CN210978747U - Horizontal fixing device for blowout pipeline of well site - Google Patents

Horizontal fixing device for blowout pipeline of well site Download PDF

Info

Publication number
CN210978747U
CN210978747U CN201922175969.3U CN201922175969U CN210978747U CN 210978747 U CN210978747 U CN 210978747U CN 201922175969 U CN201922175969 U CN 201922175969U CN 210978747 U CN210978747 U CN 210978747U
Authority
CN
China
Prior art keywords
pipeline
pipe
straight tube
fixing device
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201922175969.3U
Other languages
Chinese (zh)
Inventor
黄龙
王欣云
牟春光
刘孟杰
高萌萌
刘亮
段宇
张祥
张斌
王晓亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201922175969.3U priority Critical patent/CN210978747U/en
Application granted granted Critical
Publication of CN210978747U publication Critical patent/CN210978747U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model discloses a horizontal fixing device of well site blowout pipeline, the pipeline for turning to department provides horizontal clamp force, restriction pipeline's radial movement, compensate the fixed defect that exists of current use steel checkpost, including straight tube and pipe chute, straight tube and pipe chute are connected by the elbow, it sets up a locating plate in straight tube and pipe chute lower part, welds two identical fixed stop above the locating plate, fixed stop can be tangent with the periphery of straight tube and pipe chute respectively, two identical U-shaped recesses are transversely seted up along the locating plate, set up two identical adjustable fender in the inside of U-shaped recess, fixed stop and adjustable fender are by the bolt-up.

Description

Horizontal fixing device for blowout pipeline of well site
Technical Field
The utility model relates to a pipeline anchor clamps specifically relate to a well site blowout pipeline horizontal fixation device.
Background
The blowout pipeline of the well site is used as an important component of well control equipment, plays a key role in well killing operation construction, generally comprises a pipeline, a short joint, an elbow, a bolt, a nut and other elements, and has the total length of nearly one hundred meters after connection.
At present, the main problems of the blowout pipeline are that leakage occurs due to untight sealing of a certain section of pipeline, particularly, leakage occurs mainly at the joint of an elbow, and at present, workers usually connect a horizontal pipeline and an inclined pipeline by using a 120-degree elbow, because media in the pipeline flow unevenly, threads of the elbow can be ground flat after the joint is impacted by the media for a long time, the sealing performance is reduced, leakage occurs, the environment is easily polluted, and the leaked gas easily harms the safety of people and livestock around.
The currently known fixing device is that the ground anchor is tied on the place with the interval of 5-10 meters, the ground anchor comprises a semicircular clip, the inner wall of the semicircular clip is provided with a rubber cushion, the rubber cushion is used for fastening after the pipeline is compressed, but the fixing clip is usually arranged on the top of the pipeline, the pipeline is fixed and compressed by a vertical bolt, the restriction on the horizontal movement of the pipeline is poor, when the pipeline swings horizontally, the vertical bolt bears the transverse alternating load because of the acting force of the medium in the pipeline, the bolt is easy to loosen after long-term work, the model of the pipeline is various, accordingly, the clips with various calibers need to be matched, and the defect of high cost and poor effect exists in the practical application process.
SUMMERY OF THE UTILITY MODEL
For solving the technical problem, the utility model provides a well site blowout pipeline horizontal fixation device provides horizontal clamp force for the pipeline that turns to the department, and the radial movement of restriction pipeline remedies the fixed defect that exists of current use steel checkpost.
The technical scheme is as follows: the horizontal fixing device for the blowout pipeline of the well site comprises a straight pipe and an inclined pipe, wherein the straight pipe and the inclined pipe are connected through an elbow, and the horizontal fixing device is characterized in that a positioning plate is arranged at the lower part of the straight pipe and the lower part of the inclined pipe, two identical fixed baffles are welded on the positioning plate, the fixed baffles can be tangent to the outer peripheries of the straight pipe and the inclined pipe respectively, two identical U-shaped grooves are transversely formed in the positioning plate, two identical movable baffles are arranged inside the U-shaped grooves, and the fixed baffles and the movable baffles are fixed through bolts.
Furthermore, the lower parts of the straight pipe and the inclined pipe are provided with bearing steel plates, and a damping spring is arranged between the bearing steel plates and the positioning plate.
Further, the side surfaces of the fixed baffle and the movable baffle are both provided with rubber gaskets.
Has the advantages that: the utility model discloses a through providing horizontal clamp force for the pipeline that turns to the department, can effectively restrict the radial movement of pipeline, eliminate the pipeline and lack the drawback of radial restraint when using current steel checkpost to fix, and this utility model simple structure, easy preparation.
Drawings
FIG. 1 is a schematic plane structure of the utility model;
FIG. 2 is a schematic elevation structure of the utility model;
description of reference numerals:
1. bending the pipe; 2. positioning a plate; 3. an inclined tube; 4. fixing a baffle plate; 5. a straight pipe; 6. a bolt; 7. a U-shaped groove; 8. a movable baffle; 9. a load-bearing steel plate; 10. a shock absorbing spring.
Detailed Description
The embodiments of the invention will be described in detail below with reference to the accompanying fig. 1 to 2, but the invention can be implemented in many different ways as defined and covered by the claims.
It should be noted that the following description of the embodiments refers to the accompanying drawings, in which like numerals refer to the same or similar elements throughout the different views, unless otherwise specified.
It is also to be understood that the following detailed description is exemplary and is intended to provide further explanation of the invention as claimed, unless otherwise specified, and all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this disclosure belongs.
Combine attached drawing 1 to attached drawing 2, the utility model provides a well site blowout pipeline horizontal fixation device, including straight tube 5 and pipe chute 3, straight tube 5 and pipe chute 3 are connected by elbow 1, and it is in the lower part of straight tube 5 and pipe chute 3 sets up a locating plate 2 two identical fixed stop 4 of the higher authority welding of locating plate 2, fixed stop 4 can respectively with the outer periphery of straight tube 5 and pipe chute 3 is tangent, two identical U-shaped recesses 7 are transversely seted up along locating plate 2U-shaped recess 7's inside sets up two identical adjustable fender 8, fixed stop 4 and adjustable fender 8 fixed by bolt 6.
By the structure of above-mentioned embodiment can discover, use bolt 6 to fasten fixed stop 4 and adjustable fender 8 after the staff, fixed stop 4 and adjustable fender 8 can provide radial clamp force for straight tube 5 and pipe chute 3, just so can avoid pipeline horizontal migration to remedy the defect that straight tube 5 and pipe chute 3 lack radial restraint, in the actual operation process, locating plate 2 can be fixed on the sandbox, also can fix on the concrete prefabricated member, the staff can confirm according to the topography at construction site.
With reference to fig. 1 to 2, the lower parts of the straight pipe 5 and the inclined pipe 3 are provided with bearing steel plates 9, and a damping spring 10 is arranged between the bearing steel plates 9 and the positioning plate 2.
The utility model discloses an in the above-mentioned embodiment, damping spring 10 that bearing steel sheet 9 and locating plate 2 set up can provide vertical buffering for straight tube 5 and pipe chute 3, and although straight tube 5 and pipe chute 3 have obtained radial clamp tightly, nevertheless lack the restraint in the vertical direction, so straight tube 5 and pipe chute 3 still appear the condition that the screw thread damaged easily at the position of being connected with elbow 1, utilize the characteristic that damping spring 10 possessed just can effectively solve this problem.
In the concrete implementation process, this utility model can also use with current steel checkpost cooperation, after using the steel checkpost to vertically compress tightly straight tube 5 and pipe chute 3, can set up this utility model within 0.5 meters to 1 meter with the steel checkpost interval.
To sum up, this utility model creatively has utilized fixed stop 4 and adjustable fender 8 cooperation to provide horizontal clamp force for the pipeline, compares with prior art, has the advantage of effectively restricting pipeline horizontal migration, simultaneously, this utility model simple structure, simple to operate still has easy preparation, advantage that the cost of manufacture is low.

