CN211421027U CN201921698890.2U CN201921698890U CN211421027U CN 211421027 U CN211421027 U CN 211421027U CN 201921698890 U CN201921698890 U CN 201921698890U CN 211421027 U CN211421027 U CN 211421027U
Authority
CN
China
Prior art keywords
dam
slope
groove
green
rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921698890.2U
Other languages
Chinese (zh)
Inventor
龙启兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui qiaohai Construction Engineering Co., Ltd
Original Assignee
龙启兵
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 龙启兵 filed Critical 龙启兵
Priority to CN201921698890.2U priority Critical patent/CN211421027U/en
Application granted granted Critical
Publication of CN211421027U publication Critical patent/CN211421027U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Abstract

The utility model discloses an ecological support bracket for hydraulic engineering, including the dam body, the dam body transversely runs through there is the strengthening rib, the dam body is vertical to run through there is the stand, the strengthening rib is with the crisscross welded fastening of stand, the inside packing of dam body has concrete layer, stand upper end fixedly connected with is domatic, domatic vertical equidistance distributes and has the baffle, top-down equidistance is provided with the guide plate between the baffle, the guide plate is the V-arrangement structure. The utility model discloses a be in same level with the quarter butt with the long-pole groove, the quarter butt groove is in same level with the stock, realizes the dislocation of the two alternately, and the fastening bolt hole of three hornblocks corner of rethread finally realizes closely fixing between domatic and the stand, adopts the joint screw thread to think the mode of combination, has both improved connection stability, has quick assembly disassembly's effect to the maintenance in later stage simultaneously.

Description

Ecological support for hydraulic engineering
Technical Field
The utility model relates to a hydraulic engineering technical field especially relates to an ecological support bracket for hydraulic engineering.
Background
Hydraulic engineering is the surface water and the groundwater that are used for controlling and allotment nature, reach the earth's surface water and the groundwater of harmfully having a profit the purpose and the engineering of building, also known as water engineering, water is the essential valuable resource of human production and life, and in order to guarantee the stability of side slope in hydraulic engineering construction process, side slope supporting structure need be built usually, be used for protecting the integrality of side slope, side slope supporting structure is mortar masonry stone structure or concrete structure usually, traditional domatic pouring in the building process adopts integrative casting, the later maintenance cost is high and the degree of difficulty is big, lacks the planning of green planting simultaneously, to considering inadequately in the aspect of from landscape effect and water purification.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving hydraulic engineering and strutting the support and be not convenient for later maintenance, and the poor problem of sight ecotype, and the ecological support for hydraulic engineering who provides.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides an ecological support bracket for hydraulic engineering, includes the dam body, the dam body transversely runs through there is the strengthening rib, the dam body is vertical to run through there is the stand, the strengthening rib is crisscross welded fastening with the stand, the dam body is inside to be filled there is concrete layer, stand upper end fixedly connected with is domatic, domatic vertical equidistance distributes and has the baffle, top-down equidistance is provided with the guide plate between the baffle, the guide plate is the V-arrangement structure, the spout has been seted up to domatic both sides sliding connection slide bar between the spout, the green board of planting of slide bar middle part fixedly connected with, green board top surface equidistance of planting distributes and has green.
Preferably, a motor is fixedly mounted on the top of the slope, a lifting rod is fixedly connected to the center of the top of the green plant plate, the other end of the lifting rod penetrates through the top of the green plant plate and is fixedly connected with the output end of the motor, positioning rods are symmetrically distributed on two sides of the top of the green plant plate, and the positioning rods penetrate through two sides of the top of the slope.
Preferably, the left side and the right side of the top end of the upright post are fixedly connected with short rods, the upper outer wall and the lower outer wall of the top of the upright post are fixedly connected with long rods, and the upright post and the slope are fixedly connected through triangular blocks.
Preferably, three turning play of triangle piece all is provided with the fastening bolt hole, the stand groove has been seted up at the triangle piece middle part, the short pole groove has been seted up to the stand groove outer wall left and right sides, the long pole groove has been seted up to the upper and lower extreme of stand groove outer wall.
Preferably, the upright posts are matched with the upright post grooves, the long rods are matched with the long rod grooves, and the short rods are matched with the short rod grooves.
Preferably, the guide plate is of an inverted V-shaped structure, and a gap is arranged between the green plant plate and the guide plate.
The utility model has the advantages that:
1. the utility model firstly fixes the reinforcing rib and one end of the upright post on the dam body by welding, and simultaneously fixes the reinforcing rib and the upright post by welding, then fills the mixed concrete into the dam body to complete the fixation between the dam body, the reinforcing rib and the upright post, and fixedly connects the slope surface on the upper end of the upright post after the concrete is solidified, wherein, a long rod and a short rod are arranged around the top end of the upright post, the upright post penetrates through the slope surface and is fixed by a triangular block, a long rod groove and a short rod groove are respectively arranged around the triangular block, the short rod and the long rod groove are matched and correspond by matching the long rod and the short rod groove, thereby completing the matching of the triangular block and the upright post, then, the triangular block is rotated by 90 degrees to ensure that the long rod groove and the short rod are at the same level, the short rod groove and the long rod are at the same level, the dislocation intersection of the two is realized, and then passes, finally realize domatic and the stand between closely fixed, adopt the joint screw thread to want the mode of combination, both improved connection stability, have quick assembly disassembly's effect to the maintenance in later stage simultaneously.
2. It plants the board to slide to be provided with green in domatic top, and the motor through the top drives the flexible of lifter, accomplishes the lift of planting the board to green, avoids green vegetation to flood when the water level is too high, sets up the purification absorption that green board of planting acted on the water, has good view effect simultaneously, is provided with the guide plate at domatic top surface, adopts the structure of falling V-arrangement, is convenient for with ponding dispersion refluence, helps protecting domatic.
Drawings
Fig. 1 is a side sectional view of an ecological support bracket for hydraulic engineering according to the present invention;
fig. 2 is a schematic view of a slope structure of an ecological supporting bracket for hydraulic engineering according to the present invention;
fig. 3 is a top view of a slope surface of an ecological supporting bracket for hydraulic engineering according to the present invention;
fig. 4 is a top view of a slope surface of an ecological supporting bracket for hydraulic engineering according to the present invention;
fig. 5 is a cross-sectional view of a column of the ecological supporting bracket for hydraulic engineering of the present invention;
fig. 6 is the utility model provides a three hornblock schematic structure views of ecological support bracket for hydraulic engineering.
In the figure: 1. a dam body; 2. reinforcing ribs; 3. a column; 4. a slope surface; 5. a baffle plate; 6. a baffle; 7. a chute; 8. positioning a rod; 9. a lifting rod; 10. a motor; 11. a green plant plate; 12. A green plant groove; 13. a triangular block; 14. a short bar; 15. a long rod; 16. a column groove; 17. a short rod groove; 18. a long rod groove.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1-6, an ecological supporting bracket for hydraulic engineering comprises a dam body 1, reinforcing ribs 2 transversely penetrate through the dam body 1, upright posts 3 vertically penetrate through the dam body 1, the reinforcing ribs 2 are welded and fixed with the upright posts 3 in a staggered manner, a concrete layer is filled in the dam body 1, a slope 4 is fixedly connected to the upper ends of the upright posts 3, baffles 5 are distributed at equal intervals in the vertical direction of the slope 4, guide plates 6 are arranged at equal intervals from top to bottom between the baffles 5, the guide plates 6 are in a V-shaped structure, sliding grooves 7 are formed in two sides of the slope 4, sliding rods are connected between the sliding grooves 7 in the two sides, green plant plates 11 are fixedly connected to the middle parts of the sliding rods, green plant grooves 12 are distributed at equal intervals on the top surfaces of the green plant plates 11, a motor 10 is fixedly installed on the top parts of the slope 4, a lifting, the board 11 top bilateral symmetry of green planting has locating lever 8, locating lever 8 runs through domatic 4 top both sides, 3 top left and right sides fixedly connected with quarter butt 14 of stand, outer wall fixedly connected with stock 15 about 3 tops of stand, stand 3 and domatic 4 pass through triangle-shaped piece 13 fixed connection, the three turning play of triangle-shaped piece 13 all is provided with the fastening bolt hole, stand groove 16 has been seted up at triangle-shaped piece 13 middle part, short rod groove 17 has been seted up to the 16 outer wall left and right sides in stand groove, long rod groove 18 has been seted up to the lower extreme on the 16 outer walls in stand groove, stand 3 and stand groove 16 phase-match, stock 15 and long rod groove 18 phase-match, short rod 14 and short rod groove 17 phase-match, guide plate 6 is the structure of falling V-arrangement, it is provided with.
The working principle is as follows: before the utility model is built, firstly, the reinforcing rib 2 and one end of the upright post 3 are welded and fixed on the dam body 1, meanwhile, the reinforcing rib 2 and the upright post 3 are welded and fixed, then the mixed concrete is filled into the dam body 1, the fixation between the dam body 1, the reinforcing rib 2 and the upright post 3 is completed, the slope 4 is fixedly connected at the upper end of the upright post 3 after the concrete is solidified, wherein, a long rod 15 and a short rod 14 are arranged around the top end of the upright post 3, the upright post 3 penetrates through the slope 4 and is fixed through a triangular block 13, a long rod groove 18 and a short rod groove 17 are respectively arranged around the triangular block 13, the long rod 15 is matched and corresponds to the long rod groove 18, the short rod 14 is matched and corresponds to the short rod groove 17, thereby, the matching between the triangular block 13 and the upright post 3 is completed, then, the triangular block 13 is rotated by 90 degrees, the long rod groove 18 and the short rod 14 are at the same level, the short rod groove 17 and, the staggered crossing of the slope and the upright post is realized, the slope and the upright post 3 are finally tightly fixed through the fastening bolt holes at the corners of the triangular blocks 13, the connection stability is improved by adopting a clamping and thread combination mode, and meanwhile, the quick assembling and disassembling function is realized for later maintenance; and it plants board 11 to slide to be provided with green in domatic 4's top, and the motor 10 through the top drives the flexible of lifter 9, accomplishes the lift to green board 11 of planting, avoids green vegetation to drown when the water level is too high, sets up the purification absorption that green board 11 of planting acted on the water, has good view effect simultaneously, is provided with guide plate 6 at domatic 4's top surface, adopts the structure of falling V-arrangement, is convenient for with ponding dispersion refluence, helps the protection to domatic 4.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (6)

1. An ecological supporting bracket for hydraulic engineering comprises a dam body (1) and is characterized in that, the dam body (1) is transversely penetrated with a reinforcing rib (2), the dam body (1) is vertically penetrated with a column (3), the reinforcing ribs (2) and the upright posts (3) are welded and fixed in a staggered manner, a concrete layer is filled in the dam body (1), the upper end of the upright post (3) is fixedly connected with a slope surface (4), baffle plates (5) are vertically distributed on the slope surface (4) at equal intervals, guide plates (6) are arranged between the baffles (5) at equal intervals from top to bottom, the guide plate (6) is of a V-shaped structure, sliding grooves (7) are formed in two sides of the slope surface (4), a sliding rod is connected between the sliding grooves (7) in the two sides in a sliding manner, the sliding rod middle part fixedly connected with green board (11) of planting, green board (11) top surface equidistance of planting distributes and has green groove (12) of planting.
2. The ecological supporting bracket for the water conservancy project according to claim 1, wherein a motor (10) is fixedly installed at the top of the slope surface (4), a lifting rod (9) is fixedly connected to the center of the top of the green planting plate (11), the other end of the lifting rod (9) penetrates through the top of the green planting plate (11) and is fixedly connected with the output end of the motor (10), positioning rods (8) are symmetrically distributed on two sides of the top of the green planting plate (11), and the positioning rods (8) penetrate through two sides of the top of the slope surface (4).
3. The ecological supporting bracket for the water conservancy project according to claim 1, characterized in that short rods (14) are fixedly connected to the left and right sides of the top end of the upright post (3), long rods (15) are fixedly connected to the upper and lower outer walls of the top of the upright post (3), and the upright post (3) and the slope (4) are fixedly connected through a triangular block (13).
4. The ecological supporting bracket for the water conservancy project according to claim 3, wherein three corners of the triangular block (13) are provided with fastening bolt holes, a column groove (16) is formed in the middle of the triangular block (13), short rod grooves (17) are formed in the left side and the right side of the outer wall of the column groove (16), and long rod grooves (18) are formed in the upper end and the lower end of the outer wall of the column groove (16).
5. The ecological support bracket for the water conservancy project, as recited in claim 4, characterized in that, the upright column (3) matches with the upright column groove (16), the long rod (15) matches with the long rod groove (18), and the short rod (14) matches with the short rod groove (17).
6. The ecological supporting bracket for the water conservancy project according to claim 1, wherein the guide plate (6) is of an inverted V-shaped structure, and a gap is arranged between the green plant plate (11) and the guide plate (6).
CN201921698890.2U 2019-10-11 2019-10-11 Ecological support for hydraulic engineering Active CN211421027U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921698890.2U CN211421027U (en) 2019-10-11 2019-10-11 Ecological support for hydraulic engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921698890.2U CN211421027U (en) 2019-10-11 2019-10-11 Ecological support for hydraulic engineering

Publications (1)

Publication Number Publication Date
CN211421027U true CN211421027U (en) 2020-09-04

Family

ID=72280939

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921698890.2U Active CN211421027U (en) 2019-10-11 2019-10-11 Ecological support for hydraulic engineering

Country Status (1)

Country Link
CN (1) CN211421027U (en)

Similar Documents

Publication Publication Date Title
CN107090925A (en) Reinforced precast reinforced concrete shear wall, structural system and its construction method
CN208899746U (en) Level sizing prefabricated construction column constructing structure
CN208122027U (en) A kind of prefabricated PC frame core wall structure
CN206256622U (en) Damage with runback bit function can repair assembled coupled column
CN203867067U (en) U-shaped steel concrete compound section beam
CN211421027U (en) Ecological support for hydraulic engineering
CN208918009U (en) A kind of assembled architecture goes along with sb. to guard him the connection structure of exterior wall and steel I-beam
CN107419824A (en) The full precast shear wall structural system of regenerative steel skeleton and construction method
CN107654021A (en) A kind of assembling prefabricated reinforced concrete column and assembled combination frame building system
CN107386327A (en) U-type groove side wall no pulling rod formwork integrated with barricade and the faced wall being made up of the template
CN106948475A (en) A kind of ultra-high performance concrete frame structure assembled architecture and its construction method
CN210368583U (en) Bridge frame with lifting device
CN209907575U (en) Steel structure stabilizing device for building
CN208934394U (en) One kind can turnover type hydraulic climbing formwork wall-attaching equipment
CN207048031U (en) A kind of ultra-high performance concrete frame structure assembled architecture
CN207017484U (en) Reinforced precast reinforced concrete shear wall and structural system
CN206545216U (en) A kind of Reinforced Foundation
CN202248303U (en) Steel-concrete combined assembly integrated girder slab column node structure
CN208039980U (en) A kind of damping unit and the antidetonation Core Walls Structure system suitable for middle highlight lines area
CN108978884A (en) A kind of assembled architecture goes along with sb. to guard him the connection structure of exterior wall and steel I-beam
CN206916935U (en) Assembled grange framework
CN208039530U (en) A kind of and rigidly connected coupling beam node of the steel plate combined shear wall with U-shaped newel post
CN207582730U (en) A kind of connection structure of steel core concrete column and reinforced concrete shear wall
KR101219459B1 (en) The water-storage tank of assembly type and method for constructing thereof
CN213540425U (en) Cross section and pass bridge pier tunnel slip casting supporting construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201104

Address after: Room 1101, Hanlin Shuian, Renmin West Road, SHANGPAI Town, Feixi County, Hefei City, Anhui Province

Patentee after: Anhui qiaohai Construction Engineering Co., Ltd

Address before: No.15 Shikan group, Yongxin village, Baishui Township, Wanzai County, Yichun City, Jiangxi Province

Patentee before: Long Qibing