CN211046139U - Integrated distribution box - Google Patents
Integrated distribution box Download PDFInfo
- Publication number
- CN211046139U CN211046139U CN201922108697.5U CN201922108697U CN211046139U CN 211046139 U CN211046139 U CN 211046139U CN 201922108697 U CN201922108697 U CN 201922108697U CN 211046139 U CN211046139 U CN 211046139U
- Authority
- CN
- China
- Prior art keywords
- chamber
- box
- box body
- distribution box
- partition
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Patch Boards (AREA)
Abstract
本实用新型提供了一种综合配电箱,包括箱体,箱体内设有:第一隔板和第二隔板,两隔板自左至右间隔布置,将箱体分隔成自左至右布置的第一、第二和第三腔室;进出线单元,安装在第一腔室内,包括进线开关、出线开关、汇流排;计量单元,安装在第二腔室和第三腔室的其中一个腔室内;无功补偿单元,安装在第二腔室和第三腔室的另外一个腔室内;第二或第三腔室内预留有用于安装智能配变终端的安装空间。有益效果:将计量单元和无功补偿单元分开,避免结构过于集中,方便走线布置,走线更加美观,线路更加简洁,方便安装和检修操作。
The utility model provides an integrated distribution box, comprising a box body, the box body is provided with: a first partition plate and a second partition plate, the two partition plates are arranged at intervals from left to right, and the box body is divided into from left to right The first, second and third chambers arranged on the right; the incoming and outgoing line unit, installed in the first chamber, including the incoming line switch, the outgoing line switch, the busbar; the metering unit, installed in the second and third chambers In one of the chambers; the reactive power compensation unit is installed in the other chamber of the second chamber and the third chamber; the second or third chamber has reserved installation space for installing the intelligent distribution transformer terminal. Beneficial effects: The metering unit and the reactive power compensation unit are separated to avoid excessive concentration of the structure, facilitate the wiring arrangement, the wiring is more beautiful, the wiring is more concise, and the installation and maintenance operations are convenient.
Description
技术领域technical field
本实用新型涉及一种综合配电箱。The utility model relates to an integrated distribution box.
背景技术Background technique
综合配电箱是按照电气接线要求将低压开关设备、计量和测量装置、保护电器和辅助设备组装在封闭箱体中,从而构成的一种集计量、测量、控制、保护、电能分配、无功补偿等功能于一体的新型综合配电设备。The integrated distribution box is a kind of integrated metering, measurement, control, protection, electric energy distribution, reactive power distribution box, which is assembled in a closed box body according to the electrical wiring requirements. Compensation and other functions in one of the new integrated power distribution equipment.
例如授权公告号为CN204258076U的中国实用新型专利所公开的一种配电柜,包括柜体和柜门,柜体由纵向隔板分成左右两个腔室,在其中一个腔室的左上方设置有进线汇流排、右上方设置有负荷隔离开关、中部设置有出线汇流排、下方设置有断路器,在另一个腔室的上方设置有中央控制单元、下方设置有智能电容器。其中,进线汇流排上设置有低压进线端和电流互感器,低压进线端通过进线汇流排与负荷隔离开关进线端相连,负荷隔离开关出线端通过出线汇流排与断路器进线端相连,断路器出线端分别连接中央控制单元、智能电容器进线端。For example, a power distribution cabinet disclosed in a Chinese utility model patent with an authorization announcement number of CN204258076U includes a cabinet body and a cabinet door. The cabinet body is divided into two left and right chambers by a longitudinal partition, and a chamber is provided on the upper left of one of the chambers. The incoming busbar has a load isolating switch at the upper right, an outgoing busbar in the middle, a circuit breaker at the bottom, a central control unit above another chamber, and a smart capacitor at the bottom. Among them, the incoming busbar is provided with a low-voltage incoming terminal and a current transformer, the low-voltage incoming terminal is connected to the incoming terminal of the load isolation switch through the incoming busbar, and the outgoing terminal of the load isolation switch is connected to the incoming wire of the circuit breaker through the outgoing busbar. The outgoing end of the circuit breaker is connected to the central control unit and the incoming end of the intelligent capacitor respectively.
上述配电柜将补偿装置、计量器和中央控制单元设置在一个腔室中,结构过于集中,这样会造成走线不美观,线路比较杂乱,不方便安装以及检修操作。另外,用户在购得配电柜后,有时需要根据实际需求来配装合适的智能配变终端,上述配电柜内的中央控制单元必定只能满足部分用户的需求,致使配电柜的适用范围有限。In the above power distribution cabinet, the compensation device, the meter and the central control unit are arranged in one chamber, and the structure is too concentrated, which will cause unsightly wiring, cluttered wiring, and inconvenient installation and maintenance operations. In addition, after purchasing the power distribution cabinet, users sometimes need to assemble suitable intelligent distribution transformer terminals according to actual needs. The central control unit in the above power distribution cabinet must only meet the needs of some users, resulting in the application Limited scope.
实用新型内容Utility model content
本实用新型的目的在于提供一种综合配电箱,以解决现有技术中的配电柜由于将补偿装置、计量器和中央控制单元设置在一个腔室中而造成走线不美观、线路比较杂乱、不方便安装以及检修操作,同时还造成适用范围受限的问题。The purpose of this utility model is to provide a comprehensive distribution box, so as to solve the problem of unsightly wiring and comparison of lines caused by disposing the compensation device, the meter and the central control unit in one chamber in the distribution cabinet in the prior art. It is messy, inconvenient for installation and maintenance, and it also causes the problem of limited scope of application.
为实现上述目的,本实用新型中的采用如下技术方案:To achieve the above object, the following technical solutions are adopted in the present utility model:
综合配电箱,包括箱体和箱门,箱体内设置有:The integrated distribution box, including the box body and the box door, is provided with:
第一隔板和第二隔板,两隔板竖置且自左至右间隔布置,以将箱体分隔成自左至右依次布置的第一腔室、第二腔室和第三腔室;The first partition and the second partition, the two partitions are vertically arranged and spaced from left to right, so as to divide the box into a first chamber, a second chamber and a third chamber arranged in sequence from left to right ;
进出线单元,安装在第一腔室内,进出线单元包括进线开关、出线开关、连接进线开关和出线开关的汇流排;The incoming and outgoing line unit is installed in the first chamber, and the incoming and outgoing line unit includes an incoming line switch, an outgoing line switch, and a bus bar connecting the incoming line switch and the outgoing line switch;
计量单元,安装在第二腔室和第三腔室的其中一个腔室内;a metering unit, installed in one of the second chamber and the third chamber;
无功补偿单元,安装在第二腔室和第三腔室的另外一个腔室内;The reactive power compensation unit is installed in another chamber of the second chamber and the third chamber;
其中,第二腔室或者第三腔室内预留有用于安装智能配变终端的安装空间。Wherein, an installation space for installing an intelligent distribution transformer terminal is reserved in the second chamber or the third chamber.
上述技术方案的有益效果在于:箱体内由第一隔板和第二隔板隔开成三个腔室,进出线单元安装在第一腔室内,计量单元安装在第二腔室和第三腔室的其中一个腔室内,无功补偿单元安装在第二腔室和第三腔室的另外一个腔室内,这样就将计量单元和无功补偿单元分开,避免结构过于集中,从而方便走线的布置,能够使走线更加美观,线路更加简洁,方便安装和检修操作。同时,在第二腔室或者第三腔室内预留有用于安装智能配变终端的安装空间,也就是说没有将智能配变终端直接安装在箱体内,这样用户在购得配电柜后,可以根据实际需求配装合适的智能配变终端,可选性更多,因此本实用新型的综合配电箱拥有更大的适用范围。The beneficial effect of the above technical solution is that: the box is divided into three chambers by the first partition plate and the second partition plate, the incoming and outgoing line unit is installed in the first chamber, and the metering unit is installed in the second chamber and the third chamber In one of the chambers of the chamber, the reactive power compensation unit is installed in the second chamber and the other chamber of the third chamber, so that the metering unit and the reactive power compensation unit are separated to avoid the structure being too concentrated, so as to facilitate the wiring. The layout can make the wiring more beautiful, the line is more concise, and the installation and maintenance operations are convenient. At the same time, there is an installation space reserved for the installation of the intelligent distribution transformer terminal in the second chamber or the third chamber, that is to say, the intelligent distribution transformer terminal is not directly installed in the box, so that after purchasing the power distribution cabinet, the user can Appropriate intelligent distribution and transformer terminals can be equipped according to actual needs, and there are more options, so the integrated distribution box of the present invention has a larger scope of application.
进一步的,为了方便形成安装空间,使布局更加合理,方便后期安装智能配变终端,第二腔室内设置有横置的第三隔板,以使第二腔室具有上部空间和下部空间,计量单元安装在第二腔室的上部空间内,所述安装空间由第二腔室的下部空间构成,无功补偿单元安装在第三腔室内。Further, in order to facilitate the formation of the installation space, make the layout more reasonable, and facilitate the later installation of the intelligent distribution transformer terminal, a horizontal third partition is arranged in the second chamber, so that the second chamber has an upper space and a lower space for metering. The unit is installed in the upper space of the second chamber, the installation space is constituted by the lower space of the second chamber, and the reactive power compensation unit is installed in the third chamber.
进一步的,为了方便无功补偿单元的配置和安装,无功补偿单元包括塑壳断路器和智能电容器,塑壳断路器位于智能电容器的上方,塑壳断路器的进线端通过引出电缆与所述汇流排连接,塑壳断路器的出线端与智能电容器连接,所述引出电缆贯穿第一隔板和第二隔板。Further, in order to facilitate the configuration and installation of the reactive power compensation unit, the reactive power compensation unit includes a molded case circuit breaker and a smart capacitor. The molded case circuit breaker is located above the smart capacitor. The busbar is connected, the outgoing end of the molded case circuit breaker is connected to the smart capacitor, and the outgoing cable penetrates the first partition and the second partition.
进一步的,为了方便测量电流、电压等数据,第三腔室内于塑壳断路器的上方还设置有测量仪表。Further, in order to facilitate the measurement of current, voltage and other data, a measuring instrument is also provided above the molded case circuit breaker in the third chamber.
进一步的,为了方便进出线,同时方便对第三腔室内的器件进行安装和检修,箱体的左侧壁上设置有供进线电缆穿过的进线弯管、供出线电缆穿过的出线弯管,箱体的右侧壁上设置有侧门。Further, in order to facilitate the incoming and outgoing lines, and at the same time to facilitate the installation and maintenance of the devices in the third chamber, the left side wall of the box is provided with an incoming line elbow for the incoming line cable to pass through, and an outgoing line for the outgoing line cable to pass through. A side door is provided on the right side wall of the box body.
进一步的,为了增加更多出线的选择,箱体的底壁上设置有出线孔。Further, in order to increase the selection of more outlet cables, outlet holes are provided on the bottom wall of the box body.
进一步的,为了保证综合配电箱的散热效果,箱体的左侧壁以及后侧壁上均设置有散热口。Further, in order to ensure the heat dissipation effect of the integrated distribution box, the left side wall and the rear side wall of the box body are provided with heat dissipation ports.
附图说明Description of drawings
图1为本实用新型中综合配电箱的内部结构示意图(主视);Fig. 1 is the internal structure schematic diagram (front view) of the integrated distribution box in the utility model;
图2为本实用新型中综合配电箱的内部结构示意图(左视);Figure 2 is a schematic diagram of the internal structure of the integrated distribution box in the utility model (left view);
图3为本实用新型中综合配电箱的外观图(主视);Fig. 3 is the appearance drawing (front view) of the integrated distribution box in the utility model;
图4为本实用新型中综合配电箱的外观图(右视);Fig. 4 is the appearance drawing (right side view) of the integrated distribution box in the utility model;
图5为本实用新型中综合配电箱的外观图(左视);Fig. 5 is the appearance diagram (left view) of the integrated distribution box in the utility model;
图6为本实用新型中综合配电箱的外观图(后视);Fig. 6 is the appearance drawing (rear view) of the integrated distribution box in the utility model;
图7为本实用新型中综合配电箱的外观图(仰视)。FIG. 7 is an external view of the integrated distribution box in the utility model (viewed from the bottom).
图中:1-进线开关;2-第一腔室;3-第一隔板;4-电能表;5-第二腔室;6-测量仪表;7-侧门;8-接线盒;9-塑壳断路器;10-第三隔板;11-第三腔室;12-第二隔板;13-安装空间;14-智能电容器;15-出线弯管;16-出线开关;17-汇流排;18-进线弯管;19-固定板;20-防雨帽顶;21-前门;22-吊装件;23-侧部散热口;24-后部散热口;25-出线孔。In the figure: 1- incoming switch; 2- first chamber; 3- first partition plate; 4- electric energy meter; 5- second chamber; 6- measuring instrument; 7- side door; 8- junction box; 9 -Molded case circuit breaker; 10-Third partition; 11-Third chamber; 12-Second partition; 13-Installation space; 14-Intelligent capacitor; 15-Outlet elbow; 16-Outlet switch; 17- Busbar; 18-Inlet elbow; 19-Fixed plate; 20-Rain cap top; 21-Front door; 22-Lifting piece; 23-Side cooling vent;
具体实施方式Detailed ways
本实用新型中综合配电箱的一个实施例如图1和图3所示,包括箱体和设置在箱体前侧的前门21,箱体内自左至右间隔布置有第一隔板3和第二隔板12,两隔板竖置,将箱体分隔成自左至右依次布置的第一腔室2、第二腔室5和第三腔室11。An embodiment of the integrated distribution box in the present utility model is shown in FIG. 1 and FIG. 3 , including a box body and a
第一腔室2内安装有进出线单元,进出线单元包括进线开关1、出线开关16、连接进线开关1和出线开关16的汇流排17,进线开关1和出线开关16安装在同一个腔室内,并且上下布置,这样可以减少汇流排17的使用,节省成本。结合图2所示,第一腔室2内固定有固定板19,进线开关1和出线开关16均安装在固定板19上,固定板19距离箱体后侧壁有较小的间距,使得进线开关1和出线开关16靠近箱体后侧壁设置。如图6所示,箱体后侧壁上设置有后部散热口24,从而可以方便对箱体内的器件进行散热。An incoming and outgoing line unit is installed in the
第二腔室5内设置有横置的第三隔板10,第三隔板10将第二腔室5内分隔成上部空间和下部空间,其中上部空间内安装有计量单元,计量单元包括接线盒8和电能表4,其中接线盒8通过引出线缆与安装在进线开关1进线端上的计量互感器(图中未示出)连接,该引出线缆贯穿第一隔板3,电能表4与接线盒8连接。第二腔室5的下部空间作为预留的用于安装智能配变终端的安装空间。A horizontal
第三腔室11内安装有无功补偿单元,无功补偿单元包括塑壳断路器9和智能电容器14,塑壳断路器9位于智能电容器14的上方,塑壳断路器9的进线端通过引出电缆与汇流排17连接,该引出电缆贯穿第一隔板3和第二隔板12,塑壳断路器9的出线端与智能电容器14连接。A reactive power compensation unit is installed in the
第三腔室11内于塑壳断路器9的上方还设置有测量仪表6,测量仪表6主要是一些电流表和电压表,测量仪表6通过引出线缆与安装在进线开关1进线端上的测量互感器(图中未示出)连接,该引出电缆贯穿第一隔板3和第二隔板12。In the
如图5所示,箱体左侧壁上设置有供进线电缆穿过的进线弯管18、供出线电缆穿过的出线弯管15,同时箱体左侧壁上还设置有侧部散热口23,方便对箱体内的器件进行散热。如图7所示,箱体底壁上设置有出线孔25,使用时,用户可以根据需要选择出线孔25或者是出线弯管15作为出线结构。As shown in Figure 5, the left side wall of the box body is provided with an
如图4所示,箱体的右侧壁上设置有侧门7,方便对第三腔室11内的器件进行检修。如图3所示,箱体顶部设置有防雨帽顶20和吊装件22。As shown in FIG. 4 , a
本实用新型的综合配电箱设计有三个自左至右排布的腔室,箱体在前后方向上的深度比较浅,所有元器件都靠近箱体后侧壁设置,箱体后侧壁以及左侧壁上均设置有散热口,方便散热。箱体的前侧设置有一对前门,打开这一对前门即能满足箱体内所有部件的安装和检修,同时在箱体右侧壁上设置有侧门,这样对于第三腔室内器件的检修操作具有更多的选择。The integrated distribution box of the utility model is designed with three chambers arranged from left to right, the depth of the box body in the front and rear directions is relatively shallow, all components are arranged close to the rear side wall of the box body, and the rear side wall of the box body and There are cooling vents on the left side wall to facilitate heat dissipation. The front side of the box is provided with a pair of front doors. Opening the pair of front doors can meet the installation and maintenance of all components in the box. At the same time, a side door is arranged on the right side wall of the box, so that the maintenance operation of the components in the third chamber has the more choices.
本实用新型的综合配电箱将计量单元和无功补偿单元分开,避免结构过于集中,从而方便走线的布置,能够使走线更加美观,线路更加简洁,方便安装和检修操作。同时,在第二腔室内预留有用于安装智能配变终端的安装空间,也就是说没有将智能配变终端直接安装在箱体内,这样用户在购得配电柜后,可以根据实际需求配装合适的智能配变终端,可选性更多,因此本实用新型的综合配电箱拥有更大的适用范围。The integrated distribution box of the utility model separates the metering unit and the reactive power compensation unit to avoid excessive concentration of the structure, thereby facilitating the arrangement of the wiring, making the wiring more beautiful, the wiring more concise, and convenient for installation and maintenance operations. At the same time, there is an installation space reserved in the second chamber for installing the intelligent distribution transformer terminal, that is to say, the intelligent distribution transformer terminal is not directly installed in the box, so that after purchasing the power distribution cabinet, the user can configure it according to actual needs. By installing a suitable intelligent distribution and transformation terminal, there are more options, so the integrated distribution box of the present invention has a larger scope of application.
在综合配电箱的其他实施例中,可以仅在箱体后侧壁上设置散热口,或者是在箱体左侧壁以及侧门上设置散热口。In other embodiments of the integrated distribution box, the cooling vents may be provided only on the rear side wall of the box, or the cooling vents may be provided on the left side wall and the side door of the box.
在综合配电箱的其他实施例中,箱体底壁上不设置出线孔,仅靠左侧壁上的出线弯管出线。In other embodiments of the integrated distribution box, no outlet holes are provided on the bottom wall of the box body, and only the outlet bends on the left side wall are used to outlet.
在综合配电箱的其他实施例中,箱体左侧壁上不设置进线弯管和出线弯管,仅是设置两个孔,作为进线和出线使用;或者是将进线孔设置在箱体顶壁上,出线孔设置在箱体底壁上。In other embodiments of the integrated distribution box, the incoming line elbow and the outgoing line elbow are not provided on the left side wall of the box, but only two holes are provided for the incoming and outgoing lines; On the top wall of the box body, the outlet holes are arranged on the bottom wall of the box body.
在综合配电箱的其他实施例中,箱体右侧壁上不设置侧门,仅靠前门实现安装和检修。In other embodiments of the integrated distribution box, the side door is not provided on the right side wall of the box body, and the installation and maintenance are realized only by the front door.
在综合配电箱的其他实施例中,根据一些用户的需求,第三腔室内也可以不设置测量仪表。In other embodiments of the integrated distribution box, according to the needs of some users, no measuring instrument may be provided in the third chamber.
在综合配电箱的其他实施例中,无功补偿单元也可以是投切开关和普通电容器的组合。In other embodiments of the integrated distribution box, the reactive power compensation unit may also be a combination of a switching switch and a common capacitor.
在综合配电箱的其他实施例中,根据实际情况,计量单元也可以不包括接线盒,电能表直接与安装在进线开关进线端上的计量互感器连接。In other embodiments of the integrated distribution box, according to the actual situation, the metering unit may not include a junction box, and the electric energy meter is directly connected to the metering transformer installed on the incoming end of the incoming switch.
在综合配电箱的其他实施例中,第二腔室内也可以不设置第三隔板,计量单元靠上安装,下部留出空间作为安装智能配变终端的安装空间。In other embodiments of the integrated distribution box, the third partition plate may not be provided in the second chamber, the metering unit is installed on the upper side, and a space is reserved at the lower part as the installation space for installing the intelligent distribution transformer terminal.
在综合配电箱的其他实施例中,当计量单元安装在第二腔室内时,根据第三腔室内的情况,可以在第三腔室内预留安装智能配变终端的安装空间。In other embodiments of the integrated distribution box, when the metering unit is installed in the second chamber, according to the situation in the third chamber, an installation space for installing the intelligent distribution transformer terminal can be reserved in the third chamber.
在综合配电箱的其他实施例中,计量单元也可以安装在第三腔室内,无功补偿单元安装在第二腔室内,此时根据情况,用于安装智能配变终端的安装空间可以预留在第二腔室内,也可以预留在第三腔室内。In other embodiments of the integrated distribution box, the metering unit can also be installed in the third chamber, and the reactive power compensation unit can be installed in the second chamber. It is left in the second chamber and can also be reserved in the third chamber.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201922108697.5U CN211046139U (en) | 2019-11-29 | 2019-11-29 | Integrated distribution box |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201922108697.5U CN211046139U (en) | 2019-11-29 | 2019-11-29 | Integrated distribution box |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN211046139U true CN211046139U (en) | 2020-07-17 |
Family
ID=71535291
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201922108697.5U Expired - Fee Related CN211046139U (en) | 2019-11-29 | 2019-11-29 | Integrated distribution box |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN211046139U (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110797772A (en) * | 2019-11-29 | 2020-02-14 | 河南华盛隆源电气有限公司 | Comprehensive distribution box |
| CN116073255A (en) * | 2022-12-13 | 2023-05-05 | 辽宁华隆电力科技股份有限公司 | Low-voltage comprehensive distribution box |
-
2019
- 2019-11-29 CN CN201922108697.5U patent/CN211046139U/en not_active Expired - Fee Related
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110797772A (en) * | 2019-11-29 | 2020-02-14 | 河南华盛隆源电气有限公司 | Comprehensive distribution box |
| CN116073255A (en) * | 2022-12-13 | 2023-05-05 | 辽宁华隆电力科技股份有限公司 | Low-voltage comprehensive distribution box |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN203278004U (en) | Compact Low Voltage Distribution Cabinet | |
| CN110336194A (en) | Low-voltage cabinet and miniaturization preassembled transformer station | |
| CN110212440A (en) | A kind of small-sized preassembled transformer station | |
| CN110797772A (en) | Comprehensive distribution box | |
| CN214100414U (en) | a meter box | |
| CN204680943U (en) | integrated distribution box | |
| CN210577091U (en) | Integrated intelligent substation platform and switch board thereof | |
| CN206470308U (en) | A kind of three-phase electric energy meter terminal box and the three-phase electric energy meter comprising the terminal box | |
| CN201656254U (en) | Pole top type low-voltage comprehensive distribution box | |
| CN209981867U (en) | Small-size prepackage type transformer substation | |
| CN207426487U (en) | A kind of rural power grids low-tension distribution box | |
| CN113691146B (en) | a converter | |
| CN220628832U (en) | Novel bus bar distribution system | |
| CN207398599U (en) | A kind of high density drawer type block terminal | |
| CN207339178U (en) | integrated distribution box | |
| CN221914050U (en) | Direct current fills electric pile | |
| CN206250599U (en) | A kind of GGD ZJ measure load integrated cabinet | |
| CN221928911U (en) | Bidirectional parallel system of power supply bus | |
| CN201868741U (en) | Anti-electricity-stealing low-voltage comprehensive metering cabinet | |
| CN209592690U (en) | A kind of improved low pressure inlet wire metering cabinet of structure | |
| CN215771930U (en) | A primary side cable wiring structure of a low-voltage drawer switch cabinet drawer | |
| CN223651808U (en) | A distributed energy storage system power distribution combiner cabinet | |
| CN211296229U (en) | Charging pile | |
| CN219677791U (en) | Copper bar assembly of distribution box and distribution box | |
| CN219077030U (en) | A charging power unit and charging pile |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20200717 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |