guide rail that climbs. The utility model has the characteristics of easy operation is convenient, practices thrift installation time to save labour. The utility model is suitable for a technical field of construction.
Description
Technical Field
The utility model belongs to the technical field of construction, specifically speaking relates to an assembled outer wall climbs frame for construction.
Background
With the development of the domestic building industry, domestic high-rise residences and high-rise buildings are continuously emerged, and the traditional construction scaffold gradually embodies the disadvantages in the aspects of saving cost, reducing labor intensity, reducing potential safety hazards and the like. Aiming at high-rise buildings, the reformation of the traditional construction scaffold is imperative. The existing climbing frame is cantilevered outside a wall body, the assembly of the climbing frame is complex, the operation is complex, the installation time is greatly wasted, the strength of the climbing frame cannot be guaranteed, and potential safety hazards are brought to subsequent production operation.
SUMMERY OF THE UTILITY MODEL
The utility model provides an easy operation is convenient, practices thrift installation time to save labour's assembled outer wall climbing frame for construction.
In order to achieve the above object, the utility model adopts the following technical scheme:
the utility model provides an assembly type outer wall climbing frame for construction, attach wall support group including setting firmly a plurality of rows in the wall body outside, cantilever outside the wall body has the main frame that has a plurality of guide rails that climb along vertical extension, each the guide rail that climbs attaches wall support group sliding connection with corresponding, it is equipped with a plurality of horizontal truss groups to attach along vertical interval on the main frame, each horizontal truss group includes the horizontal truss that connects gradually along the horizontal direction, each attaches wall support group and is located the upper end and attaches wall support and be connected through electric block with main frame bottom department of correspondence, it prevents weighing down the mechanism to construct between each attaches wall support group and corresponding guide rail that climbs.
Furthermore, the wall attaching support forming the wall attaching support group is in a symmetrical corbel steel plate form, sliding rods are respectively arranged on one sides, close to each other, of the two corbel steel plates, the two sliding rods are embedded in two sides of the corresponding climbing guide rail, and the climbing guide rail is connected with the two sliding rods in a sliding mode.
Furthermore, each wall-attached support is fixed with the wall body through a plurality of wall-penetrating bolts.
Further, the diameter of the through-wall bolt is 20 mm.
Furthermore, an upper hanging ring is fixedly arranged on the uppermost wall-attached support of the wall-attached support group, a lower hanging ring is fixedly arranged on the lower portion of the main frame, and the electric hoist is respectively hung on the upper hanging ring and the lower hanging ring.
Furthermore, a vertical square steel pipe is arranged between two adjacent horizontal trusses, and the adjacent sides of the two horizontal trusses are connected together through the vertical square steel pipe through a plurality of high-strength bolts.
Further, each horizontal truss has a diagonal brace.
Furthermore, the anti-falling mechanism comprises anti-falling top struts which are respectively fixed on the wall-attached supports, one side of the climbing guide rail, which is close to the wall-attached support, is provided with a support block, and when the main frame falls down, the anti-falling top struts are supported on the support block which falls down.
Furthermore, prevent weighing down the shore including the pin joint in attaching wall support upper end bracing piece, the bracing piece slope is upwards and stretch to the main frame, and the middle part of bracing piece is equipped with the drawknot spring, the other end of drawknot spring sets firmly on attaching the wall support.
The utility model discloses owing to adopted foretell structure, it compares with prior art, and the technical progress who gains lies in: the utility model adopts a main frame assembly structure, namely, each horizontal truss of the horizontal truss group can be prefabricated, the fixing between the horizontal trusses is convenient and stable, the operation is simple and convenient, the installation time is greatly saved, and the labor force is saved; and the main frame and the wall body are connected with the corresponding wall-attached support group on the wall body in a sliding mode through the plurality of climbing guide rails, and the plurality of electric hoists are used for controlling the main frame to ascend or descend, so that the main frame slides more stably, and the main frame is fixed with the wall body more stably after being stopped.
Drawings
The accompanying drawings are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description serve to explain the invention and not to limit the invention.
In the drawings:
fig. 1 is a schematic structural diagram of an embodiment of the present invention;
FIG. 2 is an enlarged view of portion A of FIG. 1;
fig. 3 is a schematic front view of the main frame according to the embodiment of the present invention;
fig. 4 is a schematic view of a connection structure of a horizontal truss according to an embodiment of the present invention;
fig. 5 is a structural plan view of the connection between the wall-attached support and the climbing rail according to the embodiment of the present invention.
Labeling components: 1-wall attached support, 2-wall through bolt, 3-upper safety hook, 4-electric block, 5-chain block, 6-wall, 7-lower safety hook, 8-lower hanging ring, 9-cross brace, 10-upper hanging ring, 11-main frame, 12-climbing guide rail, 13-horizontal truss, 14-vertical square steel pipe, 15-shower pipe, 16-rainproof lighting device, 17-slide bar, 18-high-strength bolt, 19-support block, 20-support bar and 21-tie spring.
Detailed Description
The preferred embodiments of the present invention will be described below with reference to the accompanying drawings. It should be understood that the preferred embodiments described herein are for purposes of illustration and explanation only and are not intended to limit the invention.
The utility model discloses an assembled outer wall climbing frame for construction, as shown in fig. 1-2, attach wall support group and multirow horizontal truss group including main frame 11, multiseriate, attach the outside that wall support group is located wall body 6, each row attaches wall support 1 of wall support group and installs on wall body 6 along vertical direction interval. The specific installation mode of the wall-attached support 1 and the wall body 6 is as follows: each wall-attached support 1 is fixed with a wall body 6 through a plurality of wall-penetrating bolts 2, and the diameter of each wall-penetrating bolt 2 is 20 mm. The main frame 11 is cantilevered outside the wall body 6, a plurality of climbing guide rails 12 are fixedly mounted on one side of the main frame 11 close to the wall body 6 side by side, each climbing guide rail 12 extends along the vertical direction, and each climbing guide rail 12 is connected with each wall-attached support 1 of the corresponding wall-attached support group in a sliding manner. The plurality of horizontal truss groups are assembled on the main frame 11 at intervals in the vertical direction, and each horizontal truss group includes horizontal trusses 13 connected in sequence in the horizontal direction. Each wall-attached support group is positioned at the corresponding position of the uppermost wall-attached support 1 and the bottom of the main frame 11 and is connected through an electric hoist 4, and an anti-falling mechanism is constructed between each wall-attached support group and the corresponding climbing guide rail 12. The utility model discloses the advantage lies in: the utility model adopts the main frame 11 assembly type structure, namely, each horizontal truss 13 of the horizontal truss group can be prefabricated, the fixing between the horizontal trusses 13 is convenient and stable, the operation is simple and convenient, the installation time is greatly saved, and the labor force is saved; and main frame 11 and wall body 6 attach wall support group sliding connection through a plurality of climbing guide rail 12 and the correspondence on the wall body 6, and control by a plurality of electric block 4 and rise or descend, make the slip of main frame 11 more stable on the one hand, on the other hand obtains that main frame 11 is fixed more firm with wall body 6 after stopping.
As a preferred embodiment of the present invention, as shown in fig. 5, the wall-attached support 1 constituting the wall-attached support group is in the form of symmetrical corbel steel plates, slide bars 17 are fixed on one sides of the two corbel steel plates close to each other, the two slide bars 17 are embedded on two sides of the corresponding climbing guide rail 12, and the climbing guide rail 12 is slidably connected with the two slide bars 17. An upper lifting ring 10 is arranged between the two corbel steel plates of the wall attaching support 1, a lower lifting ring 8 is arranged at the lower end of the main frame 11, and the electric hoist 4 is hung on the upper lifting ring 10 of the wall attaching support 1 and the lower lifting ring 8 of the main frame 11 through an upper safety lifting hook 3 on the electric hoist and a lower safety lifting hook 7 on a chain block 5 of the electric hoist. The slide bar 17 is welded on the wall attaching support 1, the climbing guide rail 12 is embedded in the middle of the slide bar 17, and the upper hanging ring 10 is welded on the wall attaching support 1 at the upper end and is welded in a full welding mode.
As a preferred embodiment of the present invention, as shown in fig. 3, the main frame 11 is provided with a plurality of spraying devices and a rainproof lighting device 16, the spraying devices include spraying pipes 15 bound on the main frame 11, the spraying pipes 15 are provided with nozzles, the water inlet of the spraying pipes 15 is connected with a rubber hose, the length of the rubber hose is enough for the main frame 11 to slide on the wall 6 without obstructing the sliding, and the water inlet of the rubber hose is connected with a pressure water pump. The spray pipe 15 is attached to the vertical square steel pipe 14 of the main frame 11 and the horizontal truss 13 through a hoop, the spray pipe 15 is a galvanized steel pipe, and the spray head is a universal oscillating spray head. The rainproof lighting device 16 adopts a rainproof moving head light beam lamp of a model CL-BM350, and the rainproof lighting device 16 is fixed on the outer surface of the main frame 11 through bolts. In the embodiment, the spraying equipment and the rainproof lighting device 16 are arranged on the main frame 11, so that the requirements of dust removal on a construction site, water spraying maintenance on the outer wall of a building, night construction lighting and the like are met, the multifunctional waterproof building is multipurpose, the construction is rapid and convenient, and the construction quality is effectively improved.
