CN210917894U CN201921480061.7U CN201921480061U CN210917894U CN 210917894 U CN210917894 U CN 210917894U CN 201921480061 U CN201921480061 U CN 201921480061U CN 210917894 U CN210917894 U CN 210917894U
Authority
CN
China
Prior art keywords
air
piece
block
air entrainment
semi
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921480061.7U
Other languages
Chinese (zh)
Inventor
舒雨兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yingtan Hesheng Energy Saving Building Materials Co ltd
Original Assignee
Yingtan Hesheng Energy Saving Building Materials Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yingtan Hesheng Energy Saving Building Materials Co ltd filed Critical Yingtan Hesheng Energy Saving Building Materials Co ltd
Priority to CN201921480061.7U priority Critical patent/CN210917894U/en
Application granted granted Critical
Publication of CN210917894U publication Critical patent/CN210917894U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Floor Finish (AREA)

Abstract

The utility model discloses a gas filling piece assembled floor body, which comprises a base, the installation is installed respectively on the base face of base and is filled gas piece one and fill gas piece two, and is two sets of the book of base is installed reinforcing bar bundle frame to department, fill gas piece one is located fill gas piece two is in on the same horizontal plane, fill gas piece one with fill gas piece two's upper surface has all been seted up reinforcing bar bundle frame, the horizontal bar is installed to reinforcing bar bundle frame's middle part. The utility model discloses in, at the semi-arc pillar of the preceding facade installation of air entrainment piece two to the semi-arc groove of offering at the back facade of air entrainment piece one, semi-arc pillar and semi-arc groove, in air entrainment piece two and air entrainment piece one mutual displacement, and with semi-arc pillar card go into the notch in semi-arc groove in, realize the butt joint effect.

Description

Air-entraining block assembled floor slab
Technical Field
The utility model belongs to the technical field of the floor body, specifically be an air entrainment piece assembled floor body.
Background
The existing residential construction adopts site construction and a method of casting concrete on site, and the complete site construction has the following defects: the field construction procedure and management are complex, and the construction cost is high; the construction waste is more, and the construction site is not easy to clean; the noise of the site construction seriously affects the life and work of surrounding residents and is not beneficial to the environmental protection; the quality of site construction is not easy to be guaranteed due to the influence of factors such as building materials, climatic conditions, site management, quality of workers and the like. Therefore, the assembled building is widely popularized in China, and at present, in a high-rise building, the air-adding block is generally adopted, has the advantages of light volume weight, high heat preservation efficiency, good sound absorption, processability and the like, but the existing air-adding block is used for a non-bearing filling wall, a concrete layer is painted on site, cracking is easy to occur, diffusion of leaked rainwater is difficult, the heat preservation effect and the service life are influenced, and even the wall body is mildewed. And the fixation of the air-entraining block is not firm, the construction process is complicated, and the construction quality can not be ensured.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a: in order to solve the above-mentioned problems, an air-entraining block fabricated floor is provided.
The utility model adopts the technical scheme as follows:
the utility model provides a gas filling piece assembled floor body, includes the base, the installation is installed respectively on the base face of base and is filled gas piece one and fill gas piece two, and is two sets of the book of base is to the department and is installed reinforcing bar bundle frame, fill gas piece one is located fill gas piece two is in on the same horizontal plane, fill gas piece one with fill gas piece two's upper surface and all seted up reinforcing bar bundle frame, the horizontal bar is installed to the middle part that the reinforcing bar bundle was put up.
The middle part of the rear vertical face of the first air-entraining block is provided with a semi-arc groove, the middle part of the front vertical face of the second air-entraining block is provided with a semi-arc support, and the semi-arc support and the semi-arc groove are in a semi-arc shape.
The middle part of the rear vertical face of the first air adding block is provided with a corresponding strip, and the middle part of the front vertical face of the second air adding block is provided with a vertical strip.
The vertical strips and the corresponding strips are in the shape of transverse strips and grooves, and the vertical strips and the corresponding strips are located on the same transverse horizontal plane.
And the periphery of the rear vertical surface of the first air adding block is provided with round holes, and the four groups of round holes are equal in size.
Wherein, the spliced eye has all been seted up to the left and right sides of horizontal bar, and the otter board is installed to the spliced eye.
To sum up, owing to adopted above-mentioned technical scheme, the beneficial effects of the utility model are that:
1. the utility model discloses in, at the semi-arc pillar of the preceding facade installation of air entrainment piece two to the semi-arc groove of offering at the back facade of air entrainment piece one, semi-arc pillar and semi-arc groove, in air entrainment piece two and air entrainment piece one mutual displacement, and with semi-arc pillar card go into the notch in semi-arc groove in, realize the butt joint effect.
2. The utility model discloses in, bundle the frame at the reinforcing bar that the upper surface of air entrainment piece one was seted up to bundle the horizontal bar of the middle part installation of frame at the reinforcing bar for with external otter board contact, and add the concrete in with it, it is fixed to realize carrying out the concrete to the air entrainment piece of air entrainment piece top.
Drawings
FIG. 1 is a schematic diagram of the structure of the present invention;
FIG. 2 is a connection diagram of the air-filling block of the present invention;
fig. 3 is an enlarged view of a position a in fig. 2 of the present invention.
The labels in the figure are: 1. a base; 2. a first air adding block; 3. a second air-adding block; 4. a steel bar bundle frame; 5. a horizontal bar; 6. erecting strips; 7. a half arc strut; 8. a circular hole; 9. a half-arc groove; 10. and (4) applying the strips.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are for purposes of illustration only and are not intended to limit the invention.
Referring to fig. 1-3, an air-entraining block assembled floor slab comprises a base 1, a first air-entraining block 2 and a second air-entraining block 3 are respectively installed on the base surface of the base 1, a reinforcing steel bar bundling frame 4 is installed at the folding position of two groups of the base 1, the first air-entraining block 2 is positioned on the same horizontal plane of the second air-entraining block 3, the upper surfaces of the first air-entraining block 2 and the second air-entraining block 3 are both provided with the reinforcing steel bar bundling frame 4, the middle part of the reinforcing steel bar bundling frame 4 is provided with a cross bar 5, the middle part of the rear vertical surface of the first air-entraining block 2 is provided with a semi-arc groove 9, the middle part of the front vertical surface of the second air-entraining block 3 is provided with a semi-arc pillar 7, the semi-arc pillar 7 and the semi-arc groove 9 are both in semi-arc shape for convenient clamping, the middle part of the rear vertical surface of the first air-entraining block 2 is provided with a corresponding bar 10, the middle part of the, the vertical strips 6 and the corresponding strips 10 are located on the same horizontal plane, round holes 8 are formed in the periphery of the rear vertical face of the first air adding block 2, the four round holes 8 are equal in size, plug holes are formed in the left side and the right side of the transverse strips 5, and the net plates are installed in the plug holes.
The working principle is as follows: when the air-entraining block I2 is used, the air-entraining block I2 is butted with the air-entraining block II 3, the air-entraining block I2 and the air-entraining block II 3 are mutually extruded, a semi-arc groove 9 which is formed in the back surface of the air-entraining block I2 is used for adding concrete, the air-entraining block II 3 is displaced towards the back vertical surface of the air-entraining block I2 and is mutually connected to achieve fixation, and when the air-entraining block II 3 is displaced towards the air-entraining block I2, the vertical strip 6 on the air-entraining block II 3 and the corresponding strip 10 on the air-entraining block I2 are required to be positioned on the same horizontal plane when needing to be noticed;
secondly, a half-arc strut 7 is arranged on the front vertical surface of the air-adding block II 3, a half-arc groove 9, a half-arc strut 7 and a half-arc groove 9 are arranged on the rear vertical surface of the air-adding block I2, and when the air-adding block II 3 and the air-adding block I2 are displaced mutually, the half-arc strut 7 is clamped into a notch of the half-arc groove 9, so that a butt joint effect is realized;
the upper surface of the air-entrapping block I2 is provided with a steel bar bundle frame 4, and a transverse bar 5 arranged in the middle of the steel bar bundle frame 4 is used for contacting with an external net plate and adding concrete into the net plate, so that the air-entrapping block above the air-entrapping block I2 is fixed with the concrete.
The above description is only exemplary of the present invention and should not be construed as limiting the present invention, and any modifications, equivalents and improvements made within the spirit and principles of the present invention are intended to be included within the scope of the present invention.

Claims (6)

1. The utility model provides an aerated block assembled floor body, includes base (1), its characterized in that: install respectively on the base face of base (1) and install air entrainment piece (2) and air entrainment piece two (3), two sets of the book of base (1) is to the department installs reinforcing bar bundle frame (4), air entrainment piece (2) are located air entrainment piece two (3) are in on the same horizontal plane, air entrainment piece (2) with reinforcing bar bundle frame (4) have all been seted up to the upper surface of air entrainment piece two (3), horizontal bar (5) are installed to the middle part of reinforcing bar bundle frame (4).
2. An air-filled block fabricated floor of claim 1, wherein: half arc groove (9) have been seted up to the back facade middle part of air entrainment piece one (2), half arc pillar (7) are installed to the preceding facade middle part of air entrainment piece two (3), half arc pillar (7) with half arc groove (9) are the semiarchy shape.
3. An air-filled block fabricated floor of claim 1, wherein: the middle part of the rear vertical face of the air-adding block I (2) is provided with a corresponding strip (10), and the middle part of the front vertical face of the air-adding block II (3) is provided with a vertical strip (6).
4. An air-filled block fabricated floor of claim 3, wherein: the vertical strips (6) and the corresponding strips (10) are in the shape of transverse strips and grooves, and the vertical strips (6) and the corresponding strips (10) are all located on the same transverse horizontal plane.
5. An air-filled block fabricated floor of claim 1, wherein: round holes (8) are formed in the periphery of the rear vertical face of the first air-entraining block (2), and the four groups of round holes (8) are equal in size.
6. An air-filled block fabricated floor of claim 1, wherein: the left side and the right side of the transverse bar (5) are both provided with splicing holes, and the screen plates are installed in the splicing holes.
CN201921480061.7U 2019-09-06 2019-09-06 Air-entraining block assembled floor slab Expired - Fee Related CN210917894U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921480061.7U CN210917894U (en) 2019-09-06 2019-09-06 Air-entraining block assembled floor slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921480061.7U CN210917894U (en) 2019-09-06 2019-09-06 Air-entraining block assembled floor slab

Publications (1)

Publication Number Publication Date
CN210917894U true CN210917894U (en) 2020-07-03

Family

ID=71361949

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921480061.7U Expired - Fee Related CN210917894U (en) 2019-09-06 2019-09-06 Air-entraining block assembled floor slab

Country Status (1)

Country Link
CN (1) CN210917894U (en)

Similar Documents

Publication Publication Date Title
CN109853800B (en) Assembled low-energy-consumption curtain wall system and construction method thereof
CN214246093U (en) Assembled steel construction center braced frame system
CN211735945U (en) Steel construction building assembled heat preservation wallboard
CN210917894U (en) Air-entraining block assembled floor slab
CN109989516B (en) Building block and construction process thereof
CN204001289U (en) There is the light steel keel partition that carries the arm of encorbelmenting
CN215406722U (en) Steel house
CN212896972U (en) Steel construction assembled wallboard is built in room
CN214423395U (en) Assembled waterproof wall of leading
CN210622162U (en) Be used for hanging stone material square column futilely and become cylinder node structure
CN209742111U (en) Concatenation formula noise insulation for construction
CN206015685U (en) A kind of Collapsible Loess District deep basal pit diaphram wall inner support system
CN211714286U (en) Building curtain wall convenient to installation and dismantlement
CN216515703U (en) Basic cushion cap for building engineering
CN221168693U (en) Be used for box structure bottom surface clear water concrete construction template
CN215564978U (en) Transformer substation is with assembled enclosure
CN205637338U (en) Multi -chamber concatenation type steel pipe -concrete composite post
CN212583338U (en) Steel construction house outer wall reinforcing apparatus
CN217326035U (en) Novel furred ceiling corner connecting piece
CN212376057U (en) Sound insulation board with heat preservation function
CN214091170U (en) Assembled villa structure
CN219753597U (en) Heat-insulation waterproof curtain wall
CN221030738U (en) Thermal insulation structure of outer wall
CN211691094U (en) Assembled roofing piece waterproof construction
CN217439398U (en) Safe steel construction wall planking mounting structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200703

Termination date: 20210906

CF01 Termination of patent right due to non-payment of annual fee