CN211713684U - Bridge overhauls platform - Google Patents

Bridge overhauls platform Download PDF

Info

Publication number
CN211713684U
CN211713684U CN202020125770.XU CN202020125770U CN211713684U CN 211713684 U CN211713684 U CN 211713684U CN 202020125770 U CN202020125770 U CN 202020125770U CN 211713684 U CN211713684 U CN 211713684U
Authority
CN
China
Prior art keywords
bridge
frame base
platform
work platform
crossbeam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020125770.XU
Other languages
Chinese (zh)
Inventor
陆中凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Angushun Machinery Technology Wuxi Co ltd
Original Assignee
Angushun Machinery Technology Wuxi Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Angushun Machinery Technology Wuxi Co ltd filed Critical Angushun Machinery Technology Wuxi Co ltd
Priority to CN202020125770.XU priority Critical patent/CN211713684U/en
Application granted granted Critical
Publication of CN211713684U publication Critical patent/CN211713684U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to a bridge overhauls instrument field, discloses bridge overhauls platform, including hanging mechanism and work platform, hang the mechanism and include the frame base, be equipped with the balancing weight on the frame base, the front end and the rear end of frame base all set up the walking dolly, and the walking dolly rolls and sets up on laying the track at the bridge floor, and the track sets up along bridge length direction, frame base top fixed connection crossbeam, and work platform sets up in the one end that the bridge was picked out to the crossbeam, and work platform is L shape structure. In the scheme, a constructor can carry out maintenance operation in an operation area of the working platform, so that the safety is greatly improved, the physical consumption of the constructor is reduced, and the construction efficiency is improved; the suspension mechanism can move along the rail, so that the time for erecting the suspension mechanism is reduced, and the construction efficiency is further improved.