As a preferred embodiment of the present invention, as shown in fig. 3 and 4, a vertical square steel tube 14 is provided between two adjacent horizontal trusses 13, the vertical square steel tube 14 extends from the bottom end of the main frame 11 to the top end, and two horizontal trusses 13 of each horizontal truss group close to both sides of the vertical square steel tube 14 are fixedly connected together through a high-strength bolt 18 penetrating through the vertical square steel tube 14. Wherein, the concrete connection mode is as follows: vertical square steel pipe 14 and horizontal truss 13 pass through 10mm bolt fastening, and both ends respectively are equipped with three 18 through holes of bolt that excel in about horizontal truss 13, and the bolt hole diameter is 10.5mm, and horizontal truss 1313 is long 1200mm, wide 80mm, and high 600mm is equipped with the bracing in the middle, and vertical square steel pipe 14 cross sectional area is 80 mm.
As a preferred embodiment of the present invention, as shown in fig. 1, the side of the main frame 11 is connected to the vertical square steel pipe 14 and the climbing rail 12 through bolts by means of the cross braces 9. The purpose of the cross braces 9 is to reinforce the strength of the main frame 11.
As a preferred embodiment of the present invention, as shown in fig. 1 and fig. 2, the anti-falling mechanism includes anti-falling top stays respectively fixed on the respective wall-attached supports 1, a support block 19 is provided on one side of the climbing rail 12 close to the wall-attached support 1, and when the main frame 11 falls, the anti-falling top stays are supported on the support block 19 that falls. The anti-falling top support comprises a support rod 20 pivoted to the upper end of the wall-attached support 1, the support rod 20 inclines upwards and extends to the main frame 11, a drawknot spring 21 is fixedly installed in the middle of the support rod 20, and the other end of the drawknot spring 21 is fixedly installed on the wall-attached support 1. The drawknot spring 21 can ensure that the anti-falling top bracing is in a working state at all times and cannot change along with the movement of the climbing guide rail 12.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described in the foregoing embodiments, or equivalents may be substituted for elements thereof. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the scope of the protection of the claims of the present invention.
Claims (9)
1. The utility model provides a frame is climbed to assembled outer wall for construction which characterized in that: including setting firmly a plurality of rows in the wall body outside attach wall support group, hang outside the wall body and choose the main frame that has a plurality of guide rails that climb along vertical extension, each the guide rail that climbs with corresponding attach wall support group sliding connection, it has a plurality of horizontal truss groups to assemble along vertical interval on the main frame, each horizontal truss group includes the horizontal truss who connects gradually along the horizontal direction, each attaches wall support group and is located the upper end and attaches wall support and be connected through electric block with the main frame bottom department of correspondence, it has anti-falling mechanism to construct between each attaches wall support group and corresponding guide rail that climbs.
2. The fabricated exterior wall climbing frame for building construction according to claim 1, wherein: the wall-attached support forming the wall-attached support group adopts a symmetrical corbel steel plate form, slide bars are respectively arranged on one sides of the two corbel steel plates close to each other, the two slide bars are embedded on two sides of the corresponding climbing guide rail, and the climbing guide rail is connected with the two slide bars in a sliding manner.
3. The fabricated exterior wall climbing frame for building construction according to claim 1, wherein: each wall-attached support is fixed with the wall body through a plurality of wall-penetrating bolts.
4. The fabricated exterior wall climbing frame for building construction according to claim 3, wherein: the diameter of the through-wall bolt is 20 mm.
5. The fabricated exterior wall climbing frame for building construction according to claim 1, wherein: an upper hanging ring is fixedly arranged on the wall-attached support at the uppermost end of the wall-attached support group, a lower hanging ring is fixedly arranged at the lower part of the main frame, and the electric hoist is respectively hung on the upper hanging ring and the lower hanging ring.
6. The fabricated exterior wall climbing frame for building construction according to claim 1, wherein: and a vertical square steel pipe is arranged between the two adjacent horizontal trusses, and the mutually close sides of the two horizontal trusses are connected together through the vertical square steel pipe through a plurality of high-strength bolts.
7. The fabricated exterior wall climbing frame for building construction according to claim 1, wherein: each horizontal truss has a diagonal brace.
8. The fabricated exterior wall climbing frame for building construction according to claim 1, wherein: the anti-falling mechanism comprises anti-falling top struts which are respectively fixed on the wall-attached supports, one side of the climbing guide rail, which is close to the wall-attached support, is provided with a support block, and when the main frame falls down, the anti-falling top struts are supported on the falling support block.
9. The fabricated exterior wall climbing frame for building construction according to claim 8, wherein: the anti-falling top support comprises a support rod which is pivoted to the upper end of the wall-attached support, the support rod inclines upwards and extends to the main frame, a drawknot spring is arranged in the middle of the support rod, and the other end of the drawknot spring is fixedly arranged on the wall-attached support.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202020063396.5U CN211736326U (en) | 2020-01-13 | 2020-01-13 | Fabricated outer wall climbing frame for building construction |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202020063396.5U CN211736326U (en) | 2020-01-13 | 2020-01-13 | Fabricated outer wall climbing frame for building construction |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN211736326U true CN211736326U (en) | 2020-10-23 |
Family
ID=72882003
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202020063396.5U Expired - Fee Related CN211736326U (en) | 2020-01-13 | 2020-01-13 | Fabricated outer wall climbing frame for building construction |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN211736326U (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113605667A (en) * | 2021-09-08 | 2021-11-05 | 东莞市建安集团有限公司 | Climbing frame system for building construction |
| CN115370118A (en) * | 2022-09-02 | 2022-11-22 | 中建一局集团第五建筑有限公司 | Assembly type climbing frame for building and using method thereof |
| CN115450417A (en) * | 2022-10-13 | 2022-12-09 | 中天建设集团有限公司 | Combined type climbing frame supporting structure of high-rise large-spacing staggered balcony building and climbing frame construction method |
| CN118007924A (en) * | 2024-02-19 | 2024-05-10 | 山东历控建设发展有限公司 | Integrated lifting climbing frame and construction process thereof |
-
2020
- 2020-01-13 CN CN202020063396.5U patent/CN211736326U/en not_active Expired - Fee Related
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113605667A (en) * | 2021-09-08 | 2021-11-05 | 东莞市建安集团有限公司 | Climbing frame system for building construction |
| CN113605667B (en) * | 2021-09-08 | 2022-12-02 | 东莞市建安集团有限公司 | Climbing frame system for building construction |
| CN115370118A (en) * | 2022-09-02 | 2022-11-22 | 中建一局集团第五建筑有限公司 | Assembly type climbing frame for building and using method thereof |
| CN115370118B (en) * | 2022-09-02 | 2023-10-27 | 中建一局集团第五建筑有限公司 | Assembled climbing frame for building and application method thereof |
| CN115450417A (en) * | 2022-10-13 | 2022-12-09 | 中天建设集团有限公司 | Combined type climbing frame supporting structure of high-rise large-spacing staggered balcony building and climbing frame construction method |
| CN115450417B (en) * | 2022-10-13 | 2024-03-08 | 中天建设集团有限公司 | Combined climbing frame supporting structure of high-rise large-spacing staggered balcony building and construction method thereof |
| CN118007924A (en) * | 2024-02-19 | 2024-05-10 | 山东历控建设发展有限公司 | Integrated lifting climbing frame and construction process thereof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN100590277C (en) | Overhead bridge type suspension scaffold | |
| CN102864936B (en) | Combination lifting construction method for large-scale high hollow building roof of steel structure | |
| CN202000646U (en) | Self-lifting construction platform integrating vertical transportation device and mould frame | |
| CN215803108U (en) | Attached beam type hanging basket | |
| CN103806645B (en) | Light intelligent hydraulic climbing formwork device with good wind-resistant and fireproof performances | |
| CN105484502A (en) | Combination installation method for steel structure roofing purlins and support bars of industrial factory building | |
| CN108979131B (en) | Integral lifting platform device for high-rise building construction steel formwork and operation frame | |
| CN209494204U (en) | Suspension type steel ladder | |
| CN107090968A (en) | Integrated form attached lifting scaffold and its elevating method | |
| CN206942245U (en) | Prefabricated case beam tie with reinforcing bar construction frame | |
| CN215291322U (en) | Integrally assembled attached scaffold | |
| CN210316599U (en) | A curtain wall annular track for roof frame beams | |
| CN211923476U (en) | Electric hoist lifting system attached to lifting scaffold | |
| CN105776092B (en) | A kind of extended position nacelle device | |
| CN211499713U (en) | All-steel attached lifting scaffold | |
| CN211173007U (en) | Novel tripod of encorbelmenting | |
| CN204081433U (en) | Steel structural roof liner profiled sheet construction Special-purpose hanger basket support | |
| CN210857952U (en) | Novel attached lifting scaffold | |
| CN221029677U (en) | Hanging basket safety bottom-holding platform | |
| CN219585686U (en) | Safe telescopic channel for suspended tower crane driver | |
| CN206158146U (en) | Novel building section of thick bamboo well construction operation platform | |
| CN212926984U (en) | Mobile suspended operating platform | |
| CN211644382U (en) | Tower crane attached stay bar walkway platform system | |
| CN212336763U (en) | Curtain wall installation guide rail device fixed on roof flower frame beam | |
| CN117090408A (en) | Attached lifting protection shed and installation and lifting method thereof |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20201023 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |