CN211340808U - Pile foundation pit supporting construction behind preceding wall - Google Patents

Pile foundation pit supporting construction behind preceding wall Download PDF

Info

Publication number
CN211340808U
CN211340808U CN201922198164.0U CN201922198164U CN211340808U CN 211340808 U CN211340808 U CN 211340808U CN 201922198164 U CN201922198164 U CN 201922198164U CN 211340808 U CN211340808 U CN 211340808U
Authority
CN
China
Prior art keywords
pile
foundation pit
wall
row
beams
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201922198164.0U
Other languages
Chinese (zh)
Inventor
刘卫未
周予启
谢志成
雷作鹏
聂艳侠
李玲玲
李四平
张珍林
邵丽萍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Co Create Golden Technique Project Management Beijing Co ltd
China Construction First Group Construction and Development Co Ltd
Original Assignee
Co Create Golden Technique Project Management Beijing Co ltd
China Construction First Group Construction and Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Co Create Golden Technique Project Management Beijing Co ltd, China Construction First Group Construction and Development Co Ltd filed Critical Co Create Golden Technique Project Management Beijing Co ltd
Priority to CN201922198164.0U priority Critical patent/CN211340808U/en
Application granted granted Critical
Publication of CN211340808U publication Critical patent/CN211340808U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

A front wall and rear pile foundation pit supporting structure comprises supporting piles, a diaphragm wall, coupling beams, cover plates and three-axis mixing piles; the diaphragm wall is arranged along the through length of the side wall of the foundation pit; the top of the underground diaphragm wall is provided with a front row of crown beams; the support piles are arranged at intervals along the extending direction of the underground diaphragm wall, and a space is reserved between the support piles and the underground diaphragm wall; the top of the supporting pile is provided with a back row of crown beams; the connecting beam is connected between the rear row of crown beams and the front row of crown beams; the cover plate is arranged in a rectangular lattice surrounded by the rear row of crown beams, the front row of crown beams and the connecting beams; the horizontal section of the triaxial mixing pile is in a grid shape and is arranged in the soil body at the bottom of the foundation pit close to the front side surface of the diaphragm wall; the triaxial stirring stake is consolidated and is 5 ~ 10 times the stake footpath of fender pile, and the length that the triaxial stirring stake lower part passed the weak soil layer in foundation ditch below is not less than 1 times the wall thickness of diaphragm wall. The utility model provides a difference nature, the unreasonable and the complicated technical problem of construction process of two rows of stake atress characteristics around traditional double row stake is not considered.

Description

一种前墙后桩基坑支护结构A front wall and rear pile foundation pit support structure

技术领域technical field

本实用新型属于建筑工程施工领域,特别是一种前墙后桩基坑支护结构。The utility model belongs to the field of building engineering construction, in particular to a front wall and rear pile foundation pit supporting structure.

背景技术Background technique

随着城市用地的愈发紧张,城市建筑纵向延伸的趋势越来越明显,具体表现为向上建造越来越高、向下开挖越来越深,建筑基坑支护难度逐渐增大,且城市建设项目周围往往存在大量商场民房、地下管线、地铁等设施,周围环境复杂,能用于基坑支护结构施工的场地狭小;这种情况下施工锚杆会使有效锚固长度不足,影响锚固效果,施工不当还会造成基坑周边建(构)筑物的损害或违反城市地下空间规划等规定,因此不适合采用;而施工内支撑往往造价高、工期长、施工复杂,还会占用坑内空间,影响主体结构正常施工,因而也较少采用。双排桩支护结构具有侧向刚度大、变形控制强、占用空间小等优点,能够有效约束基坑变形,且双排桩施工本身也不会对周围建(构)筑物产生损害,在基坑支护中得到了越来越多的应用。常规的双排桩是由沿基坑侧壁排列设置的前后两排支护桩以及冠梁、连梁衔接成的刚架式支挡结构。大量研究表明,坑外的主动土压力主要由前排桩分担,而后排桩除了具有分担部分土压力的“支挡”作用外,还兼有对前排桩的“拉锚”作用。目前,传统的双排桩选型往往前后排桩型、桩参数相同,未考虑前后两排桩受力特点的差异性,受力不合理;且对于软土和砂卵地层广泛分布的软弱松散地区,桩间距一般设计较小,必要时还要施工相互咬合的高压旋喷或水泥土搅拌桩来截水挡砂,施工类型多,工艺复杂。As urban land becomes more and more tense, the trend of longitudinal extension of urban buildings is becoming more and more obvious. The concrete manifestations are that the upward construction is higher and higher, the downward excavation is deeper and deeper, the difficulty of building foundation pit support is gradually increasing, and There are often a large number of shopping malls, private houses, underground pipelines, subways and other facilities around urban construction projects. The surrounding environment is complex, and the site that can be used for the construction of foundation pit supporting structures is small. In this case, the construction of anchor rods will cause insufficient anchorage length, affecting the anchorage. In addition, improper construction will also cause damage to buildings (structures) around the foundation pit or violate the urban underground space planning and other regulations, so it is not suitable for use; while the support inside the construction is often expensive, long construction period, complicated construction, and will occupy the pit. space, affecting the normal construction of the main structure, so it is rarely used. The double-row pile supporting structure has the advantages of large lateral stiffness, strong deformation control, and small footprint, which can effectively restrain the deformation of the foundation pit, and the double-row pile construction itself will not cause damage to the surrounding buildings (structures). Foundation pit support has been more and more applications. The conventional double-row pile is a rigid-frame retaining structure formed by the front and rear rows of support piles, crown beams, and coupling beams arranged along the sidewall of the foundation pit. A large number of studies have shown that the active earth pressure outside the pit is mainly shared by the front row piles, and the rear row piles not only have the "support" function of sharing part of the earth pressure, but also have the "anchor" effect on the front row piles. At present, the selection of traditional double-row piles often has the same pile type and pile parameters in the front and rear rows, and does not consider the difference in the mechanical characteristics of the front and rear rows of piles, and the force is unreasonable. In some areas, the pile spacing is generally designed to be small, and if necessary, high-pressure rotary jetting or cement-soil mixing piles that interlock with each other should be constructed to intercept water and sand. There are many construction types and complex processes.

实用新型内容Utility model content

本实用新型的目的是提供一种前墙后桩基坑支护结构,要解决传统的双排桩未考虑前后两排桩受力特点的差异性、受力不合理以及施工工艺复杂的技术问题。The purpose of the utility model is to provide a front wall and rear pile foundation pit support structure, to solve the technical problems that the traditional double-row piles do not consider the difference in the force characteristics of the front and rear two rows of piles, the force is unreasonable, and the construction process is complicated. .

为实现上述目的,本实用新型采用如下技术方案。To achieve the above purpose, the present invention adopts the following technical solutions.

一种前墙后桩基坑支护结构,包括有支护桩、地连墙、连梁、盖板和三轴搅拌桩;所述地连墙沿着基坑的侧壁通长布置,且地连墙的底部伸入基坑以下位置处;所述地连墙的顶部设置有前排冠梁,且前排冠梁的顶面不低于基坑的顶部;所述支护桩有一组,沿着地连墙的延伸方向间隔设置在基坑外侧的土体中,一组支护桩与地连墙之间留有间距;所述支护桩的顶部设置有后排冠梁,且后排冠梁的顶面与前排冠梁的顶面平齐;所述连梁有一组,平行间隔连接在后排冠梁与前排冠梁之间,并且连梁与支护桩对应设置;所述盖板设置在后排冠梁、前排冠梁以及连梁围成的矩形框格中;所述三轴搅拌桩的水平切面呈格栅状,且紧贴着地连墙的前侧面设置基坑底部的土体中;所述三轴搅拌桩的加固宽度为5~10倍的支护桩的桩径,三轴搅拌桩的下部穿过基坑下方软弱土层的长度不小于1倍的地连墙的墙厚。A front wall and rear pile foundation pit supporting structure, comprising supporting piles, ground connecting walls, connecting beams, cover plates and triaxial stirring piles; The bottom of the ground connecting wall extends into the position below the foundation pit; the top of the ground connecting wall is provided with a front row of crown beams, and the top surface of the front row of crown beams is not lower than the top of the foundation pit; the support piles have a set of , arranged in the soil outside the foundation pit at intervals along the extension direction of the ground connecting wall, leaving a space between a group of supporting piles and the ground connecting wall; the top of the supporting piles is provided with a rear row of crown beams, and The top surface of the row crown beams is flush with the top surface of the front row crown beams; the coupling beams have a group, which are connected between the rear row crown beams and the front row crown beams at parallel intervals, and the coupling beams and the supporting piles are arranged correspondingly; The cover plate is arranged in the rectangular frame enclosed by the rear crown beam, the front row crown beam and the connecting beam; the horizontal section of the three-axis stirring pile is in the shape of a grid, and is arranged close to the front side of the ground connecting wall. In the soil at the bottom of the foundation pit; the reinforcement width of the triaxial stirring pile is 5 to 10 times the diameter of the supporting pile, and the length of the lower part of the triaxial stirring pile passing through the soft soil layer below the foundation pit is not less than 1 times. The wall thickness of the ground-to-wall.

优选的,所述地连墙为现浇钢筋混凝土地下连续墙;该地连墙的下端穿过基坑下方的软土层,且伸入基坑底部的深度不小于基坑深度的0.6倍。Preferably, the ground connecting wall is a cast-in-place reinforced concrete underground continuous wall; the lower end of the ground connecting wall passes through the soft soil layer below the foundation pit, and the depth extending into the bottom of the foundation pit is not less than 0.6 times the depth of the foundation pit.

优选的,所述支护桩为灌注桩,相邻支护桩之间的中心距为1~2倍的支护桩的桩径。Preferably, the supporting piles are cast-in-place piles, and the center distance between adjacent supporting piles is 1-2 times the diameter of the supporting piles.

优选的,所述前排冠梁和后排冠梁均为现浇钢筋混凝土梁;所述前排冠梁的宽度比地连墙的墙厚大0~200mm,后排冠梁的宽度比支护桩的桩径大0~200mm;所述前排冠梁的高度为0.6~1倍的地连墙墙厚,后排冠梁的高度为0.6~1倍的支护桩的桩径,且前排冠梁的高度与后排冠梁的高度相适应。Preferably, the front-row crown beams and the rear-row crown beams are both cast-in-place reinforced concrete beams; the width of the front-row crown beams is 0-200 mm larger than the wall thickness of the ground connecting wall, and the width of the rear-row crown beams is larger than that of the support beams. The pile diameter of the guard pile is 0 to 200mm larger; the height of the front row of crown beams is 0.6 to 1 times the thickness of the ground connection wall, and the height of the rear row of crown beams is 0.6 to 1 times the pile diameter of the support piles, and The height of the front row of crown beams is adapted to the height of the rear row of crown beams.

优选的,所述连梁为现浇钢筋混凝土梁,连梁的宽度与后排冠梁的宽度相适应,连梁的高度与后排冠梁的高度相适应。Preferably, the coupling beam is a cast-in-place reinforced concrete beam, the width of the coupling beam is adapted to the width of the rear row of crown beams, and the height of the coupling beam is adapted to the height of the rear row of crown beams.

优选的,所述盖板为现浇钢筋混凝土板,盖板的厚度为0.5~1倍的连梁高度;所述盖板与连梁一体浇筑成型。Preferably, the cover plate is a cast-in-place reinforced concrete plate, and the thickness of the cover plate is 0.5 to 1 times the height of the coupling beam; the cover plate and the coupling beam are integrally cast and formed.

优选的,所述支护桩的中心到地连墙中轴线的距离为3~5倍支护桩的桩径。Preferably, the distance from the center of the supporting pile to the central axis of the ground connection wall is 3 to 5 times the diameter of the supporting pile.

与现有技术相比本实用新型具有以下特点和有益效果。Compared with the prior art, the utility model has the following features and beneficial effects.

1、本实用新型的复合双排基坑支护结构充分利用了双排桩受力特点,采用支护桩和地连墙相结合的整体结构,利用地连墙强度可靠、承压力大的优点来分担大部分土压力,后排桩采用支护桩对地连墙起拉锚作用,能有效控制基坑变形。1. The composite double-row foundation pit supporting structure of the present utility model makes full use of the stress characteristics of the double-row piles, adopts the overall structure combining the supporting piles and the ground connecting wall, and utilizes the advantages of reliable strength and high bearing pressure of the ground connecting wall. To share most of the earth pressure, the rear row piles use supporting piles to act as anchors to the ground connecting wall, which can effectively control the deformation of the foundation pit.

2、本实用新型的复合双排基坑支护结构可充分利用建筑主体的地下结构外墙,大大节省工程造价,且相较于传统双排桩支护结构,地连墙本身具有截水挡砂的功能,无需额外施工截水帷幕,配合基坑内的三轴搅拌桩进行土体加固,特别适用于软土和砂卵地层分布的地区基坑支护。2. The composite double-row foundation pit supporting structure of the present invention can make full use of the outer wall of the underground structure of the main body of the building, which greatly saves the project cost, and compared with the traditional double-row pile supporting structure, the ground connection wall itself has a water blocking barrier. The function of sand does not require additional construction of a water-cutting curtain, and is used for soil reinforcement with the triaxial stirring piles in the foundation pit, which is especially suitable for foundation pit support in areas where soft soil and sand egg strata are distributed.

3、本实用新型的复合双排基坑支护结构通过桩、墙的合理布置能够有效控制基坑变形,坑内不用做支撑,坑外不用打锚杆,施工工艺简单,占用场地小,不妨碍建筑主体结构的施工,还不会对周围建(构)筑物产生破坏,同时能减少传统因施工基坑内撑或锚杆产生的分道养护时间;本实用新型缩短了施工周期,具有良好的经济和社会效益。3. The composite double-row foundation pit support structure of the present utility model can effectively control the deformation of the foundation pit through the reasonable arrangement of the piles and walls, no support is required in the pit, no bolting is required outside the pit, the construction process is simple, the site occupation is small, and it is not hindered. The construction of the main structure of the building will not cause damage to the surrounding buildings (structures), and at the same time, it can reduce the traditional maintenance time due to the inner support of the construction foundation pit or the anchor rod; the utility model shortens the construction period and has good performance. economic and social benefits.

4、本实用新型的三轴搅拌桩加固宽度为5~10倍的支护桩的桩径,并且三轴搅拌桩下部穿过软弱土层不小于1倍的地连墙的墙厚;此处的三轴搅拌桩加固宽度值能够有效的防止地连墙和支护桩倾覆失稳,且使经济效益最佳;同时,三轴搅拌桩穿过软弱土层的深度也在保证整个支护结构的稳定性的同时,使施工简易。4. The reinforcement width of the triaxial stirring pile of the present utility model is 5 to 10 times the diameter of the supporting pile, and the lower part of the triaxial stirring pile passes through the soft soil layer and is not less than 1 times the wall thickness of the ground connection wall; here The reinforcement width of the triaxial stirring pile can effectively prevent the overturning and instability of the ground connecting wall and the supporting pile, and achieve the best economic benefit; at the same time, the depth of the triaxial stirring pile passing through the soft soil layer also ensures the entire supporting structure. At the same time of stability, the construction is easy.

