CN211689947U - Lifting beam and beam moving integrated support mechanism - Google Patents
Lifting beam and beam moving integrated support mechanism Download PDFInfo
- Publication number
- CN211689947U CN211689947U CN201922399365.7U CN201922399365U CN211689947U CN 211689947 U CN211689947 U CN 211689947U CN 201922399365 U CN201922399365 U CN 201922399365U CN 211689947 U CN211689947 U CN 211689947U
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- main truss
- lifting
- pipe column
- support mechanism
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 71
- 239000010959 steel Substances 0.000 claims abstract description 71
- 238000003860 storage Methods 0.000 claims abstract description 13
- 238000009826 distribution Methods 0.000 claims abstract description 11
- 238000010276 construction Methods 0.000 abstract description 14
- 238000004519 manufacturing process Methods 0.000 description 4
- 238000010586 diagram Methods 0.000 description 3
- 238000009434 installation Methods 0.000 description 3
- 238000000034 method Methods 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 2
- 238000005096 rolling process Methods 0.000 description 2
- 238000003466 welding Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本实用新型提供一种提梁及移梁一体化支架机构,包括梁段提升系统、主桁架、主桁架牵引系统、钢管立柱支架和存梁支架,所述的梁段提升系统与主桁架通过分配梁连接,所述的主桁架两侧均设有钢管立柱支架,所述的主桁架通过主桁架牵引系统与钢管立柱支架连接,所述的存梁支架一端位于钢管立柱支架下方;所述的梁段提升系统下端连接有梁段。本实用新型中梁段提升系统安装在主桁架上,主桁架通过两侧的钢管立柱支架将力作用在钢管立柱基础上,梁段提升到位后,利用主桁架牵引系统将梁段牵引到指定位置。通过主桁架牵引系统移梁增加了移梁的安全性,该机构能够实现提梁及移梁一体化施工。
The utility model provides a beam-lifting and beam-moving integrated support mechanism, which includes a beam section lifting system, a main truss, a main truss traction system, a steel pipe column support and a beam storage support. The beam section lifting system and the main truss pass through the distribution beam connection, both sides of the main truss are provided with steel pipe column brackets, the main truss is connected with the steel pipe column bracket through the main truss traction system, and one end of the beam storage bracket is located below the steel pipe column bracket; the beam section The lower end of the hoisting system is connected with a beam segment. The middle beam section lifting system of the utility model is installed on the main truss, the main truss acts on the steel pipe column foundation through the steel pipe column brackets on both sides, and after the beam section is lifted in place, the main truss traction system is used to pull the beam section to the designated position . The safety of moving the beam is increased by the main truss traction system, and the mechanism can realize the integrated construction of lifting the beam and moving the beam.
Description
技术领域technical field
本实用新型涉及桥梁梁段提升及滑移领域,更具体的说它涉及一种提梁及移梁一体化支架机构。The utility model relates to the field of bridge beam section lifting and sliding, in particular to a beam-lifting and beam-moving integrated support mechanism.
背景技术Background technique
随着我国桥梁建设极速的发展,桥梁上部结构架设受地理位置和地形条件影响较大,在桥梁梁段合龙过程中,如何实现大吨位梁段架设安装已经成为一种迫切需要解决的问题。With the rapid development of bridge construction in my country, the erection of bridge superstructure is greatly affected by geographical location and terrain conditions. In the process of bridge girder section closing, how to achieve the erection and installation of large tonnage girder sections has become an urgent problem to be solved.
以往梁段在提升时,主要采用提梁机等设备进行梁段的提升,提升设备结构复杂,制造成本较高,不易安装拆卸。且常规提梁设备只能小范围的进行梁段的移动调整,无法满足梁段精确控制到位的要求。In the past, when the beam section was lifted, equipment such as a beam lifting machine was mainly used to lift the beam section. The lifting equipment had a complex structure, high manufacturing cost, and was not easy to install and disassemble. In addition, the conventional beam lifting equipment can only adjust the movement of the beam segment in a small range, which cannot meet the requirements of precise control of the beam segment in place.
实用新型内容Utility model content
为了克服现有梁段的提升装置复杂,且成本高、不易拆卸的问题,本实用新型提供一种提梁及移梁一体化支架机构,本实用新型结构稳定、制造成本低、易于安装拆卸。本实用新型提供的一体化支架机构,可以安全稳定的完成梁段的提升及滑移,实现提梁、移梁一体化施工,有效的降低施工风险,保证大吨位梁段的现场施工效率。In order to overcome the problems that the existing beam section lifting device is complex, high cost and difficult to disassemble, the utility model provides an integrated support mechanism for beam lifting and beam shifting, which is stable in structure, low in manufacturing cost and easy to install and disassemble. The integrated support mechanism provided by the utility model can complete the lifting and sliding of the beam section safely and stably, realize the integrated construction of lifting and moving the beam, effectively reduce the construction risk, and ensure the on-site construction efficiency of the large-tonnage beam section.
本实用新型采用的技术方案为:The technical scheme adopted by the utility model is:
提梁及移梁一体化支架机构,包括梁段提升系统、主桁架、主桁架牵引系统、钢管立柱支架和存梁支架,所述的梁段提升系统与主桁架通过分配梁连接,所述的主桁架两侧均设有钢管立柱支架,所述的主桁架通过主桁架牵引系统与钢管立柱支架连接,所述的存梁支架一端位于钢管立柱支架下方;所述的梁段提升系统下端连接有梁段。The beam-lifting and beam-moving integrated support mechanism includes a beam section lifting system, a main truss, a main truss traction system, a steel pipe column bracket and a beam storage bracket. The beam section lifting system is connected with the main truss through the distribution beam, and the main truss Both sides of the truss are provided with steel pipe column brackets, the main truss is connected with the steel pipe column bracket through the main truss traction system, one end of the beam storage bracket is located below the steel pipe column bracket; the lower end of the beam section lifting system is connected with a beam part.
所述的梁段提升系统由四台液压连续千斤顶以及配套的导向架、卷线盘和吊索具组成,所述的液压连续千斤顶设在分配梁上,所述的液压连续千斤顶与导向架连接,导向架与卷线盘连接;所述的吊索具设在液压连续千斤顶下端,且与梁段连接。The beam section lifting system is composed of four hydraulic continuous jacks and supporting guide frames, reels and slings. The hydraulic continuous jacks are arranged on the distribution beam, and the hydraulic continuous jacks are connected with the guide frame. , the guide frame is connected with the reel; the sling is arranged at the lower end of the hydraulic continuous jack and connected with the beam section.
所述的分配梁为四个,均匀分布在主桁架上。There are four distribution beams, which are evenly distributed on the main truss.
所述的主桁架牵引系统包括反力座、空心千斤顶、主桁连接装置和精轧螺纹钢,所述的主桁架牵引系统通过主桁连接装置与主桁架连接,所述的反力座与钢管立柱支架的横向承重梁连接,所述的精轧螺纹钢与主桁连接装置连接,所述的空心千斤顶设在反力座的一端,且与设在反力座另一端的精轧螺纹钢连接。The main truss traction system includes a reaction force seat, a hollow jack, a main truss connection device and a finishing rebar, the main truss traction system is connected to the main truss through the main truss connection device, and the reaction force seat is connected to the steel pipe. The transverse load-bearing beams of the column brackets are connected, the finishing threaded steel is connected with the main girder connecting device, and the hollow jack is arranged at one end of the reaction force seat, and is connected with the finishing rolling threaded steel arranged at the other end of the reaction force seat. .
所述的钢管立柱支架包括混凝土扩大基础、钢管立柱、平联、斜撑、纵向承重梁和横向承重梁,所述的纵向承重梁和横向承重梁垂直设置,纵向承重梁与混凝土扩大基础之间通过钢管立柱连接,钢管立柱横向之间通过平联和斜撑连接。The steel pipe column support includes a concrete expansion foundation, a steel pipe column, a parallel connection, a diagonal bracing, a longitudinal load-bearing beam and a transverse load-bearing beam, and the longitudinal load-bearing beam and the transverse load-bearing beam are vertically arranged, and the longitudinal load-bearing beam and the concrete expansion foundation are between. The steel pipe columns are connected by horizontal joints and diagonal braces.
所述的钢管立柱采用φ630×8mm的钢管,所述的平联采用φ426×6mm的钢管,所述的斜撑采用2Ⅰ25a的工字型钢。The steel pipe uprights are made of φ630×8mm steel pipes, the flat joints are made of φ426×6mm steel pipes, and the diagonal braces are made of 2I25a I-shaped steel.
本实用新型的有益效果是:The beneficial effects of the present utility model are:
本实用新型通过梁段提升系统进行梁段的提升,通过主桁牵引系统带动梁段移动的方式进行梁段的滑移到位,提供了一种提梁、移梁一体化支架机构,适用于大吨位梁段提升,具有结构稳定、制造成本低、易于安装拆卸的优点,通过主桁架牵引系统移梁增加了移梁的安全性,同时该机构能够实现提梁、移梁一体化施工,提供一种提梁、移梁施工方法。The utility model lifts the beam section through the beam section lifting system, and slides the beam section into place by driving the beam section to move through the main truss traction system, thereby providing an integrated support mechanism for lifting the beam and moving the beam, which is suitable for large tonnage. The beam section lifting has the advantages of stable structure, low manufacturing cost, and easy installation and disassembly. The beam shifting through the main truss traction system increases the safety of the beam shifting. At the same time, the mechanism can realize the integrated construction of beam lifting and beam shifting, providing a beam lifting system. , Moving beam construction method.
以下将结合附图进行进一步的说明。Further description will be given below in conjunction with the accompanying drawings.
附图说明Description of drawings
图1是本实用新型的整体示意图。Fig. 1 is the overall schematic diagram of the present invention.
图2是本实用新型的主视图。Figure 2 is a front view of the present invention.
图3是本实用新型的平面布置图。FIG. 3 is a plan layout view of the present utility model.
图4是本实用新型的侧面布置图。Figure 4 is a side layout view of the present invention.
图5是本实用新型的梁段提升系统示意图。FIG. 5 is a schematic diagram of the beam section lifting system of the present invention.
图6是本实用新型的主桁架牵引系统示意图。6 is a schematic diagram of the main truss traction system of the present invention.
图中,附图标记为:1、梁段提升系统;2、主桁架;3、主桁架牵引系统;4、钢管立柱支架;5、存梁支架;6、梁段;7、液压连续千斤顶;8、导向架;9、卷线盘;10、吊索具;11、分配梁;12、反力座;13、空心千斤顶;14、主桁连接装置;15、精轧螺纹钢;16、钢管立柱;17、平联;18、斜撑;19、纵向承重梁;20、横向承重梁;21、混凝土扩大基础。In the figure, the reference signs are: 1, beam section lifting system; 2, main truss; 3, main truss traction system; 4, steel pipe column support; 5, beam storage support; 6, beam section; 7, hydraulic continuous jack; 8. Guide frame; 9. Reel; 10. Sling; 11. Distribution beam; 12. Reaction seat; 13. Hollow jack; 14. Main truss connection device; Column; 17, flat joint; 18, diagonal brace; 19, longitudinal load-bearing beam; 20, transverse load-bearing beam; 21, concrete expansion foundation.
具体实施方式Detailed ways
实施例1:Example 1:
为了克服现有梁段的提升装置复杂,且成本高、不易拆卸的问题,本实用新型提供如图1-6所示的一种提梁及移梁一体化支架机构,本实用新型结构稳定、制造成本低、易于安装拆卸。本实用新型提供的一体化支架机构,可以安全稳定的完成梁段的提升及滑移,实现提梁、移梁一体化施工,有效的降低施工风险,保证大吨位梁段的现场施工效率。In order to overcome the problems that the existing beam section lifting device is complex, high cost and difficult to disassemble, the present invention provides a beam-lifting and beam-moving integrated support mechanism as shown in Figs. Low cost, easy to install and dismantle. The integrated support mechanism provided by the utility model can complete the lifting and sliding of the beam section safely and stably, realize the integrated construction of lifting and moving the beam, effectively reduce the construction risk, and ensure the on-site construction efficiency of the large-tonnage beam section.
一种提梁及移梁一体化支架机构,包括梁段提升系统1、主桁架2、主桁架牵引系统3、钢管立柱支架4和存梁支架5,所述的梁段提升系统1与主桁架2通过分配梁11连接,所述的主桁架2两侧均设有钢管立柱支架4,所述的主桁架2通过主桁架牵引系统3与钢管立柱支架4连接,所述的存梁支架5一端位于钢管立柱支架4下方;所述的梁段提升系统1下端连接有梁段6。A beam-lifting and beam-moving integrated support mechanism includes a beam section lifting system 1, a main truss 2, a main
本实用新型中梁段提升系统1安装在主桁架2上,主桁架2通过两侧的钢管立柱支架4将力作用在钢管立柱基础上,梁段6提升到位后,利用主桁架牵引系统3将梁段6牵引到存梁支架5。通过主桁架牵引系统3移梁增加了移梁的安全性,且实现提梁及移梁一体化施工。The middle beam section lifting system 1 of the present invention is installed on the main truss 2. The main truss 2 acts on the steel pipe column foundation through the steel pipe column brackets 4 on both sides. After the beam section 6 is lifted in place, the main
本实用新型适用于大吨位梁段6提升,具有结构稳定、制造成本低、易于安装拆卸的优点,通过主桁架牵引系统3移动梁段6增加了移梁的安全性,实现提梁、移梁一体化施工。The utility model is suitable for the lifting of large-tonnage beam sections 6, and has the advantages of stable structure, low manufacturing cost, and easy installation and disassembly. The beam section 6 is moved by the main
实施例2:Example 2:
基于实施例1的基础上,本实施例中,所述的梁段提升系统1由四台液压连续千斤顶7以及配套的导向架8、卷线盘9和吊索具10组成,所述的液压连续千斤顶7设在分配梁11上,所述的液压连续千斤顶7与导向架8连接,导向架8与卷线盘9连接;所述的吊索具10设在液压连续千斤顶7下端,且与梁段6连接。On the basis of Embodiment 1, in this embodiment, the beam section lifting system 1 is composed of four hydraulic
所述的分配梁11为四个,均匀分布在主桁架2上。There are four
