CN211146548U - A system for improving boiler efficiency by utilizing low temperature waste heat of flue gas - Google Patents

A system for improving boiler efficiency by utilizing low temperature waste heat of flue gas Download PDF

Info

Publication number
CN211146548U
CN211146548U CN201922203679.5U CN201922203679U CN211146548U CN 211146548 U CN211146548 U CN 211146548U CN 201922203679 U CN201922203679 U CN 201922203679U CN 211146548 U CN211146548 U CN 211146548U
Authority
CN
China
Prior art keywords
outlet
inlet
flue gas
tower
steam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201922203679.5U
Other languages
Chinese (zh)
Inventor
周贤
张海峰
彭烁
钟迪
王保民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huaneng Clean Energy Research Institute
Original Assignee
Huaneng Clean Energy Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huaneng Clean Energy Research Institute filed Critical Huaneng Clean Energy Research Institute
Priority to CN201922203679.5U priority Critical patent/CN211146548U/en
Application granted granted Critical
Publication of CN211146548U publication Critical patent/CN211146548U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E20/00—Combustion technologies with mitigation potential
    • Y02E20/34—Indirect CO2mitigation, i.e. by acting on non CO2directly related matters of the process, e.g. pre-heating or heat recovery

Landscapes

  • Treating Waste Gases (AREA)

Abstract

本实用新型提供的一种利用烟气低温余热提高锅炉效率的系统,包括燃煤锅炉、除尘器、湿法脱硫塔、闪蒸塔、引射器和汽轮机,其中,燃煤锅炉的烟气出口连接除尘器的入口,除尘器的出口连接湿法脱硫塔的底部入口,湿法脱硫塔的底部脱硫浆液出口与闪蒸塔的入口连接;闪蒸塔的冷浆液出口与湿法脱硫塔顶部的冷浆液入口连接;闪蒸塔的负压蒸汽出口与引射器的蒸汽入口连接;燃煤锅炉蒸汽出口连接汽轮机的入口,汽轮机中部设置有抽汽口,所述抽汽口连接引射器的抽汽入口,引射器的出口连接燃煤锅炉的空气入口;本实用新型结构简单,能够通过回收湿法脱硫塔内脱硫浆液的热量达到深度回收烟气余热的目的,提高能源利用效率。

Figure 201922203679

The utility model provides a system for improving boiler efficiency by utilizing low-temperature waste heat of flue gas, comprising a coal-fired boiler, a dust collector, a wet desulfurization tower, a flash tower, an ejector and a steam turbine, wherein the flue gas outlet of the coal-fired boiler is The inlet of the dust collector is connected, the outlet of the dust collector is connected to the bottom inlet of the wet desulfurization tower, the desulfurization slurry outlet of the bottom of the wet desulfurization tower is connected to the inlet of the flash tower; the cold slurry outlet of the flash tower is connected to the top of the wet desulfurization tower. The cold slurry inlet is connected; the negative pressure steam outlet of the flash tower is connected with the steam inlet of the ejector; the steam outlet of the coal-fired boiler is connected with the inlet of the steam turbine, and a steam extraction port is arranged in the middle of the steam turbine, and the steam extraction port is connected with the ejector. The extraction steam inlet and the ejector outlet are connected to the air inlet of the coal-fired boiler; the utility model has a simple structure, and can achieve the purpose of deep recovery of flue gas waste heat by recovering the heat of the desulfurization slurry in the wet desulfurization tower, thereby improving energy utilization efficiency.

Figure 201922203679

Description

一种利用烟气低温余热提高锅炉效率的系统A system for improving boiler efficiency by utilizing low temperature waste heat of flue gas

技术领域technical field

本实用新型属于火力发电节能减排领域,具体涉及一种利用烟气低温余热提高锅炉效率的系统。The utility model belongs to the field of energy saving and emission reduction of thermal power generation, in particular to a system for improving boiler efficiency by utilizing low-temperature waste heat of flue gas.

背景技术Background technique

目前多数燃煤热电联产机组普遍采取了多种节能措施,冷端损失基本消除,节能潜力大幅降低后,排烟损失占据了锅炉各项损失中的最大一部分。回收烟气余热以降低排烟温度,减少排烟损失,可以有效提高机组能源利用效率。烟气余热回收主要采用间壁式换热器的方式,由于燃煤烟气为含灰含酸气体,容易造成换热器的磨损与腐蚀,设备可靠性大多较差。At present, most coal-fired cogeneration units have generally adopted a variety of energy-saving measures. The cold-end losses are basically eliminated. After the energy-saving potential is greatly reduced, the exhaust gas loss accounts for the largest part of the boiler losses. The waste heat of flue gas is recovered to reduce the temperature of exhaust gas and reduce the loss of exhaust gas, which can effectively improve the energy utilization efficiency of the unit. The waste heat recovery of flue gas mainly adopts the method of partition heat exchanger. Since coal-fired flue gas contains ash and acid gas, it is easy to cause wear and corrosion of heat exchanger, and the reliability of equipment is mostly poor.

采用湿法脱硫浆液闪蒸的方式,将脱硫浆液引入负压状态的闪蒸塔内,发生闪蒸过程,产生大量负压闪蒸蒸汽,清洁的负压闪蒸蒸汽通过冷凝器或者热泵等设备,完成了冷凝放热,可实现了热量的回收利用,水蒸气凝结形成的水分可有效降低机组整体水耗。由于闪蒸的蒸发冷却原理使得浆液温度降低,利用冷却后的脱硫浆液对烟气进行喷淋,达到降低烟气温度与含水量的目的,实现消除白色烟羽视觉污染的目的。The wet desulfurization slurry is flashed, and the desulfurization slurry is introduced into the flash tower in the negative pressure state. The flashing process occurs, and a large amount of negative pressure flash steam is generated. The clean negative pressure flash steam passes through the condenser or heat pump and other equipment. , the condensation heat release is completed, and the heat recovery and utilization can be realized, and the moisture formed by the condensation of water vapor can effectively reduce the overall water consumption of the unit. Due to the evaporative cooling principle of flash evaporation, the temperature of the slurry is reduced, and the cooled desulfurization slurry is used to spray the flue gas to reduce the temperature and water content of the flue gas, and to eliminate the visual pollution of white plumes.

此外,向助燃空气中注入水蒸气或水后,湿空气混合物进入燃气轮机、锅炉等燃烧设备燃烧,能降低燃烧过程中热力型NOx的生成。In addition, after injecting water vapor or water into the combustion air, the moist air mixture enters into combustion equipment such as gas turbines and boilers for combustion, which can reduce the generation of thermal NOx during the combustion process.

但是现有的燃煤热电联产机组的高温烟气并未完全利用,造成资源浪费。However, the high-temperature flue gas of the existing coal-fired cogeneration unit is not fully utilized, resulting in waste of resources.

发明内容SUMMARY OF THE INVENTION

本实用新型的目的在于提供一种利用烟气低温余热提高锅炉效率的系统,能够间接回收湿法脱硫后烟气余热,提高锅炉效率,降低NOx排放,同时实现降低烟气内水蒸气含量,回收凝结水,消除白色烟羽视觉污染现象。The purpose of this utility model is to provide a system for improving boiler efficiency by utilizing low-temperature waste heat of flue gas, which can indirectly recover waste heat of flue gas after wet desulfurization, improve boiler efficiency, reduce NOx emission, reduce the water vapor content in flue gas, and recover Condensate water, eliminate the visual pollution phenomenon of white smoke plume.

为了达到上述目的,本实用新型采用的技术方案是:In order to achieve the above-mentioned purpose, the technical scheme that the utility model adopts is:

本实用新型提供的一种利用烟气低温余热提高锅炉效率的系统,包括燃煤锅炉、除尘器、湿法脱硫塔、闪蒸塔、引射器和汽轮机,其中,燃煤锅炉的烟气出口连接除尘器的入口,除尘器的出口连接湿法脱硫塔的底部入口,湿法脱硫塔的底部脱硫浆液出口与闪蒸塔的入口连接;闪蒸塔的冷浆液出口与湿法脱硫塔顶部的冷浆液入口连接;闪蒸塔的负压蒸汽出口与引射器的蒸汽入口连接;燃煤锅炉蒸汽出口连接汽轮机的入口,汽轮机中部设置有抽汽口,所述抽汽口连接引射器的抽汽入口,引射器的出口连接燃煤锅炉的空气入口。The utility model provides a system for improving boiler efficiency by utilizing low-temperature waste heat of flue gas, comprising a coal-fired boiler, a dust collector, a wet desulfurization tower, a flash tower, an ejector and a steam turbine, wherein the flue gas outlet of the coal-fired boiler is The inlet of the dust collector is connected, the outlet of the dust collector is connected to the bottom inlet of the wet desulfurization tower, the desulfurization slurry outlet of the bottom of the wet desulfurization tower is connected to the inlet of the flash tower; the cold slurry outlet of the flash tower is connected to the top of the wet desulfurization tower. The cold slurry inlet is connected; the negative pressure steam outlet of the flash tower is connected with the steam inlet of the ejector; the steam outlet of the coal-fired boiler is connected with the inlet of the steam turbine, and a steam extraction port is arranged in the middle of the steam turbine, and the steam extraction port is connected with the ejector. The extraction steam inlet and the ejector outlet are connected to the air inlet of the coal-fired boiler.

优选地,所述除尘器的出口与湿法脱硫塔的底部入口之间设置有引风机。Preferably, an induced draft fan is provided between the outlet of the dust collector and the bottom inlet of the wet desulfurization tower.

优选地,所述湿法脱硫塔的底部脱硫浆液出口与闪蒸塔的入口之间设置有第一浆液泵。Preferably, a first slurry pump is provided between the bottom desulfurization slurry outlet of the wet desulfurization tower and the inlet of the flash tower.

优选地,所述湿法脱硫塔的顶部设置有烟气出口,所述烟气出口连接有烟囱。Preferably, the top of the wet desulfurization tower is provided with a flue gas outlet, and the flue gas outlet is connected with a chimney.

优选地,所述闪蒸塔的冷浆液出口与湿法脱硫塔顶部的冷浆液入口之间设置有第二浆液泵。Preferably, a second slurry pump is provided between the cold slurry outlet of the flash tower and the cold slurry inlet of the top of the wet desulfurization tower.

优选地,所述闪蒸塔的负压蒸汽出口还连接有冷凝器;所述汽轮机上设置的乏汽出口连接有冷凝器。Preferably, the negative pressure steam outlet of the flash tower is also connected with a condenser; the spent steam outlet provided on the steam turbine is connected with a condenser.

优选地,所述引射器的出口与燃煤锅炉的空气入口之间设置有压缩机。Preferably, a compressor is provided between the outlet of the ejector and the air inlet of the coal-fired boiler.

与现有技术相比,本实用新型的有益效果是:Compared with the prior art, the beneficial effects of the present utility model are:

本实用新型提供的一种利用烟气低温余热提高锅炉效率的系统,能够通过回收湿法脱硫塔内脱硫浆液的热量达到深度回收烟气余热的目的,提高能源利用效率;将引射器排出的尾气送入燃煤锅炉的空气入口,与空气混合,使进入锅炉的空气含湿量增加,并使空气含氧量降低,降低了锅炉内煤粉火焰绝对燃烧温度,从而降低NOx的生成量;利用闪蒸器能够通过闪蒸的方法从脱硫浆液提取大量水蒸气,水蒸气凝结后形成的凝结水水质良好,可以作为电厂系统补水,减小电厂水耗;脱硫浆液闪蒸后,实现了脱硫浆液的蒸发冷却,冷浆液喷淋烟气后可大幅降低离开脱硫塔的烟气温度与含水率,实现了消除白色烟羽视觉污染的目的;本实用新型结构简单、成本低、通用性强。The utility model provides a system for improving boiler efficiency by utilizing low-temperature waste heat of flue gas, which can achieve the purpose of deep recovery of waste heat of flue gas by recovering the heat of desulfurization slurry in a wet desulfurization tower, thereby improving energy utilization efficiency; The exhaust gas is sent to the air inlet of the coal-fired boiler and mixed with air, which increases the moisture content of the air entering the boiler and reduces the oxygen content of the air, which reduces the absolute combustion temperature of the pulverized coal flame in the boiler, thereby reducing the generation of NOx; The flash evaporator can extract a large amount of water vapor from the desulfurization slurry by flashing, and the condensed water formed after the condensation of the water vapor is of good quality, which can be used as water supply for the power plant system to reduce the water consumption of the power plant; after the desulfurization slurry is flashed, the desulfurization slurry is realized. The evaporative cooling of the cold slurry can greatly reduce the temperature and moisture content of the flue gas leaving the desulfurization tower after spraying the flue gas with the cold slurry, and realize the purpose of eliminating the visual pollution of white smoke plumes; the utility model has the advantages of simple structure, low cost and strong versatility.

附图说明Description of drawings

图1本实用新型涉及的系统结构示意图。Figure 1 is a schematic diagram of the system structure involved in the present invention.

具体实施方式Detailed ways

下面结合附图,对本实用新型进一步详细说明。The present utility model will be further described in detail below in conjunction with the accompanying drawings.

如图1所示,本实用新型提供的一种利用烟气低温余热提高锅炉效率的系统,包括燃煤锅炉1、除尘器2、引风机3、湿法脱硫塔4、第一浆液泵5、闪蒸塔6、第二浆液泵7、烟囱8、引射器9、汽轮机10、压缩机11和冷凝器12,其中,燃煤锅炉1的烟气出口连接除尘器2的入口,除尘器2的出口经过引风机3连接湿法脱硫塔4的底部入口,湿法脱硫塔4的底部脱硫浆液出口经过第一浆液泵5与闪蒸塔6的入口连接;湿法脱硫塔4顶部的烟气连接烟囱8。As shown in Figure 1, the utility model provides a system for improving boiler efficiency by utilizing low-temperature waste heat of flue gas, including a coal-fired boiler 1, a dust collector 2, an induced draft fan 3, a wet desulfurization tower 4, a first slurry pump 5, The flash tower 6, the second slurry pump 7, the chimney 8, the ejector 9, the steam turbine 10, the compressor 11 and the condenser 12, wherein the flue gas outlet of the coal-fired boiler 1 is connected to the inlet of the dust collector 2, and the dust collector 2 The outlet is connected to the bottom inlet of the wet desulfurization tower 4 through the induced draft fan 3, and the desulfurization slurry outlet at the bottom of the wet desulfurization tower 4 is connected to the inlet of the flash tower 6 through the first slurry pump 5; the flue gas at the top of the wet desulfurization tower 4 is connected. Connect chimney 8.

闪蒸塔6的冷浆液出口经过第二浆液泵7与湿法脱硫塔4顶部的冷浆液入口连接。The cold slurry outlet of the flash tower 6 is connected to the cold slurry inlet of the top of the wet desulfurization tower 4 through the second slurry pump 7 .

闪蒸塔6的负压蒸汽出口分为两路,一路与冷凝器12的入口连接,冷凝器12上设置有冷凝水出口;另一路与引射器9的蒸汽入口连接。The negative pressure steam outlet of the flash tower 6 is divided into two paths, one is connected to the inlet of the condenser 12 , which is provided with a condensed water outlet; the other is connected to the steam inlet of the ejector 9 .

燃煤锅炉1的蒸汽出口连接汽轮机10的入口,汽轮机10中部设置有抽汽口,所述抽汽口连接引射器9的抽汽入口,引射器9的出口经过压缩机11连接燃煤锅炉1的空气入口。The steam outlet of the coal-fired boiler 1 is connected to the inlet of the steam turbine 10. The steam turbine 10 is provided with a steam extraction port in the middle. Air inlet of boiler 1.

汽轮机10上设置的乏汽出口连接冷凝器12的入口。The exhausted steam outlet provided on the steam turbine 10 is connected to the inlet of the condenser 12 .

该系统的工作过程:The working process of the system:

燃煤锅炉1产生的烟气经过除尘器2,再由引风机3送入湿法脱硫塔4中,烟气在湿法脱硫塔4内与顶部喷淋下来的脱硫浆液发生脱硫反应,同时降温增湿。The flue gas generated by the coal-fired boiler 1 passes through the dust collector 2, and then is sent to the wet desulfurization tower 4 by the induced draft fan 3. The flue gas in the wet desulfurization tower 4 undergoes a desulfurization reaction with the desulfurization slurry sprayed from the top, and the temperature is lowered at the same time. Humidify.

湿法脱硫塔4底部出口脱硫浆液经过第一浆液泵5送入闪蒸塔6,闪蒸塔6内脱硫浆液经过蒸发冷却过程,闪蒸出负压蒸汽,同时降温成为冷浆液,所述冷浆液经过第二浆液泵7送入湿法脱硫塔4,从顶部喷淋至塔内,经过喷淋及脱硫反应后烟气经过除雾器,离开湿法脱硫塔4,送入烟囱8,排入大气。The desulfurization slurry at the bottom outlet of the wet desulfurization tower 4 is sent to the flash tower 6 through the first slurry pump 5, and the desulfurization slurry in the flash tower 6 undergoes an evaporative cooling process to flash out negative pressure steam, and at the same time cool down to become a cold slurry. The slurry is sent to the wet desulfurization tower 4 through the second slurry pump 7, and sprayed from the top into the tower. After spraying and desulfurization reaction, the flue gas passes through the mist eliminator, leaves the wet desulfurization tower 4, and is sent to the chimney 8. into the atmosphere.

燃煤锅炉1产生的蒸汽送入汽轮机10发电,汽轮机10的中部设置抽汽口,抽汽送入引射器9,并在引射器9内产生负压,汽轮机10的乏汽送至凝汽器12。The steam generated by the coal-fired boiler 1 is sent to the steam turbine 10 to generate electricity. A steam extraction port is arranged in the middle of the steam turbine 10, and the extracted steam is sent to the ejector 9, and negative pressure is generated in the ejector 9, and the exhausted steam of the steam turbine 10 is sent to the condensing device. Steamer 12.

闪蒸塔6产生的一部分负压蒸汽在压差作用下进入引射器9,与汽轮机抽汽混合后再由压缩机11加热后混合进入燃煤锅炉1的空气;闪蒸塔6产生的另一部分负压蒸汽在冷凝器12中冷凝,形成凝结水。A part of the negative pressure steam generated by the flash tower 6 enters the ejector 9 under the action of the pressure difference, and is mixed with the extraction steam of the steam turbine and then heated by the compressor 11 and mixed into the air of the coal-fired boiler 1; A portion of the negative pressure steam is condensed in the condenser 12 to form condensed water.

Claims (7)

1. A system for improving boiler efficiency by using low-temperature waste heat of flue gas is characterized by comprising a coal-fired boiler (1), a dust remover (2), a wet desulphurization tower (4), a flash tower (6), an ejector (9) and a steam turbine (10), wherein a flue gas outlet of the coal-fired boiler (1) is connected with an inlet of the dust remover (2), an outlet of the dust remover (2) is connected with a bottom inlet of the wet desulphurization tower (4), and a bottom desulphurization slurry outlet of the wet desulphurization tower (4) is connected with an inlet of the flash tower (6); a cold slurry outlet of the flash tower (6) is connected with a cold slurry inlet at the top of the wet desulphurization tower (4); a negative pressure steam outlet of the flash tower (6) is connected with a steam inlet of the ejector (9); the steam outlet of the coal-fired boiler (1) is connected with the inlet of a steam turbine (10), the middle part of the steam turbine (10) is provided with a steam extraction port, the steam extraction port is connected with the steam extraction inlet of an ejector (9), and the outlet of the ejector (9) is connected with the air inlet of the coal-fired boiler (1).
2. The system for improving the efficiency of the boiler by utilizing the low-temperature waste heat of the flue gas as claimed in claim 1, wherein an induced draft fan (3) is arranged between the outlet of the dust remover (2) and the bottom inlet of the wet desulphurization tower (4).
3. The system for improving the efficiency of the boiler by utilizing the low-temperature waste heat of the flue gas as claimed in claim 1, wherein a first slurry pump (5) is arranged between the outlet of the bottom desulfurization slurry of the wet desulfurization tower (4) and the inlet of the flash tower (6).
4. The system for improving the efficiency of the boiler by utilizing the low-temperature waste heat of the flue gas as claimed in claim 1, wherein a flue gas outlet is arranged at the top of the wet desulphurization tower (4), and a chimney (8) is connected to the flue gas outlet.
5. The system for improving the efficiency of the boiler by utilizing the low-temperature waste heat of the flue gas as claimed in claim 1, wherein a second slurry pump (7) is arranged between the cold slurry outlet of the flash tower (6) and the cold slurry inlet at the top of the wet desulphurization tower (4).
6. The system for improving the efficiency of the boiler by utilizing the low-temperature waste heat of the flue gas as claimed in claim 1, wherein a condenser (12) is further connected to a negative pressure steam outlet of the flash tower (6); and a dead steam outlet arranged on the steam turbine (10) is connected with a condenser (12).
7. The system for improving the efficiency of the boiler by utilizing the low-temperature waste heat of the flue gas as claimed in claim 1, wherein a compressor (11) is arranged between the outlet of the ejector (9) and the air inlet of the coal-fired boiler (1).
CN201922203679.5U 2019-12-10 2019-12-10 A system for improving boiler efficiency by utilizing low temperature waste heat of flue gas Active CN211146548U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922203679.5U CN211146548U (en) 2019-12-10 2019-12-10 A system for improving boiler efficiency by utilizing low temperature waste heat of flue gas

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922203679.5U CN211146548U (en) 2019-12-10 2019-12-10 A system for improving boiler efficiency by utilizing low temperature waste heat of flue gas

Publications (1)

Publication Number Publication Date
CN211146548U true CN211146548U (en) 2020-07-31

Family

ID=71777364

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922203679.5U Active CN211146548U (en) 2019-12-10 2019-12-10 A system for improving boiler efficiency by utilizing low temperature waste heat of flue gas

Country Status (1)

Country Link
CN (1) CN211146548U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110864324A (en) * 2019-12-10 2020-03-06 中国华能集团清洁能源技术研究院有限公司 System and method for improving boiler efficiency by using low-temperature waste heat of flue gas
CN115898970A (en) * 2022-10-31 2023-04-04 华能(上海)电力检修有限责任公司 An energy storage system for reducing power consumption of induced draft fans of coal-fired boilers

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110864324A (en) * 2019-12-10 2020-03-06 中国华能集团清洁能源技术研究院有限公司 System and method for improving boiler efficiency by using low-temperature waste heat of flue gas
CN115898970A (en) * 2022-10-31 2023-04-04 华能(上海)电力检修有限责任公司 An energy storage system for reducing power consumption of induced draft fans of coal-fired boilers

Similar Documents

Publication Publication Date Title
CN110425902A (en) Flue gas waste heat recycling system and method after wet desulphurization
CN110864324A (en) System and method for improving boiler efficiency by using low-temperature waste heat of flue gas
CN105909330B (en) A kind of flue gas waste heat recovery and smoke processing system based on Organic Rankine Cycle
CN111396913A (en) System and method for recovering flue gas waste heat and moisture of coal-fired unit
CN110864342A (en) Water replenishing system and method for indirectly heating heat supply network by using low-temperature waste heat of flue gas
CN109237505A (en) The device and its working method that water disappears white are received in a kind of classification waste heat recycling condensation of flue gas
CN110375325A (en) A kind of gas fired-boiler flue gas disappears white and advanced recycling system for waste heat completely
CN207379110U (en) A kind of energy-saving and water-saving type coal-burning boiler wet flue gas depth total system
CN111594813A (en) A combined cycle high-efficiency clean power generation device and method utilizing low-temperature latent heat of flue gas
CN109945277A (en) An energy-saving system using electric heat pump to deeply recover waste heat from flue gas of thermal power plant for central heating
CN212057351U (en) Recovery system of residual heat of flue gas and moisture of coal-fired unit
CN113998751A (en) System for desulfurization slurry flash distillation is carried hot water intaking
CN211204094U (en) Utilize air and condensate water to eliminate power station waste heat utilization system of white cigarette in coordination
CN211119603U (en) A system for indirect heating of flue gas with low temperature waste heat and water supply for heating network
CN210512728U (en) Flue gas waste heat recovery utilizes system after wet flue gas desulfurization
CN210638065U (en) Gas boiler flue gas is totally disappeared white and waste heat degree of depth recycle system
CN209464819U (en) A kind of flue gas of energy-saving hot water coproduction disappears white device
CN115183306A (en) System and method for supplying heat by virtue of desulfurization slurry flash evaporation and solar energy complementation
CN110006063A (en) A deep utilization system of flue gas waste heat of coal-fired boiler with desulfurization tower
CN105509038A (en) Bubbling fluidized bed O2/H2O pressurized oxygen-enriched combustion system
CN114151822A (en) System and method for preheating pulverized coal by flash evaporation and heat extraction of desulfurization slurry
CN201723313U (en) Gas turbine combined cycling device for distributed air and fuel humidification
CN211651283U (en) A device for deep recovery of waste heat from boiler flue gas and air humidification
CN217763601U (en) System for complementary heat supply of desulfurization thick liquid flash distillation and solar energy
CN212226984U (en) Combined-cycle efficient clean power generation device utilizing low-temperature latent heat of flue gas

Legal Events

Date Code Title Description
GR01 Patent grant