CN211169627U - A hoisting device for coal mine maintenance equipment - Google Patents

A hoisting device for coal mine maintenance equipment Download PDF

Info

Publication number
CN211169627U
CN211169627U CN201922134824.9U CN201922134824U CN211169627U CN 211169627 U CN211169627 U CN 211169627U CN 201922134824 U CN201922134824 U CN 201922134824U CN 211169627 U CN211169627 U CN 211169627U
Authority
CN
China
Prior art keywords
rack
fixedly connected
hoisting
coal mine
hook
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201922134824.9U
Other languages
Chinese (zh)
Inventor
赵颖超
彭天府
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201922134824.9U priority Critical patent/CN211169627U/en
Application granted granted Critical
Publication of CN211169627U publication Critical patent/CN211169627U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

本实用新型涉及煤矿检修设备技术领域,更具体的说是一种煤矿检修设备起吊装置,启动驱动电机,驱动电机带动驱动齿轮转动,驱动齿轮驱动第一齿条和第二齿条向中心或两侧同时运动,第一齿条和第二齿条的滑动带动两个滑动连接块滑动,两个滑动连接块带动两个移动电机架滑动,两个移动电机架滑动带动两个上升电机滑动,两个上升电机带动两个吊钩机构滑动,两个限位杆可以通过拧下两个限位螺母实现两个吊钩的安装,两个吊钩钩住设备后安装两个限位杆防止松脱,启动两个上升电机,两个上升电机的转动会对两个绳索收紧,实现对待检修装置的起吊,两个绳索限位板防止两个绳索脱落,对人或物造成损伤。

Figure 201922134824

The utility model relates to the technical field of coal mine maintenance equipment, in particular to a hoisting device for coal mine maintenance equipment, which starts a driving motor, the driving motor drives a driving gear to rotate, and the driving gear drives a first rack and a second rack to the center or two The sides move at the same time, the sliding of the first rack and the second rack drives the two sliding connection blocks to slide, the two sliding connection blocks drive the two moving motor frames to slide, and the two moving motor frames slide to drive the two ascending motors to slide, and the two moving motor frames slide. Two lifting motors drive the two hook mechanisms to slide, and the two limit rods can be installed by unscrewing the two limit nuts. After the two hooks are hooked to the equipment, two limit rods are installed to prevent loosening. , Start the two lifting motors, the rotation of the two lifting motors will tighten the two ropes to achieve the lifting of the device to be repaired, and the two rope limit plates prevent the two ropes from falling off and causing damage to people or objects.

Figure 201922134824

Description

一种煤矿检修设备起吊装置A hoisting device for coal mine maintenance equipment

技术领域technical field

本实用新型涉及煤矿检修设备技术领域,更具体的说是一种煤矿检修设备起吊装置。The utility model relates to the technical field of coal mine maintenance equipment, in particular to a hoisting device for coal mine maintenance equipment.

背景技术Background technique

公开号为CN209352426U的实用新型公开了一种煤矿检修设备起吊装置,主要是为了提供一种新型结构的煤矿检修设备的起吊装置,方便高效的完成煤矿检修设备的吊装搬运工作,该起吊装置包括龙门架体结构的起吊基座,起吊基座包括上部设置的梯形结构的吊装架,在吊装架的下部设置有四个相互对称布置的吊装支腿,在每一个吊装支腿的底部设置有吊装锁紧连接装置,在吊装锁紧连接装置内设置有吊装倒链,在吊装架的顶部中间位置处还设置有防脱起吊座体,该新型结构设计的煤矿检修设备起吊装置,极大的提高了煤矿检修设备的检修进度,降低了检修成本,同时有效的避免了检修设备在起重吊装过程中的坠落现象,极大的保护了生产工人的劳动安全。该实用新型的缺点是不能调节两个起吊装置的宽度,使被检修设备更平稳的被吊起。The utility model with publication number CN209352426U discloses a hoisting device for coal mine maintenance equipment, mainly to provide a hoisting device for coal mine maintenance equipment with a new structure, which is convenient and efficient to complete the hoisting and handling work of coal mine maintenance equipment, and the hoisting device includes a gantry. The hoisting base of the frame structure, the hoisting base includes a hoisting frame of a trapezoidal structure arranged on the upper part, and four hoisting legs arranged symmetrically with each other are arranged at the lower part of the hoisting frame, and a hoisting lock is arranged at the bottom of each hoisting leg The tightening connection device is provided with a hoisting inverted chain in the hoisting locking connection device, and an anti-dropping hoisting body is also set at the middle position of the top of the hoisting frame. The maintenance progress of the coal mine maintenance equipment reduces the maintenance cost, and at the same time effectively avoids the falling phenomenon of the maintenance equipment during the lifting and hoisting process, which greatly protects the labor safety of the production workers. The disadvantage of the utility model is that the width of the two hoisting devices cannot be adjusted, so that the overhauled equipment can be hoisted more smoothly.

实用新型内容Utility model content

本实用新型的目的是提供一种煤矿检修设备起吊装置,具有可以调节两个起吊装置的宽度,使被检修设备更平稳的被吊起的优点。The purpose of the utility model is to provide a hoisting device for coal mine maintenance equipment, which has the advantage that the width of two hoisting devices can be adjusted, so that the maintenance equipment can be hoisted more smoothly.

本实用新型的目的通过以下技术方案来实现:The purpose of the present utility model is achieved through the following technical solutions:

一种煤矿检修设备起吊装置,包括支撑机构、吊钩机构、起吊机构和调节机构,调节机构固定连接在支撑机构上,起吊机构有两个,两个起吊机构分别滑动连接在支撑机构的左右两侧,两个起吊机构分别固定连接在调节机构的左右两侧,吊钩机构有两个,两个吊钩机构分别固定连接在两个起吊机构上,所述调节机构包括第一齿条、固定电机架、驱动齿轮、驱动电机和第二齿条,固定电机架固定连接在支撑机构的中部,驱动电机固定连接在固定电机架上,驱动齿轮固定连接在驱动电机的输出轴上,第一齿条和第二齿条分别滑动连接在固定电机架的前后两侧,驱动齿轮与第一齿条啮合传动,驱动齿轮与第二齿条啮合传动。A hoisting device for coal mine maintenance equipment, comprising a support mechanism, a hook mechanism, a hoisting mechanism and an adjusting mechanism. side, two hoisting mechanisms are fixedly connected to the left and right sides of the adjusting mechanism respectively, there are two hook mechanisms, and the two hook mechanisms are fixedly connected to the two hoisting mechanisms respectively, and the adjusting mechanism includes a first rack, a fixed The motor frame, the driving gear, the driving motor and the second rack, the fixed motor frame is fixedly connected to the middle of the support mechanism, the driving motor is fixedly connected to the fixed motor frame, the driving gear is fixedly connected to the output shaft of the driving motor, the first tooth The rack and the second rack are slidably connected to the front and rear sides of the fixed motor frame respectively, the driving gear meshes with the first rack for transmission, and the driving gear meshes with the second rack for transmission.

所述支撑机构包括固定底板、支撑框架、齿条滑道和滑道固定块,两个固定底板分别固定在支撑框架的左右两侧的下端,两个滑道固定块均固定连接在支撑框架的上端,两个滑道固定块上均设置有两个齿条滑道,固定电机架固定连接在支撑框架的中部,第一齿条和第二齿条分别滑动连接在与其相同一侧的两个齿条滑道上。The support mechanism includes a fixed base plate, a support frame, a rack slideway and a slideway fixing block, the two fixed baseplates are respectively fixed at the lower ends of the left and right sides of the support frame, and the two slideway fixing blocks are fixedly connected to the support frame. At the upper end, two rack slides are provided on the two slideway fixing blocks, the fixed motor frame is fixedly connected to the middle of the support frame, and the first rack and the second rack are respectively slidably connected to the two racks on the same side. on the rack slide.

所述起吊机构包括绳索限位板、移动电机架、上升电机和滑动连接块,两个滑动连接块分别固定连接在第一齿条和第二齿条上,两个滑动连接块分别滑动连接在支撑框架的左右两侧,两个移动电机架分别固定连接在两个滑动连接块的下端,两个上升电机分别固定连接在两个移动电机架上,两个绳索限位板分别固定连接在两个上升电机的输出轴的端部。The hoisting mechanism includes a rope limit plate, a mobile motor frame, a lifting motor and a sliding connection block, the two sliding connection blocks are respectively fixedly connected to the first rack and the second rack, and the two sliding connection blocks are respectively slidably connected to the On the left and right sides of the support frame, two mobile motor frames are fixedly connected to the lower ends of the two sliding connection blocks, respectively, the two ascending motors are fixedly connected to the two mobile motor frames, and the two rope limit plates are fixedly connected to the two The end of the output shaft of a lift motor.

所述吊钩机构包括吊钩、限位杆、限位螺母、吊钩连接板和绳索,两个绳索的上端分别固定连接在两个上升电机的输出轴上,两个吊钩连接板分别固定连接在两个绳索的下端,两个吊钩分别固定连接在两个吊钩连接板上,两个限位杆分别通过限位螺母可拆卸连接在两个吊钩上。The hook mechanism includes a hook, a limit rod, a limit nut, a hook connecting plate and a rope. The upper ends of the two ropes are respectively fixed and connected to the output shafts of the two lifting motors, and the two hook connecting plates are respectively fixed. Connected to the lower ends of the two ropes, the two hooks are respectively fixedly connected to the two hook connecting plates, and the two limit rods are detachably connected to the two hooks through the limit nuts respectively.

所述两个上升电机的转速相同。The rotational speeds of the two ascending motors are the same.

本实用新型一种煤矿检修设备起吊装置的有益效果为:本实用新型一种煤矿检修设备起吊装置,可以通过驱动电机带动驱动齿轮驱动第一齿条和第二齿条实现对两个吊钩机构宽度的调节,实现设备更稳定、更安全的起吊;还可以通过两个上升电机实现对两个绳索的收紧实现对维修设备的起吊;还可以通过两个限位杆和两个限位螺母实现对检修设备的防脱限位,保证维修人员的人身安全。The beneficial effects of the hoisting device for coal mine maintenance equipment of the utility model are as follows: the utility model is a hoisting device for coal mine maintenance equipment, which can drive the driving gear to drive the first rack and the second rack through the driving motor to realize the two hook mechanisms. The width adjustment can realize more stable and safer lifting of the equipment; it is also possible to tighten the two ropes through the two lifting motors to realize the lifting of the maintenance equipment; it is also possible to use two limit rods and two limit nuts. Realize the anti-dropping limit of maintenance equipment and ensure the personal safety of maintenance personnel.

附图说明Description of drawings

下面结合附图和具体实施方法对本实用新型做进一步详细的说明。The present utility model will be described in further detail below in conjunction with the accompanying drawings and specific implementation methods.

图1是本实用新型煤矿检修设备起吊装置的整体结构示意图;Fig. 1 is the overall structure schematic diagram of the utility model coal mine maintenance equipment hoisting device;

图2是本实用新型支撑机构的结构示意图;Fig. 2 is the structural representation of the support mechanism of the present invention;

图3是本实用新型吊钩机构的结构示意图;Fig. 3 is the structural representation of the hook mechanism of the present utility model;

图4是本实用新型起吊机构的结构示意图;Fig. 4 is the structural representation of the hoisting mechanism of the present utility model;

图5是本实用新型调节机构的结构示意图。FIG. 5 is a schematic structural diagram of the adjusting mechanism of the present invention.

图中:支撑机构1;固定底板1-1;支撑框架1-2;齿条滑道1-3;滑道固定块1-4;吊钩机构2;吊钩2-1;限位杆2-2;限位螺母2-3;吊钩连接板2-4;绳索2-5;起吊机构3;绳索限位板3-1;移动电机架3-2;上升电机3-3;滑动连接块3-4;调节机构4;第一齿条4-1;固定电机架4-2;驱动齿轮4-3;驱动电机4-4;第二齿条4-5。In the figure: support mechanism 1; fixed bottom plate 1-1; support frame 1-2; rack slideway 1-3; slideway fixing block 1-4; hook mechanism 2; hook 2-1; limit rod 2 -2; limit nut 2-3; hook connecting plate 2-4; rope 2-5; lifting mechanism 3; rope limit plate 3-1; moving motor frame 3-2; lifting motor 3-3; sliding connection block 3-4; adjustment mechanism 4; first rack 4-1; fixed motor frame 4-2; drive gear 4-3; drive motor 4-4; second rack 4-5.

具体实施方式Detailed ways

下面结合附图对本实用新型作进一步详细说明。The present utility model will be described in further detail below in conjunction with the accompanying drawings.

具体实施方式一:Specific implementation one:

下面结合图1-5说明本实施方式,一种煤矿检修设备起吊装置,包括支撑机构1、吊钩机构2、起吊机构3和调节机构4,调节机构4固定连接在支撑机构1上,起吊机构3有两个,两个起吊机构3分别滑动连接在支撑机构1的左右两侧,两个起吊机构3分别固定连接在调节机构4的左右两侧,吊钩机构2 有两个,两个吊钩机构2分别固定连接在两个起吊机构3上,所述调节机构4 包括第一齿条4-1、固定电机架4-2、驱动齿轮4-3、驱动电机4-4和第二齿条 4-5,固定电机架4-2固定连接在支撑机构1的中部,驱动电机4-4固定连接在固定电机架4-2上,驱动齿轮4-3固定连接在驱动电机4-4的输出轴上,第一齿条4-1和第二齿条4-5分别滑动连接在固定电机架4-2的前后两侧,驱动齿轮4-3与第一齿条4-1啮合传动,驱动齿轮4-3与第二齿条4-5啮合传动,启动驱动电机4-4,驱动电机4-4带动驱动齿轮4-3转动,驱动齿轮4-3驱动第一齿条4-1和第二齿条4-5向中心或两侧同时运动。The present embodiment will be described below with reference to FIGS. 1-5, a hoisting device for coal mine maintenance equipment, including a support mechanism 1, a hook mechanism 2, a hoisting mechanism 3 and an adjustment mechanism 4, the adjustment mechanism 4 is fixedly connected to the support mechanism 1, and the hoisting mechanism 3 There are two, two hoisting mechanisms 3 are slidably connected to the left and right sides of the support mechanism 1, two hoisting mechanisms 3 are fixedly connected to the left and right sides of the adjusting mechanism 4, respectively, there are two hook mechanisms 2, two hoisting mechanisms 3 The hook mechanism 2 is fixedly connected to the two hoisting mechanisms 3 respectively, and the adjusting mechanism 4 includes a first rack 4-1, a fixed motor frame 4-2, a driving gear 4-3, a driving motor 4-4 and a second tooth Article 4-5, the fixed motor frame 4-2 is fixedly connected to the middle of the support mechanism 1, the driving motor 4-4 is fixedly connected to the fixed motor frame 4-2, and the driving gear 4-3 is fixedly connected to the driving motor 4-4. On the output shaft, the first rack 4-1 and the second rack 4-5 are slidably connected to the front and rear sides of the fixed motor frame 4-2 respectively, and the driving gear 4-3 meshes with the first rack 4-1 for transmission. The drive gear 4-3 meshes with the second rack 4-5 for transmission, starts the drive motor 4-4, the drive motor 4-4 drives the drive gear 4-3 to rotate, and the drive gear 4-3 drives the first rack 4-1 and The second racks 4-5 move to the center or both sides simultaneously.

具体实施方式二:Specific implementation two:

下面结合图1-5说明本实施方式,所述支撑机构1包括固定底板1-1、支撑框架1-2、齿条滑道1-3和滑道固定块1-4,两个固定底板1-1分别固定在支撑框架1-2的左右两侧的下端,两个滑道固定块1-4均固定连接在支撑框架1-2 的上端,两个滑道固定块1-4上均设置有两个齿条滑道1-3,固定电机架4-2固定连接在支撑框架1-2的中部,第一齿条4-1和第二齿条4-5分别滑动连接在与其相同一侧的两个齿条滑道1-3上,四个齿条滑道1-3对第一齿条4-1和第二齿条4-5的滑动起到限位和导向的作用。The present embodiment will be described below with reference to FIGS. 1-5 . The support mechanism 1 includes a fixed base plate 1-1, a support frame 1-2, a rack slideway 1-3 and a slideway fixing block 1-4. Two fixed base plates 1 -1 are respectively fixed on the lower ends of the left and right sides of the support frame 1-2, the two slideway fixing blocks 1-4 are fixedly connected to the upper end of the support frame 1-2, and the two slideway fixing blocks 1-4 are both arranged on There are two rack slideways 1-3, the fixed motor frame 4-2 is fixedly connected to the middle of the support frame 1-2, and the first rack 4-1 and the second rack 4-5 are slidably connected to the same one. On the two rack slideways 1-3 on the side, the four rack slideways 1-3 play the role of limiting and guiding the sliding of the first rack 4-1 and the second rack 4-5.

具体实施方式三:Specific implementation three:

下面结合图1-5说明本实施方式,所述起吊机构3包括绳索限位板3-1、移动电机架3-2、上升电机3-3和滑动连接块3-4,两个滑动连接块3-4分别固定连接在第一齿条4-1和第二齿条4-5上,两个滑动连接块3-4分别滑动连接在支撑框架1-2的左右两侧,两个移动电机架3-2分别固定连接在两个滑动连接块3-4的下端,两个上升电机3-3分别固定连接在两个移动电机架3-2上,两个绳索限位板3-1分别固定连接在两个上升电机3-3的输出轴的端部,第一齿条4-1和第二齿条4-5的滑动带动两个滑动连接块3-4滑动,两个滑动连接块 3-4带动两个移动电机架3-2滑动,两个移动电机架3-2滑动带动两个上升电机 3-3滑动,两个上升电机3-3带动两个吊钩机构2滑动,两个绳索限位板3-1防止两个绳索2-5脱落,对人或物造成损伤。The present embodiment will be described below with reference to FIGS. 1-5 . The hoisting mechanism 3 includes a rope limit plate 3-1, a moving motor frame 3-2, a lifting motor 3-3 and a sliding connection block 3-4, two sliding connection blocks. 3-4 are fixedly connected to the first rack 4-1 and the second rack 4-5 respectively, two sliding connecting blocks 3-4 are respectively slidingly connected to the left and right sides of the supporting frame 1-2, two moving motors The frames 3-2 are respectively fixedly connected to the lower ends of the two sliding connection blocks 3-4, the two ascending motors 3-3 are respectively fixedly connected to the two moving motor frames 3-2, and the two rope limit plates 3-1 are respectively Fixedly connected to the ends of the output shafts of the two ascending motors 3-3, the sliding of the first rack 4-1 and the second rack 4-5 drives the two sliding connection blocks 3-4 to slide, and the two sliding connection blocks 3-4 drives the two mobile motor frames 3-2 to slide, the two mobile motor frames 3-2 slide to drive the two lift motors 3-3 to slide, the two lift motors 3-3 drive the two hook mechanisms 2 to slide, and the two lift motors 3-3 slide. A rope limit plate 3-1 prevents the two ropes 2-5 from falling off and causing damage to people or objects.

具体实施方式四:Specific implementation four:

下面结合图1-5说明本实施方式,所述吊钩机构2包括吊钩2-1、限位杆 2-2、限位螺母2-3、吊钩连接板2-4和绳索2-5,两个绳索2-5的上端分别固定连接在两个上升电机3-3的输出轴上,两个吊钩连接板2-4分别固定连接在两个绳索2-5的下端,两个吊钩2-1分别固定连接在两个吊钩连接板2-4上,两个限位杆2-2分别通过限位螺母2-3可拆卸连接在两个吊钩2-1上,两个上升电机3-3的转动会对两个绳索2-5收紧,实现对待检修装置的起吊,两个限位杆2-2可以通过拧下两个限位螺母2-3实现两个吊钩2-1的安装,两个吊钩2-1钩住设备后安装两个限位杆2-2防止松脱。The present embodiment will be described below with reference to FIGS. 1-5. The hook mechanism 2 includes a hook 2-1, a limit rod 2-2, a limit nut 2-3, a hook connecting plate 2-4 and a rope 2-5 , the upper ends of the two ropes 2-5 are fixedly connected to the output shafts of the two lifting motors 3-3 respectively, and the two hook connecting plates 2-4 are fixedly connected to the lower ends of the two ropes 2-5 respectively. The hooks 2-1 are fixedly connected to the two hook connecting plates 2-4 respectively, and the two limit rods 2-2 are detachably connected to the two hooks 2-1 through the limit nuts 2-3 respectively. The rotation of the lifting motor 3-3 will tighten the two ropes 2-5 to realize the lifting of the device to be repaired. The two limit rods 2-2 can be realized by unscrewing the two limit nuts 2-3 to achieve two hooks For the installation of 2-1, install two limit rods 2-2 after the two hooks 2-1 are hooked to the equipment to prevent loosening.

具体实施方式五:Specific implementation five:

下面结合图1-5说明本实施方式,所述两个上升电机3-3的转速相同,实现两个吊钩2-1的同步上升。The present embodiment will be described below with reference to FIGS. 1-5 . The rotation speeds of the two lifting motors 3-3 are the same, so that the two hooks 2-1 can be lifted synchronously.

本实用新型一种煤矿检修设备起吊装置,其使用原理为:启动驱动电机4-4,驱动电机4-4带动驱动齿轮4-3转动,驱动齿轮4-3驱动第一齿条4-1和第二齿条4-5向中心或两侧同时运动,四个齿条滑道1-3对第一齿条4-1和第二齿条4-5的滑动起到限位和导向的作用,第一齿条4-1和第二齿条4-5的滑动带动两个滑动连接块3-4滑动,两个滑动连接块3-4带动两个移动电机架3-2滑动,两个移动电机架3-2滑动带动两个上升电机3-3滑动,两个上升电机3-3 带动两个吊钩机构2滑动,两个限位杆2-2可以通过拧下两个限位螺母2-3实现两个吊钩2-1的安装,两个吊钩2-1钩住设备后安装两个限位杆2-2防止松脱,启动两个上升电机3-3,两个上升电机3-3的转动会对两个绳索2-5收紧,实现对待检修装置的起吊,两个绳索限位板3-1防止两个绳索2-5脱落,对人或物造成损伤。The utility model is a hoisting device for coal mine maintenance equipment. The second rack 4-5 moves to the center or both sides simultaneously, and the four rack slideways 1-3 play a limiting and guiding role for the sliding of the first rack 4-1 and the second rack 4-5 , the sliding of the first rack 4-1 and the second rack 4-5 drives the two sliding connection blocks 3-4 to slide, the two sliding connection blocks 3-4 drive the two mobile motor frames 3-2 to slide, and the two The moving motor frame 3-2 slides to drive the two lift motors 3-3 to slide, the two lift motors 3-3 drive the two hook mechanisms 2 to slide, and the two limit rods 2-2 can be unscrewed by unscrewing the two limit nuts. 2-3 Realize the installation of two hooks 2-1. After the two hooks 2-1 are hooked to the equipment, install two limit rods 2-2 to prevent loosening, start the two lift motors 3-3, and the two lift The rotation of the motor 3-3 will tighten the two ropes 2-5 to realize the lifting of the device to be repaired. The two rope limit plates 3-1 prevent the two ropes 2-5 from falling off and causing damage to people or objects.

当然,上述说明并非对本实用新型的限制,本实用新型也不仅限于上述举例,本技术领域的普通技术人员在本实用新型的实质范围内所做出的变化、改型、添加或替换,也属于本实用新型的保护范围。Of course, the above description does not limit the present utility model, and the present utility model is not limited to the above-mentioned examples. Changes, modifications, additions or replacements made by those of ordinary skill in the technical field within the essential scope of the present utility model also belong to the scope of the present utility model. The scope of protection of the utility model.

Claims (5)

1.一种煤矿检修设备起吊装置,包括支撑机构(1)、吊钩机构(2)、起吊机构(3)和调节机构(4),调节机构(4)固定连接在支撑机构(1)上,起吊机构(3)有两个,两个起吊机构(3)分别滑动连接在支撑机构(1)的左右两侧,两个起吊机构(3)分别固定连接在调节机构(4)的左右两侧,吊钩机构(2)有两个,两个吊钩机构(2)分别固定连接在两个起吊机构(3)上,其特征在于:所述调节机构(4)包括第一齿条(4-1)、固定电机架(4-2)、驱动齿轮(4-3)、驱动电机(4-4)和第二齿条(4-5),固定电机架(4-2)固定连接在支撑机构(1)的中部,驱动电机(4-4)固定连接在固定电机架(4-2)上,驱动齿轮(4-3)固定连接在驱动电机(4-4)的输出轴上,第一齿条(4-1)和第二齿条(4-5)分别滑动连接在固定电机架(4-2)的前后两侧,驱动齿轮(4-3)与第一齿条(4-1)啮合传动,驱动齿轮(4-3)与第二齿条(4-5)啮合传动。1. A lifting device for coal mine maintenance equipment, comprising a support mechanism (1), a hook mechanism (2), a lifting mechanism (3) and an adjustment mechanism (4), wherein the adjustment mechanism (4) is fixedly connected to the support mechanism (1) , There are two hoisting mechanisms (3), the two hoisting mechanisms (3) are respectively slidably connected to the left and right sides of the supporting mechanism (1), and the two hoisting mechanisms (3) are fixedly connected to the left and right sides of the adjusting mechanism (4). There are two hook mechanisms (2), and the two hook mechanisms (2) are fixedly connected to the two lifting mechanisms (3) respectively, and it is characterized in that: the adjustment mechanism (4) includes a first rack ( 4-1), the fixed motor frame (4-2), the drive gear (4-3), the drive motor (4-4) and the second rack (4-5), the fixed motor frame (4-2) is fixedly connected In the middle of the support mechanism (1), the drive motor (4-4) is fixedly connected to the fixed motor frame (4-2), and the drive gear (4-3) is fixedly connected to the output shaft of the drive motor (4-4). , the first rack (4-1) and the second rack (4-5) are slidably connected to the front and rear sides of the fixed motor frame (4-2), respectively, and the driving gear (4-3) is connected to the first rack (4-3). 4-1) Mesh transmission, the driving gear (4-3) meshes with the second rack (4-5) for transmission. 2.根据权利要求1所述的一种煤矿检修设备起吊装置,其特征在于:所述支撑机构(1)包括固定底板(1-1)、支撑框架(1-2)、齿条滑道(1-3)和滑道固定块(1-4),两个固定底板(1-1)分别固定在支撑框架(1-2)的左右两侧的下端,两个滑道固定块(1-4)均固定连接在支撑框架(1-2)的上端,两个滑道固定块(1-4)上均设置有两个齿条滑道(1-3),固定电机架(4-2)固定连接在支撑框架(1-2)的中部,第一齿条(4-1)和第二齿条(4-5)分别滑动连接在与其相同一侧的两个齿条滑道(1-3)上。2 . The hoisting device for coal mine maintenance equipment according to claim 1 , wherein the support mechanism ( 1 ) comprises a fixed bottom plate ( 1-1 ), a support frame ( 1-2 ), a rack slide ( 1-3) and the slideway fixing block (1-4), the two fixed bottom plates (1-1) are respectively fixed on the lower ends of the left and right sides of the support frame (1-2), and the two slideway fixing blocks (1- 4) Both are fixedly connected to the upper end of the support frame (1-2), two rack slides (1-3) are arranged on the two slideway fixing blocks (1-4), and the motor frame (4-2) is fixed. ) is fixedly connected to the middle of the support frame (1-2), and the first rack (4-1) and the second rack (4-5) are slidably connected to the two rack slideways (1) on the same side respectively. -3) on. 3.根据权利要求2所述的一种煤矿检修设备起吊装置,其特征在于:所述起吊机构(3)包括绳索限位板(3-1)、移动电机架(3-2)、上升电机(3-3)和滑动连接块(3-4),两个滑动连接块(3-4)分别固定连接在第一齿条(4-1)和第二齿条(4-5)上,两个滑动连接块(3-4)分别滑动连接在支撑框架(1-2)的左右两侧,两个移动电机架(3-2)分别固定连接在两个滑动连接块(3-4)的下端,两个上升电机(3-3)分别固定连接在两个移动电机架(3-2)上,两个绳索限位板(3-1)分别固定连接在两个上升电机(3-3)的输出轴的端部。3. A coal mine maintenance equipment hoisting device according to claim 2, characterized in that: the hoisting mechanism (3) comprises a rope limit plate (3-1), a mobile motor frame (3-2), a lifting motor (3-3) and a sliding connection block (3-4), the two sliding connection blocks (3-4) are fixedly connected to the first rack (4-1) and the second rack (4-5) respectively, The two sliding connection blocks (3-4) are respectively slidably connected to the left and right sides of the support frame (1-2), and the two mobile motor frames (3-2) are respectively fixedly connected to the two sliding connection blocks (3-4) At the lower end of the cable, two ascending motors (3-3) are fixedly connected to the two moving motor frames (3-2) respectively, and two rope limit plates (3-1) are fixedly connected to the two ascending motors (3-2) respectively. 3) the end of the output shaft. 4.根据权利要求3所述的一种煤矿检修设备起吊装置,其特征在于:所述吊钩机构(2)包括吊钩(2-1)、限位杆(2-2)、限位螺母(2-3)、吊钩连接板(2-4)和绳索(2-5),两个绳索(2-5)的上端分别固定连接在两个上升电机(3-3)的输出轴上,两个吊钩连接板(2-4)分别固定连接在两个绳索(2-5)的下端,两个吊钩(2-1)分别固定连接在两个吊钩连接板(2-4)上,两个限位杆(2-2)分别通过限位螺母(2-3)可拆卸连接在两个吊钩(2-1)上。4. A hoisting device for coal mine maintenance equipment according to claim 3, characterized in that: the hook mechanism (2) comprises a hook (2-1), a limit rod (2-2), a limit nut (2-3), the hook connecting plate (2-4) and the rope (2-5), the upper ends of the two ropes (2-5) are fixedly connected to the output shafts of the two ascending motors (3-3) respectively , the two hook connecting plates (2-4) are respectively fixedly connected to the lower ends of the two ropes (2-5), and the two hooks (2-1) are fixedly connected to the two hook connecting plates (2-4) respectively ), the two limit rods (2-2) are respectively detachably connected to the two hooks (2-1) through the limit nuts (2-3). 5.根据权利要求4所述的一种煤矿检修设备起吊装置,其特征在于:所述两个上升电机(3-3)的转速相同。5 . The hoisting device for coal mine maintenance equipment according to claim 4 , wherein the rotation speed of the two lifting motors ( 3 - 3 ) is the same. 6 .
CN201922134824.9U 2019-12-03 2019-12-03 A hoisting device for coal mine maintenance equipment Expired - Fee Related CN211169627U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922134824.9U CN211169627U (en) 2019-12-03 2019-12-03 A hoisting device for coal mine maintenance equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922134824.9U CN211169627U (en) 2019-12-03 2019-12-03 A hoisting device for coal mine maintenance equipment

Publications (1)

Publication Number Publication Date
CN211169627U true CN211169627U (en) 2020-08-04

Family

ID=71817894

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922134824.9U Expired - Fee Related CN211169627U (en) 2019-12-03 2019-12-03 A hoisting device for coal mine maintenance equipment

Country Status (1)

Country Link
CN (1) CN211169627U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112591618A (en) * 2020-12-18 2021-04-02 江西鑫通机械制造有限公司 Lifting device for coal mine maintenance equipment
CN113401821A (en) * 2021-06-25 2021-09-17 浙江信安消防工程有限公司 Fire pump trouble auxiliary overhaul device that flexibility is high

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112591618A (en) * 2020-12-18 2021-04-02 江西鑫通机械制造有限公司 Lifting device for coal mine maintenance equipment
CN113401821A (en) * 2021-06-25 2021-09-17 浙江信安消防工程有限公司 Fire pump trouble auxiliary overhaul device that flexibility is high

Similar Documents

Publication Publication Date Title
CN205472511U (en) Stable elevating platform that overhauls
CN205527406U (en) Hoist device for building portable
CN205346760U (en) Hoist overhauls uses elevating platform
CN107973226A (en) A kind of high hoisting machinery of stability
CN220952992U (en) Bridge anticollision barrier construction equipment
CN218909646U (en) High-efficient safe driving hoisting mechanism
CN218174415U (en) Cable manufacture handling device
CN219297008U (en) A manual hoisting accessory of plain type for flywheel housing
CN116101946B (en) A 3D positioning platform for substation workers
CN207259037U (en) A kind of gate-type lifting device
CN206531635U (en) Scaffold antislip ring durability test equipment
CN214527854U (en) Hoisting apparatus is used in building engineering construction
CN116177389A (en) A convenient and safe hoisting device for large equipment
CN209193408U (en) Cantilever crane
CN221971072U (en) A new type of sling that can be used in a narrow space
CN208200186U (en) Large-scale power distribution cabinet transfer device
CN109231027B (en) Lifting device for constructional engineering
CN217148356U (en) Large-scale coal chemical industry equipment overhauls uses hoist and mount frame
CN208308313U (en) A kind of Architectural Equipment device for hoisting
CN216377318U (en) A a gallows hoist and mount conveyer for EPC engineering
CN106315409A (en) Lifting frame with speed adjusting function
CN211688126U (en) Building engineering hoist device
CN223592263U (en) Hoisting structure for double-portal crane
CN218560945U (en) Novel tower crane's balanced davit
CN207566821U (en) Boiler maintenance platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200804