CN210947656U CN201921060886.3U CN201921060886U CN210947656U CN 210947656 U CN210947656 U CN 210947656U CN 201921060886 U CN201921060886 U CN 201921060886U CN 210947656 U CN210947656 U CN 210947656U
Authority
CN
China
Prior art keywords
double
stainless steel
escalator
bolt
pipe clamp
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921060886.3U
Other languages
Chinese (zh)
Inventor
张延年
王彬
秦桂娟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenyang Jianzhu University
Original Assignee
Shenyang Jianzhu University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenyang Jianzhu University filed Critical Shenyang Jianzhu University
Priority to CN201921060886.3U priority Critical patent/CN210947656U/en
Application granted granted Critical
Publication of CN210947656U publication Critical patent/CN210947656U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Ladders (AREA)
  • Escalators And Moving Walkways (AREA)

Abstract

一种双梯脚手架装置,属于施工设备领域,所述装置为在两扶梯之间设置施工平台,所述施工平台固定与两扶梯的横杆固定连接,所述扶梯与墙体之间设有支撑装置;所述支撑装置包括不锈钢压片、不锈钢钢管、双螺栓管夹,所述施工平台为两相互平行的矩形钢管一端与扶梯横杆经双螺栓管夹垂直相连,下端焊接由矩形钢管围城的三角形支架。本实用新型通过将施工平台搭设在两扶梯之间,施工平台与扶梯之间经双螺栓管夹连接,双螺栓管夹可拆卸,实现提升或者降低整个脚手架的高度,这样可以为建筑外墙施工作业和内墙装修的工作人员提供升降作业和工具的运输,使用起来十分的方便,同时也降低了成本。

Figure 201921060886

A double-ladder scaffolding device belongs to the field of construction equipment. The device is to set up a construction platform between two escalators, the construction platform is fixedly connected to the crossbars of the two escalators, and a support is provided between the escalator and the wall. The supporting device includes stainless steel sheet, stainless steel steel pipe, and double-bolt pipe clamp, and the construction platform is two mutually parallel rectangular steel pipes. Triangular bracket. In the utility model, the construction platform is erected between two escalators, the construction platform and the escalator are connected by a double-bolt pipe clamp, and the double-bolt pipe clamp can be disassembled, so that the height of the whole scaffold can be raised or lowered, which can be used for the construction of the exterior wall of the building. The staff of the operation and interior wall decoration provide lifting operations and transportation of tools, which are very convenient to use and reduce costs at the same time.

Figure 201921060886

Description

一种双梯脚手架装置A double ladder scaffolding device

技术领域technical field

本发明属于施工设备领域,具体涉及一种双梯脚手架装置。The invention belongs to the field of construction equipment, in particular to a double-ladder scaffolding device.

背景技术Background technique

在建筑外墙作业或者内墙装修时门式脚手架使不可或缺的一种设备,他使用起来十分灵活、方便很多。它在施工现场可以为工人解决垂直和水平运输的问题。它还具有装拆简单,承载性能好,使用安全可靠等特点。Portal scaffolding is an indispensable equipment when working on exterior walls of buildings or decorating interior walls. It is very flexible and convenient to use. It can solve the problem of vertical and horizontal transportation for workers on the construction site. It also has the characteristics of simple assembly and disassembly, good bearing performance, and safe and reliable use.

但是门式脚手架在使用过程中它又存在许多问题,门式脚手架他的各个部件之间是互相配套的,它的大小高度不可以任意改变,这就造成了在施工过程中如果希望改变他的规格,那么只能重新购买合适大小的门式脚手架来适应施工的需要。操作起来十分不便,开销也会增大。However, there are many problems in the use of portal scaffolding. The various components of portal scaffolding are matched with each other, and its size and height cannot be changed arbitrarily, which results in the construction process if you want to change his Specifications, then you can only re-purchase portal scaffolding of suitable size to meet the needs of construction. It is very inconvenient to operate, and the cost will increase.

发明内容SUMMARY OF THE INVENTION

为了解决上述技术问题,本实用新型提供一种双梯脚手架装置,通过将施工平台搭设在两扶梯之间,施工平台与扶梯之间经双螺栓管夹连接,双螺栓管夹可拆卸,实现提升或者降低整个脚手架的高度,这样可以为建筑外墙施工作业和内墙装修的工作人员提供升降作业和工具的运输,使用起来十分的方便,同时也降低了成本。本实用新型In order to solve the above-mentioned technical problems, the utility model provides a double-ladder scaffolding device. By erecting a construction platform between two escalators, the construction platform and the escalator are connected by a double-bolt pipe clamp, and the double-bolt pipe clamp can be disassembled to realize lifting. Or reduce the height of the entire scaffolding, which can provide lifting operations and transportation of tools for the staff working on the exterior wall construction and interior wall decoration of the building, which is very convenient to use and reduces costs. The utility model

本实用新型采用的技术方案如下:The technical scheme adopted by the utility model is as follows:

一种双梯脚手架装置,所述装置包括扶梯、不锈钢压片、不锈钢钢管、双螺栓管夹、矩形钢管、膨胀螺栓、长矩形钢管,所述装置为在两扶梯之间设置施工平台,所述施工平台固定与两扶梯的横杆固定连接,可拆卸,所述扶梯与墙体之间设有支撑装置;所述支撑装置包括不锈钢压片、不锈钢钢管、双螺栓管夹,所述不锈钢压片为片状结构,其两端制有螺栓孔,所述不锈钢压片与墙体之间经膨胀螺栓固定相连,所述不锈钢压片中部焊接有与之垂直的不锈钢钢管,所述不锈钢钢管另一端焊接双螺栓管夹,所述双螺栓管夹与扶梯的横杆相连;所述施工平台为两相互平行的矩形钢管一端与扶梯横杆经双螺栓管夹垂直相连,左右两矩形钢管之间水平向垂直焊接长矩形钢管,二者焊接处竖向焊接矩形钢管,竖向的矩形钢管下端焊接由矩形钢管围城的三角形支架,所述两三角形矩形钢管之间上方为搭建平台,所述护栏与三角形支架与扶梯横杆连接处经双螺栓管夹固定连接,可拆卸。A double-ladder scaffolding device, the device comprises an escalator, a stainless steel sheet, a stainless steel steel pipe, a double-bolt pipe clamp, a rectangular steel pipe, an expansion bolt, and a long rectangular steel pipe, the device is to set a construction platform between the two escalators, and the The construction platform is fixedly connected to the crossbars of the two escalators and can be dismantled. A support device is provided between the escalator and the wall; the support device includes a stainless steel sheet, a stainless steel pipe, and a double-bolt pipe clamp. The stainless steel sheet It is a sheet-like structure with bolt holes at both ends. The stainless steel sheet and the wall are fixedly connected by expansion bolts. The middle of the stainless steel sheet is welded with a stainless steel pipe perpendicular to it, and the other end of the stainless steel pipe is Two-bolt pipe clamps are welded, and the two-bolt pipe clamps are connected with the crossbar of the escalator; the construction platform is two mutually parallel rectangular steel pipes and one end is vertically connected with the escalator crossbar through the double-bolt pipe clamps, and the left and right rectangular steel pipes are horizontally connected. Weld the long rectangular steel pipe vertically, the rectangular steel pipe is welded vertically at the welding place of the two, and the triangular bracket surrounded by the rectangular steel pipe is welded at the lower end of the vertical rectangular steel pipe. The upper part of the two triangular rectangular steel pipes is a building platform. The connection between the bracket and the escalator crossbar is fixedly connected by a double-bolt pipe clamp, which can be disassembled.

进一步地,所述不锈钢压片厚度为5mm。Further, the thickness of the stainless steel sheet is 5mm.

进一步地,所述双螺栓管夹厚度为3mm。Further, the thickness of the double-bolt pipe clamp is 3mm.

进一步地,所述矩形钢管管壁厚度为3mm。Further, the thickness of the wall of the rectangular steel pipe is 3mm.

进一步地,所述扶梯上下两侧开设有螺栓孔。Further, bolt holes are provided on the upper and lower sides of the escalator.

进一步地,所述双螺栓管夹(4)与扶梯(1)横杆连接处设置橡胶垫片。Further, a rubber gasket is provided at the connection between the double-bolt pipe clamp (4) and the cross bar of the escalator (1).

本实用新型的有益效果:The beneficial effects of the present utility model:

本装置采用上述设计,通过将施工平台搭设在两扶梯之间,施工平台与扶梯之间经双螺栓管夹连接,双螺栓管夹可拆卸,实现提升或者降低整个脚手架的高度,这样可以为建筑外墙施工作业和内墙装修的工作人员提供升降作业和工具的运输,使用起来十分的方便,同时也降低了成本。The device adopts the above-mentioned design. By erecting the construction platform between two escalators, the construction platform and the escalator are connected by double-bolt pipe clamps. The staff of the exterior wall construction work and the interior wall decoration provide lifting work and transportation of tools, which is very convenient to use and reduces the cost at the same time.

附图说明Description of drawings

图1 为双梯脚手架装置工作状态图;Figure 1 is the working state diagram of the double-ladder scaffolding device;

图2为脚手架支撑固定装置;Figure 2 is a scaffolding support fixture;

图3为 脚手架护栏固定装置;Figure 3 is the scaffolding guardrail fixing device;

图4 为双螺栓管夹结构示意图;Figure 4 is a schematic diagram of the structure of the double-bolt pipe clamp;

图5 为单片双螺栓管夹主视图。Figure 5 is the front view of the single-piece two-bolt pipe clamp.

图中部件:1扶梯、2不锈钢压片、3不锈钢钢管、4双螺栓管夹、5矩形钢管、6膨胀螺栓、7螺栓孔、8长矩形钢管、9螺栓。Parts in the picture: 1 escalator, 2 stainless steel sheet, 3 stainless steel steel pipe, 4 double-bolt pipe clamp, 5 rectangular steel pipe, 6 expansion bolts, 7 bolt holes, 8 long rectangular steel pipes, 9 bolts.

具体实施方式Detailed ways

为了进一步说明本实用新型,下面结合附图及实施例对本实用新型进行详细地描述,但不能将它们理解为对本实用新型保护范围的限定。In order to further illustrate the present utility model, the present utility model will be described in detail below with reference to the accompanying drawings and embodiments, but they should not be construed as limiting the protection scope of the present utility model.

一种双梯脚手架系统,不锈钢压片两端留孔,穿插膨胀螺栓固定于墙上,中间焊接不锈钢钢管,钢管另一端焊接双螺栓管夹,U型口正对另一个双螺栓管夹,两边留孔穿插螺栓,使其连接扶梯横杆,整个装置用来固定扶梯。取两根矩形钢管一端焊接双螺栓管夹,U型口正对另一个双螺栓管夹,两边留孔穿插螺栓,使其与扶梯横杆连接,另一端与另外一根钢管焊接成“F”型,另外取三根钢管,首尾相接焊接成三角形,把两者焊接在一起。两一个扶梯执行相同操作,中间用矩形钢管焊接,形成一个脚手架护栏以及一个脚手板的搭建平台。通过改变双螺栓管夹的位置可以提升或者降低整个脚手架的高度,这样可以为建筑外墙施工作业和内墙装修的工作人员提供升降作业和工具的运输。A double-ladder scaffolding system, holes are left at both ends of the stainless steel sheet, and expansion bolts are inserted to fix it on the wall, a stainless steel steel pipe is welded in the middle, a double-bolt pipe clamp is welded at the other end of the steel pipe, and the U-shaped opening is facing the other double-bolt pipe clamp. Leave holes and insert bolts to connect the escalator crossbar, and the whole device is used to fix the escalator. Take two rectangular steel pipes and weld a double-bolt pipe clamp at one end, the U-shaped mouth is facing the other double-bolt pipe clamp, leave holes on both sides to insert bolts to connect with the escalator crossbar, and weld the other end with another steel pipe to form "F" Type, take another three steel pipes, weld them end to end to form a triangle, and weld the two together. Two escalators perform the same operation, and are welded with rectangular steel pipes in the middle to form a scaffolding guardrail and a scaffolding platform. By changing the position of the double-bolt pipe clamp, the height of the entire scaffold can be raised or lowered, which can provide lifting operations and tool transportation for the construction and interior wall decoration workers of the building.

所述的不锈钢压片,厚度为5mm左右,为了给扶梯提供可靠的支撑。The thickness of the stainless steel sheet is about 5mm, in order to provide reliable support for the escalator.

所述的双螺栓管夹,厚度为3mm左右,双螺栓管夹需挂在扶梯的横杆上,厚度大则稳定性强。The thickness of the double-bolt pipe clamp is about 3mm, and the double-bolt pipe clamp needs to be hung on the cross bar of the escalator, and the greater the thickness, the stronger the stability.

所述的矩形钢管,管壁厚度为3mm左右,同样是为了保证整个脚手架的安全性。For the rectangular steel pipe, the thickness of the pipe wall is about 3mm, which is also to ensure the safety of the entire scaffold.

实施例1Example 1

一种双梯脚手架装置,包括扶梯1、不锈钢压片2、不锈钢钢管3、双螺栓管夹4、矩形钢管5、膨胀螺栓6、螺栓孔7、长矩形钢管8、螺栓9。A double-ladder scaffolding device comprises an escalator 1 , a stainless steel pressing sheet 2 , a stainless steel steel pipe 3 , a double-bolt pipe clamp 4 , a rectangular steel pipe 5 , an expansion bolt 6 , a bolt hole 7 , a long rectangular steel pipe 8 , and a bolt 9 .

所述扶梯1是长约4米的扶梯,并在两侧的上、下端各留一个螺栓孔7,当长度不够时可利用螺栓穿孔,连接另一个扶梯增加长度,方便作业。不锈钢压片2是一个长约10厘米,厚度为5mm的不锈钢片,两边留孔,穿插膨胀螺栓往墙上固定,中间焊接不锈钢管连接扶梯,用来固定整个扶梯。The escalator 1 is about 4 meters long and has a bolt hole 7 at the upper and lower ends of both sides. When the length is not enough, bolt holes can be used to connect another escalator to increase the length, which is convenient for operation. The stainless steel sheet 2 is a stainless steel sheet with a length of about 10 cm and a thickness of 5 mm. There are holes on both sides, and expansion bolts are inserted to fix it to the wall. The stainless steel pipe is welded in the middle to connect the escalator to fix the entire escalator.

不锈钢钢管3是一根长约30厘米不锈钢管。钢管尺寸为40*50*2,一端焊接不锈钢压片,另一端焊接一个双螺栓管夹,U型口正对另一个双螺栓管夹,所述双螺栓管夹4直径与扶梯横杆相匹配,厚度3mm,宽度100mm,两头夹片长50mm。两双螺栓管夹两边经螺栓9固定连接。两边留孔穿插螺栓,将双螺栓管夹的卡槽套在扶梯的横杆上,用来固定扶梯。所述双螺栓管夹4与扶梯横杆连接处设置橡胶垫片,起到防滑作用。The stainless steel pipe 3 is a stainless steel pipe about 30 cm long. The size of the steel pipe is 40*50*2, one end is welded with stainless steel sheet, the other end is welded with a double-bolt pipe clamp, the U-shaped mouth is facing the other double-bolt pipe clamp, and the diameter of the double-bolt pipe clamp 4 matches the escalator crossbar , the thickness is 3mm, the width is 100mm, and the length of the clips at both ends is 50mm. The two sides of the two double-bolt pipe clamps are fixedly connected by bolts 9. There are holes on both sides to insert bolts, and the grooves of the double-bolt pipe clamps are placed on the crossbar of the escalator to fix the escalator. A rubber gasket is provided at the connection between the double-bolt pipe clamp 4 and the escalator cross bar, which plays a role of anti-slip.

矩形钢管5是几段长约1米厚度为3mm的钢管,焊接成如图所1示的形状,前端焊有双螺栓管夹,双螺栓管夹的厚度为3mm,U型口正对另一个双螺栓管夹,两边留孔穿插螺栓,将双螺栓管夹的卡槽套在扶梯的横杆上,用来固定脚手架的脚手板和脚手架护栏。The rectangular steel pipe 5 is several sections of steel pipes with a length of about 1 meter and a thickness of 3 mm, which are welded into the shape shown in Figure 1. The front end is welded with a double-bolt pipe clamp, the thickness of the double-bolt pipe clamp is 3mm, and the U-shaped mouth is facing the other. Double-bolt pipe clamps, with holes on both sides to insert bolts, set the grooves of the double-bolt pipe clamps on the crossbar of the escalator to fix the scaffolding boards and scaffolding guardrails.

长矩形钢管8是一个长约8米,厚度为3mm的矩形钢管,两端焊接于矩形钢管上,使其形成一个脚手架护栏装置以及一个脚手板搭设的平台。The long rectangular steel pipe 8 is a rectangular steel pipe with a length of about 8 meters and a thickness of 3 mm. Both ends are welded to the rectangular steel pipe to form a scaffolding guardrail device and a platform on which a scaffolding board is erected.

使用时底部扶梯1置于地面上,不锈钢钢管3承担扶梯与墙之间的支持力。When in use, the bottom escalator 1 is placed on the ground, and the stainless steel pipe 3 bears the supporting force between the escalator and the wall.

以上所述仅是本实用新型的优选实施方式,应当指出,对于本技术领域的普通技术人员来说,在不脱离本实用新型原理的前提下,还可以做出若干改进和润饰,这些改进和润饰也应视为本实用新型的保护范围。The above are only the preferred embodiments of the present invention. It should be pointed out that for those skilled in the art, without departing from the principles of the present invention, several improvements and modifications can be made. These improvements and Retouching should also be regarded as the protection scope of the present invention.

Claims (6)

1.一种双梯脚手架装置,其特征在于:所述装置包括扶梯(1)、不锈钢压片(2)、不锈钢钢管(3)、双螺栓管夹(4)、矩形钢管(5)、膨胀螺栓(6)、长矩形钢管(8),所述装置为在两扶梯(1)之间设置施工平台,所述施工平台固定与两扶梯(1)的横杆固定连接,可拆卸,所述扶梯(1)与墙体之间设有支撑装置;所述支撑装置包括不锈钢压片(2)、不锈钢钢管(3)、双螺栓管夹(4),所述不锈钢压片(2)为片状结构,其两端制有螺栓孔,所述不锈钢压片(2)与墙体之间经膨胀螺栓(6)固定相连,所述不锈钢压片(2)中部焊接有与之垂直的不锈钢钢管(3),所述不锈钢钢管(3)另一端焊接双螺栓管夹(4),所述双螺栓管夹(4)与扶梯(1)的横杆相连;所述施工平台为两相互平行的矩形钢管(5)一端与扶梯横杆经双螺栓管夹(4)垂直相连,左右两矩形钢管(5)之间水平向垂直焊接长矩形钢管(8)围成护栏,二者焊接处竖向焊接矩形钢管(5),竖向的矩形钢管(5)下端焊接由矩形钢管(5)围成的三角形支架,所述由矩形钢管(5)围成的三角形支架之间上方为搭建平台,所述护栏、三角形支架与扶梯(1)横杆连接处经双螺栓管夹(4)固定连接,可拆卸。1. A double-ladder scaffolding device, characterized in that: the device comprises an escalator (1), a stainless steel sheet (2), a stainless steel steel pipe (3), a double-bolt pipe clamp (4), a rectangular steel pipe (5), an expansion Bolts (6), long rectangular steel pipes (8), the device is to set up a construction platform between the two escalators (1), the construction platform is fixedly connected to the crossbars of the two escalators (1), and can be dismantled, and the A support device is provided between the escalator (1) and the wall; the support device includes a stainless steel sheet (2), a stainless steel pipe (3), and a double-bolt pipe clamp (4), and the stainless steel sheet (2) is a sheet The stainless steel pressing sheet (2) and the wall are fixedly connected by expansion bolts (6), and the stainless steel pressing sheet (2) is welded with a vertical stainless steel pipe in the middle. (3), the other end of the stainless steel steel pipe (3) is welded with a double-bolt pipe clamp (4), and the double-bolt pipe clamp (4) is connected with the cross bar of the escalator (1); the construction platform is two parallel to each other. One end of the rectangular steel pipe (5) is vertically connected to the escalator crossbar via a double-bolt pipe clamp (4), and a long rectangular steel pipe (8) is welded horizontally and vertically between the left and right rectangular steel pipes (5) to form a guardrail. The rectangular steel pipe (5) is welded, and the lower end of the vertical rectangular steel pipe (5) is welded with a triangular support surrounded by the rectangular steel pipe (5). The connection between the guardrail, the triangular bracket and the escalator (1) cross bar is fixedly connected by the double-bolt pipe clamp (4), which can be disassembled. 2.根据权利要求1所述的一种双梯脚手架装置,其特征在于:所述不锈钢压片(2)厚度为5mm。2 . The double-ladder scaffolding device according to claim 1 , wherein the stainless steel pressing sheet ( 2 ) has a thickness of 5 mm. 3 . 3.根据权利要求1所述的一种双梯脚手架装置,其特征在于:所述双螺栓管夹(4)厚度为3mm。3 . The double-ladder scaffolding device according to claim 1 , wherein the thickness of the double-bolt pipe clamp ( 4 ) is 3 mm. 4 . 4.根据权利要求1所述的一种双梯脚手架装置,其特征在于:所述矩形钢管(5)管壁厚度为3mm。4 . The double-ladder scaffolding device according to claim 1 , wherein the thickness of the wall of the rectangular steel pipe ( 5 ) is 3 mm. 5 . 5.根据权利要求1所述的一种双梯脚手架装置,其特征在于:所述扶梯(1)上下两侧开设有螺栓孔(7)。5 . The double-ladder scaffolding device according to claim 1 , wherein bolt holes ( 7 ) are provided on the upper and lower sides of the escalator ( 1 ). 6 . 6.根据权利要求1所述的一种双梯脚手架装置,其特征在于:所述双螺栓管夹(4)与扶梯(1)横杆连接处设置橡胶垫片。6 . The double-ladder scaffolding device according to claim 1 , wherein a rubber gasket is provided at the connection between the double-bolt pipe clamp ( 4 ) and the cross bar of the escalator ( 1 ). 7 .
CN201921060886.3U 2019-07-09 2019-07-09 Double-ladder scaffold device Expired - Fee Related CN210947656U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921060886.3U CN210947656U (en) 2019-07-09 2019-07-09 Double-ladder scaffold device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921060886.3U CN210947656U (en) 2019-07-09 2019-07-09 Double-ladder scaffold device

Publications (1)

Publication Number Publication Date
CN210947656U true CN210947656U (en) 2020-07-07

Family

ID=71396236

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921060886.3U Expired - Fee Related CN210947656U (en) 2019-07-09 2019-07-09 Double-ladder scaffold device

Country Status (1)

Country Link
CN (1) CN210947656U (en)

Similar Documents

Publication Publication Date Title
CN203654692U (en) Overhanging type mobile scaffold
CN113931436B (en) A formwork support system
CN102926554A (en) Steel hanging seat formwork support and construction method thereof
CN207110413U (en) A kind of portable scaffold for building
CN201991229U (en) Combined fixture of beam
CN111350337A (en) Bearing frame for building construction
CN205637534U (en) Size and height -adjustable's instrument formula elevator shaft operating platform
CN211447777U (en) Fixing device for the upper part of the formwork of the outer concrete part of the moment-stiffened column
CN207905342U (en) A kind of scaffold for building with self-locking function
CN209443835U (en) A kind of architectural engineering temporary distribution box folding protective device
CN105781090A (en) Tool-type elevator shaft operating platform with adjustable size and height
CN110242035A (en) A double-ladder scaffolding device
CN205617772U (en) Gallows structure under lifting foot hand rack special use
CN206769350U (en) Outer on large-sized station boiler Steel Structure chooses net scaffold
CN113931354B (en) Cantilever scaffold and curtain wall integrated structure and construction method
CN103758334A (en) Scaffold structure for building external wall construction
CN204623801U (en) A kind of scaffold clamp
CN203050070U (en) Potable wall-mounting-type scaffold
CN211473340U (en) A closed protection device for the bottom plate of a cantilevered scaffold
CN224200234U (en) Auxiliary platform for assembling and disassembling equipment above step of operation station
CN205857663U (en) A kind of folding hoistway operation platform
CN217167200U (en) An adjustable steel plate positioning welding combination device
CN209653943U (en) A kind of groined type climbing ladder apparatus of safe ready
CN219034083U (en) Beam frame device easy to install
CN207332271U (en) Scaffolding for foundation pit slope construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200707