Claims (3)

1. The utility model provides a horizontal fixing device of well site blowout pipeline, includes straight tube and pipe chute, and straight tube and pipe chute are connected characterized by the elbow: the positioning plate is characterized in that a positioning plate is arranged below a straight pipe and an inclined pipe, two identical fixed baffles are welded on the positioning plate, the side surfaces of the fixed baffles are tangent to the outer peripheries of the straight pipe and the inclined pipe, two identical U-shaped grooves are transversely formed in the positioning plate, two identical movable baffles are arranged in the U-shaped grooves, and the fixed baffles and the movable baffles are fixed through bolts.
2. The horizontal fixing device for the blowout pipeline of the well site as claimed in claim 1, wherein: and the lower parts of the straight pipe and the inclined pipe are provided with bearing steel plates, and a damping spring is arranged between the bearing steel plates and the positioning plate.
3. The horizontal fixing device for the blowout pipeline of the well site as claimed in claim 1, wherein: the side surfaces of the fixed baffle and the movable baffle are both provided with rubber gaskets.
CN201922175969.3U 2019-11-27 2019-11-27 Horizontal fixing device for blowout pipeline of well site Expired - Fee Related CN210978747U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922175969.3U CN210978747U (en) 2019-11-27 2019-11-27 Horizontal fixing device for blowout pipeline of well site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922175969.3U CN210978747U (en) 2019-11-27 2019-11-27 Horizontal fixing device for blowout pipeline of well site

Publications (1)

Publication Number Publication Date
CN210978747U true CN210978747U (en) 2020-07-10

Family

ID=71445481

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922175969.3U Expired - Fee Related CN210978747U (en) 2019-11-27 2019-11-27 Horizontal fixing device for blowout pipeline of well site

Country Status (1)

Country Link
CN (1) CN210978747U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111779915A (en) * 2020-07-16 2020-10-16 石研研 Basement electrical equipment pipeline hanger system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111779915A (en) * 2020-07-16 2020-10-16 石研研 Basement electrical equipment pipeline hanger system

Similar Documents

Publication Publication Date Title
CN210978747U (en) Horizontal fixing device for blowout pipeline of well site
CN201795174U (en) Fixing support for erecting and laying ductile iron pipes
CN107013753A (en) A kind of antidetonation vibration isolation support
CN204852619U (en) Can have enough to meet need pump line fixing device of use
CN209370602U (en) Pipeline of nuclear power plant damper mount connection structure
CN210068200U (en) Telescopic device for railway tunnel lining
CN114484084B (en) Pipeline support hanger and building structure with antidetonation bracing
CN105570545B (en) Industrial pipeline dynamic vibration absorber
RU176343U1 (en) Support is bandage unpacked
CN207864834U (en) High temperature resistant clip
CN206157907U (en) Antidetonation connecting piece
CN112253851A (en) Vibration damper for inhibiting vibration of high-frequency shell wall of pipeline
CN211203207U (en) Pipe fitting connecting hoop assembly
CN108561633A (en) A kind of steel shockproof pipe clamp
CN214093452U (en) Split flange plate
CN211624438U (en) Waterproof wall bushing structure with neutral surface provided with flexible dynamic seal assembly
CN210569371U (en) Ammonia refrigeration machine room pipeline system
CN207947578U (en) A kind of cable testing bridge antidetonation suspension and support
CN212617032U (en) Cast iron pipeline water-closing test tool
CN210106807U (en) Anti-seismic support air pipe flange clamp with longitudinal limiting capacity
CN208816867U (en) A kind of antidetonation pipeline branch suspension clamp
CN220904136U (en) PE four-way electrofusion welding protection device not affected by external force
CN213954552U (en) Temporary fire-fighting pipeline fixing device
CN215763924U (en) Low-temperature anti-vibration support used under strong vibration condition
CN216743135U (en) Air pipe anti-seismic support

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200710

Termination date: 20201127

CF01 Termination of patent right due to non-payment of annual fee