5、本实用新型的支护桩的中心到地连墙中轴线的距离为2~5倍支护桩的桩径,在这个排距之间,本实用新型的支护结构受力最为合理,保证整个结构的刚度达到。5. The distance from the center of the supporting pile of the present utility model to the central axis of the ground connecting wall is 2 to 5 times the diameter of the supporting pile. Between this row distance, the supporting structure of the present utility model is the most reasonable in stress. Ensure that the rigidity of the entire structure is achieved.

附图说明Description of drawings

下面结合附图对本实用新型做进一步详细的说明。The present utility model will be described in further detail below in conjunction with the accompanying drawings.

图1是本实用新型中支护桩与地连墙连接结构的立体结构示意图。FIG. 1 is a three-dimensional schematic diagram of the connection structure between the supporting pile and the ground connecting wall in the present invention.

图2是本实用新型的前墙后桩基坑支护结构支撑在基坑侧壁处的竖向剖面示意图。FIG. 2 is a schematic vertical cross-sectional view of the front wall and rear pile foundation pit supporting structure supported at the side wall of the foundation pit according to the present invention.

图3是本实用新型中支护桩与地连墙连接结构的平面结构示意图。FIG. 3 is a schematic plan view of the connection structure between the supporting pile and the ground connecting wall in the present invention.

图4是本实用新型中三轴搅拌桩设置在地连墙一侧的平面结构示意图。Figure 4 is a schematic plan view of the structure of the three-axis stirring pile arranged on one side of the ground connection wall in the present invention.

附图标记:1-地连墙、2-支护桩、3-前排冠梁、4-后排冠梁、5-连梁、6-盖板、7-三轴搅拌桩、8-基坑。Reference signs: 1-ground connecting wall, 2-supporting pile, 3-front row crown beam, 4-rear row crown beam, 5-connecting beam, 6-cover plate, 7-triaxial stirring pile, 8-base pit.

具体实施方式Detailed ways

本实施例中,基坑8的长为170余米、宽为150余米、开挖深度为16.3米,基坑8开挖范围内主要为杂填土、细粉砂和中粗砂层,坑底附近有一层约9m厚的淤泥质土。基坑支护采用前墙后桩基坑支护结构。In this embodiment, the length of the foundation pit 8 is more than 170 meters, the width is more than 150 meters, and the excavation depth is 16.3 meters. There is a layer of silty soil about 9m thick near the bottom of the pit. The foundation pit support adopts the front wall and rear pile foundation pit support structure.

如图1-4所示,这种前墙后桩基坑支护结构,包括有支护桩2、地连墙1、连梁5、盖板6和三轴搅拌桩7;所述地连墙1沿着基坑8的侧壁通长布置,且地连墙1的底部伸入基坑8以下位置处;所述地连墙1的顶部设置有前排冠梁3,且前排冠梁3的顶面不低于基坑8的顶部;所述支护桩2有一组,沿着地连墙1的延伸方向间隔设置在基坑8外侧的土体中,一组支护桩2与地连墙1之间留有间距;所述支护桩2的顶部设置有后排冠梁4,且后排冠梁4的顶面与前排冠梁3的顶面平齐;所述连梁5有一组,平行间隔连接在后排冠梁4与前排冠梁3之间,并且连梁5与支护桩2对应设置;所述盖板6设置在后排冠梁4、前排冠梁3以及连梁5围成的矩形框格中;所述三轴搅拌桩7的水平切面呈格栅状,且紧贴着地连墙1的前侧面设置基坑8底部的土体中;所述三轴搅拌桩7的加固宽度为5~10倍的支护桩2的桩径,三轴搅拌桩7的下部穿过基坑8下方软弱土层的长度不小于1倍的地连墙1的墙厚。As shown in Figures 1-4, this front wall and rear pile foundation pit supporting structure includes supporting piles 2, ground connecting walls 1, connecting beams 5, cover plates 6 and triaxial stirring piles 7; The wall 1 is arranged along the side wall of the foundation pit 8, and the bottom of the ground connecting wall 1 extends into the position below the foundation pit 8; the top of the ground connecting wall 1 is provided with a front row crown beam 3, and the front row crown The top surface of the beam 3 is not lower than the top of the foundation pit 8; the supporting piles 2 have a group, which are arranged in the soil outside the foundation pit 8 at intervals along the extension direction of the ground connection wall 1, and a group of supporting piles 2 and A space is left between the ground connecting walls 1; the top of the supporting pile 2 is provided with a rear row crown beam 4, and the top surface of the rear row crown beam 4 is flush with the top surface of the front row crown beam 3; There is a set of beams 5, which are connected between the rear row crown beams 4 and the front row crown beams 3 at parallel intervals, and the connecting beams 5 are arranged corresponding to the supporting piles 2; the cover plates 6 are arranged on the rear row crown beams 4 and the front row. In the rectangular frame enclosed by the crown beam 3 and the connecting beam 5; the horizontal section of the three-axis stirring pile 7 is in the shape of a grid, and the front side of the ground connecting wall 1 is arranged in the soil at the bottom of the foundation pit 8; The reinforcement width of the triaxial stirring pile 7 is 5 to 10 times the diameter of the supporting pile 2, and the lower part of the triaxial stirring pile 7 passes through the ground connecting wall whose length is not less than 1 times the length of the soft soil layer below the foundation pit 8. 1 wall thickness.

本实施例中,所述三轴搅拌桩7的桩径为0.85m、同组三轴搅拌桩7间中心距0.6m,三轴搅拌桩7在平面上呈格栅式布置。In this embodiment, the pile diameter of the triaxial stirring piles 7 is 0.85m, the center distance between the triaxial stirring piles 7 in the same group is 0.6m, and the triaxial stirring piles 7 are arranged in a grid pattern on the plane.

本实施例中,所述地连墙1为现浇钢筋混凝土地下连续墙;地连墙1的厚度为不小于1m;该地连墙1的下端穿过基坑8下方的软土层,地连墙1底部深入基坑8底部的深度18.8m。In this embodiment, the ground connecting wall 1 is a cast-in-place reinforced concrete underground continuous wall; the thickness of the ground connecting wall 1 is not less than 1 m; the lower end of the ground connecting wall 1 passes through the soft soil layer under the foundation pit 8, and the ground The depth of the bottom of the connecting wall 1 to the bottom of the foundation pit 8 is 18.8m.

当然在其他实施例中,所述地连墙1底部深入基坑8底部的深度需要根据稳定性计算得到,为不小于基坑8深度的0.6倍。Of course, in other embodiments, the depth of the bottom of the ground connecting wall 1 to the bottom of the foundation pit 8 needs to be calculated according to the stability, and is not less than 0.6 times the depth of the foundation pit 8 .

本实施例中,所述支护桩2为灌注桩,支护桩2的桩径为1m~1.5 m,相邻支护桩2之间的中心距为1.5m,支护桩2的嵌固深度18.8m,支护桩2的桩心与地连墙1轴线之间的距离为4.5m~5m。In this embodiment, the supporting piles 2 are cast-in-place piles, the diameter of the supporting piles 2 is 1m-1.5m, the center distance between adjacent supporting piles 2 is 1.5m, and the supporting piles 2 are embedded The depth is 18.8m, and the distance between the core of the supporting pile 2 and the axis of the ground connecting wall 1 is 4.5m to 5m.

当然在其他实施例中,所述相邻支护桩2之间的中心距为还可以在1~2倍的支护桩2的桩径范围内选择。Of course, in other embodiments, the center distance between the adjacent supporting piles 2 can also be selected within the range of 1-2 times the diameter of the supporting piles 2 .

本实施例中,所述前排冠梁3和后排冠梁4均为现浇钢筋混凝土梁;所述前排冠梁3的宽度比地连墙1的墙厚大0~200mm,后排冠梁4的宽度比支护桩2的桩径大0~200mm;所述前排冠梁3的高度为0.6~1倍的地连墙1墙厚,后排冠梁4的高度为0.6~1倍的支护桩2的桩径,且前排冠梁3的高度与后排冠梁4的高度相适应。In this embodiment, the front-row crown beams 3 and the rear-row crown beams 4 are both cast-in-place reinforced concrete beams; The width of the crown beam 4 is 0-200mm larger than the pile diameter of the supporting pile 2; the height of the front-row crown beam 3 is 0.6-1 times the thickness of the ground connecting wall 1, and the height of the rear-row crown beam 4 is 0.6-1 1 times the pile diameter of the supporting pile 2, and the height of the front row of crown beams 3 is adapted to the height of the rear row of crown beams 4.

本实施例中,所述连梁5为现浇钢筋混凝土梁,连梁5的宽度与后排冠梁4的宽度相适应,连梁5的高度与后排冠梁4的高度相适应;连梁5轴线与支护桩2的桩心至地连墙1的轴线的垂线重合。In the present embodiment, the coupling beam 5 is a cast-in-place reinforced concrete beam, the width of the coupling beam 5 is adapted to the width of the rear row crown beam 4, and the height of the coupling beam 5 is adapted to the height of the rear row crown beam 4; The axis of the beam 5 coincides with the vertical line from the core of the supporting pile 2 to the axis of the ground connecting wall 1 .

本实施例中,所述盖板6为现浇钢筋混凝土板,盖板6的厚度为0.5~1倍的连梁5高度;所述盖板6与连梁5一体浇筑成型。In this embodiment, the cover plate 6 is a cast-in-place reinforced concrete plate, and the thickness of the cover plate 6 is 0.5 to 1 times the height of the coupling beam 5 ; the cover plate 6 and the coupling beam 5 are integrally cast and formed.

本实施例中,所述支护桩2的中心到地连墙1中轴线的距离为3~5倍支护桩2的桩径。In this embodiment, the distance from the center of the supporting pile 2 to the central axis of the ground connecting wall 1 is 3 to 5 times the diameter of the supporting pile 2 .

这种前墙后桩基坑支护结构的施工方法,包括步骤如下。The construction method of the supporting structure of the pile foundation pit behind the front wall includes the following steps.

步骤一,平整场地,根据施工图纸定位放线。Step 1, leveling the site, positioning and laying out lines according to the construction drawings.

步骤二,做成槽工艺试验,以检验施工设备性能和确定施工工艺;为避免槽壁塌孔,在淤泥、淤泥质土、砂层等软弱松散地层成槽困难处保证槽内泥浆面的足够高度,在砂层施工时适当提高泥浆比重与粘度。其中,地连墙1采用跳槽施工。Step 2, make a tank process test to test the performance of the construction equipment and determine the construction process; in order to avoid the collapse of the tank wall, ensure that the mud surface in the tank is sufficient in the difficult places where it is difficult to form a tank in the soft and loose strata such as silt, silt soil and sand layer. When the sand layer is constructed, the specific gravity and viscosity of the mud should be appropriately increased. Among them, the ground connecting wall 1 adopts job-hopping construction.

步骤三,将待浇筑的地连墙1划分为若干组地连墙段。Step 3: Divide the ground connecting wall 1 to be poured into several groups of ground connecting wall sections.

步骤四,进行第一组地连墙段的浇筑。The fourth step is to perform the pouring of the first group of ground connecting wall sections.

步骤五,待第一组地连墙段浇筑完成并达到设计强度的70%以上时,进行第二组地连墙段的施工,并同时进行第一组地连墙段对应区段内支护桩2的施工和三轴搅拌桩7的施工; 第二组地连墙段与第一组地连墙段对应连接。Step 5: When the first group of ground connecting wall sections are poured and reach more than 70% of the design strength, the construction of the second group of ground connecting wall sections is carried out, and at the same time, the support in the corresponding section of the first group of ground connecting wall sections is carried out. The construction of the pile 2 and the construction of the three-axis stirring pile 7;

步骤六,按照步骤五的施工过程施工剩余组地连墙段、支护桩2和三轴搅拌桩7,直至所有的地连墙段、支护桩2和三轴搅拌桩7施工完毕。Step 6, construct the remaining ground connecting wall sections, supporting piles 2 and triaxial stirring piles 7 according to the construction process of step five, until all ground connecting wall sections, supporting piles 2 and triaxial stirring piles 7 are constructed.

步骤七,清除地连墙1和支护桩2顶部的残渣、浮土和积水,凿毛清洗至设计标高。Step 7, remove the residue, floating soil and accumulated water on the top of the ground connecting wall 1 and the supporting pile 2, and clean the chisel to the design elevation.

步骤八,施工后排冠梁4和前排冠梁3。Step 8, construct the crown beam 4 of the rear row and the crown beam 3 of the front row.

步骤九,浇筑连梁5和盖板6混凝土,至此施工完毕。Step 9, pouring the concrete of the connecting beam 5 and the cover plate 6, so far the construction is completed.

本实施例中,进行地连墙段的施工时,每段地连墙段从底到顶连续浇筑且浇筑标高比墙顶设计标高高0.8m;In this embodiment, during the construction of the ground connecting wall section, each ground connecting wall section is continuously poured from the bottom to the top, and the pouring elevation is 0.8m higher than the design elevation of the wall top;

支护桩2采取隔桩施工,并在前一根支护桩2的混凝土灌注24小时后进行相邻支护桩2桩施工;支护桩2的混凝土超灌高度0.8mThe supporting pile 2 shall be constructed by spacing piles, and the adjacent supporting pile 2 shall be constructed 24 hours after the concrete of the previous supporting pile 2 is poured; the concrete of the supporting pile 2 shall be overfilled by 0.8m

三轴搅拌桩7采用套打一孔的成桩方法施工,前一根施工的三轴搅拌桩7与后一根施工的三轴搅拌桩7的搭接时间间隔不大于24小时。The triaxial stirring pile 7 is constructed by the method of punching a hole, and the overlapping time interval of the triaxial stirring pile 7 constructed in the previous construction and the triaxial stirring pile 7 constructed in the latter construction is not more than 24 hours.

本实施例中,若前一根施工的三轴搅拌桩7与后一根施工的三轴搅拌桩7的搭接时间间隔,采取局部补桩或注浆措施。In this embodiment, if the time interval between the three-axis stirring piles 7 constructed before and the three-axis stirring piles 7 constructed by the next one is overlapped, measures of local pile supplementation or grouting are taken.

本实施例中,在三轴搅拌桩7正式施工前,先做工艺性试桩,确定水泥浆水灰比为1.0、水泥掺入比为20%、注浆泵出口压力保持在0.5~0.6MPa、三轴搅拌桩7的提升速度不超过123cm/min、下沉速度不超过80cm/min,三轴搅拌桩7施工工艺采用二搅二喷法。In this embodiment, before the triaxial mixing pile 7 is formally constructed, a technical test pile is firstly performed to determine that the water-cement ratio of the cement slurry is 1.0, the mixing ratio of cement is 20%, and the outlet pressure of the grouting pump is kept at 0.5-0.6MPa . The lifting speed of the three-shaft stirring pile 7 is not more than 123cm/min, and the sinking speed is not more than 80cm/min.

本实施例中,所述地连墙1的嵌固深度与支护桩2的嵌固深度相适应;所述前排冠梁3、后排冠梁4、连梁5以及盖板6的顶部平齐。In this embodiment, the embedding depth of the ground connecting wall 1 is compatible with the embedding depth of the supporting piles 2; flush.

本实施例中,步骤八中后排冠梁4和前排冠梁3施工前清除地连墙1和支护桩2顶部的残渣、浮土和积水,凿毛清洗至设计标高,梁底部坐落在桩、墙顶新鲜混凝土面上。In the present embodiment, in step 8, before the construction of the rear crown beam 4 and the front row crown beam 3, the residue, floating soil and accumulated water on the top of the ground connecting wall 1 and the supporting pile 2 are removed, and the chisel is cleaned to the design elevation, and the bottom of the beam is located On piles, fresh concrete on top of walls.

以上实施例仅用以说明本实用新型的技术方案,而非对本实用新型保护范围的限制,凡在本实用新型的精神和原则之内所做的任何修改、等同替换和改进等,均应包含在本实用新型的保护范围之内。The above embodiments are only used to illustrate the technical solutions of the present invention, rather than limiting the scope of protection of the present invention. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present invention shall include within the scope of protection of the present invention.

Claims (7)

1. The utility model provides a pile foundation pit supporting construction behind preceding wall which characterized in that: comprises a support pile (2), a ground connecting wall (1), a connecting beam (5), a cover plate (6) and a triaxial mixing pile (7); the underground diaphragm wall (1) is arranged along the through length of the side wall of the foundation pit (8), and the bottom of the underground diaphragm wall (1) extends into the position below the foundation pit (8); the top of the underground diaphragm wall (1) is provided with a front row of crown beams (3), and the top surfaces of the front row of crown beams (3) are not lower than the top of the foundation pit (8); the supporting piles (2) are arranged in a group and are arranged in the soil body outside the foundation pit (8) at intervals along the extending direction of the underground diaphragm wall (1), and a space is reserved between the supporting piles (2) and the underground diaphragm wall (1); the top of the supporting pile (2) is provided with a back row of crown beams (4), and the top surfaces of the back row of crown beams (4) are flush with the top surfaces of the front row of crown beams (3); the connecting beams (5) are connected between the rear row of crown beams (4) and the front row of crown beams (3) in parallel at intervals, and the connecting beams (5) are arranged corresponding to the support piles (2); the cover plate (6) is arranged in a rectangular lattice surrounded by the rear row of crown beams (4), the front row of crown beams (3) and the connecting beams (5); the horizontal section of the triaxial mixing pile (7) is in a grid shape, and the horizontal section is tightly attached to the front side surface of the diaphragm wall (1) and arranged in a soil body at the bottom of the foundation pit (8); the reinforcing width of the triaxial mixing pile (7) is 5-10 times of the pile diameter of the support pile (2), and the length of the lower part of the triaxial mixing pile (7) penetrating through a soft soil layer below the foundation pit (8) is not less than 1 time of the wall thickness of the diaphragm wall (1).
2. The front wall rear pile foundation pit supporting structure of claim 1, wherein: the underground continuous wall (1) is a cast-in-place reinforced concrete underground continuous wall; the lower end of the diaphragm wall (1) penetrates through a soft soil layer below the foundation pit (8), and the depth of the diaphragm wall extending into the bottom of the foundation pit (8) is not less than 0.6 time of the depth of the foundation pit (8).
3. The front wall rear pile foundation pit supporting structure of claim 1, wherein: the supporting piles (2) are cast-in-place piles, and the center distance between every two adjacent supporting piles (2) is 1-2 times of the pile diameter of the supporting piles (2).
4. The front wall rear pile foundation pit supporting structure of claim 1, wherein: the front row of crown beams (3) and the rear row of crown beams (4) are cast-in-place reinforced concrete beams; the width of the front row of crown beams (3) is 0-200 mm larger than the wall thickness of the diaphragm wall (1), and the width of the rear row of crown beams (4) is 0-200 mm larger than the pile diameter of the support piles (2); the height of the front row of crown beams (3) is 0.6-1 time of the wall thickness of the diaphragm wall (1), the height of the rear row of crown beams (4) is 0.6-1 time of the pile diameter of the supporting piles (2), and the height of the front row of crown beams (3) is adapted to the height of the rear row of crown beams (4).
5. The front wall rear pile foundation pit supporting structure of claim 4, wherein: the connecting beam (5) is a cast-in-place reinforced concrete beam, the width of the connecting beam (5) is adapted to the width of the back row crown beam (4), and the height of the connecting beam (5) is adapted to the height of the back row crown beam (4).
6. The front wall rear pile foundation pit supporting structure of claim 1, wherein: the cover plate (6) is a cast-in-place reinforced concrete plate, and the thickness of the cover plate (6) is 0.5-1 time of the height of the connecting beam (5); the cover plate (6) and the connecting beam (5) are integrally cast.
7. The front wall rear pile foundation pit supporting structure of claim 1, wherein: the distance from the center of the supporting pile (2) to the central axis of the underground diaphragm wall (1) is 3-5 times of the pile diameter of the supporting pile (2).
CN201922198164.0U 2019-12-10 2019-12-10 Pile foundation pit supporting construction behind preceding wall Expired - Fee Related CN211340808U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922198164.0U CN211340808U (en) 2019-12-10 2019-12-10 Pile foundation pit supporting construction behind preceding wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922198164.0U CN211340808U (en) 2019-12-10 2019-12-10 Pile foundation pit supporting construction behind preceding wall

Publications (1)

Publication Number Publication Date
CN211340808U true CN211340808U (en) 2020-08-25

Family

ID=72092228

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922198164.0U Expired - Fee Related CN211340808U (en) 2019-12-10 2019-12-10 Pile foundation pit supporting construction behind preceding wall

Country Status (1)

Country Link
CN (1) CN211340808U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110952567A (en) * 2019-12-10 2020-04-03 中建一局集团建设发展有限公司 Front wall and rear pile composite double-row foundation pit supporting structure and construction method thereof
CN112575794A (en) * 2020-12-23 2021-03-30 中国水利水电第七工程局有限公司 Deep silt geological foundation pit support structure and construction method thereof
CN113152427A (en) * 2021-05-07 2021-07-23 深圳大学 Protection structure and method for adjacent underground pipeline of riprap reclamation sea area excavation project
CN113585168A (en) * 2021-08-20 2021-11-02 中交第四航务工程勘察设计院有限公司 Sheet pile shore-connection type high-pile wharf structure suitable for deep peat soil soft foundation and construction method
CN115450221A (en) * 2022-10-19 2022-12-09 中铁十五局集团城市轨道交通工程有限公司 A construction method for a subway crossing a river

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110952567A (en) * 2019-12-10 2020-04-03 中建一局集团建设发展有限公司 Front wall and rear pile composite double-row foundation pit supporting structure and construction method thereof
CN112575794A (en) * 2020-12-23 2021-03-30 中国水利水电第七工程局有限公司 Deep silt geological foundation pit support structure and construction method thereof
CN113152427A (en) * 2021-05-07 2021-07-23 深圳大学 Protection structure and method for adjacent underground pipeline of riprap reclamation sea area excavation project
CN113585168A (en) * 2021-08-20 2021-11-02 中交第四航务工程勘察设计院有限公司 Sheet pile shore-connection type high-pile wharf structure suitable for deep peat soil soft foundation and construction method
CN115450221A (en) * 2022-10-19 2022-12-09 中铁十五局集团城市轨道交通工程有限公司 A construction method for a subway crossing a river

Similar Documents

Publication Publication Date Title
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN205742213U (en) Foundation pit supporting construction
CN100580190C (en) Building foundation pit support structure
CN105220703B (en) Enclosing type deepwater platform construction method based on condition of sand backfilling balance method
CN110952567A (en) Front wall and rear pile composite double-row foundation pit supporting structure and construction method thereof
CN203213124U (en) Steel sheet pile and cement-mixed pile combined support
CN207003499U (en) A kind of anti-floating lifting device of underground tunnel upper excavation of foundation pit
CN102330436B (en) Composite retaining structure and composite retaining method for half geotechnical layer ultradeep round spiral flow tank
CN105239578B (en) Water-rich sand layer deep foundation pit underwater construction method
CN103469798B (en) A kind of foundation pit supporting construction and construction method thereof
CN203729308U (en) Double-row pile supporting system of reinforced concrete pile combined structural steel cement mixing pile wall
CN203684230U (en) Prefabricated double-row pile structure
CN102691302B (en) Concrete structure for supporting deep foundation pit
CN106013171A (en) Semi-rigid and semi-flexible support structure and method for deep foundation pit side wall
CN109024662A (en) Method of the anchor pile underpinning without basement building underground space increasing layer
CN106245927A (en) A kind of frame structure building underground that is applicable to increases method and the building of layer
CN115653000A (en) Gravity pipe gallery in-situ protection structure system in foundation pit range and construction method
CN118668715A (en) Foundation pit water-stop supporting device and dewatering construction method thereof
CN105064711B (en) Method for constructing underground garage between residential buildings
CN110080169A (en) A kind of construction method reclaimed fields from the sea utilized based on basement
CN207003421U (en) A kind of steel plate pilework for being seated hard rock top surface
CN205954638U (en) Half semi -rigid flexible supporting construction of deep basal pit lateral wall
CN111485560A (en) Supporting structure of deep foundation pit under ultra-wide pipeline and construction method of deep foundation pit under ultra-wide pipeline
CN204898684U (en) Super dark excavation supporting system
CN206189447U (en) Partly strut formula retaining wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200825

CF01 Termination of patent right due to non-payment of annual fee