本实用新型中所述的梁段提升系统1由4台S185多门朗液压连续千斤顶7以及配套的导向架8、卷线盘9和吊索具10组成。实际使用时,4台185t液压千斤顶7及吊索具10对应梁段6上的4个临时吊点,提升钢绞线吊耳与梁段吊耳铰接连接。使梁段6平稳匀速的提升到设计高度。The beam section lifting system 1 described in the present utility model is composed of four S185 Dormon Lang hydraulic
所述的主桁架牵引系统3包括反力座12、空心千斤顶13、主桁连接装置14和精轧螺纹钢15,所述的主桁架牵引系统3通过主桁连接装置14与主桁架2连接,所述的反力座12与钢管立柱支架4的横向承重梁20连接,所述的精轧螺纹钢15与主桁连接装置14连接,所述的空心千斤顶13设在反力座12的一端,且与设在反力座12另一端的精轧螺纹钢15连接。The main
本实用新型提供的主桁架牵引系统3包括作用在横向承重梁20上的反力座12、提供牵引力的空心千斤顶13、主桁连接装置14及精轧螺纹钢15。通过空心千斤顶13牵引精轧螺纹钢15带动主桁架2及梁段6整体水平移动至存梁支架5上。The main
所述的钢管立柱支架4包括混凝土扩大基础21、钢管立柱16、平联17、斜撑18、纵向承重梁19和横向承重梁20,所述的纵向承重梁19和横向承重梁20垂直设置,纵向承重梁19与混凝土扩大基础21之间通过钢管立柱16连接,钢管立柱16横向之间通过平联17和斜撑18连接。The steel pipe column support 4 includes a
所述的钢管立柱16采用φ630×8mm的钢管,所述的平联17采用φ426×6mm的钢管,所述的斜撑18采用2Ⅰ25a的工字型钢。The
所述的横向承重梁20和纵向承重梁19均采用2HN900×300的型钢,纵向承重梁19与所述的钢管立柱16之间设置十字撑加劲,横向承重梁20和纵向承重梁19通过焊接的方式连接。The transverse load-
所述的钢管立柱支架4高于存梁支架5。The steel pipe column support 4 is higher than the
本实用新型中,混凝土扩大基础21混凝土标号为C30,布置2层:“HRB335-25”的横纵向钢筋网,其间使用“HRB335-32”的竖向钢筋进行连接。钢管立柱16采用φ630×8mm的钢管,横向之间采用平联17和斜撑18进行连接。平联17采用φ426×6mm的钢管,所述的斜撑18采用2Ⅰ25a的工字型钢。横向承重梁20和纵向承重梁19采用2HN900×300的型钢。纵向承重梁19与所述的钢管立柱16之间设置十字撑加劲,并使用盖板通过焊接的方式连接,纵向承重梁19和横向承重梁20通过焊接的方式连接。In the utility model, the
实际使用时,布置混凝土扩大基础21来保证地基承载力满足要求,在混凝土浇筑前进行钢管立柱16预埋件的预埋,来保证钢管立柱支架4结构的整体稳定性满足要求,钢管立柱16横向之间布置钢管平联17及工字钢斜撑18来确保支架结构的横向稳定。In actual use, the
本实用新型在实际使用时,梁段6到达梁段提升系统1正下方,控制梁段提升系统1将梁段6提升到与设计标高高度一致的位置,通过主桁架牵引系统3将梁段6滑移到存梁支架5上,最终实现梁段的提升及滑移,使用该一体化支架机构有效的提高了梁段就位的施工效率。When the utility model is actually used, the beam section 6 reaches directly below the beam section lifting system 1, the beam section lifting system 1 is controlled to lift the beam section 6 to a position consistent with the design elevation, and the beam section 6 is lifted by the main
通过主桁架牵引系统3移梁增加了移梁的安全性,且实现提梁及移梁一体化施工。The safety of moving the beam is increased through the main
上面结合附图对本实用新型的实施方式做出了详细的说明,但本实用新型并不限于上述实施方式,在本领域普通技术人员所具备的知识范围内,还可以在不脱离本实用新型宗旨的前提下做出各种变化,其都在该技术的保护范围内。本实用新型中未详细描述的装置结构及其方法均为现有技术,本实用新型中将不再进行一一的说明。The embodiments of the present utility model have been described in detail above in conjunction with the accompanying drawings, but the present utility model is not limited to the above-mentioned embodiments. Within the scope of knowledge possessed by those of ordinary skill in the art, the present utility model can also be used without departing from the purpose of the present utility model. Various changes are made under the premise of this technology, which are all within the protection scope of this technology. The device structures and methods that are not described in detail in the present invention are all in the prior art, and will not be described one by one in the present invention.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201922399365.7U CN211689947U (en) | 2019-12-27 | 2019-12-27 | Lifting beam and beam moving integrated support mechanism |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201922399365.7U CN211689947U (en) | 2019-12-27 | 2019-12-27 | Lifting beam and beam moving integrated support mechanism |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN211689947U true CN211689947U (en) | 2020-10-16 |
Family
ID=72795475
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201922399365.7U Active CN211689947U (en) | 2019-12-27 | 2019-12-27 | Lifting beam and beam moving integrated support mechanism |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN211689947U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110965478A (en) * | 2019-12-27 | 2020-04-07 | 中交二公局第二工程有限公司 | A beam-lifting and beam-moving integrated support mechanism |
-
2019
- 2019-12-27 CN CN201922399365.7U patent/CN211689947U/en active Active
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110965478A (en) * | 2019-12-27 | 2020-04-07 | 中交二公局第二工程有限公司 | A beam-lifting and beam-moving integrated support mechanism |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101220580B (en) | Longitudinal multi-point continuous drag construction method for steel truss girders | |
| CN206796168U (en) | The complete erecting device of prefabricated case beam reinforcing bar is used in construction | |
| CN108560927A (en) | A kind of Lift-on/Lift-off System and its application method of reinforced concrete column | |
| CN104310165A (en) | Guide rail type adhesion construction lifter and construction method thereof | |
| CN101736703B (en) | 3000t special bridge girder erection machine for integrally erecting 120m-span double-layer four-line steel beam bridge for highway and railway | |
| CN113136993B (en) | Overhanging outer curtain wall supporting structure of building adjacent to historical landscape protection and construction method thereof | |
| CN109024291A (en) | A kind of integration Bridge Erector and its working method | |
| CN110965478A (en) | A beam-lifting and beam-moving integrated support mechanism | |
| CN205205685U (en) | Span wire pier is function portal device at most | |
| CN112160246B (en) | Method for installing composite beam | |
| CN102225580B (en) | Method for longitudinally moving box girder internal mold | |
| CN211689947U (en) | Lifting beam and beam moving integrated support mechanism | |
| CN100365237C (en) | A self-elevating deformable and detachable overall lifting steel platform system and construction method | |
| CN115961549A (en) | Rear-feeding beam type erection construction method for large-tonnage whole-section steel beam of cable-stayed bridge | |
| CN202881858U (en) | Jig frame used for vertical assembly construction of truss arc bridge | |
| CN116122579B (en) | Hoisting method for bidirectional bending dome bracket | |
| CN107237251B (en) | A kind of access bridge flat stacking sets up the construction method of interim steel bridge | |
| CN115491993B (en) | A method for hoisting and installing small longitudinal and transverse sections of wide steel box beams | |
| CN113585097B (en) | Construction process suitable for mounting bridge girder erection machine | |
| CN107700363B (en) | A bridge tower platform with self-contained lifting system and its construction method | |
| CN212000656U (en) | A construction device for a special-shaped steel bridge across a river | |
| CN115613455A (en) | A prestressed tensioning operation platform for 0# block transverse diaphragm of liftable cantilevered beam | |
| CN116892172A (en) | A method for erecting segments of a multi-span continuous steel truss bridge co-constructed by public rail | |
| CN207619857U (en) | Bailey beam erection crane horizontal sliding device | |
| CN207727618U (en) | Basement contignation template system for pit top-down |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| TR01 | Transfer of patent right | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20250313 Address after: 210000 No. 396 Binjiang Avenue, Jiangbei new area, Nanjing, Jiangsu Patentee after: East China Construction Co., Ltd. of CCCC Second Highway Engineering Co.,Ltd. Country or region after: China Address before: 710119 No.29, No.1 Enterprise Park, West Avenue, high tech Zone, Xi'an City, Shaanxi Province Patentee before: CCCC-SHEC SECOND ENGINEERING Co.,Ltd. Country or region before: China |