Description

Bridge overhauls platform
Technical Field
The utility model relates to a bridge overhauls instrument field, concretely relates to bridge overhauls platform.
Background
In the bridge maintenance engineering, the existing drain pipe is dismantled, the drain pipe is newly arranged, the landscape lamp belt is dismantled, the anti-throwing net is replaced, and the like, the works need long-time and safe construction outside the bridge by constructors, and the traditional construction mostly adopts the schemes of safety ropes, simple hanging baskets and the like, so that the constructors have high physical strength consumption in the construction process, the safety is low, and the construction efficiency is also influenced.
SUMMERY OF THE UTILITY MODEL
In view of the not enough of background art, the utility model provides a bridge overhauls platform, the problem of solution is among the prior art, and traditional construction scheme is low, consume physical power big to constructor's safety protection, also influences the efficiency of construction.
For solving the technical problem, the utility model provides a following technical scheme:
bridge overhauls platform, including hanging mechanism and work platform, hang the mechanism and include the frame base, be equipped with the balancing weight on the frame base, the front end and the rear end of frame base all set up the walking dolly, the walking dolly rolls and sets up on laying the track at the bridge floor, the track sets up along bridge length direction, frame base top fixed connection crossbeam, work platform sets up in the one end that the bridge was picked out to the crossbeam, work platform is L shape structure, the tip of work platform's vertical section top fixed connection crossbeam, work platform's horizontal segment sets up operation district and rail guard, the vertical support of crossbeam top fixed connection, vertical support top are to pasting tight wire rope, and the both ends of wire rope difference fixed connection crossbeam.
Preferably, the working platform is formed by connecting H steel, channel steel and angle steel.
Preferably, the frame base includes fixed plate and fly leaf, the fly leaf sets up on the fixed plate along crossbeam length direction activity, the balancing weight sets up on the fly leaf, the one end that work platform was kept away from to the fly leaf is equipped with collapsible supporting leg, can drag out the fly leaf to keeping away from work platform one side from this, based on lever principle, has prolonged the arm of force of balancing weight, has increased the moment of balancing weight, consequently can realize the balance with less, lighter balancing weight.
Preferably, the fixed plate is provided with a sliding groove along the length direction of the cross beam, the bottom surface of the movable plate is provided with a sliding strip corresponding to the sliding groove, and the sliding strip is connected in the sliding groove in a sliding manner.
Compared with the prior art, the utility model following beneficial effect has at least:
1) the constructors can carry out maintenance operation in the operation area of the working platform, the safety is greatly improved, the physical consumption of the constructors is reduced, and the construction efficiency is further improved;
2) the suspension mechanism can move along the rail, so that the time for erecting the suspension mechanism is reduced, and the construction efficiency is further improved.
Drawings
The utility model discloses there is following figure:
FIG. 1 is a schematic view of the present invention;
fig. 2 is a side view of the present invention;
fig. 3 is a top view of the present invention;
fig. 4 is a side view of the working platform of the present invention;
fig. 5 is a schematic view of the fixed plate and the movable plate of the present invention;
figure 6 is a schematic view of the foldable support leg of the present invention.
Detailed Description
The present invention will now be described in further detail with reference to the accompanying drawings. These drawings are simplified schematic drawings and illustrate the basic structure of the present invention only in a schematic manner, and thus show only the components related to the present invention.
As shown in fig. 1-6, the bridge maintenance platform comprises a suspension mechanism 1 and a working platform 2, the suspension mechanism 1 comprises a frame base 3, a balancing weight 4 is arranged on the frame base 3, a walking trolley 5 is arranged at the front end and the rear end of the frame base 3, the walking trolley 5 is arranged on a track laid on a bridge floor in a rolling mode, the track is arranged along the length direction of the bridge, a cross beam 6 is fixedly connected to the top of the frame base 3, the working platform 2 is arranged at one end, where the cross beam 6 picks out the bridge, the working platform 2 is of an L-shaped structure, the top end of a vertical section of the working platform 2 is fixedly connected to the end of the cross beam 6, a working area 7 and a protective guard 8 are arranged at the horizontal section of the working platform 2, a vertical support 9 is fixedly connected above the cross beam 6, a tight steel wire rope 10 is abutted to the.
Work platform 2 is connected by H steel, channel-section steel and angle steel and constitutes, and can become the cat ladder structure, and the constructor of being convenient for scrambles from top to bottom.
In addition, the frame base 3 includes a fixed plate 11 and a movable plate 12, the movable plate 12 is movably arranged on the fixed plate 11 along the length direction of the beam 6, the counterweight block 4 is arranged on the movable plate 12, and one end of the movable plate 12, which is far away from the working platform 2, is provided with a foldable supporting leg 13, so that the movable plate 12 can be pulled out to one side, which is far away from the working platform 2, based on the lever principle, the force arm of the counterweight block 4 is prolonged, the moment of the counterweight block 4 is increased, and therefore, the balance can be realized by using fewer.
In addition, the fixed plate 11 is provided with a sliding groove 14 along the length direction of the beam 6, the bottom surface of the movable plate 12 is provided with a sliding strip 15 corresponding to the sliding groove 14, and the sliding strip 15 is slidably connected in the sliding groove 14.
In the scheme, a constructor can carry out maintenance operation in an operation area of the working platform, so that the safety is greatly improved, the physical consumption of the constructor is reduced, and the construction efficiency is improved; the suspension mechanism can move along the rail, so that the time for erecting the suspension mechanism is reduced, and the construction efficiency is further improved.
In light of the above, the present invention is not limited to the above embodiments, and various changes and modifications can be made by the worker without departing from the scope of the present invention. The technical scope of the present invention is not limited to the content of the specification, and must be determined according to the scope of the claims.

Claims (4)

1. Bridge overhauls platform, its characterized in that: including hanging mechanism and work platform, hanging mechanism includes the frame base, is equipped with the balancing weight on the frame base, and the front end and the rear end of frame base all set up the walking dolly, the walking dolly rolls to set up on laying the track of bridge floor, frame base top fixed connection crossbeam, work platform sets up in the one end that the bridge was picked out to the crossbeam, work platform is L shape structure, the tip of work platform's vertical section top fixed connection crossbeam, work platform's horizontal segment sets up operation district and rail guard, the vertical support of crossbeam top fixed connection, vertical support top are to pasting tight wire rope, and the both ends of wire rope difference fixed connection crossbeam.
2. The bridge service platform of claim 1, wherein: the working platform is formed by connecting H steel, channel steel and angle steel.
3. The bridge service platform of claim 1, wherein: the frame base comprises a fixed plate and a movable plate, the movable plate is movably arranged on the fixed plate along the length direction of the beam, the balancing weight is arranged on the movable plate, and one end, away from the working platform, of the movable plate is provided with a foldable supporting leg.
4. The bridge service platform of claim 3, wherein: the fixed plate is provided with a sliding groove along the length direction of the cross beam, the bottom surface of the movable plate is provided with a sliding strip corresponding to the sliding groove, and the sliding strip is connected in the sliding groove in a sliding mode.
CN202020125770.XU 2020-01-19 2020-01-19 Bridge overhauls platform Active CN211713684U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020125770.XU CN211713684U (en) 2020-01-19 2020-01-19 Bridge overhauls platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020125770.XU CN211713684U (en) 2020-01-19 2020-01-19 Bridge overhauls platform

Publications (1)

Publication Number Publication Date
CN211713684U true CN211713684U (en) 2020-10-20

Family

ID=72824561

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020125770.XU Active CN211713684U (en) 2020-01-19 2020-01-19 Bridge overhauls platform

Country Status (1)

Country Link
CN (1) CN211713684U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113215978A (en) * 2021-05-13 2021-08-06 中国化学工程第四建设有限公司 Construction method for laying pipeline along with bridge
CN116949944A (en) * 2023-09-08 2023-10-27 郑州新大方重工科技有限公司 Frame plate machine for bridge deck plate paving construction and construction process thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113215978A (en) * 2021-05-13 2021-08-06 中国化学工程第四建设有限公司 Construction method for laying pipeline along with bridge
CN113215978B (en) * 2021-05-13 2022-05-17 中国化学工程第四建设有限公司 Construction method for laying pipeline along with bridge
CN116949944A (en) * 2023-09-08 2023-10-27 郑州新大方重工科技有限公司 Frame plate machine for bridge deck plate paving construction and construction process thereof

Similar Documents

Publication Publication Date Title
CN202323777U (en) Continuous traveling device for bridge suspension casting hanging basket
CN203904856U (en) Movable construction platform for construction outside bridge guardrail
CN202465099U (en) Single-girder partial hanging gantry crane
CN203007831U (en) Bridge maintenance vehicle
CN219823501U (en) Tower crane lifting hook safety auxiliary structure
CN208586532U (en) A kind of bridge construction Bridge Erector
CN201729606U (en) Movable rope bearing device of tower crane
CN217350385U (en) Adjustable compensating beam hoist reaches bridge deck crane including this hoist
CN110748140A (en) Track beam hanging basket special for stepped curtain wall
CN204778289U (en) Cable support tower construction reinforcing bar festival section hoist
CN208280028U (en) A kind of segment splicing Bridge Erector
CN202429913U (en) Movable crane
CN202705904U (en) Small-radius hydraulic power tyre bridge girder erection machine
CN206487128U (en) A kind of Guiding Support Elevating Scaffold
CN209699495U (en) A kind of prestressed stretch-draw platform
CN207312996U (en) A kind of high aerial rail road lifting gear
CN206142667U (en) Bridge crane's crane span structure
CN201292510Y (en) Weight rolling moving device for suspension bridge main beam by subsection top-pushing method
CN220889310U (en) Exterior wall coating spraying equipment
CN203781684U (en) Front hanging system of erection crane of cable-stayed bridge
CN220952977U (en) Accurate positioning and mounting device for partial cable-stayed bridge cable guide pipe
CN219568619U (en) T roof beam hogging moment stretch-draw support device
CN223104079U (en) A movable sky anchor construction platform device
CN205990197U (en) A kind of balance crane lifting elongated object
CN203639821U (en) Anti-swing hanging basket of principal rafter inspection trolley

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant